Qualification of manufacturing
equipment
Prepared by: khushboo kunkulol
Guided by: Dr. Ganesh andhale sir.
Alard college of pharmacy, pune.
Equipment Qualification:
 Equipment is an collective analytical measurement assembled to perform a mechanical process.
 Without an equipment we cannot manufacture a product.
 So, EQ ( Equipment Qualification) is action of proving that an equipment works correctly and
accordingly so, as to give the accurate and reliable result.
 If equipment is validated we can ensure that our product is of best quality.
 So term validation and qualification are interlinked to each other.
QUALIFICATION:
Qualification is a process of proving and documenting that an equipment or its ancillary
system are installed properly, work accordingly, and lead to actual expected result.
So, term QUALIFICATION is categorised into four different parts as followed:
I. Design Qualification
II. Installed Qualification
III. Operational Qualification
IV. Performance Qualification.
WHY IT IS REQUIRED?
 To increased throughput
 For reduction in rejections and reworking
 For reduction in utility costs
 For avoidance of capital expenditures
 Fewer complaints about process-related failures
 Reduced testing in-process and in finished goods
 More rapid and reliable start-up of new equipment
 Easier scale-up from development work
 Easier maintenance of equipment
 Improved employee awareness of processes
 More rapid automation
Who should do Equipment Validation? :
 The vendor or the user has the ultimate responsibility for the accuracy of the analysis
results and also for equipment qualification.
 DQ should always be done by the user.
 While IQ for a small and low cost instrument is usually done by the user, IQ for large,
complex and high cost instruments should be done by the vendor.
 OQ can be done by either the user or the vendor.
 PQ should always be done by the user because it is very application specific, and the
vendor may not be familiar with these.
 As PQ should be done on a daily basis, this practically limits this task to the user.
Design Qualification (DQ):
 "Design qualification (DQ) defines the functional and operational specifications of the
instrument and details for the conscious decisions in the selection of the supplier".
 The steps that should be considered for inclusion in a design qualification. Description of the
analysis problem, Description of the intended use of the equipment, Description of the intended
environment, Preliminary selection of the functional and performance specifications,
Preliminary selection of the supplier, Final selection of the equipment, Final selection of the
supplier, Development and documentation of final functional and operational specifications,
Installation Qualification (IQ):
 “Installation qualification establishes that the instrument is received as designed and specified,
that it is properly installed in the selected environment, and that this environment is suitable for
the operation and use of the instrument.”
The qualification involves the coordinated efforts of:
 The vendor.
 The operating department.
 The project team (which provide input into the purchase, installation, operation and
maintenance of the equipment).
Operational Qualification (OQ):
 "Operational qualification (OQ) is the process of demonstrating that an instrument will function
according to its operational specification in the selected environment”.
 The proper operation of equipment is verified by performing the test functions specified in the
protocol.
 A conclusion is drawn regarding the operation of equipment after the test functions are checked
and all data has been analyzed.
Following are the contents of equipment operation qualification:
 1. Application S.O.P’s
 2. Utilization List
 3. Process Description
 4. Test Instrument Utilized To Conduct Test
 5. Test Instrument Calibration
 6. Critical Parameters
 7. Test Function (List)
 8. Test Function Summaries
Performance Qualification (PQ):
 "Performance Qualification (PQ) is the process of demonstrating that an instrument
consistently performs according to a specification appropriate for its routine use ".
 PQ should always be performed under conditions that are similar to routine sample
analysis.
 PQ should be performed on a daily basis or whenever the equipment is being used.
 In practice, PQ can mean system suitability testing, where critical key system
performance characteristics are measured and compared with documented.
LIST OF MANUFACTURING EQUIPMENT
USED MORE OFFENLY:
 Dry powder mixer
 FBD ( Fluidised Bed Dryer)
 Tablet Compression Machine
 Autoclave
 Capsule filing machine
 Homogenizer
Dry Powder Mixer:
 The mixing of dry ingredient that is excipient and API is critical step in
solid dosage form preparation that affect content uniformity at great extent.
Types of Powder Blender:
 V cone Blender
 Double Cone Blender
 Drum mixture
 Ribbon Blender
 Conical Screw Mixer
 Tumble Blender.
URS for Powder Blender:
 Operating criteria must be adequate
 Spare should be available
 Easy maintenance
 Equipment should not disseminate dust
 Low cost
 Non reactive surfactant
 Capacity
 Mixing speed
Installation Qualification:
Detail of Equipment:
 Equipment name, made by and model no. shall be noted down.
 Location for installation equipment shall be checked
 Utilities required shall be listed down
 Any deviation observed while following above procedure should be informed
for corrective action.
Installation Procedure:
 After checking all the specifications as mentioned in the selection criteria,
service engineer shall verify the equipment.
 Authorized validation team shall carry out installation checks.
Sr
no.
Description Specification Method of
Evaluation
Observation
1 Equipment type Visual inspection
2 Surface Finish Visual Inspection
3 Driving motor Visual Inspection
4 Gear box Visual Inspection
5 Control panel
and button
Visual Inspection
6 Dimension Measure tape
Operational qualification:
 After completions of successful installation qualification initiate the actual operation of to ensure
that machine is operating within specification.
 Check the operation qualification parameters against their specifications.
 Document the deviation details
 The Quality head and the department head shall decide whether deviation is acceptable or not.
Sr
no
Description Specification Method of Evaluation Observation
1 On/off switch Lift the On switch and
ensure that power supply is
as required by proper
visualizing either
drum/cone started to rotate
or not.
2 RPM (Revolution
per minute)
Measure the actual RPM
using stop watch
3 Gross Capacity Fill the drum/cone with
potable water and record
Performance qualification
 Load the materials to be mixed in the mixer
 Start the mixer and rotate it for the time as mentioned in the BMR.
 After completion of mixing switch OFF the mixer and separate out the drum.
 Collect the sample as per sampling procedure.
 Send the samples to Quality control dept. for content uniformity, bulk density
and sieve analysis
Fluid Bed Dryer:
 Fluid bed drying is most widely used technique for drying pharmaceutical powders and
granulation.
 The direct contact between particles and air/gas is possible in fluid bed system.
 Here any type of inert gas or air is used.
 They can be designed in either batch or continuous type fluid bed dryer
PRINCIPLE:
 In fluidized bed dryer, hot air is passed at high pressure through a perforated bottom of
the container containing granules to be dried.
 The granules are lifted from the bottom and suspended in the stream of air.
 This condition is called fluidized state.
FBD DESIGN QUALIFICATION:
 The goal is to perform something similar to a risk analysis and to check the design
documents of a technical system to ensure that then fulfils the user requirements.
In fluidized bed dryer the design of the instrument should be:
 Should occupy small place
 Based on our requirement we can go for horizontal or vertical.
 The bed which contain the material should be dried in conical shape or less some particles
may retain as such at the corners
 All technical considerations should be kept in mind while doing the design.
Installation Qualification (IQ):
Installation Qualification for fluidized bed dryer include the following steps:
 Verifying the approved purchase order.
 Check the manufacturer and supplier.
 Check for any physical damage.
 Verify that the utilities required are available.
 User manual
 Maintenance manual.
 List of charge parts.
 Electrical drawings.
Specially for FBD:
 Air temperature distribution.
 Inlet air installation
 Microbiological quality of the inlet air.
 Influence on weather on inlet air conditions.
Operational Qualification (OQ):
Documented verification that the system performs as intended throughout all anticipated operating
ranges, Some of them include:
 Verify alarm control.
 Verify that all switches and push button are functioning properly.
 Heat should distributed equally through out the system.
 Do the tests for uniform distribution of air.
 Establish training program for relevant stages.
 Operate all parts at their low, medium, and high level.
Run three batches of each product and analyze for:
 Speed of air (velocity of air).
 Active ingredients homogeneity.
 Moisture content.
 Particle size distribution.
 Percentage fines.
 Tap density.
 Based on this data we can fix drying end points for each process.
Performance Qualification (PQ):
PQ means to check what we want actually for that particular process from the equipment, what
processes are to be monitored.
 Inlet air speed.
 Quality of air.
 Uniform distribution of air.
 Mixing of air with temperature.
Run the trail batch during operation and there should not be any change in the
 Size
 Shape
 Surface characteristics.
Reference:
 https://www.slideshare.net/priyanka_odela/equipment-validation-of-
fbd#:~:text=Installation%20Qualification%20(IQ)Installation%20Qualification%2
0for%20fluidized%20bed%20dryer%20include,the%20utilities%20required%20ar
e%20available
 https://www.jgtps.com/admin/uploads/1fwM9K.pdf
 https://pharmapathway.com/basics-of-equipment-qualification/
 https://www.slideshare.net/JadhavAnkushJadhav/qualification-of-manufacturing-
equipments
Qualification of manufacturing equipment.

Weitere ähnliche Inhalte

Was ist angesagt?

Qualification of laboratory equipments by Mayuri Soni
Qualification of laboratory equipments by Mayuri SoniQualification of laboratory equipments by Mayuri Soni
Qualification of laboratory equipments by Mayuri SoniMayuri Soni
 
Qualification Of Autoclave
Qualification Of AutoclaveQualification Of Autoclave
Qualification Of Autoclave8669290285
 
Validation utility system
Validation utility systemValidation utility system
Validation utility systemPRANJAY PATIL
 
Auditing of quality assurance and maintenance of engineering department
Auditing of quality assurance and   maintenance of engineering departmentAuditing of quality assurance and   maintenance of engineering department
Auditing of quality assurance and maintenance of engineering departmentPriyanka Kandhare
 
Vendor qualification
Vendor qualificationVendor qualification
Vendor qualificationShihabPatel
 
CHAPTER-1 DEFICIENCIES.pdf
CHAPTER-1 DEFICIENCIES.pdfCHAPTER-1 DEFICIENCIES.pdf
CHAPTER-1 DEFICIENCIES.pdfDr. Dinesh Mehta
 
Auditing of vendors and production department
Auditing of vendors and production departmentAuditing of vendors and production department
Auditing of vendors and production departmentshreyashChaudhari6
 
Validation utility system
Validation utility systemValidation utility system
Validation utility systemArpitSuralkar
 
Validation of compressed air and nitrogen
Validation of compressed air and nitrogenValidation of compressed air and nitrogen
Validation of compressed air and nitrogenManiKandan1405
 
Manufacturing operation and controls
Manufacturing operation and controls Manufacturing operation and controls
Manufacturing operation and controls sachin pawar
 
Distribution, Electronic data handling and controlled documentation by Khushb...
Distribution, Electronic data handling and controlled documentation by Khushb...Distribution, Electronic data handling and controlled documentation by Khushb...
Distribution, Electronic data handling and controlled documentation by Khushb...KhushbooKunkulol
 
Qualification of Dry Heat Sterilizer or Tunnel.pptx
Qualification of Dry Heat Sterilizer or Tunnel.pptxQualification of Dry Heat Sterilizer or Tunnel.pptx
Qualification of Dry Heat Sterilizer or Tunnel.pptxDhruvi50
 
Auditing of Granulation Operation in Dry Production Area
Auditing of Granulation Operation in Dry Production AreaAuditing of Granulation Operation in Dry Production Area
Auditing of Granulation Operation in Dry Production AreaPritam Kolge
 
validation of analytical method used in cleaning
validation of analytical method used in cleaningvalidation of analytical method used in cleaning
validation of analytical method used in cleaningKUNDLAJAYALAKSHMI
 

Was ist angesagt? (20)

Qualification of laboratory equipments by Mayuri Soni
Qualification of laboratory equipments by Mayuri SoniQualification of laboratory equipments by Mayuri Soni
Qualification of laboratory equipments by Mayuri Soni
 
Qualification Of Autoclave
Qualification Of AutoclaveQualification Of Autoclave
Qualification Of Autoclave
 
Cleaning validation
Cleaning validationCleaning validation
Cleaning validation
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
Auditing of quality assurance and maintenance of engineering department
Auditing of quality assurance and   maintenance of engineering departmentAuditing of quality assurance and   maintenance of engineering department
Auditing of quality assurance and maintenance of engineering department
 
Vendor qualification
Vendor qualificationVendor qualification
Vendor qualification
 
CHAPTER-1 DEFICIENCIES.pdf
CHAPTER-1 DEFICIENCIES.pdfCHAPTER-1 DEFICIENCIES.pdf
CHAPTER-1 DEFICIENCIES.pdf
 
Pharmaceutical validation of water system
Pharmaceutical validation of  water system Pharmaceutical validation of  water system
Pharmaceutical validation of water system
 
Auditing of vendors and production department
Auditing of vendors and production departmentAuditing of vendors and production department
Auditing of vendors and production department
 
Qualification of Dry Powder Mixture
Qualification of Dry Powder Mixture Qualification of Dry Powder Mixture
Qualification of Dry Powder Mixture
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
Validation of compressed air and nitrogen
Validation of compressed air and nitrogenValidation of compressed air and nitrogen
Validation of compressed air and nitrogen
 
Manufacturing operation and controls
Manufacturing operation and controls Manufacturing operation and controls
Manufacturing operation and controls
 
Distribution, Electronic data handling and controlled documentation by Khushb...
Distribution, Electronic data handling and controlled documentation by Khushb...Distribution, Electronic data handling and controlled documentation by Khushb...
Distribution, Electronic data handling and controlled documentation by Khushb...
 
Water system validation
Water system validationWater system validation
Water system validation
 
Qualification of Dry Heat Sterilizer or Tunnel.pptx
Qualification of Dry Heat Sterilizer or Tunnel.pptxQualification of Dry Heat Sterilizer or Tunnel.pptx
Qualification of Dry Heat Sterilizer or Tunnel.pptx
 
Computer system validations
Computer system validationsComputer system validations
Computer system validations
 
Auditing of Granulation Operation in Dry Production Area
Auditing of Granulation Operation in Dry Production AreaAuditing of Granulation Operation in Dry Production Area
Auditing of Granulation Operation in Dry Production Area
 
validation of analytical method used in cleaning
validation of analytical method used in cleaningvalidation of analytical method used in cleaning
validation of analytical method used in cleaning
 
Validation qualification
Validation qualificationValidation qualification
Validation qualification
 

Ähnlich wie Qualification of manufacturing equipment.

Equipment validation of fbd
Equipment validation of fbdEquipment validation of fbd
Equipment validation of fbdpriyanka odela
 
Validation of equipments
Validation of equipmentsValidation of equipments
Validation of equipmentssuhasini
 
Qualification of Laboratory Equipments.pptx
Qualification of Laboratory Equipments.pptxQualification of Laboratory Equipments.pptx
Qualification of Laboratory Equipments.pptxHemlataMore3
 
Cleanroom Qualification
Cleanroom QualificationCleanroom Qualification
Cleanroom QualificationAnwar Munjewar
 
solid tablet validation
solid tablet validationsolid tablet validation
solid tablet validationaqsa fatima
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Malla Reddy College of Pharmacy
 
ICH AND WHO GUIDELINES FOR VALIDATION OF EQUIPMENTS.pptx
ICH AND WHO GUIDELINES FOR VALIDATION OF EQUIPMENTS.pptxICH AND WHO GUIDELINES FOR VALIDATION OF EQUIPMENTS.pptx
ICH AND WHO GUIDELINES FOR VALIDATION OF EQUIPMENTS.pptxABG
 
types of validation
types of validation types of validation
types of validation AbdulNaim14
 
Processs validation
Processs validationProcesss validation
Processs validationMani Kandan
 
Pharmaceutical validation, Quantification, streamlining, validation masterplan.
Pharmaceutical validation, Quantification, streamlining, validation masterplan.Pharmaceutical validation, Quantification, streamlining, validation masterplan.
Pharmaceutical validation, Quantification, streamlining, validation masterplan.begalavenu
 
Process Validation.pptx
Process Validation.pptxProcess Validation.pptx
Process Validation.pptxRameshAmuluru1
 
b.Types of validation.gayathri - gayathri murali.pptx
b.Types of validation.gayathri - gayathri murali.pptxb.Types of validation.gayathri - gayathri murali.pptx
b.Types of validation.gayathri - gayathri murali.pptxAarthi358332
 
Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects Apoorva Bauskar
 
validationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdfvalidationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdfAkashChaudhary749568
 

Ähnlich wie Qualification of manufacturing equipment. (20)

Equipment validation of fbd
Equipment validation of fbdEquipment validation of fbd
Equipment validation of fbd
 
Equipment validation of tablet compression ( machine)
Equipment validation of tablet compression ( machine)Equipment validation of tablet compression ( machine)
Equipment validation of tablet compression ( machine)
 
Validation of equipments
Validation of equipmentsValidation of equipments
Validation of equipments
 
Equipment qualification
Equipment qualificationEquipment qualification
Equipment qualification
 
Qualification of Laboratory Equipments.pptx
Qualification of Laboratory Equipments.pptxQualification of Laboratory Equipments.pptx
Qualification of Laboratory Equipments.pptx
 
Cleanroom Qualification
Cleanroom QualificationCleanroom Qualification
Cleanroom Qualification
 
Doc1 copy
Doc1   copyDoc1   copy
Doc1 copy
 
solid tablet validation
solid tablet validationsolid tablet validation
solid tablet validation
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...
 
ICH AND WHO GUIDELINES FOR VALIDATION OF EQUIPMENTS.pptx
ICH AND WHO GUIDELINES FOR VALIDATION OF EQUIPMENTS.pptxICH AND WHO GUIDELINES FOR VALIDATION OF EQUIPMENTS.pptx
ICH AND WHO GUIDELINES FOR VALIDATION OF EQUIPMENTS.pptx
 
types of validation
types of validation types of validation
types of validation
 
Validation
ValidationValidation
Validation
 
IQ-OQ-PQ-for-FBD.pptx
IQ-OQ-PQ-for-FBD.pptxIQ-OQ-PQ-for-FBD.pptx
IQ-OQ-PQ-for-FBD.pptx
 
Processs validation
Processs validationProcesss validation
Processs validation
 
Validation
ValidationValidation
Validation
 
Pharmaceutical validation, Quantification, streamlining, validation masterplan.
Pharmaceutical validation, Quantification, streamlining, validation masterplan.Pharmaceutical validation, Quantification, streamlining, validation masterplan.
Pharmaceutical validation, Quantification, streamlining, validation masterplan.
 
Process Validation.pptx
Process Validation.pptxProcess Validation.pptx
Process Validation.pptx
 
b.Types of validation.gayathri - gayathri murali.pptx
b.Types of validation.gayathri - gayathri murali.pptxb.Types of validation.gayathri - gayathri murali.pptx
b.Types of validation.gayathri - gayathri murali.pptx
 
Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects
 
validationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdfvalidationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdf
 

Kürzlich hochgeladen

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseAnaAcapella
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structuredhanjurrannsibayan2
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsKarakKing
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jisc
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Pooja Bhuva
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Pooja Bhuva
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 

Kürzlich hochgeladen (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 

Qualification of manufacturing equipment.

  • 1. Qualification of manufacturing equipment Prepared by: khushboo kunkulol Guided by: Dr. Ganesh andhale sir. Alard college of pharmacy, pune.
  • 2. Equipment Qualification:  Equipment is an collective analytical measurement assembled to perform a mechanical process.  Without an equipment we cannot manufacture a product.  So, EQ ( Equipment Qualification) is action of proving that an equipment works correctly and accordingly so, as to give the accurate and reliable result.  If equipment is validated we can ensure that our product is of best quality.  So term validation and qualification are interlinked to each other. QUALIFICATION: Qualification is a process of proving and documenting that an equipment or its ancillary system are installed properly, work accordingly, and lead to actual expected result. So, term QUALIFICATION is categorised into four different parts as followed: I. Design Qualification II. Installed Qualification III. Operational Qualification IV. Performance Qualification.
  • 3. WHY IT IS REQUIRED?  To increased throughput  For reduction in rejections and reworking  For reduction in utility costs  For avoidance of capital expenditures  Fewer complaints about process-related failures  Reduced testing in-process and in finished goods  More rapid and reliable start-up of new equipment  Easier scale-up from development work  Easier maintenance of equipment  Improved employee awareness of processes  More rapid automation
  • 4. Who should do Equipment Validation? :  The vendor or the user has the ultimate responsibility for the accuracy of the analysis results and also for equipment qualification.  DQ should always be done by the user.  While IQ for a small and low cost instrument is usually done by the user, IQ for large, complex and high cost instruments should be done by the vendor.  OQ can be done by either the user or the vendor.  PQ should always be done by the user because it is very application specific, and the vendor may not be familiar with these.  As PQ should be done on a daily basis, this practically limits this task to the user.
  • 5. Design Qualification (DQ):  "Design qualification (DQ) defines the functional and operational specifications of the instrument and details for the conscious decisions in the selection of the supplier".  The steps that should be considered for inclusion in a design qualification. Description of the analysis problem, Description of the intended use of the equipment, Description of the intended environment, Preliminary selection of the functional and performance specifications, Preliminary selection of the supplier, Final selection of the equipment, Final selection of the supplier, Development and documentation of final functional and operational specifications, Installation Qualification (IQ):  “Installation qualification establishes that the instrument is received as designed and specified, that it is properly installed in the selected environment, and that this environment is suitable for the operation and use of the instrument.” The qualification involves the coordinated efforts of:  The vendor.  The operating department.  The project team (which provide input into the purchase, installation, operation and maintenance of the equipment).
  • 6. Operational Qualification (OQ):  "Operational qualification (OQ) is the process of demonstrating that an instrument will function according to its operational specification in the selected environment”.  The proper operation of equipment is verified by performing the test functions specified in the protocol.  A conclusion is drawn regarding the operation of equipment after the test functions are checked and all data has been analyzed. Following are the contents of equipment operation qualification:  1. Application S.O.P’s  2. Utilization List  3. Process Description  4. Test Instrument Utilized To Conduct Test  5. Test Instrument Calibration  6. Critical Parameters  7. Test Function (List)  8. Test Function Summaries
  • 7. Performance Qualification (PQ):  "Performance Qualification (PQ) is the process of demonstrating that an instrument consistently performs according to a specification appropriate for its routine use ".  PQ should always be performed under conditions that are similar to routine sample analysis.  PQ should be performed on a daily basis or whenever the equipment is being used.  In practice, PQ can mean system suitability testing, where critical key system performance characteristics are measured and compared with documented.
  • 8. LIST OF MANUFACTURING EQUIPMENT USED MORE OFFENLY:  Dry powder mixer  FBD ( Fluidised Bed Dryer)  Tablet Compression Machine  Autoclave  Capsule filing machine  Homogenizer
  • 9. Dry Powder Mixer:  The mixing of dry ingredient that is excipient and API is critical step in solid dosage form preparation that affect content uniformity at great extent. Types of Powder Blender:  V cone Blender  Double Cone Blender  Drum mixture  Ribbon Blender  Conical Screw Mixer  Tumble Blender.
  • 10. URS for Powder Blender:  Operating criteria must be adequate  Spare should be available  Easy maintenance  Equipment should not disseminate dust  Low cost  Non reactive surfactant  Capacity  Mixing speed
  • 11. Installation Qualification: Detail of Equipment:  Equipment name, made by and model no. shall be noted down.  Location for installation equipment shall be checked  Utilities required shall be listed down  Any deviation observed while following above procedure should be informed for corrective action. Installation Procedure:  After checking all the specifications as mentioned in the selection criteria, service engineer shall verify the equipment.  Authorized validation team shall carry out installation checks.
  • 12. Sr no. Description Specification Method of Evaluation Observation 1 Equipment type Visual inspection 2 Surface Finish Visual Inspection 3 Driving motor Visual Inspection 4 Gear box Visual Inspection 5 Control panel and button Visual Inspection 6 Dimension Measure tape
  • 13. Operational qualification:  After completions of successful installation qualification initiate the actual operation of to ensure that machine is operating within specification.  Check the operation qualification parameters against their specifications.  Document the deviation details  The Quality head and the department head shall decide whether deviation is acceptable or not. Sr no Description Specification Method of Evaluation Observation 1 On/off switch Lift the On switch and ensure that power supply is as required by proper visualizing either drum/cone started to rotate or not. 2 RPM (Revolution per minute) Measure the actual RPM using stop watch 3 Gross Capacity Fill the drum/cone with potable water and record
  • 14. Performance qualification  Load the materials to be mixed in the mixer  Start the mixer and rotate it for the time as mentioned in the BMR.  After completion of mixing switch OFF the mixer and separate out the drum.  Collect the sample as per sampling procedure.  Send the samples to Quality control dept. for content uniformity, bulk density and sieve analysis
  • 15. Fluid Bed Dryer:  Fluid bed drying is most widely used technique for drying pharmaceutical powders and granulation.  The direct contact between particles and air/gas is possible in fluid bed system.  Here any type of inert gas or air is used.  They can be designed in either batch or continuous type fluid bed dryer PRINCIPLE:  In fluidized bed dryer, hot air is passed at high pressure through a perforated bottom of the container containing granules to be dried.  The granules are lifted from the bottom and suspended in the stream of air.  This condition is called fluidized state.
  • 16. FBD DESIGN QUALIFICATION:  The goal is to perform something similar to a risk analysis and to check the design documents of a technical system to ensure that then fulfils the user requirements. In fluidized bed dryer the design of the instrument should be:  Should occupy small place  Based on our requirement we can go for horizontal or vertical.  The bed which contain the material should be dried in conical shape or less some particles may retain as such at the corners  All technical considerations should be kept in mind while doing the design.
  • 17. Installation Qualification (IQ): Installation Qualification for fluidized bed dryer include the following steps:  Verifying the approved purchase order.  Check the manufacturer and supplier.  Check for any physical damage.  Verify that the utilities required are available.  User manual  Maintenance manual.  List of charge parts.  Electrical drawings. Specially for FBD:  Air temperature distribution.  Inlet air installation  Microbiological quality of the inlet air.  Influence on weather on inlet air conditions.
  • 18. Operational Qualification (OQ): Documented verification that the system performs as intended throughout all anticipated operating ranges, Some of them include:  Verify alarm control.  Verify that all switches and push button are functioning properly.  Heat should distributed equally through out the system.  Do the tests for uniform distribution of air.  Establish training program for relevant stages.  Operate all parts at their low, medium, and high level. Run three batches of each product and analyze for:  Speed of air (velocity of air).  Active ingredients homogeneity.  Moisture content.  Particle size distribution.  Percentage fines.  Tap density.  Based on this data we can fix drying end points for each process.
  • 19. Performance Qualification (PQ): PQ means to check what we want actually for that particular process from the equipment, what processes are to be monitored.  Inlet air speed.  Quality of air.  Uniform distribution of air.  Mixing of air with temperature. Run the trail batch during operation and there should not be any change in the  Size  Shape  Surface characteristics.