1. Regional Development Council
Northern Mindanao
BAGONG PAG-ASA ORGANIC VILLAGE
Brgy. Tacub, Kauswagan Lanao del Norte
AS OF September 30, 2021 PROGRESS PHOTOS
TOP VIEW
Target accomplishment = 80.60%
Actual Accomplishment = 78.93%
Variance = -1.67%
Remarks: 87 housing units at various stage of construction.
38 units up to roof panels 8 units up to roof frames
28 units up to assembled casted panels 13 units up to footing / wall footing
Block 2
Block 1
Block 3
Block 2
Block 1:
26 Out Of 26 Housing Units Up To Wall Assembled Panels
Al Housing Units Up To Roof Framing/Panels
Block 2:
28 Out Of 32 Housing Units Up To Wall Assembled Panels
7 Housing Units Up To Roof Framing
12 Housing Units Up To Roof Panel
Block 3:
17 Out Of 29 Housing Units Up
To Wall Assembled Panels
Block 2:
On-going roofing works