SlideShare ist ein Scribd-Unternehmen logo
1 von 18
AHPTUN SEAFOODS LLP. 
September 2014
The Old Plant Site 
• First steps involved a 
major clean up of the 
site both inside and out. 
• The Site will serve as a 
operational staging area 
and allow expansion of 
seed production 
capacity.
Cleaning Up Inside 
It was obvious that the inside 
and outside of the facility had 
not been maintained for some 
years and required a major 
clean-up, painting, repairs to 
the water and septic systems, 
and removal of dilapidated
And Outside 
The old mobile home was dismantled and 
removed.
And Outside 
571 hours have been spent on the 
clean-up and improvements at 
the Cannery Road site which 
included the removal of 11.25 
tonnes of debris.
Clean Up
Dumpster Loads
Out with the old….
Out with the old…. 
Major amount of brush removal 
and tree falling was required as 
the site was well overgrown.
….and in with the new! 
The old pump 
house had to be 
removed and a 
new one built in 
it’s place.
New Gate Installation 
A new gate was 
installed at the 
entrance to the 
property to limit 
access and provide 
some security.
Constructing the Hatchery 
• In early 2013 Ocean 
Protein began to make 
significant changes to 
the Cannery Road site. 
• Hired new Hatchery 
Manager David Shupert 
and new Hatchery 
Technicians. 
• Significant investment 
in new equipment.
Hatchery Success 
The hatchery crew has 
had success in 2014 with 
the production of Pacific 
oyster seed.
Community Benefits 
• Ocean Protein Canada, at 
peak operations in 2013, 
had 10 Sliammon First 
Nation members on payroll. 
• Sliammon members have 
been trained in First Aid, 
vessel operations, shellfish 
husbandry, shellfish 
hatchery algae and larvae 
culture techniques, 
construction, and facility 
design and implementation.
Goldberg Harvesting 
2,931 hours have been spent 
harvesting oysters from the 
Goldberg site at a total cost of 
approx $55,689.00 in labour.
Cannery Road Ramp and Float 
The old ramp and float at 
the Cannery Road site is in 
need of repair as the ramp 
has fallen into the water 
and the dock anchors 
have let go.
SE Harwood Island 
• 24 hectare sub-tidal 
geoduck aquaculture 
site – 20 year Licence of 
Occupation has been 
issued; awaiting Federal 
Aquaculture Licence. 
• 3 additional sites on 
Harwood Island under a 
BC Land Act Notation of 
Interest for the 
Sliammon Nation.
New Deepwater Site Application 
In June 2013, Ocean Protein 
on behalf of the Sliammon 
First Nation made 
application for a 1 acre 
deep-water site fronting the 
Cannery Road up-land site. 
This site is now tenured and 
licenced for the culture of 
Pacific oyster, Japanese 
Scallop and Pacific Scallop.

Weitere ähnliche Inhalte

Was ist angesagt?

Australia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project ManagerAustralia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project Manager
Niels Asjee
 
Marine_Brochure_For_Web
Marine_Brochure_For_WebMarine_Brochure_For_Web
Marine_Brochure_For_Web
Mike Bisland
 
Pipeline Abandonment Project
Pipeline Abandonment ProjectPipeline Abandonment Project
Pipeline Abandonment Project
Kathy Cain
 
Gold coast management
Gold coast managementGold coast management
Gold coast management
Noel Jenkins
 
Fall town meeting 2009 article 8
Fall town meeting 2009   article 8Fall town meeting 2009   article 8
Fall town meeting 2009 article 8
Marblehead.Works
 
ICLR Friday Forum: Tantramar Marshes Flooding (March 19, 2021)
ICLR Friday Forum: Tantramar Marshes Flooding (March 19, 2021)ICLR Friday Forum: Tantramar Marshes Flooding (March 19, 2021)
ICLR Friday Forum: Tantramar Marshes Flooding (March 19, 2021)
glennmcgillivray
 
Bahrain - Half Moon Bay Project - Project Manager
Bahrain - Half Moon Bay Project - Project ManagerBahrain - Half Moon Bay Project - Project Manager
Bahrain - Half Moon Bay Project - Project Manager
Niels Asjee
 
JG Fort Burgoyne Jan2015PRESENTATION
JG Fort Burgoyne Jan2015PRESENTATIONJG Fort Burgoyne Jan2015PRESENTATION
JG Fort Burgoyne Jan2015PRESENTATION
Jane Garrett
 

Was ist angesagt? (20)

Australia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project ManagerAustralia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project Manager
 
Pavel, joseph
Pavel, josephPavel, joseph
Pavel, joseph
 
Marine_Brochure_For_Web
Marine_Brochure_For_WebMarine_Brochure_For_Web
Marine_Brochure_For_Web
 
Ec rmx cs_ca_calpine
Ec rmx cs_ca_calpineEc rmx cs_ca_calpine
Ec rmx cs_ca_calpine
 
Masterplan presentation v13
Masterplan presentation v13Masterplan presentation v13
Masterplan presentation v13
 
Pipeline Abandonment Project
Pipeline Abandonment ProjectPipeline Abandonment Project
Pipeline Abandonment Project
 
Amendment Requests for Whitewater Reach Protection Project
Amendment Requests for Whitewater Reach Protection ProjectAmendment Requests for Whitewater Reach Protection Project
Amendment Requests for Whitewater Reach Protection Project
 
Waikorire/Pilot Bay presented by Caryn Rawlinson
Waikorire/Pilot Bay presented by Caryn RawlinsonWaikorire/Pilot Bay presented by Caryn Rawlinson
Waikorire/Pilot Bay presented by Caryn Rawlinson
 
Gold coast management
Gold coast managementGold coast management
Gold coast management
 
Fall town meeting 2009 article 8
Fall town meeting 2009   article 8Fall town meeting 2009   article 8
Fall town meeting 2009 article 8
 
Marina Barrage
Marina BarrageMarina Barrage
Marina Barrage
 
quarrying
quarryingquarrying
quarrying
 
Glen Echo land purchase
Glen Echo land purchaseGlen Echo land purchase
Glen Echo land purchase
 
QB Poster4
QB Poster4QB Poster4
QB Poster4
 
Shark Bay Upgrade
Shark Bay UpgradeShark Bay Upgrade
Shark Bay Upgrade
 
ICLR Friday Forum: Tantramar Marshes Flooding (March 19, 2021)
ICLR Friday Forum: Tantramar Marshes Flooding (March 19, 2021)ICLR Friday Forum: Tantramar Marshes Flooding (March 19, 2021)
ICLR Friday Forum: Tantramar Marshes Flooding (March 19, 2021)
 
Bahrain - Half Moon Bay Project - Project Manager
Bahrain - Half Moon Bay Project - Project ManagerBahrain - Half Moon Bay Project - Project Manager
Bahrain - Half Moon Bay Project - Project Manager
 
VSL_____(3190)
VSL_____(3190)VSL_____(3190)
VSL_____(3190)
 
JG Fort Burgoyne Jan2015PRESENTATION
JG Fort Burgoyne Jan2015PRESENTATIONJG Fort Burgoyne Jan2015PRESENTATION
JG Fort Burgoyne Jan2015PRESENTATION
 
Buzzards Bay Coalition 2015 Annual Report
Buzzards Bay Coalition 2015 Annual ReportBuzzards Bay Coalition 2015 Annual Report
Buzzards Bay Coalition 2015 Annual Report
 

Andere mochten auch

Chapters 20 and 21 vocab student version
Chapters 20 and 21 vocab student versionChapters 20 and 21 vocab student version
Chapters 20 and 21 vocab student version
eschott
 
Chapter 4 federalism quiz
Chapter 4 federalism quizChapter 4 federalism quiz
Chapter 4 federalism quiz
eschott
 
Judicial branch
Judicial branchJudicial branch
Judicial branch
eschott
 
Discours pm décl gouv 10 12 2013
Discours pm décl gouv  10 12 2013Discours pm décl gouv  10 12 2013
Discours pm décl gouv 10 12 2013
Roland Arens
 
Energyandutilities 110208103027-phpapp02
Energyandutilities 110208103027-phpapp02Energyandutilities 110208103027-phpapp02
Energyandutilities 110208103027-phpapp02
joindanville
 
Ch. 17 the economic system
Ch. 17 the economic systemCh. 17 the economic system
Ch. 17 the economic system
eschott
 
American Foreign Policy
American Foreign PolicyAmerican Foreign Policy
American Foreign Policy
eschott
 
Macroeconomics 09
Macroeconomics 09Macroeconomics 09
Macroeconomics 09
eschott
 
Public opinion and the mass media powerpoint
Public opinion and the mass media powerpointPublic opinion and the mass media powerpoint
Public opinion and the mass media powerpoint
eschott
 

Andere mochten auch (13)

Chapters 20 and 21 vocab student version
Chapters 20 and 21 vocab student versionChapters 20 and 21 vocab student version
Chapters 20 and 21 vocab student version
 
Chapter 4 federalism quiz
Chapter 4 federalism quizChapter 4 federalism quiz
Chapter 4 federalism quiz
 
Dada2
Dada2Dada2
Dada2
 
Judicial branch
Judicial branchJudicial branch
Judicial branch
 
Changes 2011
Changes 2011Changes 2011
Changes 2011
 
Discours pm décl gouv 10 12 2013
Discours pm décl gouv  10 12 2013Discours pm décl gouv  10 12 2013
Discours pm décl gouv 10 12 2013
 
Energyandutilities 110208103027-phpapp02
Energyandutilities 110208103027-phpapp02Energyandutilities 110208103027-phpapp02
Energyandutilities 110208103027-phpapp02
 
2008 aout b protegez vous
2008 aout b protegez vous2008 aout b protegez vous
2008 aout b protegez vous
 
Optica
OpticaOptica
Optica
 
Ch. 17 the economic system
Ch. 17 the economic systemCh. 17 the economic system
Ch. 17 the economic system
 
American Foreign Policy
American Foreign PolicyAmerican Foreign Policy
American Foreign Policy
 
Macroeconomics 09
Macroeconomics 09Macroeconomics 09
Macroeconomics 09
 
Public opinion and the mass media powerpoint
Public opinion and the mass media powerpointPublic opinion and the mass media powerpoint
Public opinion and the mass media powerpoint
 

Ähnlich wie 2014pp

WS_May_News Q1 2015 Final
WS_May_News Q1 2015 FinalWS_May_News Q1 2015 Final
WS_May_News Q1 2015 Final
Jim Jones
 
Australia - Ichthys GEP Project - Project Manager
Australia - Ichthys GEP Project - Project ManagerAustralia - Ichthys GEP Project - Project Manager
Australia - Ichthys GEP Project - Project Manager
Niels Asjee
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
Mike Vernon
 
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
Erin Vieira
 

Ähnlich wie 2014pp (20)

Orlando 2015
Orlando 2015Orlando 2015
Orlando 2015
 
WS_May_News Q1 2015 Final
WS_May_News Q1 2015 FinalWS_May_News Q1 2015 Final
WS_May_News Q1 2015 Final
 
Auxico Resources Corporate Presentation
Auxico Resources Corporate PresentationAuxico Resources Corporate Presentation
Auxico Resources Corporate Presentation
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
 
Escravos
EscravosEscravos
Escravos
 
Gef iw eco-skn_project_cwwa-conference_presentation_hsahely_oct2021
Gef iw eco-skn_project_cwwa-conference_presentation_hsahely_oct2021Gef iw eco-skn_project_cwwa-conference_presentation_hsahely_oct2021
Gef iw eco-skn_project_cwwa-conference_presentation_hsahely_oct2021
 
(XIMB) Sustainability - Aquaculture industry
(XIMB) Sustainability - Aquaculture industry(XIMB) Sustainability - Aquaculture industry
(XIMB) Sustainability - Aquaculture industry
 
Cronulla wastewater treatment plant
Cronulla wastewater treatment plantCronulla wastewater treatment plant
Cronulla wastewater treatment plant
 
Australia - Ichthys GEP Project - Project Manager
Australia - Ichthys GEP Project - Project ManagerAustralia - Ichthys GEP Project - Project Manager
Australia - Ichthys GEP Project - Project Manager
 
Highbank Resources - MDRC Presentation
Highbank Resources - MDRC PresentationHighbank Resources - MDRC Presentation
Highbank Resources - MDRC Presentation
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
Nov 16 2016 nps presentation west pond[2995]
Nov 16 2016 nps presentation west pond[2995]Nov 16 2016 nps presentation west pond[2995]
Nov 16 2016 nps presentation west pond[2995]
 
Jeff Polenik, Robindale Energy,"Leanor GFCC - A Positive Impact
Jeff Polenik, Robindale Energy,"Leanor GFCC - A Positive ImpactJeff Polenik, Robindale Energy,"Leanor GFCC - A Positive Impact
Jeff Polenik, Robindale Energy,"Leanor GFCC - A Positive Impact
 
Adrian shepherd
Adrian shepherdAdrian shepherd
Adrian shepherd
 
Peatland Rewetting in the South West
Peatland Rewetting in the South WestPeatland Rewetting in the South West
Peatland Rewetting in the South West
 
ES_Kokanee_poster_final
ES_Kokanee_poster_finalES_Kokanee_poster_final
ES_Kokanee_poster_final
 
10 090.public consultation
10 090.public consultation10 090.public consultation
10 090.public consultation
 
Overliner or Landfill Mining?
Overliner or Landfill Mining?Overliner or Landfill Mining?
Overliner or Landfill Mining?
 
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
 
Channel June 2018: Community Information Session
Channel June 2018: Community Information SessionChannel June 2018: Community Information Session
Channel June 2018: Community Information Session
 

Kürzlich hochgeladen

Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot ReportFuture of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Dubai Multi Commodity Centre
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...
srcw2322l101
 
Constitution of Company Article of Association
Constitution of Company Article of AssociationConstitution of Company Article of Association
Constitution of Company Article of Association
seri bangash
 

Kürzlich hochgeladen (20)

Aptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdfAptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdf
 
Raising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE VenturesRaising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE Ventures
 
FEXLE- Salesforce Field Service Lightning
FEXLE- Salesforce Field Service LightningFEXLE- Salesforce Field Service Lightning
FEXLE- Salesforce Field Service Lightning
 
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdfبروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
 
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot ReportFuture of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
 
Toyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsToyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & Transformations
 
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptxBlinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
 
Equinox Gold Corporate Deck May 24th 2024
Equinox Gold Corporate Deck May 24th 2024Equinox Gold Corporate Deck May 24th 2024
Equinox Gold Corporate Deck May 24th 2024
 
Falcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small BusinessesFalcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small Businesses
 
Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...
 
Your Work Matters to God RestorationChurch.pptx
Your Work Matters to God RestorationChurch.pptxYour Work Matters to God RestorationChurch.pptx
Your Work Matters to God RestorationChurch.pptx
 
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdfDaftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
 
Engagement Rings vs Promise Rings | Detailed Guide
Engagement Rings vs Promise Rings | Detailed GuideEngagement Rings vs Promise Rings | Detailed Guide
Engagement Rings vs Promise Rings | Detailed Guide
 
Constitution of Company Article of Association
Constitution of Company Article of AssociationConstitution of Company Article of Association
Constitution of Company Article of Association
 
Sedex Members Ethical Trade Audit (SMETA) Measurement Criteria
Sedex Members Ethical Trade Audit (SMETA) Measurement CriteriaSedex Members Ethical Trade Audit (SMETA) Measurement Criteria
Sedex Members Ethical Trade Audit (SMETA) Measurement Criteria
 
HR and Employment law update: May 2024.
HR and Employment law update:  May 2024.HR and Employment law update:  May 2024.
HR and Employment law update: May 2024.
 
How to refresh to be fit for the future world
How to refresh to be fit for the future worldHow to refresh to be fit for the future world
How to refresh to be fit for the future world
 
stock price prediction using machine learning
stock price prediction using machine learningstock price prediction using machine learning
stock price prediction using machine learning
 
How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?
 

2014pp

  • 1. AHPTUN SEAFOODS LLP. September 2014
  • 2. The Old Plant Site • First steps involved a major clean up of the site both inside and out. • The Site will serve as a operational staging area and allow expansion of seed production capacity.
  • 3. Cleaning Up Inside It was obvious that the inside and outside of the facility had not been maintained for some years and required a major clean-up, painting, repairs to the water and septic systems, and removal of dilapidated
  • 4. And Outside The old mobile home was dismantled and removed.
  • 5. And Outside 571 hours have been spent on the clean-up and improvements at the Cannery Road site which included the removal of 11.25 tonnes of debris.
  • 8. Out with the old….
  • 9. Out with the old…. Major amount of brush removal and tree falling was required as the site was well overgrown.
  • 10. ….and in with the new! The old pump house had to be removed and a new one built in it’s place.
  • 11. New Gate Installation A new gate was installed at the entrance to the property to limit access and provide some security.
  • 12. Constructing the Hatchery • In early 2013 Ocean Protein began to make significant changes to the Cannery Road site. • Hired new Hatchery Manager David Shupert and new Hatchery Technicians. • Significant investment in new equipment.
  • 13. Hatchery Success The hatchery crew has had success in 2014 with the production of Pacific oyster seed.
  • 14. Community Benefits • Ocean Protein Canada, at peak operations in 2013, had 10 Sliammon First Nation members on payroll. • Sliammon members have been trained in First Aid, vessel operations, shellfish husbandry, shellfish hatchery algae and larvae culture techniques, construction, and facility design and implementation.
  • 15. Goldberg Harvesting 2,931 hours have been spent harvesting oysters from the Goldberg site at a total cost of approx $55,689.00 in labour.
  • 16. Cannery Road Ramp and Float The old ramp and float at the Cannery Road site is in need of repair as the ramp has fallen into the water and the dock anchors have let go.
  • 17. SE Harwood Island • 24 hectare sub-tidal geoduck aquaculture site – 20 year Licence of Occupation has been issued; awaiting Federal Aquaculture Licence. • 3 additional sites on Harwood Island under a BC Land Act Notation of Interest for the Sliammon Nation.
  • 18. New Deepwater Site Application In June 2013, Ocean Protein on behalf of the Sliammon First Nation made application for a 1 acre deep-water site fronting the Cannery Road up-land site. This site is now tenured and licenced for the culture of Pacific oyster, Japanese Scallop and Pacific Scallop.