PRESSURE TEST :-PRESSURE TEST :-
Introduction :Introduction :
ƒ Pressure Test is performed or conducted when
there are new or old operating equipment like
Boilers, Heat Exchangers, Pipe Connections and
other pressure vessels installed.
ƒ All pressure vessels must go through the pressure
test before they are permitted to operate.
ƒ In Malaysia, there are the regulation enforced by
Malaysian Authority under the Department of
Occupational Safety and Health (DOSH).
ƒ There are 2 pressure tests performed :-
Pressure Leak Test
Pressure Strength Test - commonly known
as Hydrostatic Test.
PRESSURE TEST cont :-PRESSURE TEST cont :-
Objectives :Objectives :
ƒ Fired and Unfired pressure vessels are under
government regulation, their objectives are to
prevent :-
accidents that could cause undue risk to
the personnel working at or near the plant
equipment,
accidents that could cause several severe
material damage and consequently
substantial economic losses,
accidents that could cause risk of pollution
to the environment,
downtime in plant production.
PRESSURE TEST cont :-PRESSURE TEST cont :-
Definition:Definition:
ƒ Design Pressure :
ƒ The pressure used in the design of a vessel.
It is manufacturer recommended design
pressure on each equipment. This design
pressure is higher than operating pressure
and it will satisfy the requirement of the
pressure of the fluid and other content of
the vessel standard.
ƒ Operating Pressure :
ƒ This is the pressure which pressure vessel
can work safely or operate normally.
PRESSURE TEST cont :-PRESSURE TEST cont :-
DefinitionDefinition contcont ::
ƒ Maximum Allowable Working Pressure (MAWP) :
ƒ It is the internal pressure at which the weakest element
of the vessel is loaded to the ultimate permissible point,
when the vessel is assumed to be :-
corroded condition
under the effect of a designed temperature
in normal operating condition
under the effect of other loading, like wind, external
pressure, etc.
ƒ This MAWP is higher than operating pressure.
ƒ Test Pressure :
ƒ This is manufacturer recommended hydrostatic pressure
test when the vessel or equipment is new as appeared on
the equipment name plate.
PRESSURE TEST cont :-PRESSURE TEST cont :-
1. Pressure Leak Test (1.10 x MAWP) :1. Pressure Leak Test (1.10 x MAWP) :
The purpose is to detect leaking paths through the
"pressure envelope" in either direction.
The methods used may be straightforward using water
or gas, like air or inner search gases.
Leakage detection may be visual or measurement of
pressure drop, pressure vacuum decay rate, trace gas
or water respond to detection instrument, audible or
ultrasonic devices, fluorescent dyes, etc.
The pressure applied in the case of trace gas techniques
should be of a very low order and for audible or visual
technique it should be equal to the working pressure of
the vessel with small multiplying factor but it should
not in any circumstances exceed 110% of the MAWP.
PRESSURE TEST cont :-PRESSURE TEST cont :-
2. Hydrostatic Test (1.50 x MAWP) :2. Hydrostatic Test (1.50 x MAWP) :
ƒ Is the statutory requirement of pressure vessel in
order to verify and demonstrate the continued
fitness for services.
ƒ The pressure applied may approach up to original
design pressure with a suitable correction factor
applied for the ambient design temperature
differential and deviation from the new and old
condition.
ƒ In practice, the standard hydrostatic pressure test is
equal to 150% of the MAWP.
ƒ Hydrostatic should also be applied when repairs
or modifications have been carried out which
affect the structural integrity of the pressure shell
and foundation.
PRESSURE TEST cont :-PRESSURE TEST cont :-
2. Hydrostatic Test (1.50 x MAWP) cont :2. Hydrostatic Test (1.50 x MAWP) cont :
ƒ Also hydrostatic test is conducted after all
fabrication work has been completed.
ƒ During the testing process temporary
gasket may be used
ƒ Hydrostatic Test Pressure =
1.5 (MAWP) (stress value at test temp.F)
(stress value at design temp.F)
# NOTE : All hydrostatic Test shall be witnessed by Inspector.
However, the Senior Inspector may approve the following
person to witness the mentioned test during off-hours.
PRESSURE TEST cont :-PRESSURE TEST cont :-
2. Hydrostatic Test (1.50 x MAWP) cont :2. Hydrostatic Test (1.50 x MAWP) cont :
ƒ For pipeline, the test pressure shall be
governed by the line flange rating unless the
line is for a non-critical services when
inspections will advice the test pressure
Pressure Rating (psi) 150 300 400 600 900 1500 2500
Hydrostatic Test (psi) 450 1100 1450 2175 3250 5400 9000
PRESSURE TEST cont :-PRESSURE TEST cont :-
Hydrostatic Test Procedure on Pipes :Hydrostatic Test Procedure on Pipes :
The steps below are typical procedures while other
may have added requirements :-
1 Bolts together the 2 pipes.
2 Connect the elbow casting simplifies the end of the pipelines.
The fitting of the elbow casting simplifies the process of filling
the pipeline with water.
3 Bolt a flange fitted with a shut off cock to the other end of the
pipe.
4 Close the shut off cock and fill the pipeline with water until the
water start to flow through the elbow.
5 Bolt a flange with a pressure gauge connection to the elbow
casting
6 Connect the test pump to the shut off cock
PRESSURE TEST cont :-PRESSURE TEST cont :-
Hydrostatic Test Procedure on PipesHydrostatic Test Procedure on Pipes (cont):(cont):
7 Open the shut off cock and operate the test pump until
water overflows from the pressure gauge connection
(BLEEDING PROCESS).
8 Fit the pressure gauge.
9 Operate the test pump until the pressure gauge indicates the
specified test pressure.
10Inspect for leaks in the pipeline at the flange joint, as well as
the pipe system in general.
11Release the pressure from the pipeline through the test
pump discharge cock.
12Disconnect the test pump and drain the pipeline through the
shut off cock.
13Remove the blank flanges and dismantle the pipe joints.
PRESSURE TEST cont :-PRESSURE TEST cont :-
Hydrostatic Test Procedure on PipesHydrostatic Test Procedure on Pipes (cont):(cont):
PRESSURE TEST cont :-PRESSURE TEST cont :-
Safety Requirements :Safety Requirements :
ƒ Safety Requirements :-
1Depressurising the equipment after inspection
and the test has been approved must be done by
releasing the pressure slowly through the vent
and drain valves.
2The vent valve needs to be opened to release
pressure and yo admit air when draining to
prevent collapsing of the system by pulling a
vacuum.
3Never leave equipment an attended at any time
when it is under pressure.
4Always wear safety gear when conducting
hydrostatic test.
ƒ The record and inspection report are to be
kept properly according to the requirements of
inspection manual of pressure vessels. It is
necessary to keep a record of all inspection
result of each vessel from the initial inspection
to the latest inspection, so that comparison
and analysis can be made from these inspection
result.
ƒ Plan and report are to be submitted for
evaluation before issuance of inspection
certificate by Malaysian Authority (DOSH).
PRESSURE TEST cont :-PRESSURE TEST cont :-
Safety RequirementsSafety Requirements contcont ::

Weitere ähnliche Inhalte

Was ist angesagt?

Piping sample report
Piping sample reportPiping sample report
Piping sample report
ram111eg
 

Was ist angesagt? (20)

Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas EngineerPiping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
 
7) hydro test 3
7) hydro test 37) hydro test 3
7) hydro test 3
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
 
Pressure testing
Pressure testingPressure testing
Pressure testing
 
valve maintenance-packing-replacement
valve maintenance-packing-replacementvalve maintenance-packing-replacement
valve maintenance-packing-replacement
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
 
Piping components, materials, codes and standards part 1- pipe
Piping components, materials, codes and standards   part 1- pipePiping components, materials, codes and standards   part 1- pipe
Piping components, materials, codes and standards part 1- pipe
 
Piping design and flexibility analysis
Piping design and flexibility analysisPiping design and flexibility analysis
Piping design and flexibility analysis
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
 
190391352-Pressure-Testing.ppt
190391352-Pressure-Testing.ppt190391352-Pressure-Testing.ppt
190391352-Pressure-Testing.ppt
 
Valves ppt
Valves pptValves ppt
Valves ppt
 
Piping handbook
Piping handbookPiping handbook
Piping handbook
 
Testing of Safety Valves
Testing of Safety ValvesTesting of Safety Valves
Testing of Safety Valves
 
Flanged Joint Alignment
Flanged Joint AlignmentFlanged Joint Alignment
Flanged Joint Alignment
 
Emergency Shutdown System, ESD System - Worldwide Oilfield Machine
Emergency Shutdown System, ESD System - Worldwide Oilfield MachineEmergency Shutdown System, ESD System - Worldwide Oilfield Machine
Emergency Shutdown System, ESD System - Worldwide Oilfield Machine
 
Different types of valves used in piping
Different types of valves used in pipingDifferent types of valves used in piping
Different types of valves used in piping
 
Butt fusion welding procedure eng
Butt fusion welding procedure engButt fusion welding procedure eng
Butt fusion welding procedure eng
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 

Andere mochten auch

Materials Handling Ppt
Materials Handling PptMaterials Handling Ppt
Materials Handling Ppt
Colleen True
 
Pressure vessel manufacturing
Pressure vessel manufacturingPressure vessel manufacturing
Pressure vessel manufacturing
physics101
 

Andere mochten auch (16)

Manpower planning job analysis for restaurant hotel
Manpower planning job analysis for restaurant hotelManpower planning job analysis for restaurant hotel
Manpower planning job analysis for restaurant hotel
 
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & MarkingPipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
 
Iso 9001 training
Iso 9001 trainingIso 9001 training
Iso 9001 training
 
Welding defects
Welding defectsWelding defects
Welding defects
 
Material Handling Equipments
Material Handling EquipmentsMaterial Handling Equipments
Material Handling Equipments
 
Materials Handling Ppt
Materials Handling PptMaterials Handling Ppt
Materials Handling Ppt
 
Welding defects
Welding defectsWelding defects
Welding defects
 
Quality Improvement Methods
Quality Improvement MethodsQuality Improvement Methods
Quality Improvement Methods
 
Material Handling
Material HandlingMaterial Handling
Material Handling
 
Pressure vessel manufacturing
Pressure vessel manufacturingPressure vessel manufacturing
Pressure vessel manufacturing
 
ISO 9001: 2008 QMS Awareness PPT
ISO 9001: 2008 QMS Awareness PPTISO 9001: 2008 QMS Awareness PPT
ISO 9001: 2008 QMS Awareness PPT
 
The new ISO 9001:2015
The new ISO 9001:2015The new ISO 9001:2015
The new ISO 9001:2015
 
Welding Presentation.
Welding Presentation.Welding Presentation.
Welding Presentation.
 
training & development ppt
training & development ppttraining & development ppt
training & development ppt
 
Welding ppt
Welding pptWelding ppt
Welding ppt
 
Hypothesis testing; z test, t-test. f-test
Hypothesis testing; z test, t-test. f-testHypothesis testing; z test, t-test. f-test
Hypothesis testing; z test, t-test. f-test
 

Ähnlich wie pipefitting pressure-test

Regulator – inspection & testing
Regulator – inspection & testingRegulator – inspection & testing
Regulator – inspection & testing
GasUtility
 
Pressure safety valves
Pressure safety valvesPressure safety valves
Pressure safety valves
Amol Dudhate
 
Pressure Vacuum Relief Valve.pptx
Pressure Vacuum Relief Valve.pptxPressure Vacuum Relief Valve.pptx
Pressure Vacuum Relief Valve.pptx
SwamiVidya
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
Mark Platten
 
Pressure Reliveing Devices1
Pressure Reliveing Devices1Pressure Reliveing Devices1
Pressure Reliveing Devices1
Om Pratap Singh
 
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
holegajendra
 
control valve functional testing - Swetha
control valve functional testing - Swethacontrol valve functional testing - Swetha
control valve functional testing - Swetha
Swetha Sundaram
 

Ähnlich wie pipefitting pressure-test (20)

NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0
 
Lessons learned solving pilot valve instability issues on LNG storage tanks
Lessons learned solving pilot valve instability issues on LNG storage tanksLessons learned solving pilot valve instability issues on LNG storage tanks
Lessons learned solving pilot valve instability issues on LNG storage tanks
 
Regulator – inspection & testing
Regulator – inspection & testingRegulator – inspection & testing
Regulator – inspection & testing
 
PSV Sizing.pdf
PSV Sizing.pdfPSV Sizing.pdf
PSV Sizing.pdf
 
Pressure safety valves
Pressure safety valvesPressure safety valves
Pressure safety valves
 
Pressure Vacuum Relief Valve.pptx
Pressure Vacuum Relief Valve.pptxPressure Vacuum Relief Valve.pptx
Pressure Vacuum Relief Valve.pptx
 
Liquid permeability
Liquid permeabilityLiquid permeability
Liquid permeability
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
I hydro 7500-film test
I hydro 7500-film test I hydro 7500-film test
I hydro 7500-film test
 
Edited j6.doc
Edited j6.docEdited j6.doc
Edited j6.doc
 
Leak Tests.pptx
Leak Tests.pptxLeak Tests.pptx
Leak Tests.pptx
 
Pressure Reliveing Devices1
Pressure Reliveing Devices1Pressure Reliveing Devices1
Pressure Reliveing Devices1
 
pipe friction for laminar
pipe friction for laminarpipe friction for laminar
pipe friction for laminar
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
 
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
 
Instrumentation & Control Lab Manual.pdf
Instrumentation & Control Lab Manual.pdfInstrumentation & Control Lab Manual.pdf
Instrumentation & Control Lab Manual.pdf
 
control valve functional testing - Swetha
control valve functional testing - Swethacontrol valve functional testing - Swetha
control valve functional testing - Swetha
 
In situ permeability testing in boreholes
In situ permeability testing in boreholesIn situ permeability testing in boreholes
In situ permeability testing in boreholes
 
Detail product SGS test 2015 - VIB factory.PDF
Detail product SGS test  2015 - VIB factory.PDFDetail product SGS test  2015 - VIB factory.PDF
Detail product SGS test 2015 - VIB factory.PDF
 
Safety Aspects in Reactors in API & Chemical Industries
Safety Aspects in Reactors in API & Chemical IndustriesSafety Aspects in Reactors in API & Chemical Industries
Safety Aspects in Reactors in API & Chemical Industries
 

Kürzlich hochgeladen

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 

Kürzlich hochgeladen (20)

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 

pipefitting pressure-test

  • 1. PRESSURE TEST :-PRESSURE TEST :- Introduction :Introduction : ƒ Pressure Test is performed or conducted when there are new or old operating equipment like Boilers, Heat Exchangers, Pipe Connections and other pressure vessels installed. ƒ All pressure vessels must go through the pressure test before they are permitted to operate. ƒ In Malaysia, there are the regulation enforced by Malaysian Authority under the Department of Occupational Safety and Health (DOSH). ƒ There are 2 pressure tests performed :- Pressure Leak Test Pressure Strength Test - commonly known as Hydrostatic Test.
  • 2. PRESSURE TEST cont :-PRESSURE TEST cont :- Objectives :Objectives : ƒ Fired and Unfired pressure vessels are under government regulation, their objectives are to prevent :- accidents that could cause undue risk to the personnel working at or near the plant equipment, accidents that could cause several severe material damage and consequently substantial economic losses, accidents that could cause risk of pollution to the environment, downtime in plant production.
  • 3. PRESSURE TEST cont :-PRESSURE TEST cont :- Definition:Definition: ƒ Design Pressure : ƒ The pressure used in the design of a vessel. It is manufacturer recommended design pressure on each equipment. This design pressure is higher than operating pressure and it will satisfy the requirement of the pressure of the fluid and other content of the vessel standard. ƒ Operating Pressure : ƒ This is the pressure which pressure vessel can work safely or operate normally.
  • 4. PRESSURE TEST cont :-PRESSURE TEST cont :- DefinitionDefinition contcont :: ƒ Maximum Allowable Working Pressure (MAWP) : ƒ It is the internal pressure at which the weakest element of the vessel is loaded to the ultimate permissible point, when the vessel is assumed to be :- corroded condition under the effect of a designed temperature in normal operating condition under the effect of other loading, like wind, external pressure, etc. ƒ This MAWP is higher than operating pressure. ƒ Test Pressure : ƒ This is manufacturer recommended hydrostatic pressure test when the vessel or equipment is new as appeared on the equipment name plate.
  • 5. PRESSURE TEST cont :-PRESSURE TEST cont :- 1. Pressure Leak Test (1.10 x MAWP) :1. Pressure Leak Test (1.10 x MAWP) : The purpose is to detect leaking paths through the "pressure envelope" in either direction. The methods used may be straightforward using water or gas, like air or inner search gases. Leakage detection may be visual or measurement of pressure drop, pressure vacuum decay rate, trace gas or water respond to detection instrument, audible or ultrasonic devices, fluorescent dyes, etc. The pressure applied in the case of trace gas techniques should be of a very low order and for audible or visual technique it should be equal to the working pressure of the vessel with small multiplying factor but it should not in any circumstances exceed 110% of the MAWP.
  • 6. PRESSURE TEST cont :-PRESSURE TEST cont :- 2. Hydrostatic Test (1.50 x MAWP) :2. Hydrostatic Test (1.50 x MAWP) : ƒ Is the statutory requirement of pressure vessel in order to verify and demonstrate the continued fitness for services. ƒ The pressure applied may approach up to original design pressure with a suitable correction factor applied for the ambient design temperature differential and deviation from the new and old condition. ƒ In practice, the standard hydrostatic pressure test is equal to 150% of the MAWP. ƒ Hydrostatic should also be applied when repairs or modifications have been carried out which affect the structural integrity of the pressure shell and foundation.
  • 7. PRESSURE TEST cont :-PRESSURE TEST cont :- 2. Hydrostatic Test (1.50 x MAWP) cont :2. Hydrostatic Test (1.50 x MAWP) cont : ƒ Also hydrostatic test is conducted after all fabrication work has been completed. ƒ During the testing process temporary gasket may be used ƒ Hydrostatic Test Pressure = 1.5 (MAWP) (stress value at test temp.F) (stress value at design temp.F) # NOTE : All hydrostatic Test shall be witnessed by Inspector. However, the Senior Inspector may approve the following person to witness the mentioned test during off-hours.
  • 8. PRESSURE TEST cont :-PRESSURE TEST cont :- 2. Hydrostatic Test (1.50 x MAWP) cont :2. Hydrostatic Test (1.50 x MAWP) cont : ƒ For pipeline, the test pressure shall be governed by the line flange rating unless the line is for a non-critical services when inspections will advice the test pressure Pressure Rating (psi) 150 300 400 600 900 1500 2500 Hydrostatic Test (psi) 450 1100 1450 2175 3250 5400 9000
  • 9. PRESSURE TEST cont :-PRESSURE TEST cont :- Hydrostatic Test Procedure on Pipes :Hydrostatic Test Procedure on Pipes : The steps below are typical procedures while other may have added requirements :- 1 Bolts together the 2 pipes. 2 Connect the elbow casting simplifies the end of the pipelines. The fitting of the elbow casting simplifies the process of filling the pipeline with water. 3 Bolt a flange fitted with a shut off cock to the other end of the pipe. 4 Close the shut off cock and fill the pipeline with water until the water start to flow through the elbow. 5 Bolt a flange with a pressure gauge connection to the elbow casting 6 Connect the test pump to the shut off cock
  • 10. PRESSURE TEST cont :-PRESSURE TEST cont :- Hydrostatic Test Procedure on PipesHydrostatic Test Procedure on Pipes (cont):(cont): 7 Open the shut off cock and operate the test pump until water overflows from the pressure gauge connection (BLEEDING PROCESS). 8 Fit the pressure gauge. 9 Operate the test pump until the pressure gauge indicates the specified test pressure. 10Inspect for leaks in the pipeline at the flange joint, as well as the pipe system in general. 11Release the pressure from the pipeline through the test pump discharge cock. 12Disconnect the test pump and drain the pipeline through the shut off cock. 13Remove the blank flanges and dismantle the pipe joints.
  • 11. PRESSURE TEST cont :-PRESSURE TEST cont :- Hydrostatic Test Procedure on PipesHydrostatic Test Procedure on Pipes (cont):(cont):
  • 12. PRESSURE TEST cont :-PRESSURE TEST cont :- Safety Requirements :Safety Requirements : ƒ Safety Requirements :- 1Depressurising the equipment after inspection and the test has been approved must be done by releasing the pressure slowly through the vent and drain valves. 2The vent valve needs to be opened to release pressure and yo admit air when draining to prevent collapsing of the system by pulling a vacuum. 3Never leave equipment an attended at any time when it is under pressure. 4Always wear safety gear when conducting hydrostatic test.
  • 13. ƒ The record and inspection report are to be kept properly according to the requirements of inspection manual of pressure vessels. It is necessary to keep a record of all inspection result of each vessel from the initial inspection to the latest inspection, so that comparison and analysis can be made from these inspection result. ƒ Plan and report are to be submitted for evaluation before issuance of inspection certificate by Malaysian Authority (DOSH). PRESSURE TEST cont :-PRESSURE TEST cont :- Safety RequirementsSafety Requirements contcont ::