HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
Risk Assessment
1. Risk Assessment
Scene Party Scene Risk-Assessment 3
number
Project On My Own - Yasmin Names Khem Slawson
Location Hall (School) Assistants Rachael Halstead
Date Assessed 22/10/2012
What hazards have What are the What measures have been taken to prevent injury or Number Who is
been identified? potential injuries damage? of responsible for
or damage? people action?
at risk
Severity (1, 2 or 3)
Trip/ fall because 2 We need to make sure that we are watching for any wires 2 Me and Rachael
there are lots of on the floor
wires
Trip on the stairs 1 We have to make sure that we are looking at the steps on 2 Me and Rachael
the stairs and holding onto the rail
Hearing loss 1 We have to make sure that the music is not really loud Lots Me and Rachael
The equipment 1 We have to make sure that we are holding onto the 1 Me and Rachael
might break equipment when we go up/down the stairs
Likelihood of occurrence: High, Medium, Unlikely