SlideShare ist ein Scribd-Unternehmen logo
1 von 10
Dulhasti Power Plant Project

Abstract

Begun in 1985, the Dulhasti power
project set in the northern Indian
provinces of Jammu and Kashmir, is
a renowned example of a disaster
in project cost estimation and
delivery.
During the inception stage, the
project’s cost was estimated to be
1.6 Billion Rupees (about $50
Million). By the time the contract
was let, the cost estimates had
risen to 4.5 Billion Rupees and later
it rose to 8, 11, 16 and 24 Billion
Rupees (nearly $750 Million). Till
2004, the project was not
completed, although well over $1
Billion was spent, just pursuing it.
This study and analysis highlights
those areas which experienced the
big hits in the cost estimation
procedures and what steps did the
Indian Govt. take in order to
sustain the budgetary perspective
and complete the project.

Karthik Murali | EMGT 709
Western New England University
March 2nd, 2013
karthik.murali@wne.edu
Case Study – Dulhasti Power Plant Project

Contents
Contents ......................................................................... 1
Summary......................................................................... 1
The Challenges................................................................ 2
Initial Challenge .............................................................. 3
Political Issues................................................................. 3
Geographical Issue ......................................................... 5
Project’s Frontier ............................................................ 6
Conclusion ...................................................................... 8
Appendix – Figures & Images ......................................... 8
Bibliography.................................................................... 9

Summary
The idea of the project was a very straightforward concept.
Dulhasti was designed as a 390MW hydroelectric power plant
to be built on Chandra River, which is a swift-flowing tributary
of the Chenab River in the Doda region, a rugged, mountainous section of the Himalayas, and
several hundred kilometers form larger cities.
The project dealt with,
1. Building a dam
2. Erect a hydroelectric generating station
3. String hundreds of miles of transmission lines
The transmission lines were to be built in a way that they start near the headwaters of a system
of rivers flowing onto the plain south of the mountain region. The contract of the project was
finalized initially for $50 Million which led the contracting organizations anticipate that the
project could be completed in a reasonable time frame.
Adv. Engr. Cost Estimation | March 5th, 2013

1
Case Study – Dulhasti Power Plant Project

The Challenges
The driving factor that led to the decision of the
construction of a hydro electrical power plant was the
geographical plus points and the natural factors that acted
as an added advantage.
Mountains, rivers that were large enough to provide the
water capacity to run a hydroelectric plant for Dulhasti
dimensions were some of the naturally available support
instruments.
The following were the challenges observed during the progress of the project,
Figure 1

Positives

Challenges

Although there were two strong positives i.e. anchoring points that led to the initiation of the
project, the challenges ousted the advantageous factors of the overall proposition. The
geographical plus points were not complementary to the problems the logistics would face and
there were political issues with the neighboring country which indirectly led to additional costs.
These problems eventually led to a huge time delay in the completion and delivery of the Dulhasti
Power Plant.

Adv. Engr. Cost Estimation | March 5th, 2013

2
Case Study – Dulhasti Power Plant Project

Initial Challenge
The contract for the power generation project was
first awarded to a French Consortium. They
immediately reverted and asked for an upward
price revision. The Indian Govt. refused, having a
doubt on the French Consortium that it had known
all along that their initial bid was too low and were
hoping to simply “buy” the project prior to
renegotiating.
Given that the Indian Govt. had refused the initial price quote revision, this resulted into a second
bidding process. There was a wide competition from other European countries then in the field.
However, the second bid offer by the French was surprisingly much lower than the first one.
Although this process initially appeared to save the Indian Govt. a lot of money, it was not a good
and smooth beginning to the partnership between the Govt. and the French Consortium.

Political Issues
The site selected for the project, unfortunately, came with
some serious drawbacks. Jammu & Kashmir shares the
border with Pakistan. As history being a strong and true
witness, India and its neighboring country have had lot of
problems. It is persistent from 1947, the year India got
independence and experienced a partition with Pakistan.
Jammu & Kashmir has been the epicenter of numerous and serious clashes between separatist
forces supported by the Pakistan Govt. and the Indian Army units stationed in the region to keep
the peace.
The construction of a power plant in such a disputed area would certainly provoke some sort of
a reaction by the nationalist groups, using terrorism as their chief means of opposition.
Adv. Engr. Cost Estimation | March 5th, 2013

3
Case Study – Dulhasti Power Plant Project
Figure 2

The power plant was to be constructed at the Kishtwar district in Jammu which is just a few miles
away from the Indo-Pak border. The Kishtwar region is prone to external attacks and influences
across the border. The construction of the dam would become an obvious target to the terrorists
and it could end up endangering the nearby inhabited villages and the national roadways of India
which is one of the prime sources for material transportation for the Indian Army.

This led to the inclusion of additional charges of security for the site and the surrounding areas,
and it undoubtedly became prohibitively expensive. The initial estimation would have certainly
not made any provision for security – around the site and the neighboring areas, this uncounted
area must have gone rising till the final completion of the project.

Adv. Engr. Cost Estimation | March 5th, 2013

4
Case Study – Dulhasti Power Plant Project

The security has to be given right from the time the project work starts on the construction site
and it has to be stabilized and continued even after the completion of the power plant in order
to ensure that the massive effort put in does not go in vain.

Geographical Issue
As mentioned earlier, the construction site was situated in
the mountainous region of Jammu & Kashmir provinces, the
site was intended to capitalize on the proximity of the large
river systems capable of providing the water capacity that
was needed to run a hydroelectric plant of Dulhasti’s
dimensions.

The geographical challenge – creation of a large plant in a region that almost totally devoid of
supporting infrastructure. This also included an adequate logistics network (roadways and
railways). The ideology of building the power plant in the foothills of the Himalayas may sound
flabbergasting and look very scenic when done, but it was absolutely not cost effective,
particularly as almost all the supplies had to be brought in with air transportation metering up
the cost bar exorbitantly.

All the raw materials viz. cement, wood, stone and steel had to be hauled by helicopters for miles
over snowbound areas. Not to forget, the climate conditions. It snows for more than half a year
in Jammu and Kashmir and convincing labor (highest authority engineers to skilled laborers who
do the hardcore jobs) to work in those conditions was impossible without paying them a fat
packet of money each month. This also surpassed the initial estimation.

Adv. Engr. Cost Estimation | March 5th, 2013

5
Case Study – Dulhasti Power Plant Project

Project’s Frontier
The following graph explains the project’s timeline in general. The
power plant initiation to completion is spread over a span of 22 long
years. The big impact on the project’s progress was due to the Kargil
War (fought between India & Pakistan over seizing the territory of
Kargil which lies in the Indian occupied Kashmir) that went on for more
than 90 long days i.e. from May to August 1999.
The impact was worsened since it was the same year the project underwent its second major
revision with regards to structure, logistics and other important dynamics that were the active
catalysts in the project.
Figure 3
1985

1990

1995

2000

2005

2010

Project's Overall Span

French Cosortium 1st Bid

1st Major Revision

2nd Major Revision

Kargil War Effects

French Consortium Backs Off

New Contract Norwegian Co.

There was more to come. After the Kargil War subsided; although the after effects were bad, the
project had no time to recoil and gain a stable resumption.

Adv. Engr. Cost Estimation | March 5th, 2013

6
Case Study – Dulhasti Power Plant Project

The reason being the French Consortium which was in-charge of the whole program backed off.
They had pulled out due to some major differences with the Indian Govt. over the cost and the
work policy.
This forced the Indian Govt. to reissue the bid and this time the project was awarded to a
Norwegian Co. that led the project work with complete charge from the year 2002 till the
completion of the completion i.e. the year 2007.
The following graph shows the cost graph for the Dulhasti Power Plant. It started with an
estimation of 50 Million $ in its year of inception and shows an exponential raise to 1.5 Billion $
till completion. This jump is enormous and disastrous at the same time as it becomes a vivid study
for cost estimation failure and project delivery.
Figure 4

Dulhasti Power Plant's Cost
1600
1400

in Million $

1200
1000
800
600
400
200
0
1985

1987

1990

1995

2000

2002

2005

2007

Year

The work on the plant continued in fits and starts for over 20 years. By the turn of the century,
over $1 Billion had been spent on the Dulhasti project and the plant was still not operational.
Further, in order to offset the expense of the project, the cost of power to be generated by the
plant has risen by over 500%, making the plant an inefficient producer of electrical power for the
countryside.

Adv. Engr. Cost Estimation | March 5th, 2013

7
Case Study – Dulhasti Power Plant Project

Conclusion
The Dulhasti Hydroelectric Power Plant finally became operational on the 7 th of
April, 2007. It has been generating 1907 Million units of electricity in a 90%
dependable year.
It is one of the major accomplishments for NHPC (National Hydroelectric Power Corporation)
thereby building one of the most important HPPs in India, thus allowing for an integrated and
efficient power development.
The Dulhasti Power Plant serves eight states and the capital of India – Delhi, Jammu & Kashmir,
Himachal Pradesh, Punjab, Haryana, Uttar Pradesh, Rajasthan, Chandigarh and Uttaranchal.

Appendix – Figures & Images
Exhibit

Title

Figure 1

SmartArt Diagram – Beam Balance

Figure 2

Northern Provinces of India

Figure 3

Project’s Timeline

Figure 4

Dulhasti Power Plant Cost Graph

Image Courtesy

www.google.com/images

Adv. Engr. Cost Estimation | March 5th, 2013

8
Case Study – Dulhasti Power Plant Project

Bibliography
1. Blog, H. (2010, October 29th). Issues and Problems in Hydro Power Development in
India. Retrieved from HydroPowerStation.Com:
http://hydropowerstation.com/?tag=dulhasti-hydroelectric-project
2. Engineering, T. (2007, Apri 10). Dulhasti Dam & Hydro Electric Power Project. Retrieved
from Tractabel-Engineering: http://www.tractebel-engineeringgdfsuez.com/reference/dul-hasti-dam-and-hydroelectric-power-project/
3. Govt. of India. (2007). Project Implementation Status Report of Central Sector Projects.
Infrastructure and Project Management Division. New Delhi: Ministry of Statistics and
Programme Implementation.
4. Knowledge, M. H. (2012, November 7th). Working Challenges in Adverse Geological
Conditions. Retrieved from Blogspot.Com:
http://mmmhydropower.blogspot.com/2012/11/working-challenges-inadverse_8814.html
5. NHPC. (2008). Dulhasti Power Plant Project. Kishtwar, Jammu & Kashmir, India.
Retrieved from http://www.youtube.com/watch?v=q9A6kbDdQKk
6. Parihar, P. (2010, February 10th). Kishtwar - Ek Jannat. Retrieved from Blogspot.Com:
http://mykishtwar.blogspot.com/2010/02/dul-hasti-project.html
7. PM News Bureau. (2005, December 5th). Dulhasti Project by March 2006. Retrieved
from Project Monitor.Com:
http://www.projectsmonitor.com/detailnews.asp?newsid=10119
8. Rocky, R. (2007, April 7th). Dulhasti - A Ray of Hope for the Dark J&K. Retrieved from
Indian Express.Com: http://www.indianexpress.com/news/dulhasti-a-ray-of-hope-for-dark--jk/28049/0

Adv. Engr. Cost Estimation | March 5th, 2013

9

Weitere ähnliche Inhalte

Was ist angesagt?

Hydropower Development in India
Hydropower Development in IndiaHydropower Development in India
Hydropower Development in IndiaSatish Taji
 
Report of Sardar Sarovar Hydro Power Plant
Report of Sardar Sarovar Hydro Power Plant Report of Sardar Sarovar Hydro Power Plant
Report of Sardar Sarovar Hydro Power Plant Sheel Shah
 
Project report on THDC Hydrop Power Plant Summer Training
Project report on THDC Hydrop Power Plant Summer TrainingProject report on THDC Hydrop Power Plant Summer Training
Project report on THDC Hydrop Power Plant Summer TrainingCharu Kandpal
 
DAMS & HYDROPOWER PROJECTS OF PAKISTAN
DAMS & HYDROPOWER PROJECTS OF PAKISTANDAMS & HYDROPOWER PROJECTS OF PAKISTAN
DAMS & HYDROPOWER PROJECTS OF PAKISTANRizwan Sarwar Awan
 
Dams and Hydropower Projects of Pakistan
Dams and Hydropower Projects of PakistanDams and Hydropower Projects of Pakistan
Dams and Hydropower Projects of PakistanRizwan Sarwar Awan
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailraceRakesh Sunari Magar
 
Conduits,intakes,power house and Accessories
Conduits,intakes,power house and AccessoriesConduits,intakes,power house and Accessories
Conduits,intakes,power house and AccessoriesYimam Alemu
 
Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)Rubnawaz Bhatti
 
TYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSTYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSRAJ BAIRWA
 
Nandipur Power Project By Wajid Hussain Khoso
Nandipur Power Project By Wajid Hussain KhosoNandipur Power Project By Wajid Hussain Khoso
Nandipur Power Project By Wajid Hussain KhosoWajid Hussain Khoso
 
Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report muhammad khurram
 
Presentation of hydro power plant
Presentation of hydro power plantPresentation of hydro power plant
Presentation of hydro power plantNazakatHussain15
 
Hydro power plants
Hydro power plants Hydro power plants
Hydro power plants FAHAD KHAN
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -HydraulicsCivil Zone
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant Prasad Vejendla
 

Was ist angesagt? (20)

Hydropower Development in India
Hydropower Development in IndiaHydropower Development in India
Hydropower Development in India
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Report of Sardar Sarovar Hydro Power Plant
Report of Sardar Sarovar Hydro Power Plant Report of Sardar Sarovar Hydro Power Plant
Report of Sardar Sarovar Hydro Power Plant
 
Project report on THDC Hydrop Power Plant Summer Training
Project report on THDC Hydrop Power Plant Summer TrainingProject report on THDC Hydrop Power Plant Summer Training
Project report on THDC Hydrop Power Plant Summer Training
 
DAMS & HYDROPOWER PROJECTS OF PAKISTAN
DAMS & HYDROPOWER PROJECTS OF PAKISTANDAMS & HYDROPOWER PROJECTS OF PAKISTAN
DAMS & HYDROPOWER PROJECTS OF PAKISTAN
 
Dams and Hydropower Projects of Pakistan
Dams and Hydropower Projects of PakistanDams and Hydropower Projects of Pakistan
Dams and Hydropower Projects of Pakistan
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
 
Conduits,intakes,power house and Accessories
Conduits,intakes,power house and AccessoriesConduits,intakes,power house and Accessories
Conduits,intakes,power house and Accessories
 
Hydro-Electric Power
Hydro-Electric PowerHydro-Electric Power
Hydro-Electric Power
 
Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)
 
TYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSTYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTS
 
Nandipur Power Project By Wajid Hussain Khoso
Nandipur Power Project By Wajid Hussain KhosoNandipur Power Project By Wajid Hussain Khoso
Nandipur Power Project By Wajid Hussain Khoso
 
Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report
 
REPORT-NHPC
REPORT-NHPCREPORT-NHPC
REPORT-NHPC
 
Presentation of hydro power plant
Presentation of hydro power plantPresentation of hydro power plant
Presentation of hydro power plant
 
Hydro power plants
Hydro power plants Hydro power plants
Hydro power plants
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
 
Hydropower
HydropowerHydropower
Hydropower
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -Hydraulics
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
 

Andere mochten auch

Positioning RIN case study pakistan
Positioning   RIN case study pakistanPositioning   RIN case study pakistan
Positioning RIN case study pakistanArmanYousaf
 
a Case study on A V Birla Group - Legacy of Free Enterprise and Diversification
 a Case study on A V Birla Group - Legacy of Free Enterprise and Diversification a Case study on A V Birla Group - Legacy of Free Enterprise and Diversification
a Case study on A V Birla Group - Legacy of Free Enterprise and DiversificationMARAM SRAVAN KUMAR
 
Rin detergent case analysis group 10
Rin detergent case analysis group 10Rin detergent case analysis group 10
Rin detergent case analysis group 10Vinamra Sangal
 
Freemium publishing - OECD case study. SSP 2013
Freemium publishing - OECD case study. SSP 2013Freemium publishing - OECD case study. SSP 2013
Freemium publishing - OECD case study. SSP 2013tobygreen
 
OECD Study on Regional Development in Brazil / Claire Charbit Deputy Head of ...
OECD Study on Regional Development in Brazil / Claire Charbit Deputy Head of ...OECD Study on Regional Development in Brazil / Claire Charbit Deputy Head of ...
OECD Study on Regional Development in Brazil / Claire Charbit Deputy Head of ...EUROsociAL II
 
United-kingdom-unleashing-productivity-oecd-main-findings-presentation
United-kingdom-unleashing-productivity-oecd-main-findings-presentationUnited-kingdom-unleashing-productivity-oecd-main-findings-presentation
United-kingdom-unleashing-productivity-oecd-main-findings-presentationOECD, Economics Department
 
1 introduction and oecd
1   introduction and oecd1   introduction and oecd
1 introduction and oecdBatuhan
 
Economic consequences of brexit OECD April 2016
Economic consequences of brexit OECD April 2016Economic consequences of brexit OECD April 2016
Economic consequences of brexit OECD April 2016OECD, Economics Department
 

Andere mochten auch (9)

Positioning RIN case study pakistan
Positioning   RIN case study pakistanPositioning   RIN case study pakistan
Positioning RIN case study pakistan
 
a Case study on A V Birla Group - Legacy of Free Enterprise and Diversification
 a Case study on A V Birla Group - Legacy of Free Enterprise and Diversification a Case study on A V Birla Group - Legacy of Free Enterprise and Diversification
a Case study on A V Birla Group - Legacy of Free Enterprise and Diversification
 
Rin detergent case analysis group 10
Rin detergent case analysis group 10Rin detergent case analysis group 10
Rin detergent case analysis group 10
 
Freemium publishing - OECD case study. SSP 2013
Freemium publishing - OECD case study. SSP 2013Freemium publishing - OECD case study. SSP 2013
Freemium publishing - OECD case study. SSP 2013
 
OECD Study on Regional Development in Brazil / Claire Charbit Deputy Head of ...
OECD Study on Regional Development in Brazil / Claire Charbit Deputy Head of ...OECD Study on Regional Development in Brazil / Claire Charbit Deputy Head of ...
OECD Study on Regional Development in Brazil / Claire Charbit Deputy Head of ...
 
United-kingdom-unleashing-productivity-oecd-main-findings-presentation
United-kingdom-unleashing-productivity-oecd-main-findings-presentationUnited-kingdom-unleashing-productivity-oecd-main-findings-presentation
United-kingdom-unleashing-productivity-oecd-main-findings-presentation
 
United kingdom-compared-to-oecd-economies
United kingdom-compared-to-oecd-economiesUnited kingdom-compared-to-oecd-economies
United kingdom-compared-to-oecd-economies
 
1 introduction and oecd
1   introduction and oecd1   introduction and oecd
1 introduction and oecd
 
Economic consequences of brexit OECD April 2016
Economic consequences of brexit OECD April 2016Economic consequences of brexit OECD April 2016
Economic consequences of brexit OECD April 2016
 

Ähnlich wie Dulhasti Power Plant Case Study

The Untold Story of Konkan Railway
The Untold Story of Konkan RailwayThe Untold Story of Konkan Railway
The Untold Story of Konkan RailwayRohit Dhoundiyal
 
Capacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryCapacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryDr. Amarjeet Singh
 
Dabhol-Power-Company PF,M.pptx
Dabhol-Power-Company PF,M.pptxDabhol-Power-Company PF,M.pptx
Dabhol-Power-Company PF,M.pptxNIHALTYAGI5
 
Project Management
Project ManagementProject Management
Project ManagementAnton Orlov
 
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYShabaz Khan
 
Time overruns welcome to power line
Time overruns   welcome to power lineTime overruns   welcome to power line
Time overruns welcome to power lineProbodh Mallick
 
5_Parth Nayanesh Patel_Report (002).pdf
5_Parth Nayanesh Patel_Report (002).pdf5_Parth Nayanesh Patel_Report (002).pdf
5_Parth Nayanesh Patel_Report (002).pdfAthimoolam M
 
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...AdrianSyaifullah2
 
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power PlantZerry Antro
 
Djibouti geothermal project study
Djibouti geothermal project studyDjibouti geothermal project study
Djibouti geothermal project studyParti Djibouti
 
Zorlu pakistan eia april 2010
Zorlu pakistan eia april 2010Zorlu pakistan eia april 2010
Zorlu pakistan eia april 2010zubeditufail
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Nikhil Jaipurkar
 
UNLOCKING OFFSHORE WIND IN TAMIL NADU
UNLOCKING OFFSHORE WIND IN TAMIL NADUUNLOCKING OFFSHORE WIND IN TAMIL NADU
UNLOCKING OFFSHORE WIND IN TAMIL NADUAurovilleConsulting
 
Hydro Priyank jain
Hydro Priyank jain Hydro Priyank jain
Hydro Priyank jain PRIYANK JAIN
 
Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022collinsR1
 
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022 Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022 collinsR1
 

Ähnlich wie Dulhasti Power Plant Case Study (20)

The Untold Story of Konkan Railway
The Untold Story of Konkan RailwayThe Untold Story of Konkan Railway
The Untold Story of Konkan Railway
 
DABHOL POWER PLANT.pdf
DABHOL POWER PLANT.pdfDABHOL POWER PLANT.pdf
DABHOL POWER PLANT.pdf
 
Capacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryCapacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel Industry
 
Tehri dam
Tehri damTehri dam
Tehri dam
 
DABHOL POWER COMPANY, INDIA
DABHOL POWER COMPANY,  INDIADABHOL POWER COMPANY,  INDIA
DABHOL POWER COMPANY, INDIA
 
Dabhol-Power-Company PF,M.pptx
Dabhol-Power-Company PF,M.pptxDabhol-Power-Company PF,M.pptx
Dabhol-Power-Company PF,M.pptx
 
Project Management
Project ManagementProject Management
Project Management
 
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
 
Time overruns welcome to power line
Time overruns   welcome to power lineTime overruns   welcome to power line
Time overruns welcome to power line
 
5_Parth Nayanesh Patel_Report (002).pdf
5_Parth Nayanesh Patel_Report (002).pdf5_Parth Nayanesh Patel_Report (002).pdf
5_Parth Nayanesh Patel_Report (002).pdf
 
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
 
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
 
Djibouti geothermal project study
Djibouti geothermal project studyDjibouti geothermal project study
Djibouti geothermal project study
 
Hydro power presentation
Hydro power presentationHydro power presentation
Hydro power presentation
 
Zorlu pakistan eia april 2010
Zorlu pakistan eia april 2010Zorlu pakistan eia april 2010
Zorlu pakistan eia april 2010
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)
 
UNLOCKING OFFSHORE WIND IN TAMIL NADU
UNLOCKING OFFSHORE WIND IN TAMIL NADUUNLOCKING OFFSHORE WIND IN TAMIL NADU
UNLOCKING OFFSHORE WIND IN TAMIL NADU
 
Hydro Priyank jain
Hydro Priyank jain Hydro Priyank jain
Hydro Priyank jain
 
Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022
 
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022 Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
 

Mehr von Karthik Murali

WNE Communicator 2015 Featured Article
WNE Communicator 2015 Featured ArticleWNE Communicator 2015 Featured Article
WNE Communicator 2015 Featured ArticleKarthik Murali
 
Thesis Part II EMGT 699
Thesis Part II EMGT 699Thesis Part II EMGT 699
Thesis Part II EMGT 699Karthik Murali
 
Thesis Part I EMGT 698
Thesis Part I EMGT 698Thesis Part I EMGT 698
Thesis Part I EMGT 698Karthik Murali
 
Leagile Manufacturing Paradigm Integration
Leagile Manufacturing Paradigm IntegrationLeagile Manufacturing Paradigm Integration
Leagile Manufacturing Paradigm IntegrationKarthik Murali
 
Application of Mathematics
Application of MathematicsApplication of Mathematics
Application of MathematicsKarthik Murali
 
Michelle Kowalsky's Recommendation
Michelle Kowalsky's RecommendationMichelle Kowalsky's Recommendation
Michelle Kowalsky's RecommendationKarthik Murali
 
Matthew Fox's Recommendation
Matthew Fox's RecommendationMatthew Fox's Recommendation
Matthew Fox's RecommendationKarthik Murali
 
Dr. Julie Drzymalski's Recommendation
Dr. Julie Drzymalski's RecommendationDr. Julie Drzymalski's Recommendation
Dr. Julie Drzymalski's RecommendationKarthik Murali
 
Dr. Christian Salmon's Recommendation
Dr. Christian Salmon's RecommendationDr. Christian Salmon's Recommendation
Dr. Christian Salmon's RecommendationKarthik Murali
 
Prof. Mike Bloom's Recommendation
Prof. Mike Bloom's RecommendationProf. Mike Bloom's Recommendation
Prof. Mike Bloom's RecommendationKarthik Murali
 
DSLR Image Quality Analysis using Minitab
DSLR Image Quality Analysis using MinitabDSLR Image Quality Analysis using Minitab
DSLR Image Quality Analysis using MinitabKarthik Murali
 
Leagile Manufacturing Paradigm Integration
Leagile Manufacturing Paradigm IntegrationLeagile Manufacturing Paradigm Integration
Leagile Manufacturing Paradigm IntegrationKarthik Murali
 
Framework for a Software Quality Rating System
Framework for a Software Quality Rating SystemFramework for a Software Quality Rating System
Framework for a Software Quality Rating SystemKarthik Murali
 
A Study on the Need for a Software Quality Rating System
A Study on the Need for a Software Quality Rating SystemA Study on the Need for a Software Quality Rating System
A Study on the Need for a Software Quality Rating SystemKarthik Murali
 

Mehr von Karthik Murali (14)

WNE Communicator 2015 Featured Article
WNE Communicator 2015 Featured ArticleWNE Communicator 2015 Featured Article
WNE Communicator 2015 Featured Article
 
Thesis Part II EMGT 699
Thesis Part II EMGT 699Thesis Part II EMGT 699
Thesis Part II EMGT 699
 
Thesis Part I EMGT 698
Thesis Part I EMGT 698Thesis Part I EMGT 698
Thesis Part I EMGT 698
 
Leagile Manufacturing Paradigm Integration
Leagile Manufacturing Paradigm IntegrationLeagile Manufacturing Paradigm Integration
Leagile Manufacturing Paradigm Integration
 
Application of Mathematics
Application of MathematicsApplication of Mathematics
Application of Mathematics
 
Michelle Kowalsky's Recommendation
Michelle Kowalsky's RecommendationMichelle Kowalsky's Recommendation
Michelle Kowalsky's Recommendation
 
Matthew Fox's Recommendation
Matthew Fox's RecommendationMatthew Fox's Recommendation
Matthew Fox's Recommendation
 
Dr. Julie Drzymalski's Recommendation
Dr. Julie Drzymalski's RecommendationDr. Julie Drzymalski's Recommendation
Dr. Julie Drzymalski's Recommendation
 
Dr. Christian Salmon's Recommendation
Dr. Christian Salmon's RecommendationDr. Christian Salmon's Recommendation
Dr. Christian Salmon's Recommendation
 
Prof. Mike Bloom's Recommendation
Prof. Mike Bloom's RecommendationProf. Mike Bloom's Recommendation
Prof. Mike Bloom's Recommendation
 
DSLR Image Quality Analysis using Minitab
DSLR Image Quality Analysis using MinitabDSLR Image Quality Analysis using Minitab
DSLR Image Quality Analysis using Minitab
 
Leagile Manufacturing Paradigm Integration
Leagile Manufacturing Paradigm IntegrationLeagile Manufacturing Paradigm Integration
Leagile Manufacturing Paradigm Integration
 
Framework for a Software Quality Rating System
Framework for a Software Quality Rating SystemFramework for a Software Quality Rating System
Framework for a Software Quality Rating System
 
A Study on the Need for a Software Quality Rating System
A Study on the Need for a Software Quality Rating SystemA Study on the Need for a Software Quality Rating System
A Study on the Need for a Software Quality Rating System
 

Kürzlich hochgeladen

Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIShubhangi Sonawane
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 

Kürzlich hochgeladen (20)

Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 

Dulhasti Power Plant Case Study

  • 1. Dulhasti Power Plant Project Abstract Begun in 1985, the Dulhasti power project set in the northern Indian provinces of Jammu and Kashmir, is a renowned example of a disaster in project cost estimation and delivery. During the inception stage, the project’s cost was estimated to be 1.6 Billion Rupees (about $50 Million). By the time the contract was let, the cost estimates had risen to 4.5 Billion Rupees and later it rose to 8, 11, 16 and 24 Billion Rupees (nearly $750 Million). Till 2004, the project was not completed, although well over $1 Billion was spent, just pursuing it. This study and analysis highlights those areas which experienced the big hits in the cost estimation procedures and what steps did the Indian Govt. take in order to sustain the budgetary perspective and complete the project. Karthik Murali | EMGT 709 Western New England University March 2nd, 2013 karthik.murali@wne.edu
  • 2. Case Study – Dulhasti Power Plant Project Contents Contents ......................................................................... 1 Summary......................................................................... 1 The Challenges................................................................ 2 Initial Challenge .............................................................. 3 Political Issues................................................................. 3 Geographical Issue ......................................................... 5 Project’s Frontier ............................................................ 6 Conclusion ...................................................................... 8 Appendix – Figures & Images ......................................... 8 Bibliography.................................................................... 9 Summary The idea of the project was a very straightforward concept. Dulhasti was designed as a 390MW hydroelectric power plant to be built on Chandra River, which is a swift-flowing tributary of the Chenab River in the Doda region, a rugged, mountainous section of the Himalayas, and several hundred kilometers form larger cities. The project dealt with, 1. Building a dam 2. Erect a hydroelectric generating station 3. String hundreds of miles of transmission lines The transmission lines were to be built in a way that they start near the headwaters of a system of rivers flowing onto the plain south of the mountain region. The contract of the project was finalized initially for $50 Million which led the contracting organizations anticipate that the project could be completed in a reasonable time frame. Adv. Engr. Cost Estimation | March 5th, 2013 1
  • 3. Case Study – Dulhasti Power Plant Project The Challenges The driving factor that led to the decision of the construction of a hydro electrical power plant was the geographical plus points and the natural factors that acted as an added advantage. Mountains, rivers that were large enough to provide the water capacity to run a hydroelectric plant for Dulhasti dimensions were some of the naturally available support instruments. The following were the challenges observed during the progress of the project, Figure 1 Positives Challenges Although there were two strong positives i.e. anchoring points that led to the initiation of the project, the challenges ousted the advantageous factors of the overall proposition. The geographical plus points were not complementary to the problems the logistics would face and there were political issues with the neighboring country which indirectly led to additional costs. These problems eventually led to a huge time delay in the completion and delivery of the Dulhasti Power Plant. Adv. Engr. Cost Estimation | March 5th, 2013 2
  • 4. Case Study – Dulhasti Power Plant Project Initial Challenge The contract for the power generation project was first awarded to a French Consortium. They immediately reverted and asked for an upward price revision. The Indian Govt. refused, having a doubt on the French Consortium that it had known all along that their initial bid was too low and were hoping to simply “buy” the project prior to renegotiating. Given that the Indian Govt. had refused the initial price quote revision, this resulted into a second bidding process. There was a wide competition from other European countries then in the field. However, the second bid offer by the French was surprisingly much lower than the first one. Although this process initially appeared to save the Indian Govt. a lot of money, it was not a good and smooth beginning to the partnership between the Govt. and the French Consortium. Political Issues The site selected for the project, unfortunately, came with some serious drawbacks. Jammu & Kashmir shares the border with Pakistan. As history being a strong and true witness, India and its neighboring country have had lot of problems. It is persistent from 1947, the year India got independence and experienced a partition with Pakistan. Jammu & Kashmir has been the epicenter of numerous and serious clashes between separatist forces supported by the Pakistan Govt. and the Indian Army units stationed in the region to keep the peace. The construction of a power plant in such a disputed area would certainly provoke some sort of a reaction by the nationalist groups, using terrorism as their chief means of opposition. Adv. Engr. Cost Estimation | March 5th, 2013 3
  • 5. Case Study – Dulhasti Power Plant Project Figure 2 The power plant was to be constructed at the Kishtwar district in Jammu which is just a few miles away from the Indo-Pak border. The Kishtwar region is prone to external attacks and influences across the border. The construction of the dam would become an obvious target to the terrorists and it could end up endangering the nearby inhabited villages and the national roadways of India which is one of the prime sources for material transportation for the Indian Army. This led to the inclusion of additional charges of security for the site and the surrounding areas, and it undoubtedly became prohibitively expensive. The initial estimation would have certainly not made any provision for security – around the site and the neighboring areas, this uncounted area must have gone rising till the final completion of the project. Adv. Engr. Cost Estimation | March 5th, 2013 4
  • 6. Case Study – Dulhasti Power Plant Project The security has to be given right from the time the project work starts on the construction site and it has to be stabilized and continued even after the completion of the power plant in order to ensure that the massive effort put in does not go in vain. Geographical Issue As mentioned earlier, the construction site was situated in the mountainous region of Jammu & Kashmir provinces, the site was intended to capitalize on the proximity of the large river systems capable of providing the water capacity that was needed to run a hydroelectric plant of Dulhasti’s dimensions. The geographical challenge – creation of a large plant in a region that almost totally devoid of supporting infrastructure. This also included an adequate logistics network (roadways and railways). The ideology of building the power plant in the foothills of the Himalayas may sound flabbergasting and look very scenic when done, but it was absolutely not cost effective, particularly as almost all the supplies had to be brought in with air transportation metering up the cost bar exorbitantly. All the raw materials viz. cement, wood, stone and steel had to be hauled by helicopters for miles over snowbound areas. Not to forget, the climate conditions. It snows for more than half a year in Jammu and Kashmir and convincing labor (highest authority engineers to skilled laborers who do the hardcore jobs) to work in those conditions was impossible without paying them a fat packet of money each month. This also surpassed the initial estimation. Adv. Engr. Cost Estimation | March 5th, 2013 5
  • 7. Case Study – Dulhasti Power Plant Project Project’s Frontier The following graph explains the project’s timeline in general. The power plant initiation to completion is spread over a span of 22 long years. The big impact on the project’s progress was due to the Kargil War (fought between India & Pakistan over seizing the territory of Kargil which lies in the Indian occupied Kashmir) that went on for more than 90 long days i.e. from May to August 1999. The impact was worsened since it was the same year the project underwent its second major revision with regards to structure, logistics and other important dynamics that were the active catalysts in the project. Figure 3 1985 1990 1995 2000 2005 2010 Project's Overall Span French Cosortium 1st Bid 1st Major Revision 2nd Major Revision Kargil War Effects French Consortium Backs Off New Contract Norwegian Co. There was more to come. After the Kargil War subsided; although the after effects were bad, the project had no time to recoil and gain a stable resumption. Adv. Engr. Cost Estimation | March 5th, 2013 6
  • 8. Case Study – Dulhasti Power Plant Project The reason being the French Consortium which was in-charge of the whole program backed off. They had pulled out due to some major differences with the Indian Govt. over the cost and the work policy. This forced the Indian Govt. to reissue the bid and this time the project was awarded to a Norwegian Co. that led the project work with complete charge from the year 2002 till the completion of the completion i.e. the year 2007. The following graph shows the cost graph for the Dulhasti Power Plant. It started with an estimation of 50 Million $ in its year of inception and shows an exponential raise to 1.5 Billion $ till completion. This jump is enormous and disastrous at the same time as it becomes a vivid study for cost estimation failure and project delivery. Figure 4 Dulhasti Power Plant's Cost 1600 1400 in Million $ 1200 1000 800 600 400 200 0 1985 1987 1990 1995 2000 2002 2005 2007 Year The work on the plant continued in fits and starts for over 20 years. By the turn of the century, over $1 Billion had been spent on the Dulhasti project and the plant was still not operational. Further, in order to offset the expense of the project, the cost of power to be generated by the plant has risen by over 500%, making the plant an inefficient producer of electrical power for the countryside. Adv. Engr. Cost Estimation | March 5th, 2013 7
  • 9. Case Study – Dulhasti Power Plant Project Conclusion The Dulhasti Hydroelectric Power Plant finally became operational on the 7 th of April, 2007. It has been generating 1907 Million units of electricity in a 90% dependable year. It is one of the major accomplishments for NHPC (National Hydroelectric Power Corporation) thereby building one of the most important HPPs in India, thus allowing for an integrated and efficient power development. The Dulhasti Power Plant serves eight states and the capital of India – Delhi, Jammu & Kashmir, Himachal Pradesh, Punjab, Haryana, Uttar Pradesh, Rajasthan, Chandigarh and Uttaranchal. Appendix – Figures & Images Exhibit Title Figure 1 SmartArt Diagram – Beam Balance Figure 2 Northern Provinces of India Figure 3 Project’s Timeline Figure 4 Dulhasti Power Plant Cost Graph Image Courtesy www.google.com/images Adv. Engr. Cost Estimation | March 5th, 2013 8
  • 10. Case Study – Dulhasti Power Plant Project Bibliography 1. Blog, H. (2010, October 29th). Issues and Problems in Hydro Power Development in India. Retrieved from HydroPowerStation.Com: http://hydropowerstation.com/?tag=dulhasti-hydroelectric-project 2. Engineering, T. (2007, Apri 10). Dulhasti Dam & Hydro Electric Power Project. Retrieved from Tractabel-Engineering: http://www.tractebel-engineeringgdfsuez.com/reference/dul-hasti-dam-and-hydroelectric-power-project/ 3. Govt. of India. (2007). Project Implementation Status Report of Central Sector Projects. Infrastructure and Project Management Division. New Delhi: Ministry of Statistics and Programme Implementation. 4. Knowledge, M. H. (2012, November 7th). Working Challenges in Adverse Geological Conditions. Retrieved from Blogspot.Com: http://mmmhydropower.blogspot.com/2012/11/working-challenges-inadverse_8814.html 5. NHPC. (2008). Dulhasti Power Plant Project. Kishtwar, Jammu & Kashmir, India. Retrieved from http://www.youtube.com/watch?v=q9A6kbDdQKk 6. Parihar, P. (2010, February 10th). Kishtwar - Ek Jannat. Retrieved from Blogspot.Com: http://mykishtwar.blogspot.com/2010/02/dul-hasti-project.html 7. PM News Bureau. (2005, December 5th). Dulhasti Project by March 2006. Retrieved from Project Monitor.Com: http://www.projectsmonitor.com/detailnews.asp?newsid=10119 8. Rocky, R. (2007, April 7th). Dulhasti - A Ray of Hope for the Dark J&K. Retrieved from Indian Express.Com: http://www.indianexpress.com/news/dulhasti-a-ray-of-hope-for-dark--jk/28049/0 Adv. Engr. Cost Estimation | March 5th, 2013 9