P6 Team Member –
Implementation Stories
Prepared by:
Luka Novosel
Primavera Consultant
Primakon
How to Make the Project Manager's
Life Easier
Session ID#: 200910
@lunovosel
About me…
■  Masters degree in Electrical Engineering
■  Primavera functional & technical consultant since 2006
■  PMI PMP certified since 2010
■  Oracle Primavera P6 & P6 R8 Implementation Specialist
■  Oracle Primavera EPPM trainer
■  PMP preparation trainer
■  Primavera EPPM API application designer & developer
■  Primavera EPPM SDK application designer & developer
About us…
■  Primakon is a privately owned consulting company
▪  www.primakon.com
■  15+ years of experience in Primavera implementations
■  Offers customer tailored education in the area of PM
methodologies and Primavera products
■  Positive references in a wide range of industries (from finance
sector to construction)
■  Present in EU & SE European markets
Presentation Overview
■  What is P6 Team Member ?
■  How to set it up
■  P6 Team Member as a part of contract management system
■  P6 Team Member in procurement management
■  P6 Team Member evolution 8.2 – 8.4
■  Lessons learned
■  Q & A
What is P6 Team Member ?
This is a subtitle or bulleted list
P6 Team Member as a Part of P6 EPPM
Suite
■  The P6 Team Member application suite is designed for project
team members to status their activities in an easy to use
interface that does not require them to learn P6.
■  P6 Team Member suite consists of:
▪  P6 Team Member web application
▪  P6 Team Member iOS application
▪  P6 Team Member email status services
■  P6 Team Member suite was introduced as a part of P6 EPPM
in version 8.2 (December 2011)
■  8.3 had a large number of improvements on 8.2
■  In 8.4 the former Timesheet (Progress Reporter) and P6
Team Member application are integrated.
P6 Team Member App vs Team Member
License
■  Old Primavera users are familiar with the license type called
Team Member
▪  That license covered p6 web, documents, issues and
timesheets
■  Team Member license in P6.2.1 to R8.1 and P6 R8.2 are not
the same thing
P6.2.1		 P6	R8.2
P6 Team Member App Licenses Cont.
■  In release 8.3 this confusion was clarified with the creation of
a new license module – Contributor (formerly Team Member)
■  In release 8.4 Team Member Interface was renamed again to
Team Member
■  Tip: If you are upgrading Primavera form release 8.1 or
previous to a newer one, remove the licenses to users that
have Team Member and manually add them after the
upgrade.
P6	R8.3	 P6	R8.4
P6 Team Member Web Application
5 Reasons Why to Use It
■  In this presentation we will focus on P6 Team Member web
application
■  5 reasons to implement this in your environment
▪  1) Easy to use
▪  2) Modern design
▪  3) Short learning curve
▪  4) Accessible from almost every imaginable place
▪  5) Ability to collect project information from numerous
contributors
How to Set Up P6 Team Member
Application
Steps to Set Up P6 Team Member Application
■  Steps needed to set up P6 Team Member application to work
on your project
1.  Set Project Preferences
2.  Define team member user and assign team member licence to
that user (under Administer / User access)
3.  Give the user access to permitted activities
4.  Set Review Required field on activities where you want to
review status updates
Steps to Set Up P6 Team Member Application
- Set Project Preferences
■  1) Set Project Preferences
▪  Tick Allow reviews for Team Member status updates
▪  Tick Review Required for new activities
▪  Define Reviewer for this project
▪  Set which data team member will see in application
P6	R	8.2	
P6	R	8.4
Steps to Set Up P6 Team Member Application
– Team Member Module Access
■  Define team member user and assign team member licence to that
user (under Administer / User access)
▪  This is needed if user will have access only to P6 Team Member
application suite
▪  Tip: User can not be assigned as Contributor and Team
Member at the same time
Steps to Set Up P6 Team Member Application
– User Access to Permitted Activities
■  There are 3 main ways to make activities visible in Team
Member to a specific user
■  1) Assign user as Activity Owner in P6 (Field Owner in Activity
view)
■  2) Assign user as a resource on activity (all assigned
resources will see activities in P6 Team Member and will be
able to update their resource assignment
Steps to Set Up P6 Team Member Application
– User Access to Permitted Activities Cont.
■  3) Assign Team Member filter to user (under Administration /
User Access) – field Team Member Filter
▪  Up to 5 different filters can be assigned to the user
▪  Activity Global and EPS codes + resources and roles can be
used
Steps to Set Up P6 Team Member Application
– Set Review Required Flag
■  4) Define which activities status update approval is needed
▪  This is per activity setting
▪  Status updates from P6 Team Member application on activities
with Review Required flag will need approval from assigned
reviewer
▪  Status updates from P6 Team Member application on activities
without this flag will be applied automatically
Use Case 1
P6 Team Member as a Part of
Contract Management System
Business Need
■  2011, Project charter for CMS was defined
■  In late 2011 during the detail project scope definition P6 Team
Member was introduced (rel. 8.2)
■  After P6 Team Member evaluation it fitted the system
perfectly
■  It will be used for :
▪  Key contract milestones approval
▪  Key process milestones update
System Description
■  Contract Management System Parts
▪  Document Management
▪  Reporting
▪  Primavera P6 Schedules
▪  Portal
▪  P6 Team Member
■  All the systems are integrated and information shared across
whole CMS
■  Primavera P6 is used for project schedule development and
schedule updates
Process Overview
1.  After contract signature the contractor develops schedule with
the representative of the buyer
2.  In separate WBS all key project milestones are created
3.  On those milestones all related documents needed for delivery
acceptance are assigned
1.  WP and Docs feature is used
2.  Document name and category are defined
—  Can be “Submitted for Acceptance” or
—  “Submitted for Information”
4.  When the schedule is approved all the documents are created
in Document Management System
5.  When physical document is uploaded in DMS a corresponding
document URL is created in P6 as a public URL
Process Overview Cont.
6.  Document versioning and approval process are done in
DMS
▪  Document status is transferred to P6
7.  When all the approval documents are approved the
contractor ‘ticks’ contractual milestone in P6 Team Member
▪  Submission date is preserved
8.  Buyer’s representative approves changes through Status
Review in P6 Web
▪  Approval date is preserved
9.  Same process with or without document management part
can be applied in the main schedule as well, if agreed.
The Process in Detail:
P6 Project For the New Contract
■  New P6 Project is created for signed contract
■  Project preferences for Team Member are configured
▪  Review required is enabled and reviewer is defined
▪  Activity owner will be used
for status updates
▪  UDF Fields are defined
The Process in Detail
Develop Schedule
■  Project schedule is developed after contract signature
■  Two main WBS level 1 are created
▪  Contract Milestones
▪  Schedule – project schedule
■  During schedule development “Review Required”
activities are identified and Owner is assigned
The Process in Detail
Document Creation
■  Documents are added through WP & Docs feature
▪  Only Title and Document Category are defined
▪  Under “Related Items” documents are assigned to activity
▪  Data is saved
The Process in Detail
Document Creation Cont.
■  Hundreds of documents, different contract milestones …
■  Quite a painful job to do in P6 Web
■  To avoid this, we’ve developed a simple Java desktop
application that will do the hard job for us
■  It parses Excel, creates Documents and links to activities
■  Link is bi-directional so Documents can be updated / deleted
as well
■  Used only in the planning phase of a project
The Process in Detail
Documents Status Tracking
■  In DMS, documents are managed, approved, rejected etc.
■  In P6 we transfer only
▪  Unique URL to the document – that way user can access related
document directly from Primavera schedule
▪  Document Status
■  Click on a view document will open document in new tab in a
browser
The Process in Detail
Documents Status Tracking Cont.
■  To help the approver we’ve created two Activity level UDF
fields
▪  # of Docs. for Approval – total number of documents that need
to be approved for this delivery milestone
▪  # of Approved Docs. – number of approved documents in DMS
(Documents with status “Approved”)
■  Custom developed background job is populating those 2
fields
The Process in Detail
P6 Team Member Status Update
■  The contractor submits status updates for contractual
milestones through P6 Team Member
■  Green tick means activity (milestone) is finished
■  In Started: Actual Start is defined
■  Save change
The Process in Detail
Approve Changes
■  After the contractor saves the data in
P6 Team Member, Reviewer is
notified
■  In the Activity window a pop-up will
appear
■  If the pop-up disappears the same
window can be accessed from
Action / Review Status Updates
The Process in Detail
Approve Changes Cont.
■  In Review Required window Reviewer can:
▪  Accept changes
▪  Override changes
▪  Put changes on hold and inform Status Updater of the reasons
for holding changes
■  More information is available
under More…
The Process in Detail
P6 Team Member Status Update
■  The contractor submits status updates for contractual
milestones through P6 Team Member
■  Green tick means activity (milestone) is finished
■  In Started: Actual Start is defined
■  Save change
The Process in Detail
Approve Changes Cont.
■  In this situation:
▪  Number of approved Docs is lower then total number of
documents for approval
▪  The reviewer will put activity on-hold
▪  He will send an email to the submitter with the reason why the
status is put on-hold
The Process in Detail
Approval Overview
■  The Reviewer and contractor can check the information and
dates when the status was submitted and approved
The Process in Detail
Approval Overview - Tips
■  Tip: If you don’t see “Update history” tab,
enable it by selecting
right click on tabs / customize tabs
■  Tip: If you don’t see data in Update history and you are sure
that there should be data, check “Show updates for” menu
▪  Default value is: Assignments – if you are using Activity that can
be confusing
Summary
■  Why P6 Team Member in this particular case
▪  Approval process was the main driver in this implementation
▪  Tracking of submission and approval dates
▪  Tracking of all changes done in the process
▪  Easy to use
▪  User can have read-only access to specific activity and still be
able to update it through P6 Team Member
Use Case 2
P6 Team Member as a Part of
Procurement Management Process
Business Need
■  Procurement office is not in direct connection with Project
Manager
■  Public procurement procedures have a great impact on
project schedule
■  Procurement officers want simple application
■  Project Managers want up-to-date information about
procurement statuses that affect their project
■  Easy access to procurement documents
■  Easy communication
■  Easy way to input data about procurements
System Description
■  P6 Team Member is used for update procurement schedules
■  Procurement schedule templates are defined with all relevant
▪  UDF fields
▪  Notebooks
▪  Activity codes
■  We are using Oracle UCM for document management
■  All procurement documentation is uploaded automatically to
P6 and UCM
■  Implementation started with P6 Team Member R8.3 and will
be updated to 8.4
Process Overview
■  System administrator creates procurement from appropriate
template
■  Responsible procurement officer is assigned as Activity
Owner on all procurement activities
■  All available documentation is uploaded to P6
■  Procurement officer updates activity statuses as procurement
progress
▪  Milestones
▪  Activities
■  Discussion is used for official collaboration
■  Notebooks will be used for notes (8.4 feature)
■  UDF and Activity codes are used for assigning attributes on
activities
System Preparation
■  System administrator creates procurement from the
appropriate template
■  All predefined Team Member settings are preserved
■  Review Required is not enabled in this case
■  Responsible procurement officer is assigned as Activity Owner
P6 Team Member for Procurement Officer
■  Team Member is the main tool for procurement officer
Procurement Officer Tasks :
Communication With Project Manager
■  For communication with the
Project Manager we are
using “Discussions”
■  New feature available across
whole P6 platform
■  Track who and when
■  (!) No undo or delete
■  Best way to communicate
between different
applications (i.e. P6 Team
Member and P6 web)
■  New discussions are marked with red number
Procurement Officer Tasks
Update Procurement Tasks
■  Milestones are checked when done
■  Activities can have predefined steps
■  By selecting Start the activity is started
■  Actual start date can be modified
Procurement Officer Tasks
Check Procurement Documents
■  By selecting activity the user can access documents assigned
to that activity (in this case DMS is Oracle UCM)
■  Document can be viewed
and downloaded from this
window
Procurement Officer Tasks :
View / Edit Activity Information
■  The user can View and edit predefined User Defined Fields
and Activity Codes
■  In our case 3 fields are available
▪  Read only – procurement type
▪  UDF – procurement code
▪  UDF – expected procurement amount
■  In addition to that, Notebook topics can be viewed and edited
(rel. 8.4) through P6 Team Member
P6 Web
■  In P6 Web procurement manager is doing the portfolio
analysis
■  All data changes are controlled
■  The project Manager can update and update project schedule
according to information received
Summary
■  Why use P6 Team Member in this case ?
▪  Simple application for users that do not know a lot about
schedules
▪  Easy communication between Project Manager (using P6 client
or Web ) and Procurement Officer (using P6 Team Member)
▪  Simple access to procurement documents
▪  Project Manager has up-to-date information about procurement
status
▪  Procurement Office Manager has overview of all procurements
through P6
▪  User adoption time to new tool is very short
P6 Team Member Evolution
R8.2 - > R8.4
P6 Team Member R8.2
P6 Team Member R 8.3
P6 Team Member R 8.4
Lessons Learned
The Good Things
■  Simple application
■  Easy and quick user adoption
■  Cheaper than full P6 Web
■  Compatible with all devices
■  Update history
▪  All information about changes is preserved
▪  Useful as an audit log
The Not So Good Things
■  First version had limited functionalities
■  Occasional bugs (i.e. 25 % bug)
■  On hold activities are poorly managed in P6 Team Member
▪  No easy way to identify on hold activities in P6 Team Member
■  Very small number of fields are visible in P6 Team Member
▪  i.e. not possible to see baseline date, baseline values, data date
■  ALL the data is lost if the project is exported via XER or XML
file
▪  This means that all update history will be lost !
■  Update history is not visible in P6 Client
Questions ?
?
Luka Novosel, M.Eng, PMP
Certified Oracle Primavera P6 EPPM Implementation Specialist
Primakon ltd
ln@primakon.com
hr.linkedin.com/in/lukanovosel
www.primakon.com
Please complete the session
evaluation
We appreciate your feedback and insight
You may complete the session evaluation either
on paper or online via the mobile app
■  Our	purpose	is	to	inform	and	educate	our	members	on	current	and	future	
func;onality	of	Oracle	Primavera	products,	while	offering	a	forum	for	peers	to	
share	their	experience	and	knowledge	in	the	use	of	Primavera.		
■  Educa;onal	opportuni;es	across	the	Primavera	product	suite	
■  Online	Learning	Series		August	17th	–	September	4th		
■  Call	for	presenta;on	opening	April	27th		
■  Monthly	Community	Calls		
■  3rd	Thursday	of	the	month	at	1:00	pm	ET	
■  Networking	with	other	users	within	the	Primavera	community	
■  Partnering	with	Oracle	Primavera	to	meet	the	needs	of	our	diverse	
membership.	
■  Membership	is	open	to	anyone	with	an	interest	in	the	Oracle	Primavera	products,	
with	no	dues	for	membership.	All	members	can	vote	on	maRers	brought	before	
the	OPSIG.	Membership	requests	may	be	reviewed	by	the	OPSIG	board.		
OPSIG is the home for
Primavera Users

Weitere ähnliche Inhalte

Was ist angesagt?

213 r 87 - guide for structural lightweight aggregate concret
213 r 87 - guide for structural lightweight aggregate concret213 r 87 - guide for structural lightweight aggregate concret
213 r 87 - guide for structural lightweight aggregate concret
MOHAMMED SABBAR
 
Tutorial Staad-Pro
Tutorial Staad-ProTutorial Staad-Pro
Tutorial Staad-Pro
Nabeh Wildan
 

Was ist angesagt? (20)

Importing Survey Data | ACAD Civil 3D | Total Station |
Importing Survey Data | ACAD Civil 3D | Total Station |Importing Survey Data | ACAD Civil 3D | Total Station |
Importing Survey Data | ACAD Civil 3D | Total Station |
 
Wind Load of Wind Turbine Tower
Wind Load of Wind Turbine TowerWind Load of Wind Turbine Tower
Wind Load of Wind Turbine Tower
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Che 1 pile foundation
Che 1 pile foundationChe 1 pile foundation
Che 1 pile foundation
 
Boq dupa
Boq dupaBoq dupa
Boq dupa
 
6. safe users-guide
6.  safe users-guide6.  safe users-guide
6. safe users-guide
 
Spun pile
Spun pileSpun pile
Spun pile
 
WIND ISSUES IN THE DESIGN OF TALL BUILDINGS
WIND ISSUES IN THE DESIGN OF TALL BUILDINGSWIND ISSUES IN THE DESIGN OF TALL BUILDINGS
WIND ISSUES IN THE DESIGN OF TALL BUILDINGS
 
213 r 87 - guide for structural lightweight aggregate concret
213 r 87 - guide for structural lightweight aggregate concret213 r 87 - guide for structural lightweight aggregate concret
213 r 87 - guide for structural lightweight aggregate concret
 
Ycef presentaion derivation of wind loading upload
Ycef presentaion derivation of wind loading uploadYcef presentaion derivation of wind loading upload
Ycef presentaion derivation of wind loading upload
 
Staadpro manual
Staadpro manualStaadpro manual
Staadpro manual
 
AL ALIA TRADING & CONTRACTING WLL
AL ALIA TRADING & CONTRACTING WLL AL ALIA TRADING & CONTRACTING WLL
AL ALIA TRADING & CONTRACTING WLL
 
89505650 concrete-beam-and-slab-design-using-prokon
89505650 concrete-beam-and-slab-design-using-prokon89505650 concrete-beam-and-slab-design-using-prokon
89505650 concrete-beam-and-slab-design-using-prokon
 
Jr. Civil Engineer Portfolio
Jr. Civil Engineer PortfolioJr. Civil Engineer Portfolio
Jr. Civil Engineer Portfolio
 
Design wind load
Design wind loadDesign wind load
Design wind load
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTION
 
63310234 sacs-example
63310234 sacs-example63310234 sacs-example
63310234 sacs-example
 
Tutorial Staad-Pro
Tutorial Staad-ProTutorial Staad-Pro
Tutorial Staad-Pro
 
PHC-Pile-Brochure.pdf
PHC-Pile-Brochure.pdfPHC-Pile-Brochure.pdf
PHC-Pile-Brochure.pdf
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 

Ähnlich wie P6 Team Member – Implementation Stories

Sahar Kamal's CV _2016
Sahar Kamal's CV _2016Sahar Kamal's CV _2016
Sahar Kamal's CV _2016
Sahar Kamal
 

Ähnlich wie P6 Team Member – Implementation Stories (20)

P6 Team Member – An Implementation Story (How to make Project Manager's life ...
P6 Team Member – An Implementation Story (How to make Project Manager's life ...P6 Team Member – An Implementation Story (How to make Project Manager's life ...
P6 Team Member – An Implementation Story (How to make Project Manager's life ...
 
Project Management Methodology for Site Launches
Project Management Methodology for Site LaunchesProject Management Methodology for Site Launches
Project Management Methodology for Site Launches
 
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
 
mg7.pptx
mg7.pptxmg7.pptx
mg7.pptx
 
Configuring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project UpdatesConfiguring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project Updates
 
Primavera- Increasing Utilization through Change Management
Primavera- Increasing Utilization through Change ManagementPrimavera- Increasing Utilization through Change Management
Primavera- Increasing Utilization through Change Management
 
E success client-software-development
E success client-software-developmentE success client-software-development
E success client-software-development
 
HPE Project and Portfolio Manager and Agile Manager
HPE Project and Portfolio Manager and Agile ManagerHPE Project and Portfolio Manager and Agile Manager
HPE Project and Portfolio Manager and Agile Manager
 
Technical Webinar: By the (Play) Book: The Agile Practice at OutSystems
Technical Webinar: By the (Play) Book: The Agile Practice at OutSystemsTechnical Webinar: By the (Play) Book: The Agile Practice at OutSystems
Technical Webinar: By the (Play) Book: The Agile Practice at OutSystems
 
B E Aerospace case study - Oracle Primavera P6 Collaborate 14
B E Aerospace case study - Oracle Primavera P6 Collaborate 14B E Aerospace case study - Oracle Primavera P6 Collaborate 14
B E Aerospace case study - Oracle Primavera P6 Collaborate 14
 
SAP sample
SAP sampleSAP sample
SAP sample
 
Sahar Kamal's CV _2016
Sahar Kamal's CV _2016Sahar Kamal's CV _2016
Sahar Kamal's CV _2016
 
Presentation Webinar OPSYS_13112018.pptx
Presentation Webinar OPSYS_13112018.pptxPresentation Webinar OPSYS_13112018.pptx
Presentation Webinar OPSYS_13112018.pptx
 
Unifier webinar-final-printed
Unifier webinar-final-printedUnifier webinar-final-printed
Unifier webinar-final-printed
 
Training on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptTraining on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.ppt
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
 
ERP / MRP - Selection, Qualifying, Implementation
ERP / MRP - Selection, Qualifying, ImplementationERP / MRP - Selection, Qualifying, Implementation
ERP / MRP - Selection, Qualifying, Implementation
 
Leveraging P6 and Unifier combined strengths - Oracle Primavera P6 Collaborat...
Leveraging P6 and Unifier combined strengths - Oracle Primavera P6 Collaborat...Leveraging P6 and Unifier combined strengths - Oracle Primavera P6 Collaborat...
Leveraging P6 and Unifier combined strengths - Oracle Primavera P6 Collaborat...
 
Epm demonstration projerct online and project server 2013
Epm demonstration projerct online and project server 2013Epm demonstration projerct online and project server 2013
Epm demonstration projerct online and project server 2013
 
Training on ASAP Methodology.ppt
Training on ASAP Methodology.pptTraining on ASAP Methodology.ppt
Training on ASAP Methodology.ppt
 

P6 Team Member – Implementation Stories

  • 1. REMINDER Check in on the COLLABORATE mobile app P6 Team Member – Implementation Stories Prepared by: Luka Novosel Primavera Consultant Primakon How to Make the Project Manager's Life Easier Session ID#: 200910 @lunovosel
  • 2. About me… ■  Masters degree in Electrical Engineering ■  Primavera functional & technical consultant since 2006 ■  PMI PMP certified since 2010 ■  Oracle Primavera P6 & P6 R8 Implementation Specialist ■  Oracle Primavera EPPM trainer ■  PMP preparation trainer ■  Primavera EPPM API application designer & developer ■  Primavera EPPM SDK application designer & developer
  • 3. About us… ■  Primakon is a privately owned consulting company ▪  www.primakon.com ■  15+ years of experience in Primavera implementations ■  Offers customer tailored education in the area of PM methodologies and Primavera products ■  Positive references in a wide range of industries (from finance sector to construction) ■  Present in EU & SE European markets
  • 4. Presentation Overview ■  What is P6 Team Member ? ■  How to set it up ■  P6 Team Member as a part of contract management system ■  P6 Team Member in procurement management ■  P6 Team Member evolution 8.2 – 8.4 ■  Lessons learned ■  Q & A
  • 5. What is P6 Team Member ? This is a subtitle or bulleted list
  • 6. P6 Team Member as a Part of P6 EPPM Suite ■  The P6 Team Member application suite is designed for project team members to status their activities in an easy to use interface that does not require them to learn P6. ■  P6 Team Member suite consists of: ▪  P6 Team Member web application ▪  P6 Team Member iOS application ▪  P6 Team Member email status services ■  P6 Team Member suite was introduced as a part of P6 EPPM in version 8.2 (December 2011) ■  8.3 had a large number of improvements on 8.2 ■  In 8.4 the former Timesheet (Progress Reporter) and P6 Team Member application are integrated.
  • 7. P6 Team Member App vs Team Member License ■  Old Primavera users are familiar with the license type called Team Member ▪  That license covered p6 web, documents, issues and timesheets ■  Team Member license in P6.2.1 to R8.1 and P6 R8.2 are not the same thing P6.2.1 P6 R8.2
  • 8. P6 Team Member App Licenses Cont. ■  In release 8.3 this confusion was clarified with the creation of a new license module – Contributor (formerly Team Member) ■  In release 8.4 Team Member Interface was renamed again to Team Member ■  Tip: If you are upgrading Primavera form release 8.1 or previous to a newer one, remove the licenses to users that have Team Member and manually add them after the upgrade. P6 R8.3 P6 R8.4
  • 9. P6 Team Member Web Application 5 Reasons Why to Use It ■  In this presentation we will focus on P6 Team Member web application ■  5 reasons to implement this in your environment ▪  1) Easy to use ▪  2) Modern design ▪  3) Short learning curve ▪  4) Accessible from almost every imaginable place ▪  5) Ability to collect project information from numerous contributors
  • 10. How to Set Up P6 Team Member Application
  • 11. Steps to Set Up P6 Team Member Application ■  Steps needed to set up P6 Team Member application to work on your project 1.  Set Project Preferences 2.  Define team member user and assign team member licence to that user (under Administer / User access) 3.  Give the user access to permitted activities 4.  Set Review Required field on activities where you want to review status updates
  • 12. Steps to Set Up P6 Team Member Application - Set Project Preferences ■  1) Set Project Preferences ▪  Tick Allow reviews for Team Member status updates ▪  Tick Review Required for new activities ▪  Define Reviewer for this project ▪  Set which data team member will see in application P6 R 8.2 P6 R 8.4
  • 13. Steps to Set Up P6 Team Member Application – Team Member Module Access ■  Define team member user and assign team member licence to that user (under Administer / User access) ▪  This is needed if user will have access only to P6 Team Member application suite ▪  Tip: User can not be assigned as Contributor and Team Member at the same time
  • 14. Steps to Set Up P6 Team Member Application – User Access to Permitted Activities ■  There are 3 main ways to make activities visible in Team Member to a specific user ■  1) Assign user as Activity Owner in P6 (Field Owner in Activity view) ■  2) Assign user as a resource on activity (all assigned resources will see activities in P6 Team Member and will be able to update their resource assignment
  • 15. Steps to Set Up P6 Team Member Application – User Access to Permitted Activities Cont. ■  3) Assign Team Member filter to user (under Administration / User Access) – field Team Member Filter ▪  Up to 5 different filters can be assigned to the user ▪  Activity Global and EPS codes + resources and roles can be used
  • 16. Steps to Set Up P6 Team Member Application – Set Review Required Flag ■  4) Define which activities status update approval is needed ▪  This is per activity setting ▪  Status updates from P6 Team Member application on activities with Review Required flag will need approval from assigned reviewer ▪  Status updates from P6 Team Member application on activities without this flag will be applied automatically
  • 17. Use Case 1 P6 Team Member as a Part of Contract Management System
  • 18. Business Need ■  2011, Project charter for CMS was defined ■  In late 2011 during the detail project scope definition P6 Team Member was introduced (rel. 8.2) ■  After P6 Team Member evaluation it fitted the system perfectly ■  It will be used for : ▪  Key contract milestones approval ▪  Key process milestones update
  • 19. System Description ■  Contract Management System Parts ▪  Document Management ▪  Reporting ▪  Primavera P6 Schedules ▪  Portal ▪  P6 Team Member ■  All the systems are integrated and information shared across whole CMS ■  Primavera P6 is used for project schedule development and schedule updates
  • 20. Process Overview 1.  After contract signature the contractor develops schedule with the representative of the buyer 2.  In separate WBS all key project milestones are created 3.  On those milestones all related documents needed for delivery acceptance are assigned 1.  WP and Docs feature is used 2.  Document name and category are defined —  Can be “Submitted for Acceptance” or —  “Submitted for Information” 4.  When the schedule is approved all the documents are created in Document Management System 5.  When physical document is uploaded in DMS a corresponding document URL is created in P6 as a public URL
  • 21. Process Overview Cont. 6.  Document versioning and approval process are done in DMS ▪  Document status is transferred to P6 7.  When all the approval documents are approved the contractor ‘ticks’ contractual milestone in P6 Team Member ▪  Submission date is preserved 8.  Buyer’s representative approves changes through Status Review in P6 Web ▪  Approval date is preserved 9.  Same process with or without document management part can be applied in the main schedule as well, if agreed.
  • 22. The Process in Detail: P6 Project For the New Contract ■  New P6 Project is created for signed contract ■  Project preferences for Team Member are configured ▪  Review required is enabled and reviewer is defined ▪  Activity owner will be used for status updates ▪  UDF Fields are defined
  • 23. The Process in Detail Develop Schedule ■  Project schedule is developed after contract signature ■  Two main WBS level 1 are created ▪  Contract Milestones ▪  Schedule – project schedule ■  During schedule development “Review Required” activities are identified and Owner is assigned
  • 24. The Process in Detail Document Creation ■  Documents are added through WP & Docs feature ▪  Only Title and Document Category are defined ▪  Under “Related Items” documents are assigned to activity ▪  Data is saved
  • 25. The Process in Detail Document Creation Cont. ■  Hundreds of documents, different contract milestones … ■  Quite a painful job to do in P6 Web ■  To avoid this, we’ve developed a simple Java desktop application that will do the hard job for us ■  It parses Excel, creates Documents and links to activities ■  Link is bi-directional so Documents can be updated / deleted as well ■  Used only in the planning phase of a project
  • 26. The Process in Detail Documents Status Tracking ■  In DMS, documents are managed, approved, rejected etc. ■  In P6 we transfer only ▪  Unique URL to the document – that way user can access related document directly from Primavera schedule ▪  Document Status ■  Click on a view document will open document in new tab in a browser
  • 27. The Process in Detail Documents Status Tracking Cont. ■  To help the approver we’ve created two Activity level UDF fields ▪  # of Docs. for Approval – total number of documents that need to be approved for this delivery milestone ▪  # of Approved Docs. – number of approved documents in DMS (Documents with status “Approved”) ■  Custom developed background job is populating those 2 fields
  • 28. The Process in Detail P6 Team Member Status Update ■  The contractor submits status updates for contractual milestones through P6 Team Member ■  Green tick means activity (milestone) is finished ■  In Started: Actual Start is defined ■  Save change
  • 29. The Process in Detail Approve Changes ■  After the contractor saves the data in P6 Team Member, Reviewer is notified ■  In the Activity window a pop-up will appear ■  If the pop-up disappears the same window can be accessed from Action / Review Status Updates
  • 30. The Process in Detail Approve Changes Cont. ■  In Review Required window Reviewer can: ▪  Accept changes ▪  Override changes ▪  Put changes on hold and inform Status Updater of the reasons for holding changes ■  More information is available under More…
  • 31. The Process in Detail P6 Team Member Status Update ■  The contractor submits status updates for contractual milestones through P6 Team Member ■  Green tick means activity (milestone) is finished ■  In Started: Actual Start is defined ■  Save change
  • 32. The Process in Detail Approve Changes Cont. ■  In this situation: ▪  Number of approved Docs is lower then total number of documents for approval ▪  The reviewer will put activity on-hold ▪  He will send an email to the submitter with the reason why the status is put on-hold
  • 33. The Process in Detail Approval Overview ■  The Reviewer and contractor can check the information and dates when the status was submitted and approved
  • 34. The Process in Detail Approval Overview - Tips ■  Tip: If you don’t see “Update history” tab, enable it by selecting right click on tabs / customize tabs ■  Tip: If you don’t see data in Update history and you are sure that there should be data, check “Show updates for” menu ▪  Default value is: Assignments – if you are using Activity that can be confusing
  • 35. Summary ■  Why P6 Team Member in this particular case ▪  Approval process was the main driver in this implementation ▪  Tracking of submission and approval dates ▪  Tracking of all changes done in the process ▪  Easy to use ▪  User can have read-only access to specific activity and still be able to update it through P6 Team Member
  • 36. Use Case 2 P6 Team Member as a Part of Procurement Management Process
  • 37. Business Need ■  Procurement office is not in direct connection with Project Manager ■  Public procurement procedures have a great impact on project schedule ■  Procurement officers want simple application ■  Project Managers want up-to-date information about procurement statuses that affect their project ■  Easy access to procurement documents ■  Easy communication ■  Easy way to input data about procurements
  • 38. System Description ■  P6 Team Member is used for update procurement schedules ■  Procurement schedule templates are defined with all relevant ▪  UDF fields ▪  Notebooks ▪  Activity codes ■  We are using Oracle UCM for document management ■  All procurement documentation is uploaded automatically to P6 and UCM ■  Implementation started with P6 Team Member R8.3 and will be updated to 8.4
  • 39. Process Overview ■  System administrator creates procurement from appropriate template ■  Responsible procurement officer is assigned as Activity Owner on all procurement activities ■  All available documentation is uploaded to P6 ■  Procurement officer updates activity statuses as procurement progress ▪  Milestones ▪  Activities ■  Discussion is used for official collaboration ■  Notebooks will be used for notes (8.4 feature) ■  UDF and Activity codes are used for assigning attributes on activities
  • 40. System Preparation ■  System administrator creates procurement from the appropriate template ■  All predefined Team Member settings are preserved ■  Review Required is not enabled in this case ■  Responsible procurement officer is assigned as Activity Owner
  • 41. P6 Team Member for Procurement Officer ■  Team Member is the main tool for procurement officer
  • 42. Procurement Officer Tasks : Communication With Project Manager ■  For communication with the Project Manager we are using “Discussions” ■  New feature available across whole P6 platform ■  Track who and when ■  (!) No undo or delete ■  Best way to communicate between different applications (i.e. P6 Team Member and P6 web) ■  New discussions are marked with red number
  • 43. Procurement Officer Tasks Update Procurement Tasks ■  Milestones are checked when done ■  Activities can have predefined steps ■  By selecting Start the activity is started ■  Actual start date can be modified
  • 44. Procurement Officer Tasks Check Procurement Documents ■  By selecting activity the user can access documents assigned to that activity (in this case DMS is Oracle UCM) ■  Document can be viewed and downloaded from this window
  • 45. Procurement Officer Tasks : View / Edit Activity Information ■  The user can View and edit predefined User Defined Fields and Activity Codes ■  In our case 3 fields are available ▪  Read only – procurement type ▪  UDF – procurement code ▪  UDF – expected procurement amount ■  In addition to that, Notebook topics can be viewed and edited (rel. 8.4) through P6 Team Member
  • 46. P6 Web ■  In P6 Web procurement manager is doing the portfolio analysis ■  All data changes are controlled ■  The project Manager can update and update project schedule according to information received
  • 47. Summary ■  Why use P6 Team Member in this case ? ▪  Simple application for users that do not know a lot about schedules ▪  Easy communication between Project Manager (using P6 client or Web ) and Procurement Officer (using P6 Team Member) ▪  Simple access to procurement documents ▪  Project Manager has up-to-date information about procurement status ▪  Procurement Office Manager has overview of all procurements through P6 ▪  User adoption time to new tool is very short
  • 48. P6 Team Member Evolution R8.2 - > R8.4
  • 50. P6 Team Member R 8.3
  • 51. P6 Team Member R 8.4
  • 53. The Good Things ■  Simple application ■  Easy and quick user adoption ■  Cheaper than full P6 Web ■  Compatible with all devices ■  Update history ▪  All information about changes is preserved ▪  Useful as an audit log
  • 54. The Not So Good Things ■  First version had limited functionalities ■  Occasional bugs (i.e. 25 % bug) ■  On hold activities are poorly managed in P6 Team Member ▪  No easy way to identify on hold activities in P6 Team Member ■  Very small number of fields are visible in P6 Team Member ▪  i.e. not possible to see baseline date, baseline values, data date ■  ALL the data is lost if the project is exported via XER or XML file ▪  This means that all update history will be lost ! ■  Update history is not visible in P6 Client
  • 55. Questions ? ? Luka Novosel, M.Eng, PMP Certified Oracle Primavera P6 EPPM Implementation Specialist Primakon ltd ln@primakon.com hr.linkedin.com/in/lukanovosel www.primakon.com
  • 56. Please complete the session evaluation We appreciate your feedback and insight You may complete the session evaluation either on paper or online via the mobile app
  • 57. ■  Our purpose is to inform and educate our members on current and future func;onality of Oracle Primavera products, while offering a forum for peers to share their experience and knowledge in the use of Primavera. ■  Educa;onal opportuni;es across the Primavera product suite ■  Online Learning Series August 17th – September 4th ■  Call for presenta;on opening April 27th ■  Monthly Community Calls ■  3rd Thursday of the month at 1:00 pm ET ■  Networking with other users within the Primavera community ■  Partnering with Oracle Primavera to meet the needs of our diverse membership. ■  Membership is open to anyone with an interest in the Oracle Primavera products, with no dues for membership. All members can vote on maRers brought before the OPSIG. Membership requests may be reviewed by the OPSIG board. OPSIG is the home for Primavera Users