Projects:
1- UNICEF projects – supplying and installing newsubmersible pumps in
barrels for ras al-ain and jezzine pumping stations .
The projects electromechanical duties:
- Replacing the vertical multistage pumps with new submersible pumps in barrels
for feeding different regions: seddqine, al bus and hanawai (all in tyre) and its
all accessories with power and control cables and control cabinet.
- Same duties were preformed for jezzine pumping station.
- All the removed parts and accessories were delivered to the water establishment
committee.
2- Mercy corps projects:
The projects duties:
- Replacing the wells’ submersible pumps and its accessories if needed with its
power and control cables and control cabinet.
- Replacing of multistage pump (booster pump) with new one (or installation of
new one) with its control and power cabinet and its accessories need on suction
and discharge lines.
3- UNICEF projects – supplying and operating submersible pumps for
wells.
The projects duties:
- Replacing the wells’ submersible pumps (or installing new one) and its
accessories needed with its power and control cables.
- Installation of lightning protection system.
- Installation of the well head accessories with different sizes as requested.
- Installation of the chlorination system to supply chlorine gas to the water from
the well.
- Building manholes for the well head accessories with steel cover and rooms for
the control cabinet and chlorination system and for the operator (if existing an
operator).
- Grounding and earthing system for the pipes, fence, control cabinet.
- Supplying and installation of prefabricated room at different sizes.
- Cyclopean concrete slab and manholes works.
- Installation of steel barrels for the submersible pump (booster pump) and
accessories (check valve, valves ...etc).
4- WARD COMPANY -DIFFERENT PUMPING STATION IN SOUTH
LEBANON:
The project duties:
- Exploring the site for installing and connecting the new (or repaired) surge tank
to the main discharge line (existing one) and its all accessories such as check
valve, expansion joint (st.steel type) and valve.
- Installation of the compressor for the surge tank and it’s all piping connections
and electrical cables.
5- MAJLES AL-JANOUB-WARD COMPANY – SHAKRA PUMPING
STATION TO BINT JBEIL AND MAIS AL-JABAL:
The project consists of Mechanical and Electrical work;
For the mechanical duties:
- Installation of new submersible pumps with power, controland level sensors for
three wells and their well head accessories.
- Installation of four submersible pumps in barrels (booster pumps) to supply Bint
Jbiel (connected to one collector in parallel) and three submersible pumps in
barrels (booster pumps) to supply Mais al Jabal (connected to another collector
in parallel also)
- Installation of all needed accessories for each booster pump and on the
collectors.
- Installation of new surge tank on bint jbiel main line for protection and all its
accessories.
- Installation of chlorination system for the main suction line to supply chlorine
gas for both main lines.
For the electrical duties:
- Installation of new sets of control cabinet represented in two sets, one for Bint
Jbiel and one for Mais al Jabal with the power connections of the submersible
pump.
- Installation of new control cabinet for each well with the power connections.
6- USAid project-CDM smith (consultant)-Rehabilitation of Batoulay and
Ouadi Jilo Pump Stations (two years duration):
The project consists of Mechanical, civil and electrical work;
For the mechanical duties:
- Replacing submersible multistage pumps (for water wells) and the associated
6’’ and 8’’ pipes with the required valves and accessories (duel plate check
valve, gate valve, air release valve and dismantling joint).
- Replacing booster pumps (multistage pumps) with piping modification and
fabrication work for the pumps suction and discharge lines (10’’, 8’’ and 6’’
pipes) with the required valves and accessories (duel plate check valve, gate
valve, air release valve and dismantling joint).
- High pressure welding and fabrication pipes (PN 40) with calibrating from 0 to
50 bar and supplying pressure gauge, differential pressure switch (high and
law).
- Supplying and installing on the wells discharge pipes located in the room below
the water tank, solar ultrasonic flow meters with all accessories, solar panel and
cables.
- All the replacement of the booster and submersible pumps comes with
replacing the main control cabinets and power and control cables.
- Repairing the surge tanks and booster pumps’ inlet strainers.
- Installation if different types of flow meters (electromagnetic and ultrasonic
flow meters).
- Designing and performed different types of welding for creating different
shapes and sizes of pipes supports.
For the electrical duties:
- Replacing and repairing all the damaged and broken lights inside and outside.
Installation of new external lights running at the photovoltaic cell.
- Installation new air conditioning system for the cooling the new control cabinets
for the booster pumps and wells pumps.
- Providing power and control cables for both submersible and horizontal pumps
and installation underground in galvanized conduits.
- Installation of solar powered batteries for the ultrasonic flow meters.
- Installation of lightning protection systems at different elevations according to
the surrounding buildings-from the nimbus head to the earth (grounding) pit
with all the required materials.
- Testing and measuring the existing power cables by performing a megger test at
different voltage values.
- Installation of 6 sets of new main control cabinet for both stations and AUX.
control panels with ATS cabinet.
- Providing grounding cables for electrical transformers and booster pumps
connected to new earth rods with resistance less than 2 ohms.
For the civil duties:
- Excavation and building of new man holes for different purposes. Excavation
and digging for revealing power cables and 24’’ pipes.
- Repairing the external of the buildings with stone gladding and water proofing
products.
- Removing the old red tiles from the buildings’ roofs and installing new one with
new zinc gutter for rain water.
- Compacting all the backfilled places with addition of layers of asphalts.
- Performing frameworks-steel bars 12mm and 14mm diameter and supplying
reinforced concrete (30 MPa) for new manholes of all wells with waterproof
materials and galvanized steel vents to prevent humidity and inside the chamber
with heavy duty iron covers.
- Waterproofing works on the roof of water tanks after screed. Using non-shrink
grout for the pads of the BPs.
- Installation of new galvanized steel ladder inside the water tank and handrails
after removing the old one.
- Painting the internal walls of both pumping stations as required, also painting
the floor with anti slip epoxy paints inside the pumping rooms of pumping
stations.
- Repairing all the aluminum doors and windows inside the pumping stations.
General work duties:
- Meeting and coordinating with the foreman for coordinating the timeline work
and for solving problems if existing.
- Supervising in the site in order to have a perfect work according to the design
and drawings.
- Performing solutions & improvement for devices according to the insulation
process. Submitting reports (weekly and monthly) for the preformed jobs with
photos of every activity.
- Taking measurements for the installed quantities to check according to the Bill
of Quantities.
- Drawing the mechanical, civil and electrical drawings for the project before
perform the work to have the approval of any activity, also deliver the as built
drawings.
- Organizing the activities sequence for the labors and foreman to finish in a
perfect, professional way and with lower cost.
- Submitting inspection document to the consultant after each item fulfilling.
- Deliver the operation and maintenance manuals for civil, electrical and
mechanical items and work.
- Testing the installed electrical and mechanical machines such as booster pumps,
submersible pumps …etc (startup testing procedures).
Projects alrawan

Weitere ähnliche Inhalte

Was ist angesagt?

Safavi-C V-English-03
Safavi-C V-English-03Safavi-C V-English-03
Safavi-C V-English-03Sahand Safavi
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins ResumeRusty Adkins
 
EXECUTED PROJECTS AT DESCON ENGINEERING
EXECUTED PROJECTS AT DESCON ENGINEERINGEXECUTED PROJECTS AT DESCON ENGINEERING
EXECUTED PROJECTS AT DESCON ENGINEERINGHafiz Ayaz
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description detailsAonghus Murray
 
Seismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresSeismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresProSIM R & D Pvt. Ltd.
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
 
CURRICULUM VITAE - Zoran Erdeljanac - English
CURRICULUM VITAE - Zoran Erdeljanac - EnglishCURRICULUM VITAE - Zoran Erdeljanac - English
CURRICULUM VITAE - Zoran Erdeljanac - Englishzoran erdeljanac
 
Resume David Karbach_Feb 2015
Resume David Karbach_Feb 2015Resume David Karbach_Feb 2015
Resume David Karbach_Feb 2015David Karbach
 
PASS/START-PROF What's new in 4.84 version
PASS/START-PROF What's new in 4.84 versionPASS/START-PROF What's new in 4.84 version
PASS/START-PROF What's new in 4.84 versionAlex Matveev
 
Seismic Qualification of Nuclear Power Plant equipments
Seismic Qualification of Nuclear Power Plant equipmentsSeismic Qualification of Nuclear Power Plant equipments
Seismic Qualification of Nuclear Power Plant equipmentsPradeep Satyanarayana
 
Solidworks Portfolio
Solidworks PortfolioSolidworks Portfolio
Solidworks PortfolioJustin Bahr
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restorationFairfax County
 

Was ist angesagt? (18)

Safavi-C V-English-03
Safavi-C V-English-03Safavi-C V-English-03
Safavi-C V-English-03
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins Resume
 
EXECUTED PROJECTS AT DESCON ENGINEERING
EXECUTED PROJECTS AT DESCON ENGINEERINGEXECUTED PROJECTS AT DESCON ENGINEERING
EXECUTED PROJECTS AT DESCON ENGINEERING
 
Reda cv en
Reda cv enReda cv en
Reda cv en
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
 
Seismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresSeismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear Structures
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
 
UKUMA OKUHLE PROJECTS & TRADING PTY PROFILE
UKUMA OKUHLE PROJECTS & TRADING PTY PROFILEUKUMA OKUHLE PROJECTS & TRADING PTY PROFILE
UKUMA OKUHLE PROJECTS & TRADING PTY PROFILE
 
CURRICULUM VITAE - Zoran Erdeljanac - English
CURRICULUM VITAE - Zoran Erdeljanac - EnglishCURRICULUM VITAE - Zoran Erdeljanac - English
CURRICULUM VITAE - Zoran Erdeljanac - English
 
Resume David Karbach_Feb 2015
Resume David Karbach_Feb 2015Resume David Karbach_Feb 2015
Resume David Karbach_Feb 2015
 
PASS/START-PROF What's new in 4.84 version
PASS/START-PROF What's new in 4.84 versionPASS/START-PROF What's new in 4.84 version
PASS/START-PROF What's new in 4.84 version
 
Cv english
Cv englishCv english
Cv english
 
Jack Oler 1
Jack Oler 1Jack Oler 1
Jack Oler 1
 
Seismic Qualification of Nuclear Power Plant equipments
Seismic Qualification of Nuclear Power Plant equipmentsSeismic Qualification of Nuclear Power Plant equipments
Seismic Qualification of Nuclear Power Plant equipments
 
Seismic capabilties - ProSIM
Seismic capabilties - ProSIMSeismic capabilties - ProSIM
Seismic capabilties - ProSIM
 
Solidworks Portfolio
Solidworks PortfolioSolidworks Portfolio
Solidworks Portfolio
 
anuj cv
anuj cvanuj cv
anuj cv
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
 

Ähnlich wie Projects alrawan

Ähnlich wie Projects alrawan (20)

Hesham Saafan C.V.1
Hesham Saafan C.V.1Hesham Saafan C.V.1
Hesham Saafan C.V.1
 
CV - AGK LinkedIn
CV - AGK LinkedInCV - AGK LinkedIn
CV - AGK LinkedIn
 
Transheat profile presentationnew
Transheat   profile presentationnewTransheat   profile presentationnew
Transheat profile presentationnew
 
wathiq alanbaki
wathiq alanbakiwathiq alanbaki
wathiq alanbaki
 
MEP JUGAADS.pptx
MEP JUGAADS.pptxMEP JUGAADS.pptx
MEP JUGAADS.pptx
 
New Sands Retreatment Plant 2
New Sands Retreatment Plant 2New Sands Retreatment Plant 2
New Sands Retreatment Plant 2
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
 
Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosnia
 
Derventa City WW Project
Derventa City WW ProjectDerventa City WW Project
Derventa City WW Project
 
COBRA PRESENTATION
COBRA  PRESENTATIONCOBRA  PRESENTATION
COBRA PRESENTATION
 
eng.ahmad fathi C.V
eng.ahmad fathi C.Veng.ahmad fathi C.V
eng.ahmad fathi C.V
 
tanajib
tanajibtanajib
tanajib
 
Small & Large scale review list
Small & Large scale review listSmall & Large scale review list
Small & Large scale review list
 
Attleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station RehabilitationAttleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station Rehabilitation
 
My Cv 05-2014
My Cv 05-2014My Cv 05-2014
My Cv 05-2014
 
Ws project ozurgeti, georgia
Ws project ozurgeti, georgiaWs project ozurgeti, georgia
Ws project ozurgeti, georgia
 
Ozurgeti City / Water Supply Project
Ozurgeti City / Water Supply ProjectOzurgeti City / Water Supply Project
Ozurgeti City / Water Supply Project
 
Sanitary Pump Station Rehabilitation
Sanitary Pump Station RehabilitationSanitary Pump Station Rehabilitation
Sanitary Pump Station Rehabilitation
 
STEVEN J
STEVEN JSTEVEN J
STEVEN J
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
 

Projects alrawan

  • 1. Projects: 1- UNICEF projects – supplying and installing newsubmersible pumps in barrels for ras al-ain and jezzine pumping stations . The projects electromechanical duties: - Replacing the vertical multistage pumps with new submersible pumps in barrels for feeding different regions: seddqine, al bus and hanawai (all in tyre) and its all accessories with power and control cables and control cabinet. - Same duties were preformed for jezzine pumping station. - All the removed parts and accessories were delivered to the water establishment committee. 2- Mercy corps projects: The projects duties: - Replacing the wells’ submersible pumps and its accessories if needed with its power and control cables and control cabinet. - Replacing of multistage pump (booster pump) with new one (or installation of new one) with its control and power cabinet and its accessories need on suction and discharge lines. 3- UNICEF projects – supplying and operating submersible pumps for wells. The projects duties: - Replacing the wells’ submersible pumps (or installing new one) and its accessories needed with its power and control cables. - Installation of lightning protection system. - Installation of the well head accessories with different sizes as requested. - Installation of the chlorination system to supply chlorine gas to the water from the well. - Building manholes for the well head accessories with steel cover and rooms for the control cabinet and chlorination system and for the operator (if existing an operator). - Grounding and earthing system for the pipes, fence, control cabinet. - Supplying and installation of prefabricated room at different sizes. - Cyclopean concrete slab and manholes works. - Installation of steel barrels for the submersible pump (booster pump) and
  • 2. accessories (check valve, valves ...etc). 4- WARD COMPANY -DIFFERENT PUMPING STATION IN SOUTH LEBANON: The project duties: - Exploring the site for installing and connecting the new (or repaired) surge tank to the main discharge line (existing one) and its all accessories such as check valve, expansion joint (st.steel type) and valve. - Installation of the compressor for the surge tank and it’s all piping connections and electrical cables. 5- MAJLES AL-JANOUB-WARD COMPANY – SHAKRA PUMPING STATION TO BINT JBEIL AND MAIS AL-JABAL: The project consists of Mechanical and Electrical work; For the mechanical duties: - Installation of new submersible pumps with power, controland level sensors for three wells and their well head accessories. - Installation of four submersible pumps in barrels (booster pumps) to supply Bint Jbiel (connected to one collector in parallel) and three submersible pumps in barrels (booster pumps) to supply Mais al Jabal (connected to another collector in parallel also) - Installation of all needed accessories for each booster pump and on the collectors. - Installation of new surge tank on bint jbiel main line for protection and all its accessories. - Installation of chlorination system for the main suction line to supply chlorine gas for both main lines. For the electrical duties: - Installation of new sets of control cabinet represented in two sets, one for Bint Jbiel and one for Mais al Jabal with the power connections of the submersible pump. - Installation of new control cabinet for each well with the power connections.
  • 3. 6- USAid project-CDM smith (consultant)-Rehabilitation of Batoulay and Ouadi Jilo Pump Stations (two years duration): The project consists of Mechanical, civil and electrical work; For the mechanical duties: - Replacing submersible multistage pumps (for water wells) and the associated 6’’ and 8’’ pipes with the required valves and accessories (duel plate check valve, gate valve, air release valve and dismantling joint). - Replacing booster pumps (multistage pumps) with piping modification and fabrication work for the pumps suction and discharge lines (10’’, 8’’ and 6’’ pipes) with the required valves and accessories (duel plate check valve, gate valve, air release valve and dismantling joint). - High pressure welding and fabrication pipes (PN 40) with calibrating from 0 to 50 bar and supplying pressure gauge, differential pressure switch (high and law). - Supplying and installing on the wells discharge pipes located in the room below the water tank, solar ultrasonic flow meters with all accessories, solar panel and cables. - All the replacement of the booster and submersible pumps comes with replacing the main control cabinets and power and control cables. - Repairing the surge tanks and booster pumps’ inlet strainers. - Installation if different types of flow meters (electromagnetic and ultrasonic flow meters). - Designing and performed different types of welding for creating different shapes and sizes of pipes supports.
  • 4. For the electrical duties: - Replacing and repairing all the damaged and broken lights inside and outside. Installation of new external lights running at the photovoltaic cell. - Installation new air conditioning system for the cooling the new control cabinets for the booster pumps and wells pumps. - Providing power and control cables for both submersible and horizontal pumps and installation underground in galvanized conduits. - Installation of solar powered batteries for the ultrasonic flow meters. - Installation of lightning protection systems at different elevations according to the surrounding buildings-from the nimbus head to the earth (grounding) pit with all the required materials. - Testing and measuring the existing power cables by performing a megger test at different voltage values. - Installation of 6 sets of new main control cabinet for both stations and AUX. control panels with ATS cabinet. - Providing grounding cables for electrical transformers and booster pumps connected to new earth rods with resistance less than 2 ohms. For the civil duties: - Excavation and building of new man holes for different purposes. Excavation and digging for revealing power cables and 24’’ pipes. - Repairing the external of the buildings with stone gladding and water proofing products. - Removing the old red tiles from the buildings’ roofs and installing new one with new zinc gutter for rain water. - Compacting all the backfilled places with addition of layers of asphalts. - Performing frameworks-steel bars 12mm and 14mm diameter and supplying reinforced concrete (30 MPa) for new manholes of all wells with waterproof
  • 5. materials and galvanized steel vents to prevent humidity and inside the chamber with heavy duty iron covers. - Waterproofing works on the roof of water tanks after screed. Using non-shrink grout for the pads of the BPs. - Installation of new galvanized steel ladder inside the water tank and handrails after removing the old one. - Painting the internal walls of both pumping stations as required, also painting the floor with anti slip epoxy paints inside the pumping rooms of pumping stations. - Repairing all the aluminum doors and windows inside the pumping stations. General work duties: - Meeting and coordinating with the foreman for coordinating the timeline work and for solving problems if existing. - Supervising in the site in order to have a perfect work according to the design and drawings. - Performing solutions & improvement for devices according to the insulation process. Submitting reports (weekly and monthly) for the preformed jobs with photos of every activity. - Taking measurements for the installed quantities to check according to the Bill of Quantities. - Drawing the mechanical, civil and electrical drawings for the project before perform the work to have the approval of any activity, also deliver the as built drawings. - Organizing the activities sequence for the labors and foreman to finish in a perfect, professional way and with lower cost. - Submitting inspection document to the consultant after each item fulfilling. - Deliver the operation and maintenance manuals for civil, electrical and mechanical items and work. - Testing the installed electrical and mechanical machines such as booster pumps, submersible pumps …etc (startup testing procedures).