Progress Review Meeting
Date: 19th May 2015
Contents
• Contract Status
• Safety Status
• Quality
• Major Concerns
• Cash Flow Chart – GDCL
• Progress of work
• Material Mobilization
• Manpower Mobilization
• Technical Man Power Mobilization
• RA Bill Payment History
• Major Events Planned for Q1 Vs Achieved
• Site Progress Photographs
Contract Brief
Main Civil Package
Civil package Awarded to Gannon Dunkerley & Company
Limited
Contract Value 141 Cr
Contractual Start Month 27-Aug-2014
Contractual End Month 18-Feb-2017
Work Progress (% till date)
Baseline Progress Actual Progress
33% 8 %
Cash Flow
Baseline Actual
42.4 Cr 11 Cr
Safety
• Total Man-hours achieved = 520, 143
• First Aid Cases = 42
• Near Miss Cases = 3
• Hospital cases = 1
• Reportable Incident Rate = 0
• NCR Issued = 3
– Note : Status Date: 18th May 2015
Quality
• No of Concrete Cubes Tested till date
– Passed = 3888 Nos
– Failed = 0 Nos
• NCR issued = 14
• Quality Concerns
– Honey combing (Major/Minor)
– Bulge of concrete
• Site Instructions issued for Quality of work
Major Concerns
S.no Description of
Item
Delay
in
days
Measures Taken/ Action Plan
1 Tower Crane 1 107 Ensured GDCL to conduct IIIrd party test for Tower
crane and same was commissioned on 2nd Apr 2015
2 Tower Crane 2 72 Material yet to be arrived, Proposed Plan for
material arrival and erection from 25th May 2015
3 FUVI Material 137 Extra Manpower to be deployed by GDCL in
assembling of FUVI Formwork sets
4 Staging &
Shuttering
Material
27 Arrival of material for Slab for Tower B & D has been
delayed, In discussions with GDCL top mgmt,
shared material delivery schedule
5 Labour Shortage - As per LOI GDCL have agreed for 640 nos, Present
available = 357 nos , further GDCL to increase the
labour strength upto 520 nos on immediate basis.
(Till date total labour reported to Site = 470 Nos as
per safety inductions conducted)
0
10
20
30
40
50
60
70
InCrore
Jul/15 Aug/15 Sep/15 Oct/15 Nov/15 Dec/15 Jan/16 Feb/16 Mar/16 Apr/16 May/16 Jun/16
A 0.8 2 4.4 7.9 11.7 16.5 22 28.5 35.3 42.4 49.9 57.7
B 0.37 1.04 2.91 4.71 7.03 11.2
Cash Flow - GDCL Index
A - Cumulative Baseline
B - Cumulative Actual
Progress of work
S.no Description
As per
Baseline
Dates committed in WPRM's
Slippage
in days29th
Jan 6th
Apr 24th
Apr 27th
Apr 8th
May
As on
19th
May
Tower A
1 LB Pour 1 9-Feb-15 30-Mar-15 22-Apr-15 6-May-15 15-May-15 15-May-15 19-May-15 95.00
2 LB Pour 2 9-Feb-15 8-Apr-15 6-May-15 15-May-15 30-May-15 30-May-15 110.00
3 UB Pour 1 16-Mar-15 17-Apr-15 17-May-15 - - 22-Jun-15 98.00
4 UB Pour 2 16-Mar-15 26-Apr-15 6-Jun-15 - - 30-Jun-15 106.00
Tower B
1 LB Pour 1 24-Jan-15 20-Mar-15 11-Apr-15 30-Apr-15 2-May-15 98.00
2 LB Pour 2 24-Jan-15 25-Mar-15 16-Apr-15 12-May-15 20-May-15 20-May-15 19-May-15 116.00
3 UB Pour 1 24-Feb-15 7-Apr-15 6-May-15 - 7-Jun-15 103.00
4 UB Pour 2 24-Feb-15 12-Apr-15 17-May-15 - 29-Jun-15
Tower C
1 LB Pour 1 27-Dec-14 20-Feb-15 24-Feb-15 59.00
2 LB Pour 2 27-Dec-14 3-Mar-15 11-Mar-15 74.00
3 UB Pour 1 28-Jan-15 10-Mar-15 22-Apr-15 24-Apr-15 86.00
4 UB Pour 2 28-Jan-15 21-Mar-15 6-May-15 15-May-15 15-May-15 19-May-15 17-May-15 109.00
5 Ground Floor Slab 1-Apr-15 9-Jun-15 69.00
Tower D
1 LB Pour 1 9-Jan-15 28-Feb-15 21-Mar-15 71.00
2 LB Pour 2 9-Jan-15 10-Mar-15 6-Apr-15 11-Apr-15 92.00
3 UB Pour 1 10-Feb-15 18-Mar-15 22-Apr-15 20-May-15 20-May-15 20-May-15 19-May-15 99.00
4 UB Pour 2 10-Feb-15 28-Mar-15 7-May-15 25-May-15 25-May-15 29-May-15 104.00
Task completed
Scheduled Date for Completion
Expected finish date
Material Mobilization
S.no Item Description Unit Received
1 2.50 M Cuplock Vertical Nos 14570
2 2.00 M Cuplock Vertical Nos 2815
3 1.50 M Cuplock Vertical Nos 3937
4 1.00 M Cuplock Vertical Nos 4293
5 Stirrup Head Nos 15350
6 1.20 M Bracing Nos 36119
7 50*50 Square Tube RM 18300
8 12 MM Thick Plywood Sqm 9950
9 MS Shuttering Sqm 3400
Man Power Mobilization
Sl # Item Description Unit
Total Nos
available
Man Power
Required
Shortage
1 Carpenter & Helper Nos 160 203 43
2 Barbender & Helper Nos 145 176 31
3
Mason & Helper for Concrete
Works
Nos 27 -
4 Unskilled Labour Nos 72 114 42
Total Manpower Qty 404 493 116
Technical Man Power Mobilization
S.no Description
Total
Required as
per LOI
Status
as on
date
1 Project Coordinator 1 1
2 Project In charge 1 1
3 Section In charge 5 5
4 Asst. Engineer – Execution 10 5
5
Quality Control Engineer & lab
Asst. 2 2
6 Billing Engineer 3 1
7 Planning Engineer 3 1
8 Safety Officer/ Stewards 6 5
9 Building Supervisor 20 4
10 Surveyor 2 2
11 Plant & machinery Team 14 24
RA Bill Payment History
RA Bill Bill Submitted
by GDCL
70% Adhoc Balance 30%
Payment
Mobilization 13th Oct 2014 21st Oct 2014 & 10th Nov 2014
1 2nd Nov 2014 17th Nov 2014 8th Dec 2014
2 5th Dec 2014 16th & 17th Dec 2014 13th Feb 2015
3 1st Jan 2015 21st Jan 2015 16th Mar 2015
4 2nd Feb 2015 17th Feb 2015 16th Mar 2015
5 15th Mar 2015 24th Mar 2015 17th Apr 2015
6 14th Apr 2015 28th Apr 2015
7 13th May 2015 Approval request
submitted to client
Major Events Planned for Q1
Location Major activities Planned
(Q1)
Work Progress
Tower A Completion upto Ground Floor
Slab
LB Floor Slab 1st Pour concrete
completed on 18th May 2015
Tower B Completion upto First Floor Slab LB Floor Slab 2nd Pour
scheduled to be completed on
19th May 2015
Tower C Completion upto Second Floor
Slab
UB Floor Slab completed
Tower D Completion upto First Floor Slab UB Floor Slab (50%) scheduled
to completed on 19th May 2015
Podium
Area
Pour 1, 3, 5,6 & 7 LB PT Slab Pour 5 Shuttering works in
progress
Retaining
Wall
Completion of Balance 811 RM
Wall concrete
Completed 650 RM of balance
811 RM leaving UG Sumps/ STP
Tank area
Site Progress Photographs – as on date 18.05.2015
Tower A
LB Floor Slab (Pour 1) Concrete in Progress
Tower A
LB Floor Slab (Pour 1) Concrete in Progress
Tower B
LB Floor Slab (Pour 2) – Reinforcement laying in Progress
Tower C
UB Floor Slab completed
Tower D
UB Floor Slab (Pour 1) Concrete scheduled for concreting on 19th May 2015
Tower C
PT Pour 7 – Shuttering in Progress
Tower C – Retaining Wall
Wall/ Raft in Progress
Tower A/B – Retaining Wall
Wall/ Raft in Progress
Thank You

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (18)

CMC cv (eng - photo) 2014
CMC cv (eng - photo) 2014 CMC cv (eng - photo) 2014
CMC cv (eng - photo) 2014
 
AtoP Pipeline fro linked in
AtoP Pipeline fro linked inAtoP Pipeline fro linked in
AtoP Pipeline fro linked in
 
Rate analysis vansheika
Rate analysis   vansheikaRate analysis   vansheika
Rate analysis vansheika
 
Job order costing
Job order costingJob order costing
Job order costing
 
Tim_Robb_Resume_PMS_ProjectDutyList_Mueller
Tim_Robb_Resume_PMS_ProjectDutyList_MuellerTim_Robb_Resume_PMS_ProjectDutyList_Mueller
Tim_Robb_Resume_PMS_ProjectDutyList_Mueller
 
Copy Of Resume
Copy Of ResumeCopy Of Resume
Copy Of Resume
 
Clean Water Facility 60% Cost Estimate Preview
Clean Water Facility 60% Cost Estimate PreviewClean Water Facility 60% Cost Estimate Preview
Clean Water Facility 60% Cost Estimate Preview
 
SK
SKSK
SK
 
rate analysis
rate analysisrate analysis
rate analysis
 
DS-16-147 DEAAG Project Update
DS-16-147 DEAAG Project UpdateDS-16-147 DEAAG Project Update
DS-16-147 DEAAG Project Update
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
 
May 2014 Construction Update PCAPP EDS
May 2014 Construction Update PCAPP EDSMay 2014 Construction Update PCAPP EDS
May 2014 Construction Update PCAPP EDS
 
Controls Why They Dont Work
Controls Why They Dont WorkControls Why They Dont Work
Controls Why They Dont Work
 
Channel 7
Channel 7Channel 7
Channel 7
 
SD Plus - Reconciliation Process
SD Plus - Reconciliation ProcessSD Plus - Reconciliation Process
SD Plus - Reconciliation Process
 
Chevron Depropanizer Project
Chevron Depropanizer ProjectChevron Depropanizer Project
Chevron Depropanizer Project
 
Completion Oil Tools Presentation
Completion Oil Tools PresentationCompletion Oil Tools Presentation
Completion Oil Tools Presentation
 
Sop On Complaint Handling
Sop On Complaint HandlingSop On Complaint Handling
Sop On Complaint Handling
 

Ähnlich wie Presentation

ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxssuser3797b9
 
PLSH PPT
PLSH PPTPLSH PPT
PLSH PPTHarish JP
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19WaqarHussain183
 
ScheduleRev- 6
ScheduleRev- 6ScheduleRev- 6
ScheduleRev- 6Muhammad Ali
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0Ahmed Khaled
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project ScheduleVirginia Kam
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129James Zhang (Chi, Zhang)
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptKingHaroldDeLeon
 
ABC_2nd Progress Mtg Briefing_011214_final.ppt
ABC_2nd Progress Mtg Briefing_011214_final.pptABC_2nd Progress Mtg Briefing_011214_final.ppt
ABC_2nd Progress Mtg Briefing_011214_final.pptKingHaroldDeLeon
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfSajidMumtazGurmani
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONcyberyogi07
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
 

Ähnlich wie Presentation (20)

ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptx
 
PLSH PPT
PLSH PPTPLSH PPT
PLSH PPT
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
ScheduleRev- 6
ScheduleRev- 6ScheduleRev- 6
ScheduleRev- 6
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project Schedule
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
AH15019
AH15019AH15019
AH15019
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
 
ABC_2nd Progress Mtg Briefing_011214_final.ppt
ABC_2nd Progress Mtg Briefing_011214_final.pptABC_2nd Progress Mtg Briefing_011214_final.ppt
ABC_2nd Progress Mtg Briefing_011214_final.ppt
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
 
FQUP PPT.pptx
FQUP PPT.pptxFQUP PPT.pptx
FQUP PPT.pptx
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATION
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 

Mehr von Krm Chari

Ancient nepal 144_03
Ancient nepal 144_03Ancient nepal 144_03
Ancient nepal 144_03Krm Chari
 
Cib15834(1)
Cib15834(1)Cib15834(1)
Cib15834(1)Krm Chari
 
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Krm Chari
 
Depreciation chart-11-12-fy
Depreciation chart-11-12-fyDepreciation chart-11-12-fy
Depreciation chart-11-12-fyKrm Chari
 
Brochure
BrochureBrochure
BrochureKrm Chari
 
Ultimate strength
Ultimate strengthUltimate strength
Ultimate strengthKrm Chari
 
Untitled Presentation
Untitled PresentationUntitled Presentation
Untitled PresentationKrm Chari
 
Masonry homes construction manual
Masonry homes construction manualMasonry homes construction manual
Masonry homes construction manualKrm Chari
 
Unit costs for standard bid items & special provision items
Unit costs for standard bid items & special provision itemsUnit costs for standard bid items & special provision items
Unit costs for standard bid items & special provision itemsKrm Chari
 

Mehr von Krm Chari (10)

Ancient nepal 144_03
Ancient nepal 144_03Ancient nepal 144_03
Ancient nepal 144_03
 
Cib15834(1)
Cib15834(1)Cib15834(1)
Cib15834(1)
 
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
 
Depreciation chart-11-12-fy
Depreciation chart-11-12-fyDepreciation chart-11-12-fy
Depreciation chart-11-12-fy
 
Brochure
BrochureBrochure
Brochure
 
Ultimate strength
Ultimate strengthUltimate strength
Ultimate strength
 
Chap1
Chap1Chap1
Chap1
 
Untitled Presentation
Untitled PresentationUntitled Presentation
Untitled Presentation
 
Masonry homes construction manual
Masonry homes construction manualMasonry homes construction manual
Masonry homes construction manual
 
Unit costs for standard bid items & special provision items
Unit costs for standard bid items & special provision itemsUnit costs for standard bid items & special provision items
Unit costs for standard bid items & special provision items
 

KĂźrzlich hochgeladen

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

KĂźrzlich hochgeladen (20)

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

Presentation

  • 2. Contents • Contract Status • Safety Status • Quality • Major Concerns • Cash Flow Chart – GDCL • Progress of work • Material Mobilization • Manpower Mobilization • Technical Man Power Mobilization • RA Bill Payment History • Major Events Planned for Q1 Vs Achieved • Site Progress Photographs
  • 3. Contract Brief Main Civil Package Civil package Awarded to Gannon Dunkerley & Company Limited Contract Value 141 Cr Contractual Start Month 27-Aug-2014 Contractual End Month 18-Feb-2017 Work Progress (% till date) Baseline Progress Actual Progress 33% 8 % Cash Flow Baseline Actual 42.4 Cr 11 Cr
  • 4. Safety • Total Man-hours achieved = 520, 143 • First Aid Cases = 42 • Near Miss Cases = 3 • Hospital cases = 1 • Reportable Incident Rate = 0 • NCR Issued = 3 – Note : Status Date: 18th May 2015
  • 5. Quality • No of Concrete Cubes Tested till date – Passed = 3888 Nos – Failed = 0 Nos • NCR issued = 14 • Quality Concerns – Honey combing (Major/Minor) – Bulge of concrete • Site Instructions issued for Quality of work
  • 6. Major Concerns S.no Description of Item Delay in days Measures Taken/ Action Plan 1 Tower Crane 1 107 Ensured GDCL to conduct IIIrd party test for Tower crane and same was commissioned on 2nd Apr 2015 2 Tower Crane 2 72 Material yet to be arrived, Proposed Plan for material arrival and erection from 25th May 2015 3 FUVI Material 137 Extra Manpower to be deployed by GDCL in assembling of FUVI Formwork sets 4 Staging & Shuttering Material 27 Arrival of material for Slab for Tower B & D has been delayed, In discussions with GDCL top mgmt, shared material delivery schedule 5 Labour Shortage - As per LOI GDCL have agreed for 640 nos, Present available = 357 nos , further GDCL to increase the labour strength upto 520 nos on immediate basis. (Till date total labour reported to Site = 470 Nos as per safety inductions conducted)
  • 7. 0 10 20 30 40 50 60 70 InCrore Jul/15 Aug/15 Sep/15 Oct/15 Nov/15 Dec/15 Jan/16 Feb/16 Mar/16 Apr/16 May/16 Jun/16 A 0.8 2 4.4 7.9 11.7 16.5 22 28.5 35.3 42.4 49.9 57.7 B 0.37 1.04 2.91 4.71 7.03 11.2 Cash Flow - GDCL Index A - Cumulative Baseline B - Cumulative Actual
  • 8. Progress of work S.no Description As per Baseline Dates committed in WPRM's Slippage in days29th Jan 6th Apr 24th Apr 27th Apr 8th May As on 19th May Tower A 1 LB Pour 1 9-Feb-15 30-Mar-15 22-Apr-15 6-May-15 15-May-15 15-May-15 19-May-15 95.00 2 LB Pour 2 9-Feb-15 8-Apr-15 6-May-15 15-May-15 30-May-15 30-May-15 110.00 3 UB Pour 1 16-Mar-15 17-Apr-15 17-May-15 - - 22-Jun-15 98.00 4 UB Pour 2 16-Mar-15 26-Apr-15 6-Jun-15 - - 30-Jun-15 106.00 Tower B 1 LB Pour 1 24-Jan-15 20-Mar-15 11-Apr-15 30-Apr-15 2-May-15 98.00 2 LB Pour 2 24-Jan-15 25-Mar-15 16-Apr-15 12-May-15 20-May-15 20-May-15 19-May-15 116.00 3 UB Pour 1 24-Feb-15 7-Apr-15 6-May-15 - 7-Jun-15 103.00 4 UB Pour 2 24-Feb-15 12-Apr-15 17-May-15 - 29-Jun-15 Tower C 1 LB Pour 1 27-Dec-14 20-Feb-15 24-Feb-15 59.00 2 LB Pour 2 27-Dec-14 3-Mar-15 11-Mar-15 74.00 3 UB Pour 1 28-Jan-15 10-Mar-15 22-Apr-15 24-Apr-15 86.00 4 UB Pour 2 28-Jan-15 21-Mar-15 6-May-15 15-May-15 15-May-15 19-May-15 17-May-15 109.00 5 Ground Floor Slab 1-Apr-15 9-Jun-15 69.00 Tower D 1 LB Pour 1 9-Jan-15 28-Feb-15 21-Mar-15 71.00 2 LB Pour 2 9-Jan-15 10-Mar-15 6-Apr-15 11-Apr-15 92.00 3 UB Pour 1 10-Feb-15 18-Mar-15 22-Apr-15 20-May-15 20-May-15 20-May-15 19-May-15 99.00 4 UB Pour 2 10-Feb-15 28-Mar-15 7-May-15 25-May-15 25-May-15 29-May-15 104.00 Task completed Scheduled Date for Completion Expected finish date
  • 9. Material Mobilization S.no Item Description Unit Received 1 2.50 M Cuplock Vertical Nos 14570 2 2.00 M Cuplock Vertical Nos 2815 3 1.50 M Cuplock Vertical Nos 3937 4 1.00 M Cuplock Vertical Nos 4293 5 Stirrup Head Nos 15350 6 1.20 M Bracing Nos 36119 7 50*50 Square Tube RM 18300 8 12 MM Thick Plywood Sqm 9950 9 MS Shuttering Sqm 3400
  • 10. Man Power Mobilization Sl # Item Description Unit Total Nos available Man Power Required Shortage 1 Carpenter & Helper Nos 160 203 43 2 Barbender & Helper Nos 145 176 31 3 Mason & Helper for Concrete Works Nos 27 - 4 Unskilled Labour Nos 72 114 42 Total Manpower Qty 404 493 116
  • 11. Technical Man Power Mobilization S.no Description Total Required as per LOI Status as on date 1 Project Coordinator 1 1 2 Project In charge 1 1 3 Section In charge 5 5 4 Asst. Engineer – Execution 10 5 5 Quality Control Engineer & lab Asst. 2 2 6 Billing Engineer 3 1 7 Planning Engineer 3 1 8 Safety Officer/ Stewards 6 5 9 Building Supervisor 20 4 10 Surveyor 2 2 11 Plant & machinery Team 14 24
  • 12. RA Bill Payment History RA Bill Bill Submitted by GDCL 70% Adhoc Balance 30% Payment Mobilization 13th Oct 2014 21st Oct 2014 & 10th Nov 2014 1 2nd Nov 2014 17th Nov 2014 8th Dec 2014 2 5th Dec 2014 16th & 17th Dec 2014 13th Feb 2015 3 1st Jan 2015 21st Jan 2015 16th Mar 2015 4 2nd Feb 2015 17th Feb 2015 16th Mar 2015 5 15th Mar 2015 24th Mar 2015 17th Apr 2015 6 14th Apr 2015 28th Apr 2015 7 13th May 2015 Approval request submitted to client
  • 13. Major Events Planned for Q1 Location Major activities Planned (Q1) Work Progress Tower A Completion upto Ground Floor Slab LB Floor Slab 1st Pour concrete completed on 18th May 2015 Tower B Completion upto First Floor Slab LB Floor Slab 2nd Pour scheduled to be completed on 19th May 2015 Tower C Completion upto Second Floor Slab UB Floor Slab completed Tower D Completion upto First Floor Slab UB Floor Slab (50%) scheduled to completed on 19th May 2015 Podium Area Pour 1, 3, 5,6 & 7 LB PT Slab Pour 5 Shuttering works in progress Retaining Wall Completion of Balance 811 RM Wall concrete Completed 650 RM of balance 811 RM leaving UG Sumps/ STP Tank area
  • 14. Site Progress Photographs – as on date 18.05.2015
  • 15. Tower A LB Floor Slab (Pour 1) Concrete in Progress
  • 16. Tower A LB Floor Slab (Pour 1) Concrete in Progress
  • 17. Tower B LB Floor Slab (Pour 2) – Reinforcement laying in Progress
  • 18. Tower C UB Floor Slab completed
  • 19. Tower D UB Floor Slab (Pour 1) Concrete scheduled for concreting on 19th May 2015
  • 20. Tower C PT Pour 7 – Shuttering in Progress
  • 21. Tower C – Retaining Wall Wall/ Raft in Progress
  • 22. Tower A/B – Retaining Wall Wall/ Raft in Progress