Contract Documents & Byelaws
Tender
Earnest money deposit (EMD)
• Earnest money deposited by each tenderer to enable the
owner to ensure that a tenderer does not refuse to execute
the work if it is awarded him. It is a guarantee for due
performance of the contract.
• Rate of EMD deposit varies from one organization to
another. It also varies with value of work.
• Normally EMD is 2% or 2.5% of estimated cost put to
tender.
• The earnest money of successful tender can be adjusted
against the security deposit required to be furnished by him.
• The earnest money of all the unsuccessful tenderers should
be returned as early as possible after the expiry of validity
period or after award of contract whichever is earlier.
Security deposit
• It is a check or safeguard for the owner to ensure that
contractor fulfills all terms & condition of contract, carries out
the work to his satisfaction , maintains desired progrss and
complete the work as envisaged in the contract agreement.
• Security deposit is refunded on
- Completion of work after expiry of defect liability period.
- On obtaining labour labour clearance certificate
- On finalization of final bill and work account.
Retention amount
- On award of contract , the contractor is required to deposit
specific amount as security deposit with the owner. Since there
may be financial constraint for the contractor to deposit such
amount at one time , an alternative method of deduction from
running bill is given to contractor . The amount of deduction made
from running bill towards security deposit is known as retention
amount.
- Thus retention amount is also a security deposit recovered
from running bills.
Method to select contractors
Method to select contractor
Post-qualificationPre-qualificationPublic tender Limited tender
Nomination
Public tender
The objective of inviting public tender are
- To give wide publicity
- To obtain competitive bids
- To provide equal opportunity to all contractors eligible to
tender.
Prequalification of contractor
- For major works, complex work , specified work and for works
of multidisciplinary involvement, contractors are prequalified to
ensure that competition is only among bidders who are capable
of executing work.
-The basic requirement of prequalification is not the selection of
the best contractor , but to eliminate incompetent and insincere
contractor.
- Prequalification notice is published in newspapers with wide
circulation. Relevant details such as nature of work ,
estimated cost , period allowed for completion and eligibility
criteria of contractors are described in the press notice.
Post qualification
- In this system two cover system is followed.
- It has inherent advantages , technical & commercial bids
and price bids are submitted in separate sealed cover.
- The technical & commercial bid containing all particulars
required to evaluate contractor’s suitability except for price
is opened first and a critical evaluation of contractor’s
capabilities is done.
- If some of the contractors are eliminated on the basis of
their technical & commercial bid, their price bid are not
opened and retained or returned to the tenderers.
Two cover system
In this system tenderers are required to submit tenders in
two covers
-The first cover contains
(i) One envelop contain EMD
(ii) Another envelop contains qualification relating to
- Work done during five year.
- Existing commitment & details of on-going works
- Works for which tenders already submitted
- Equipment details owned by the tenderer.
The second cover contains priced bill of quantities. All
duties, taxes and other levies payable by the contractor
under the contract or for any other cause shall be
included in the rates, prices and total price submitted by
the tenderers.
Limited tender
• In this method tender notice is sent to selected contractors
of repute & no press tender notice is issued.
• The lowest tenderer may be called for negotiations
• This method of selection of contractor is adopted in private
sector as an alternative to other methods.
Nomination
• Selection of a contractor by nomination is adopted for works
of small magnitude or for emergency works.
• This contract is awarded based on prevailing market rates in
respect of government work.
• In private sector the rates are negotiated with nominated
contractor keeping in view the trend of market rates.
Liquidated damage
• It is fixed stipulated sum payable by the contractor on
account of penalty for delays and does not bear any
relationship with the real damage to the owner.
• It is generally high & fixed per day for the excess period
over the specified period in the tender.
Defect liability period
• The contractor shall make good at his own cost and to the
satisfaction of the architect; all defects, shrinkages or small
faults , arising in the opinion of Architect from work or
materials not being in accordance with drawings or
specifications or schedule of quantities or instructions of
architect, which may be appear within.
Mobilisation advance
• Admissible for woks whose estimated cost put to tender is 2
crores & above.
• Maximum advance is 10% of the tendered value of work.
• Advance is paid two or three instalments.
• Proof of utilisation of first instalment is necessary before
obtaining second instalment and so on.
• Advance is given against bank guarantee bond.
A r b i t r a t i o n
Advantages of Arbitration
There are several advantages of arbitration over a court
decision
Cost
Arbitration is less expansive than court action.
Speed
Dispute are settled much faster through arbitration as
compared to law suit in the courts.
Convenience
Arbitration hearing are fixed considering the convenience of the
Both parties.
Technical knowledge
Both the parties have the distinct advantage of appointing
Arbitrator having technical knowledge & expertise which
facilitates satisfactory judgement.
Informality
Arbitration is conducted in a relatively informal atmosphere
observing certain minimum prescribed legal formalities.
Proceedings in the private premises
Arbitration proceeding are held in the private premises ,
consequently business activity of the parties do not suffer.
Termination of contract
The contract may be terminated in the following conditions
Completion of work
When the work is completed according to the contract
agreements and the owner is satisfied , the security money is
released and the contract is terminated.
By agreement
If due to some unavoidable circumstances , it is not possible to
complete the work, the contract is terminated by mutual
agreement.
By breach of conditions
If any party does not follow the conditions of contract, the party
has the right to terminate the contract due to such breach.
By impossibility to complete
When the site does not belong to the owner , or the land is
acquired by the government or it is flooded or damaged due to
natural calamities , the construction of work is impossible and
the contract is terminated.
By bankruptcy
If either party becomes bankrupt , the contract may be
terminated.

Weitere ähnliche Inhalte

Was ist angesagt?

Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and ArbitrationJIT KUMAR GUPTA
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedureShourya Puri
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -artijagadish108
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.Abhishek kumar maurya
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender ManagementAnand Subramaniam
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTVISHNU VIJAYAN
 

Was ist angesagt? (20)

Tender
TenderTender
Tender
 
Contracts
ContractsContracts
Contracts
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Construction contract
Construction contract Construction contract
Construction contract
 
Tender
TenderTender
Tender
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 

Andere mochten auch

Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project managementAli Heydari
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...Dcolearning
 
Spa Professional Practice Vi February 2010
Spa Professional Practice Vi February 2010Spa Professional Practice Vi February 2010
Spa Professional Practice Vi February 2010Design Action Group
 
Architectural competitions
Architectural  competitionsArchitectural  competitions
Architectural competitionszehbamp
 
Architecture competition annual 2008
Architecture competition annual 2008Architecture competition annual 2008
Architecture competition annual 2008architect Eman
 
The role of an Architect
The role of an ArchitectThe role of an Architect
The role of an ArchitectClara Lee
 
Role of Indian Institute of Architects as a professional body in India
Role of Indian Institute of Architects as a professional body in IndiaRole of Indian Institute of Architects as a professional body in India
Role of Indian Institute of Architects as a professional body in IndiaKrittika Walia
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site MeetingSanjay Patnaik
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Tender processing
Tender processingTender processing
Tender processingdnyandev_d
 
Architecture Professional practice
Architecture Professional  practice Architecture Professional  practice
Architecture Professional practice Ar. Mukunda K.S
 
Administrative office management (aom)
Administrative office management (aom)Administrative office management (aom)
Administrative office management (aom)Edz Gapuz
 

Andere mochten auch (20)

Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
 
Spa Professional Practice Vi February 2010
Spa Professional Practice Vi February 2010Spa Professional Practice Vi February 2010
Spa Professional Practice Vi February 2010
 
Retention fund
Retention fundRetention fund
Retention fund
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Architectural competitions
Architectural  competitionsArchitectural  competitions
Architectural competitions
 
Architecture competition annual 2008
Architecture competition annual 2008Architecture competition annual 2008
Architecture competition annual 2008
 
The role of an Architect
The role of an ArchitectThe role of an Architect
The role of an Architect
 
Role of Indian Institute of Architects as a professional body in India
Role of Indian Institute of Architects as a professional body in IndiaRole of Indian Institute of Architects as a professional body in India
Role of Indian Institute of Architects as a professional body in India
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
The architects act, 1972
The architects act, 1972The architects act, 1972
The architects act, 1972
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site Meeting
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Tender processing
Tender processingTender processing
Tender processing
 
Architecture Professional practice
Architecture Professional  practice Architecture Professional  practice
Architecture Professional practice
 
Administrative office management (aom)
Administrative office management (aom)Administrative office management (aom)
Administrative office management (aom)
 
Arbitration notes
Arbitration notesArbitration notes
Arbitration notes
 

Ähnlich wie Unit 1-Contract Documents & Byelaws

Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptxjairam131
 
Contracts Management
Contracts Management Contracts Management
Contracts Management Mohib Ullah
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tenderneharajpl
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practiceAditya Sanyal
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureHASMANIRA
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSGanesh Bhorkade
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Project procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaProject procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaGuta Mengesha
 
dsds.ppt
dsds.pptdsds.ppt
dsds.pptpisal3
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selectionanojan kanagarathnam
 

Ähnlich wie Unit 1-Contract Documents & Byelaws (20)

Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
 
Unit 5 Tendering
Unit 5 Tendering Unit 5 Tendering
Unit 5 Tendering
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tender
 
Qsct tendering dr_clj
Qsct tendering dr_cljQsct tendering dr_clj
Qsct tendering dr_clj
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Project procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaProject procuremenet contract in ethiopia
Project procuremenet contract in ethiopia
 
dsds.ppt
dsds.pptdsds.ppt
dsds.ppt
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 

Kürzlich hochgeladen

Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxPooja Bhuva
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the ClassroomPooky Knightsmith
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfDr Vijay Vishwakarma
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - Englishneillewis46
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024Elizabeth Walsh
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17Celine George
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structuredhanjurrannsibayan2
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxPooja Bhuva
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxPooja Bhuva
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxannathomasp01
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...Nguyen Thanh Tu Collection
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 

Kürzlich hochgeladen (20)

Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 

Unit 1-Contract Documents & Byelaws

  • 1. Contract Documents & Byelaws Tender
  • 2. Earnest money deposit (EMD) • Earnest money deposited by each tenderer to enable the owner to ensure that a tenderer does not refuse to execute the work if it is awarded him. It is a guarantee for due performance of the contract. • Rate of EMD deposit varies from one organization to another. It also varies with value of work. • Normally EMD is 2% or 2.5% of estimated cost put to tender. • The earnest money of successful tender can be adjusted against the security deposit required to be furnished by him. • The earnest money of all the unsuccessful tenderers should be returned as early as possible after the expiry of validity period or after award of contract whichever is earlier.
  • 3. Security deposit • It is a check or safeguard for the owner to ensure that contractor fulfills all terms & condition of contract, carries out the work to his satisfaction , maintains desired progrss and complete the work as envisaged in the contract agreement. • Security deposit is refunded on - Completion of work after expiry of defect liability period. - On obtaining labour labour clearance certificate - On finalization of final bill and work account. Retention amount - On award of contract , the contractor is required to deposit specific amount as security deposit with the owner. Since there may be financial constraint for the contractor to deposit such amount at one time , an alternative method of deduction from running bill is given to contractor . The amount of deduction made from running bill towards security deposit is known as retention amount.
  • 4. - Thus retention amount is also a security deposit recovered from running bills. Method to select contractors Method to select contractor Post-qualificationPre-qualificationPublic tender Limited tender Nomination
  • 5. Public tender The objective of inviting public tender are - To give wide publicity - To obtain competitive bids - To provide equal opportunity to all contractors eligible to tender. Prequalification of contractor - For major works, complex work , specified work and for works of multidisciplinary involvement, contractors are prequalified to ensure that competition is only among bidders who are capable of executing work. -The basic requirement of prequalification is not the selection of the best contractor , but to eliminate incompetent and insincere contractor.
  • 6. - Prequalification notice is published in newspapers with wide circulation. Relevant details such as nature of work , estimated cost , period allowed for completion and eligibility criteria of contractors are described in the press notice. Post qualification - In this system two cover system is followed. - It has inherent advantages , technical & commercial bids and price bids are submitted in separate sealed cover. - The technical & commercial bid containing all particulars required to evaluate contractor’s suitability except for price is opened first and a critical evaluation of contractor’s capabilities is done. - If some of the contractors are eliminated on the basis of their technical & commercial bid, their price bid are not opened and retained or returned to the tenderers.
  • 7. Two cover system In this system tenderers are required to submit tenders in two covers -The first cover contains (i) One envelop contain EMD (ii) Another envelop contains qualification relating to - Work done during five year. - Existing commitment & details of on-going works - Works for which tenders already submitted - Equipment details owned by the tenderer. The second cover contains priced bill of quantities. All duties, taxes and other levies payable by the contractor under the contract or for any other cause shall be included in the rates, prices and total price submitted by the tenderers.
  • 8. Limited tender • In this method tender notice is sent to selected contractors of repute & no press tender notice is issued. • The lowest tenderer may be called for negotiations • This method of selection of contractor is adopted in private sector as an alternative to other methods. Nomination • Selection of a contractor by nomination is adopted for works of small magnitude or for emergency works. • This contract is awarded based on prevailing market rates in respect of government work. • In private sector the rates are negotiated with nominated contractor keeping in view the trend of market rates.
  • 9. Liquidated damage • It is fixed stipulated sum payable by the contractor on account of penalty for delays and does not bear any relationship with the real damage to the owner. • It is generally high & fixed per day for the excess period over the specified period in the tender. Defect liability period • The contractor shall make good at his own cost and to the satisfaction of the architect; all defects, shrinkages or small faults , arising in the opinion of Architect from work or materials not being in accordance with drawings or specifications or schedule of quantities or instructions of architect, which may be appear within.
  • 10. Mobilisation advance • Admissible for woks whose estimated cost put to tender is 2 crores & above. • Maximum advance is 10% of the tendered value of work. • Advance is paid two or three instalments. • Proof of utilisation of first instalment is necessary before obtaining second instalment and so on. • Advance is given against bank guarantee bond.
  • 11. A r b i t r a t i o n
  • 12. Advantages of Arbitration There are several advantages of arbitration over a court decision Cost Arbitration is less expansive than court action. Speed Dispute are settled much faster through arbitration as compared to law suit in the courts. Convenience Arbitration hearing are fixed considering the convenience of the
  • 13. Both parties. Technical knowledge Both the parties have the distinct advantage of appointing Arbitrator having technical knowledge & expertise which facilitates satisfactory judgement. Informality Arbitration is conducted in a relatively informal atmosphere observing certain minimum prescribed legal formalities. Proceedings in the private premises Arbitration proceeding are held in the private premises , consequently business activity of the parties do not suffer.
  • 14. Termination of contract The contract may be terminated in the following conditions Completion of work When the work is completed according to the contract agreements and the owner is satisfied , the security money is released and the contract is terminated. By agreement If due to some unavoidable circumstances , it is not possible to complete the work, the contract is terminated by mutual agreement.
  • 15. By breach of conditions If any party does not follow the conditions of contract, the party has the right to terminate the contract due to such breach. By impossibility to complete When the site does not belong to the owner , or the land is acquired by the government or it is flooded or damaged due to natural calamities , the construction of work is impossible and the contract is terminated. By bankruptcy If either party becomes bankrupt , the contract may be terminated.