SlideShare ist ein Scribd-Unternehmen logo
1 von 26
Downloaden Sie, um offline zu lesen
THERMAL POWER PLANT
OPERATIONS
Simulator Part 1- Day1
MANOHAR TATWAWADI
Director, tops
9372167165, mtatwawadi@gmail.com
ELECTRICAL CHARGING
• The first step is to establish power supply for
the auxiliaries at least for cooling water /GS
water pumps
• The power supply will be required for the
Instrument Air and Service air compressors.
• For Station Lighting , other station auxiliaries
and in the Water Treatment Plant.
• The power supply may be taken from the
440/220KV GRID by Station Transformers
Care to be Taken
• Get the clearance from Switchyard for charging the
400kv/220kv breakers of the station transformers.
• Check that all CTs & PTs in the switchyard are in order
• Before charging breaker, check the isolators.
• Generally always charge the HV side breaker of the
transformers first
• Mostly all 11kv, 6.6kv, 415V boards are charged from
both sides with their respective Bus Couplers in OFF
position
• Before charging check all the transformer protections
are in service.
STATION TRANSFORMER
• All the Electrical Supply required for the station is from
the Station Transformer (generally a (220/400)/6.6KV).
The station transformer capacity is approximately 20%
of the generating capacity. The supply may be changed
over to Unit Auxiliary Transformer, after the unit is
synchronized.
• The 6.6 KV station boards are charged by charging the
station transformer from the HV side (220/400KV side)
of the transformer first. The isolators of the 400kv side
breaker are closed and then the breaker is made ON.
• The incomers to the station boards are made ON to
charge the bus bars in the Board.
CHARGING OF STATION BOARDS
CHARGNG OF UNIT BOARDS 6.6 KV (UAT A & UAT B)
UNIT TRANSFORMER
16.5KV /6.6KV 20/25MVA
UNIT TRANSFORMER
16.5KV /6.6KV 20/25MVA
Charging of LT 6.6kv/440V Boards
• Charge Boiler Boards
• Charge Turbine Boards
• Station Service Boards
• Standby Board
• New Emergency Board
• Emergency Board and
• Main Lighting Distribution Board
CHARGING OF GS AND DM WATER
• The River water Pumps, pump water for the whole
requirement of water to the TPS. This water pumped
by the RWP is sent to the WT Plant where it is treated
& stored and then made available as G.S. water.
• The General water service pumps for all auxiliaries
cooling systems are started and all cooling water
systems are charged. The overhead GS water tanks are
also filled up. The tanks are provided so as to act as
buffer in case the pumps trip or not available for some
time.
Water Cycle Establishment
• General Water System will be charged first so that it
caters the need of cooling water to all auxiliaries.
• Two GS Pumps will be started for the purpose.
• Instrument Air and Service Air Compressors will be
started when cooling water is available
• The WT Plant will be started and DM water from the
WT Plant will be made available
• DM Intermediate Tank will be filled to its full capacity.
• DM Makeup will be started for filling DM Overhead
tanks.
CHARGING OF GS WATER
The General water service pumps for all auxiliaries cooling systems are started and all cooling water systems are
charged. The overhead GS water tanks are also filled up. The tanks are provided so as to act as buffer in case the
pumps trip or not available for some time.
Charging of DM and GS Water
• After the cooling water is available for Instrument and
service air compressors, the compressors can be
started and Instrument and Service air is made
available for the operation of valves, Atomisation etc.
• From the WT Plant, the DM water will be available
now. The Intermediate DM Tank is filled up by opening
valves DM4 and DM5 and DM Makeup pumps can be
started after the Intermediate Tank Level reaches more
than 2M.
• There are two Emergency DM tanks provided in case
of failure of DM Pumps. These tanks are filled by DM
Makeup Pumps by opening the respective valves.
TYPICAL DM MAKEUP SYSTEM
DM MAKEUP AND COND CYCLE
• The Unit Drain Tank and Condenser may be filled up
with the help of DM Make up pumps by opening the
respective valves. (UDT level 2M & Condenser Level
3M).
• The Condensate Cycle can be taken into service at this
time. There are Three No of CEPs. Two are running and
one standby. The First CEP to be started is started with
its Discharge Bypass valve 10% open, so that it
develops some header pressure. (More than
14kg/cm2, otherwise the started CEP will trip on “CEP
Discharge Header Pressure Low”.) Once a pressure of
20kg/cm2 is reached, the discharge valve of the CEP is
opened.
DM MAKEUP AND COND CYCLE
• Before the CEP is started the condensate line
upto the deaerator is made through (All Heaters
Inlet / Outlet Valves open & Bypass Valves
Closed). The main Condenser level control valve
is also kept closed. (MC36 Valve closed).
• After starting the CEP and opening the discharge
valve, Main Condenser level Control Valve (MC36)
can be opened and the flow to Deaerator can be
observed.
CONDENSATE CYCLE CHARGING
The Deaerator can now be filled up by opening the Main Condensate Control Valve MC36
slightly. (About 5%). The Condenser Hotwell Level in the process will come down. The
Condensate Level has to be maintained by the Condensate makeup valve CV6 or CV7. Once
the Deaerator level reaches to about 4M close the Main Condensate Control Valve MC36 and
stop the make up to condenser
BOILER DRUM FILLING & Feed water system
• The Vents of the boiler drum shall be opened for boiler drum
filling. Also the Economiser Recirculation Valve must be
opened before starting the boiler drum filling. By starting
Boiler Filling Pump and making the circuit through for boiler
filling through the Boiler Drain header, the Boiler Drum can
now be filled up to NORMAL Level. (0.6 M).
• Boiler Drum can also be filled by opening the Feed Control
Station Low Load Line valves, the economizer inlet valve and
the boiler filling pump discharge line to FCS valve.
• After the drum Filling is done up to the normal Level , the
boiler filling valve can now be closed. The Economiser vent
valves shall also be closed as water comes out from
Economoser Vents.
• The Drum Vents and the Economiser Recirculation will be
kept open, till there is pressure in the boiler drum.
FEED WATER SYSTEM & BOILER DRUM FILLING
Feed water system
Turbine Side Activities
• Start AC LOP, AC Seal Oil Pump
• After filling the oil lines fully, start Starting Oil Pump,
observe Relay Oil Pressure 18kg/cm2.
• Lubricating Oil Pressure 4kg/cm2 before oil coolers and
1kg/cm2 after coolers
• Take trials of DC LOP and DC Seal Oil Pumps by tripping the
respective AC Pumps.
• Stop AC Lub oil and AC Seal oil Pumps. Start JOP
• Check the lub oil and seal oil pressures, if OK
• Start Barring Gear motor and check the speed of the
turbine rotor.
• Start the Hydrogen Filling in the Generator. Observe the
pressure and Purity of Hydrogen in the Generator
TURBINE OIL SYSTEM 270 MW
Seal Oil System 210 MW
Hydrogen Filling in Generator
We have Achieved
• Whole Thermal Power Plant has been electrified
• GS water made available to all auxiliaries for cooling.
Overhead GS Tank Levels 3.5M
• Cooling Towers taken in service
• Instrument Air/ Service Air Pressure 6.5kg/cm2
• Unit Drain Tank, Emergency DM Tank, Condenser,
Deaerator and boiler drum filled with DM water.
• Condensate cycle charged with DM water
• Starting Oil Pump for Turbine Lub Oil, Seal Oil and relay oil
started.
• Turbine Rotor put on barring
• Hydrogen filling in Generator started.
We have Achieved
• Instrument air/service air pressure 6.5kg/cm2
• DM Intermediate Tank Level 4.5M
• Unit Drain Tank Full to its capacity
• Condenser Hotwell Level 3M
• Deaerator Level 4M
• Boiler Drum Level 0.6M
• SOP running, AC Lub oil & Seal oil Pumps OFF
Governing Oil Pres. 18kg/cm2,
• H2/seal oil Differential Pressure 0.9 to 1 kg/cm2
• Lub oil pres. 4kg/cm2, 1kg/cm2 before, after cooler.
• Barring gear ON Turbine rotor speed 3 to 4 RPM
Operational Tests
• Condenser level low, Deaerator level low,
Boiler Drum level low, UDT level low and DM
intertank level low reset.
• Starting of DC Lub oil and Seal oil Pumps on
Turbine lub oil pr low, seal oil pr low.
• Airheater AC motor tripping and DC / Air
motor starting
• All aux are getting cooling water
THERMAL POWER PLANT OPERATIONS

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam Turbine
 
Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul
 
Final Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptxFinal Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptx
 
turbine governing oil system
turbine governing oil systemturbine governing oil system
turbine governing oil system
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
Power Plant Operations.pdf
Power Plant Operations.pdfPower Plant Operations.pdf
Power Plant Operations.pdf
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
 
660 mw turbo governing & protection system
660 mw turbo  governing & protection system660 mw turbo  governing & protection system
660 mw turbo governing & protection system
 
Condenser performance test
Condenser performance testCondenser performance test
Condenser performance test
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
Gas turbine course
Gas turbine courseGas turbine course
Gas turbine course
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
 
210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING 210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
Drun level control
Drun level controlDrun level control
Drun level control
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
Steam turbine over speed trip systems (6)
Steam turbine over speed trip systems (6)Steam turbine over speed trip systems (6)
Steam turbine over speed trip systems (6)
 

Ähnlich wie THERMAL POWER PLANT OPERATIONS

Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdf
Madan Karki
 
Module 1 heating - steam (wecompress.com)
Module 1   heating - steam (wecompress.com)Module 1   heating - steam (wecompress.com)
Module 1 heating - steam (wecompress.com)
DeepakSingh1807
 
Best steam power plant
Best steam power plant Best steam power plant
Best steam power plant
Enamul Khan
 

Ähnlich wie THERMAL POWER PLANT OPERATIONS (20)

EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
 
Turbine operation.pptx
Turbine operation.pptxTurbine operation.pptx
Turbine operation.pptx
 
TG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.pptTG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.ppt
 
Turbine Start Up.pptx
Turbine Start Up.pptxTurbine Start Up.pptx
Turbine Start Up.pptx
 
Piping system
Piping systemPiping system
Piping system
 
Hydro Power Plant Auxaleries
Hydro Power Plant AuxaleriesHydro Power Plant Auxaleries
Hydro Power Plant Auxaleries
 
Power Plant Simulator, Unloading and shutting the Turbogenerator
Power Plant Simulator, Unloading and shutting the TurbogeneratorPower Plant Simulator, Unloading and shutting the Turbogenerator
Power Plant Simulator, Unloading and shutting the Turbogenerator
 
Boiler ppt
Boiler pptBoiler ppt
Boiler ppt
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 
Oil production 2
Oil production 2Oil production 2
Oil production 2
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdf
 
Module 1 heating - steam (wecompress.com)
Module 1   heating - steam (wecompress.com)Module 1   heating - steam (wecompress.com)
Module 1 heating - steam (wecompress.com)
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
 
PUMPS.ppt
PUMPS.pptPUMPS.ppt
PUMPS.ppt
 
Rankine
RankineRankine
Rankine
 
POWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINEPOWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINE
 
Best steam power plant
Best steam power plant Best steam power plant
Best steam power plant
 
Module2.pdf
Module2.pdfModule2.pdf
Module2.pdf
 

Mehr von Manohar Tatwawadi

Mehr von Manohar Tatwawadi (20)

Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3
 
Green building concepts and good building practices
Green building concepts and good building practicesGreen building concepts and good building practices
Green building concepts and good building practices
 
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler EfficiencyAuxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
 
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIESCOMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
 
FAQ on Turbines Part 2
FAQ on Turbines Part 2FAQ on Turbines Part 2
FAQ on Turbines Part 2
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1
 
Cooling towers in thermal power plants
Cooling towers in thermal power plantsCooling towers in thermal power plants
Cooling towers in thermal power plants
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stations
 
Cost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSCost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPS
 
Environmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power StationsEnvironmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power Stations
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
 
Fuels and Combustion Equations
Fuels and Combustion EquationsFuels and Combustion Equations
Fuels and Combustion Equations
 
Basics of thermal power stations
Basics of thermal power stationsBasics of thermal power stations
Basics of thermal power stations
 
Effect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / MillsEffect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / Mills
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
 
Biomass Power Plants
Biomass Power PlantsBiomass Power Plants
Biomass Power Plants
 
Swot Analysis
Swot AnalysisSwot Analysis
Swot Analysis
 

Kürzlich hochgeladen

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Kürzlich hochgeladen (20)

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 

THERMAL POWER PLANT OPERATIONS

  • 1. THERMAL POWER PLANT OPERATIONS Simulator Part 1- Day1 MANOHAR TATWAWADI Director, tops 9372167165, mtatwawadi@gmail.com
  • 2. ELECTRICAL CHARGING • The first step is to establish power supply for the auxiliaries at least for cooling water /GS water pumps • The power supply will be required for the Instrument Air and Service air compressors. • For Station Lighting , other station auxiliaries and in the Water Treatment Plant. • The power supply may be taken from the 440/220KV GRID by Station Transformers
  • 3. Care to be Taken • Get the clearance from Switchyard for charging the 400kv/220kv breakers of the station transformers. • Check that all CTs & PTs in the switchyard are in order • Before charging breaker, check the isolators. • Generally always charge the HV side breaker of the transformers first • Mostly all 11kv, 6.6kv, 415V boards are charged from both sides with their respective Bus Couplers in OFF position • Before charging check all the transformer protections are in service.
  • 4. STATION TRANSFORMER • All the Electrical Supply required for the station is from the Station Transformer (generally a (220/400)/6.6KV). The station transformer capacity is approximately 20% of the generating capacity. The supply may be changed over to Unit Auxiliary Transformer, after the unit is synchronized. • The 6.6 KV station boards are charged by charging the station transformer from the HV side (220/400KV side) of the transformer first. The isolators of the 400kv side breaker are closed and then the breaker is made ON. • The incomers to the station boards are made ON to charge the bus bars in the Board.
  • 6. CHARGNG OF UNIT BOARDS 6.6 KV (UAT A & UAT B) UNIT TRANSFORMER 16.5KV /6.6KV 20/25MVA UNIT TRANSFORMER 16.5KV /6.6KV 20/25MVA
  • 7. Charging of LT 6.6kv/440V Boards • Charge Boiler Boards • Charge Turbine Boards • Station Service Boards • Standby Board • New Emergency Board • Emergency Board and • Main Lighting Distribution Board
  • 8. CHARGING OF GS AND DM WATER • The River water Pumps, pump water for the whole requirement of water to the TPS. This water pumped by the RWP is sent to the WT Plant where it is treated & stored and then made available as G.S. water. • The General water service pumps for all auxiliaries cooling systems are started and all cooling water systems are charged. The overhead GS water tanks are also filled up. The tanks are provided so as to act as buffer in case the pumps trip or not available for some time.
  • 9. Water Cycle Establishment • General Water System will be charged first so that it caters the need of cooling water to all auxiliaries. • Two GS Pumps will be started for the purpose. • Instrument Air and Service Air Compressors will be started when cooling water is available • The WT Plant will be started and DM water from the WT Plant will be made available • DM Intermediate Tank will be filled to its full capacity. • DM Makeup will be started for filling DM Overhead tanks.
  • 10. CHARGING OF GS WATER The General water service pumps for all auxiliaries cooling systems are started and all cooling water systems are charged. The overhead GS water tanks are also filled up. The tanks are provided so as to act as buffer in case the pumps trip or not available for some time.
  • 11. Charging of DM and GS Water • After the cooling water is available for Instrument and service air compressors, the compressors can be started and Instrument and Service air is made available for the operation of valves, Atomisation etc. • From the WT Plant, the DM water will be available now. The Intermediate DM Tank is filled up by opening valves DM4 and DM5 and DM Makeup pumps can be started after the Intermediate Tank Level reaches more than 2M. • There are two Emergency DM tanks provided in case of failure of DM Pumps. These tanks are filled by DM Makeup Pumps by opening the respective valves.
  • 13. DM MAKEUP AND COND CYCLE • The Unit Drain Tank and Condenser may be filled up with the help of DM Make up pumps by opening the respective valves. (UDT level 2M & Condenser Level 3M). • The Condensate Cycle can be taken into service at this time. There are Three No of CEPs. Two are running and one standby. The First CEP to be started is started with its Discharge Bypass valve 10% open, so that it develops some header pressure. (More than 14kg/cm2, otherwise the started CEP will trip on “CEP Discharge Header Pressure Low”.) Once a pressure of 20kg/cm2 is reached, the discharge valve of the CEP is opened.
  • 14. DM MAKEUP AND COND CYCLE • Before the CEP is started the condensate line upto the deaerator is made through (All Heaters Inlet / Outlet Valves open & Bypass Valves Closed). The main Condenser level control valve is also kept closed. (MC36 Valve closed). • After starting the CEP and opening the discharge valve, Main Condenser level Control Valve (MC36) can be opened and the flow to Deaerator can be observed.
  • 15. CONDENSATE CYCLE CHARGING The Deaerator can now be filled up by opening the Main Condensate Control Valve MC36 slightly. (About 5%). The Condenser Hotwell Level in the process will come down. The Condensate Level has to be maintained by the Condensate makeup valve CV6 or CV7. Once the Deaerator level reaches to about 4M close the Main Condensate Control Valve MC36 and stop the make up to condenser
  • 16. BOILER DRUM FILLING & Feed water system • The Vents of the boiler drum shall be opened for boiler drum filling. Also the Economiser Recirculation Valve must be opened before starting the boiler drum filling. By starting Boiler Filling Pump and making the circuit through for boiler filling through the Boiler Drain header, the Boiler Drum can now be filled up to NORMAL Level. (0.6 M). • Boiler Drum can also be filled by opening the Feed Control Station Low Load Line valves, the economizer inlet valve and the boiler filling pump discharge line to FCS valve. • After the drum Filling is done up to the normal Level , the boiler filling valve can now be closed. The Economiser vent valves shall also be closed as water comes out from Economoser Vents. • The Drum Vents and the Economiser Recirculation will be kept open, till there is pressure in the boiler drum.
  • 17. FEED WATER SYSTEM & BOILER DRUM FILLING
  • 19. Turbine Side Activities • Start AC LOP, AC Seal Oil Pump • After filling the oil lines fully, start Starting Oil Pump, observe Relay Oil Pressure 18kg/cm2. • Lubricating Oil Pressure 4kg/cm2 before oil coolers and 1kg/cm2 after coolers • Take trials of DC LOP and DC Seal Oil Pumps by tripping the respective AC Pumps. • Stop AC Lub oil and AC Seal oil Pumps. Start JOP • Check the lub oil and seal oil pressures, if OK • Start Barring Gear motor and check the speed of the turbine rotor. • Start the Hydrogen Filling in the Generator. Observe the pressure and Purity of Hydrogen in the Generator
  • 21. Seal Oil System 210 MW
  • 22. Hydrogen Filling in Generator
  • 23. We have Achieved • Whole Thermal Power Plant has been electrified • GS water made available to all auxiliaries for cooling. Overhead GS Tank Levels 3.5M • Cooling Towers taken in service • Instrument Air/ Service Air Pressure 6.5kg/cm2 • Unit Drain Tank, Emergency DM Tank, Condenser, Deaerator and boiler drum filled with DM water. • Condensate cycle charged with DM water • Starting Oil Pump for Turbine Lub Oil, Seal Oil and relay oil started. • Turbine Rotor put on barring • Hydrogen filling in Generator started.
  • 24. We have Achieved • Instrument air/service air pressure 6.5kg/cm2 • DM Intermediate Tank Level 4.5M • Unit Drain Tank Full to its capacity • Condenser Hotwell Level 3M • Deaerator Level 4M • Boiler Drum Level 0.6M • SOP running, AC Lub oil & Seal oil Pumps OFF Governing Oil Pres. 18kg/cm2, • H2/seal oil Differential Pressure 0.9 to 1 kg/cm2 • Lub oil pres. 4kg/cm2, 1kg/cm2 before, after cooler. • Barring gear ON Turbine rotor speed 3 to 4 RPM
  • 25. Operational Tests • Condenser level low, Deaerator level low, Boiler Drum level low, UDT level low and DM intertank level low reset. • Starting of DC Lub oil and Seal oil Pumps on Turbine lub oil pr low, seal oil pr low. • Airheater AC motor tripping and DC / Air motor starting • All aux are getting cooling water