PowerPoint rendering of the project goals as outlined by our team manual, prepared by myself and four team members at the 2014 International Builders Show Residential Construction Management Competition in Las Vegas, Nevada.
3. VERRADO COMMUNITY
in 1999 the Verrado Community Master Plan was approved
by the Town Council. The community was annexed to the city
of Buckeye, Arizona.
In 2007, the Buckeye General Plan designated this property
as a Master Planned Community.
Of the 7 Phases of development southwest of Phoenix, our
project is situated in Phase 3 South.
This Preliminary Plat consists of 11 development parcels
(2.101-106 and 2.201-205).
4. A single family house located
in Verrado, just 25 miles
outside Phoenix, Arizona.
Verrado is anchored by a
pedestrian-friendly Main
Street and offers residents
miles of parks and trails,
educational and recreational
facilities, a championship golf
course as well as a variety of
clubs and activities.
5. Has a hot desert climate.
The hottest month is August, with an average daily high temperature
of 105°F
The average low temperature is 43°F in January .
Elevation: 869 Ft
6. Excellent access to
transportation, with
access to Interstate 10
just one mile south and
Loop 303 just five
miles to the east.
GOOGLE EARTH VIDEO
Our parcel, contains
80 lots, of which we
have chosen lot 157,
oriented lengthwise
north to south.
7. The context is predominantly single
family detached dwellings. Duplex
residential buildings are located along
the street.
The street hierarchy includes a main
north-south avenue: Verrado Way, and
secondary local residential streets.
The site is located on an east-west
local residential street: E. Delaney
Drive. which has low traffic.
A view corridor from the street to the
east terminates at a pleasant green
open area, which reduces the effect of
heat gain and brings a microclimate to
the surroundings.
8. • The contour slopes from the north-west
to the south-east.
• Prevailing winds originating from the
north support the natural ventilation.
• Front landscape set back. Rear gardens
and open area characterize the open
space.
9. Master bedroom, great room and kitchen
have areas facing north and receive
suitable access to daylight.
Covered patio facing north has daylight
and it is cooler during most part of the day.
Game room and secondary bedroom have
areas facing north and receive access to
daylight.
Second floor has cross ventilation.
c
o
c
o
10. DUAL FLUSH TOILET
• REQUIRES LESS WATER TO OPERATE.
• PRICE COMPARISON:
COLONY- W TOILET (1.6 GPF) $147
DUAL FLUSH TOILET (1.6 & 1 GPF)
$200
PROFILE SMART 305 ROUND FRONT PLUS–
CAROMA
• HIGH EFFICIENCY DUAL FLUSH TOILET 1.28 & 0.8 GPF
• INTEGRATED SINK FOR GREATER WATER SAVINGS
11. SOLAR HOT WATER HEATING
• Uses heat from the sun to work
alongside a conventional water
heater.
• The average domestic system
reduces carbon dioxide emissions
by around 400kg per year,
depending on the fuel replaced.
• It is preferable to have a minimum
roof area of 43 sqft. facing south-
east to south-west.
• COST: $5,000 - $7,000
• Savings + Incentives
12. Division 2 - Earthwork
Division 3 - Concrete
Division 6 - Framing
Division 9 - Finishes
Division 7 - Thermal and
Moisture Protection
Division 8 - Doors and Windows
13. Division 6 - Wood/Plastic/Composites, & Supplies
Description Unit Quantity
Material Cost,
per Unit
Labor Cost Equipment Cost Total Cost Category Total
Wood and Plastic Fasteners
Framing Nails, Grip-Rite, 3" x 0.120-Guage
Smooth Shank Galvanized, 2000 per Box
Each 20 $28.65 $573.00
Rough Carpentry
Wood Framing Unit Quantity
Material Cost,
per Unit
Labor Cost Equipment Cost Total Cost Category Total
Fascia
2x6, SPF, #2, Subfascia Linear Ft. 418 $0.64 $267.10
2x4, SPF, #2, Outlooks & Nailers Linear Ft. 836 $0.43 $355.92
1st Floor Walls
Beams & Headers
2x12, SPF, #2 Each
2 @ 20', 4 @
16', 17 @ 14', 6
@ 12', 6 @ 10',
9 @ 8'
By Quote $818.59
Plywood, 1/2", OSB/CD, 4X8 sheets Each 9 $11.90 $107.14
Plates
2x4 Plate, Top, SPF Linear Ft 3110 $0.43 $1,323.73
2x6 Plate, Top, SPF* Each 3 @ 8', 3 @ 10' By Quote $34.34
2x4 (Treated) Bottom Plate, at Slab, SPF* Linear Ft 622 $0.50 $309.50
2x4, (Treated) Bottom Plate, at slab Each 3 @ 8', 3 @ 10' By Quote $53.56
2x6 (Treated) Bottom Plate, at Slab, SPF* Each 1 @ 8', 1 @ 10' By Quote $65.47
Arches
5/8" OSB, 4x8* Each 33 $20.36 $671.72
Studs
2x4 Precut @ 116 5/8", SPF Each 704 $4.32 $3,041.28
2x6, precut@ 116 5/8", SPF* Each 18 $6.48 $116.64
14. 2nd Floor Walls
Beams & Headers
2x12, SPF, #2 Each 9 @ 14', 1 @ 10' By Quote $201.89
Plywood, 1/2", OSB/CD, 4X8 sheets Each 3 $11.90 $35.71
Plates
2x4, SPF Linear Ft 2364 $0.42 $997.25
2x6, SPF* Each 4 @ 10’, 4 @ 14’ By Quote $61.06
Studs
2x4, SPF, precut @ 104-5/8" Each 426 $4 $1,656.29
2x6, SPF, precut @ 104-5/8" Each 24 $5.83 $139.97
Stairs:
2x12, SPF Each 11 @ 12', 4 @ 8' By Quote $242.50
Flooring
Subflooring:
3/4" Underlayment, X-Band, "C" Grade, 4X8, UL Plywood,
Tongue & Groove
Each 57 $30.30 $1,727.10
Adhesive, CAQ Type Each 10 $55.00 $550.00
#10 Ring Shank Nails, Pneumatic Strips Each 3 $224.00 $672.00
Exterior Wall sheathing
Windstorm, 7/16", 4'x11', OSB Sheathing Each 158 $19.49 $3,079.42
Tyvek Home Wrap, 9'x150', by Roll Each 5 $137.00 $685.00
Tyvek Stucco Wrap, 5'x200'', by Roll Each 4 $183.63 $734.52
Plastic-Hed Yellowcap Nails, 1", 2000 ct. Carton Each 1 $49.30 $49.30
Roof Decking
Plywood, OSB Techshield, 5/8"*, 4x8 Each 165 $20.35 $3,358.08
Plywood Clips, 5/8, by Carton Each 4 $6.47 $25.88
Rough Carpentry, Total $45,044.97
15. THROUGH 6/13/2014
ION
UCTION
MING
MING
NG
T. ROUGH-INS
S
ECTIONS
DOOR INSTALLATION
H MATERIALS
STALLATION
TALLATION/FINISHES
NG
ALKWAY CONCRETE
S
S
INISH
ISH
G
AL
SHES
OUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11THROUGH 6/13/2014
ION
UCTION
MING
MING
NG
T. ROUGH-INS
S
ECTIONS
DOOR INSTALLATION
MATERIALS
STALLATION
TALLATION/FINISHES
NG
ALKWAY CONCRETE
S
S
INISH
ISH
G
AL
SHES
OUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
INITIAL
CONSTRUCTION
BEGINFOUNDATION
EXCAVATIO
N
HROUGH 6/13/2014
ON
CTION
ING
MING
G
T. ROUGH-INS
ECTIONS
OOR INSTALLATION
MATERIALS
STALLATION
ALLATION/FINISHES
NG
LKWAY CONCRETE
NISH
SH
G
L
SHES
UGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11HROUGH 6/13/2014
ON
CTION
NG
MING
G
. ROUGH-INS
CTIONS
OOR INSTALLATION
MATERIALS
TALLATION
ALLATION/FINISHES
NG
LKWAY CONCRETE
NISH
SH
G
L
HES
UGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11OUGH 6/13/2014
N
TION
G
NG
ROUGH-INS
TIONS
OR INSTALLATION
ATERIALS
ALLATION
LATION/FINISHES
G
WAY CONCRETE
SH
ES
GH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11OUGH 6/13/2014
N
ION
G
G
OUGH-INS
TIONS
OR INSTALLATION
ATERIALS
ALLATION
LATION/FINISHES
WAY CONCRETE
SH
ES
GH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11UGH 6/13/2014
ON
G
OUGH-INS
ONS
R INSTALLATION
TERIALS
LLATION
ATION/FINISHES
WAY CONCRETE
H
S
H
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11GH 6/13/2014
N
UGH-INS
NS
INSTALLATION
ERIALS
ATION
TION/FINISHES
AY CONCRETE
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 112/7/2014 THROUGH 6/13/2014
ONSTRUCTION
L CONSTRUCTION
VATION
DATION
OOR FRAMING
FRAMING
LOOR FRAMING
FRAMING
H SHEATHING
BING/ELECT. ROUGH-INS
ROUGH-INS
H-INS INSPECTIONS
OW/ EXT. DOOR INSTALLATION
H ROOFING
IOR FINISH MATERIALS
ATON
HOWER INSTALLATION
OARD INSTALLATION/FINISHES
IOR PAINTING
WAY & WALKWAY CONCRETE
ANCES
& GATE
SCAPING
IOR DOORS
HING STAIRS
IOR TRIM
T FLOOR FINISH
FLOOR FINISH
H PLUMBING
H ELECTRICAL
H HVAC
ETRY
TERTOPS
ROOM FINISHES
CLEANING
WALKTHROUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16WK 112/7/2014 THROUGH 6/13/2014
ONSTRUCTION
L CONSTRUCTION
VATION
DATION
OOR FRAMING
FRAMING
LOOR FRAMING
FRAMING
H SHEATHING
BING/ELECT. ROUGH-INS
ROUGH-INS
H-INS INSPECTIONS
OW/ EXT. DOOR INSTALLATION
H ROOFING
IOR FINISH MATERIALS
ATON
HOWER INSTALLATION
OARD INSTALLATION/FINISHES
IOR PAINTING
WAY & WALKWAY CONCRETE
ANCES
& GATE
SCAPING
IOR DOORS
HING STAIRS
IOR TRIM
T FLOOR FINISH
FLOOR FINISH
H PLUMBING
H ELECTRICAL
H HVAC
ETRY
TERTOPS
ROOM FINISHES
CLEANING
WALKTHROUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16WK 112/7/2014 THROUGH 6/13/2014
ONSTRUCTION
CONSTRUCTION
ATION
ATION
OOR FRAMING
RAMING
OOR FRAMING
RAMING
SHEATHING
ING/ELECT. ROUGH-INS
ROUGH-INS
H-INS INSPECTIONS
OW/ EXT. DOOR INSTALLATION
ROOFING
OR FINISH MATERIALS
TON
HOWER INSTALLATION
OARD INSTALLATION/FINISHES
OR PAINTING
WAY & WALKWAY CONCRETE
NCES
& GATE
CAPING
OR DOORS
NG STAIRS
OR TRIM
T FLOOR FINISH
LOOR FINISH
PLUMBING
ELECTRICAL
HVAC
ETRY
ERTOPS
OOM FINISHES
CLEANING
WALKTHROUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16WK 112/7/2014 THROUGH 6/13/2014
ONSTRUCTION
L CONSTRUCTION
ATION
DATION
OOR FRAMING
FRAMING
LOOR FRAMING
FRAMING
H SHEATHING
BING/ELECT. ROUGH-INS
ROUGH-INS
H-INS INSPECTIONS
OW/ EXT. DOOR INSTALLATION
H ROOFING
IOR FINISH MATERIALS
ATON
HOWER INSTALLATION
OARD INSTALLATION/FINISHES
IOR PAINTING
WAY & WALKWAY CONCRETE
ANCES
& GATE
SCAPING
IOR DOORS
HING STAIRS
IOR TRIM
T FLOOR FINISH
FLOOR FINISH
H PLUMBING
H ELECTRICAL
H HVAC
ETRY
TERTOPS
ROOM FINISHES
CLEANING
WALKTHROUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16WK 112/7/2014 THROUGH 6/13/2014
ONSTRUCTION
L CONSTRUCTION
ATION
DATION
OOR FRAMING
FRAMING
LOOR FRAMING
FRAMING
SHEATHING
BING/ELECT. ROUGH-INS
ROUGH-INS
H-INS INSPECTIONS
OW/ EXT. DOOR INSTALLATION
ROOFING
IOR FINISH MATERIALS
ATON
HOWER INSTALLATION
OARD INSTALLATION/FINISHES
OR PAINTING
WAY & WALKWAY CONCRETE
ANCES
& GATE
SCAPING
OR DOORS
ING STAIRS
OR TRIM
T FLOOR FINISH
FLOOR FINISH
PLUMBING
ELECTRICAL
HVAC
ETRY
TERTOPS
ROOM FINISHES
CLEANING
WALKTHROUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16WK 11014
TION
SHES
ETE
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
FOUNDATIO
N
1STFLOOR
FRAMING
STAIR
FRAMING
2NDFLOOR
FRAMING
PLUMBING/ELECT.ROUGH-INS
FINISH
SHEATHING
PLUMBING/ELECT.ROUGH-
INS
HVACROUGH-
INS
FINISHSTAIRS
WINDOW/EXT.
DOOR
ROUGH-INS
INSPECTIONS
EXT.FINISH
MATERIALS
GYP.BOARD
INSTALLATION
TUB/SHOWER
INSTALLATION
HROUGH 6/13/2014
ON
CTION
NG
ING
G
. ROUGH-INS
CTIONS
OOR INSTALLATION
MATERIALS
TALLATION
ALLATION/FINISHES
G
KWAY CONCRETE
NISH
H
L
HES
UGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
WK 15
INT. PAINT
WK 17 WK 18
OF DAYS: 94
WK 8 WK 9 WK 10
5 DAYS A WEEK, 8 HOURS A DAY
WK 12 WK 13 WK 14
MILESTONES
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
2/7/2014 THROUGH 6/13/2014
ONSTRUCTION
L CONSTRUCTION
VATION
DATION
OOR FRAMING
FRAMING
LOOR FRAMING
FRAMING
H SHEATHING
BING/ELECT. ROUGH-INS
ROUGH-INS
H-INS INSPECTIONS
OW/ EXT. DOOR INSTALLATION
H ROOFING
IOR FINISH MATERIALS
ATON
HOWER INSTALLATION
OARD INSTALLATION/FINISHES
IOR PAINTING
WAY & WALKWAY CONCRETE
ANCES
& GATE
SCAPING
IOR DOORS
HING STAIRS
IOR TRIM
T FLOOR FINISH
FLOOR FINISH
H PLUMBING
H ELECTRICAL
H HVAC
ETRY
TERTOPS
ROOM FINISHES
CLEANING
WALKTHROUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16WK 11
WK 15 WK 17 WK 18
OF DAYS: 94
WK 8 WK 9 WK 10
5 DAYS A WEEK, 8 HOURS A DAY
WK 12 WK 13 WK 14
MILESTONES
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
INTERIOR
DOORS
LANDSCAPEIN
G
FENCE&
GATE
TRIMFLOOR
FINISH
APPLIANCES
CARPETFLOOR
FINISH
INTERIOR
TRIM
FINISH
STAIRS
CABINET
RY
FINISH
HVAC
FINISH
ELECT.
FINISH
PLUMBING
FINAL
WALKTHROUGH
FINAL
CLEANING
BATHROOM
FINISHES
COUNTERTO
PS
THROUGH 6/13/2014
ION
UCTION
ING
MING
NG
T. ROUGH-INS
S
ECTIONS
DOOR INSTALLATION
MATERIALS
STALLATION
TALLATION/FINISHES
NG
LKWAY CONCRETE
S
S
NISH
SH
G
AL
SHES
OUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
WK 19WK 15
INT. PAINT
WK 17 WK 18
94
WK 10
5 DAYS A WEEK, 8 HOURS A DAY
WK 12 WK 13 WK 14
MILESTONES
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
THROUGH 6/13/2014
TION
UCTION
MING
MING
NG
CT. ROUGH-INS
NS
PECTIONS
DOOR INSTALLATION
G
H MATERIALS
NSTALLATION
TALLATION/FINISHES
ING
ALKWAY CONCRETE
S
RS
FINISH
ISH
NG
CAL
ISHES
G
OUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
MILESTONES
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
STRUCTIONTIMELINE
WK 19WK 15
INT. PAINT
WK 17 WK 18
5 DAYS A WEEK, 8 HOURS A DAY
WK 12 WK 13 WK 14
MILESTONES
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
ROOFFRAMING
2NDFLOOR
FRAMING
PRE-
CONSTRUCTION
FOUN`DATIO
N
ISULATION
2/7/2014 THROUGH 6/13/2014
ONSTRUCTION
L CONSTRUCTION
ATION
DATION
OOR FRAMING
FRAMING
LOOR FRAMING
FRAMING
SHEATHING
BING/ELECT. ROUGH-INS
ROUGH-INS
H-INS INSPECTIONS
OW/ EXT. DOOR INSTALLATION
ROOFING
IOR FINISH MATERIALS
ATON
HOWER INSTALLATION
OARD INSTALLATION/FINISHES
OR PAINTING
WAY & WALKWAY CONCRETE
ANCES
& GATE
CAPING
OR DOORS
ING STAIRS
OR TRIM
T FLOOR FINISH
FLOOR FINISH
PLUMBING
ELECTRICAL
HVAC
ETRY
TERTOPS
ROOM FINISHES
CLEANING
WALKTHROUGH
WK 19WK 15
INT. PAINT
WK 17 WK 18WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 12 WK 13 WK 14
FOUNDATION
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16WK 11
WK 15 WK 17 WK 18
DAYS: 94
WK 8 WK 9 WK 10
5 DAYS A WEEK, 8 HOURS A DAY
WK 12 WK 13 WK 14
MILESTONES
PLUMBING / ELEC.
HVAC
EXT. FINISH
WK 16
ORDER TRUSSES, CONCRETE, CALL PLUMBING CONTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC CONTRACTERS FOR FINISHES
FLOORING, COUNTERTOP, CABINET CONTRACTERS
CALL INT. FINISH, LANDSCAPE CONCTRACTERS
CALL PLUMBING, ELECTRICAL, HVAC, EXT. FINISH CONTRACTERS
WK 11
DRIVEWAY/WALKWAY
CONCRETE
INTERIOR
PAINTING
17. Also with a view at
night,
which gives you an
idea of how the
interior lighting
reflects.
18. Trace Ceilings
10’ Ceilings
Arch Ways
Open Floor Plan
Many Windows
For Natural
Lighting
19. Residential Construction Management Competition(RCMC) panel of
judges.
Professor P. Victor Mirzai
Home Builders Association of Greater New Orleans
New Orleans Education League of Construction
Delgado Community College Student Government Association
Letterman's Reproduction Company
City Blueprint and Supply Company
National Housing Endowment
Without their support and along with funding this project it would have never been
completed.
Our TEAM is very happy to have an opportunity to work on this realistic national
competition project. We are extremely thankful to receive feed back
and constructive criticism from the panel of judges.