From:   Brandon Valdez                   To: David Ficklin - OnGoal
                                                                          Rory O’Connor – OnGoal
                             Office: Kansas City                          Lee Turner – OnGoal
                             Date:   9.22.2010                            Andy Heitmann – Turner
                                                                          Dave Dudzik - Turner
                             Re:     Wizards Stadium Project
                                     Update – Week of
                                     9.20.2010



 Current Activities this Week:

 Underground Utilities:
 Area 3 - Deep underground plumbing is complete to
 Column Line 6.

 Foundations:
 Area 2 Concourse Level – Last D-Line Foundations is
 complete.                                                   Field Level Area 3 – Slab preparation is
                                                             ongoing at lower dock area.
 Concrete Flatwork:
 Area 3 Field Level – Prep work for lower dock slab on
 grade has started. Area 4 – Cast-in-place concrete
 risers are ongoing.

 Structural Steel Erection:
 Area 4 – Canopy Trusses are set from Column Lines
 33-39. Area 4 – Metal decking installation in Sequence
 3-3 is complete. Field Level Area 1 – Subroof decking
 installation is ongoing
                                                             Field Level Area 2 – CMU block wall
 MEP Rough-in:                                               installation is ongoing.
 Area 3 – Underground MEP rough-in is ongoing.
 West Building - Ductwork installation on
 Concourse, Suite and Press Levels are ongoing.
 Plumbing rough-in is ongoing on Suite and
 Press Levels. Fire Protection rough-in is ongoing on
 Concourse, Suite and Press Levels. Electrical rough-in is
 ongoing on Concourse, Suite and Press Levels.


                                                             Field Level Area 1 – Subroof installation, 24”
                                                             storm line installation and metal framing are
                                                             ongoing.
Building the Future
Metal Stud Framing:
 Area 1 – Metal stud framing for Field, Concourse, Suite
 and Press Levels are ongoing. Exterior metal stud framing
 and sheathing installation is ongoing at Field, Suite, and
 Press Levels.

 Masonry:
 Area 1 Field Level – Masonry wall installation is ongoing
 in Areas E, F, G and H.                                        Area 4 – Canopy Truss erection is complete
                                                                in Sequence 3-6 from column lines 33-39.
 Area 2 and 3 Concourse Level – Masonry wall installation
 At Main Concourse Buildings are ongoing.

 Curtainwall:
 Area 1 – Curtainwall framing installation will continue
 at West Elevation. Installation of Curtainwall glass is
 ongoing.


 Projected Activities occurring next Week:
                                                                Area 1 – Shot of the West Building Field Side
 Foundations:                                                   Elevation showing progress of Canopy
 Area 3/4 Field Level – Foundations for “infill” area between   Decking and Suite Soffit installation.
 Column Lines 40-42 will be placed.

 Concrete Flatwork:
 Area 3 Field Level – Concrete placement for Slab-on
 Grade at lower dock area will begin.

 Area 3 and 4 Field Level – Installation of on-grade seating
 risers and intermediate stairs will continue.

 Structural Steel Erection:
 Area 3/4 – Structural steel erection for “infill” area will    Concourse Level Area 3 – Filled and polished
 begin.                                                         CMU Block walls at the East Concourse
                                                                Buildings.
 MEP Rough-in:
 MEP Rough-in at Concourse, Suite and Press Levels will
 continue. Ductwork installation on Concourse, Suite, and
 Press Level will continue. Fire Sprinkler installation will
 continue on Concourse, Suite and Press Levels.


Building the Future
Metal Stud Framing:
 Area 1 – Metal stud framing for Field, Concourse, Suite
 and Press Levels will continue. Exterior Framing and
 sheathing installation will continue.

 Curtainwall:
 Area 1 – Curtain Framing and Glass installation at West
 Elevation will continue. Curtainwall framing on Suite and
 Press Level balconies will continue. Curtainwall framing    Area 1 – Sheathing installation is complete
 at Field Side of Main Concourse will begin.                 at south end of West Building.




                                                             Area 1 – Shot of the west building showing
                                                             the progress of the exterior envelope.




Building the Future
Additional Photos:




Area 2/3 – Shot of truck dock area looking
northwest from under the State Avenue         Area 1 – Soffit framing and sheathing is
Bridge.                                       ongoing at all levels of the West Building.




                                              Shot of the Stadium from Village West
Roof Level Area 1 – Installation of the       Parkway and State Avenue showing
permanent roof has started.                   elevation change of roof canopy.




Area 1 – Shot of the West Building from the   Field Level Area 1 – Metal stud framing,
southeast concourse.                          drywall and in wall MEP rough-in is ongoing.




Building the Future

Weitere ähnliche Inhalte

Mehr von Kansas City Wizards

Mehr von Kansas City Wizards (13)

Memo wizards 08-25-2010
Memo wizards 08-25-2010Memo wizards 08-25-2010
Memo wizards 08-25-2010
 
Construction Update 07-28-2010
Construction Update 07-28-2010Construction Update 07-28-2010
Construction Update 07-28-2010
 
Unicorn Wizards Scouting
Unicorn Wizards ScoutingUnicorn Wizards Scouting
Unicorn Wizards Scouting
 
KC Soccer Stadium
KC Soccer Stadium KC Soccer Stadium
KC Soccer Stadium
 
Construction Update 7-6-2010
Construction Update 7-6-2010Construction Update 7-6-2010
Construction Update 7-6-2010
 
Weekly Construction Update 06-14-10
Weekly Construction Update 06-14-10Weekly Construction Update 06-14-10
Weekly Construction Update 06-14-10
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010
 
Weekly Construction Update 05-19-2010
Weekly Construction Update 05-19-2010Weekly Construction Update 05-19-2010
Weekly Construction Update 05-19-2010
 
Construction Update 5-5-2010
Construction Update 5-5-2010Construction Update 5-5-2010
Construction Update 5-5-2010
 
Construction Update 4-14-2010
Construction Update 4-14-2010Construction Update 4-14-2010
Construction Update 4-14-2010
 
Construction Update 4-7-2010
Construction Update 4-7-2010Construction Update 4-7-2010
Construction Update 4-7-2010
 
Construction Update 5-12-2010
Construction Update 5-12-2010Construction Update 5-12-2010
Construction Update 5-12-2010
 

Memo wizards 09-22-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 9.22.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 9.20.2010 Current Activities this Week: Underground Utilities: Area 3 - Deep underground plumbing is complete to Column Line 6. Foundations: Area 2 Concourse Level – Last D-Line Foundations is complete. Field Level Area 3 – Slab preparation is ongoing at lower dock area. Concrete Flatwork: Area 3 Field Level – Prep work for lower dock slab on grade has started. Area 4 – Cast-in-place concrete risers are ongoing. Structural Steel Erection: Area 4 – Canopy Trusses are set from Column Lines 33-39. Area 4 – Metal decking installation in Sequence 3-3 is complete. Field Level Area 1 – Subroof decking installation is ongoing Field Level Area 2 – CMU block wall MEP Rough-in: installation is ongoing. Area 3 – Underground MEP rough-in is ongoing. West Building - Ductwork installation on Concourse, Suite and Press Levels are ongoing. Plumbing rough-in is ongoing on Suite and Press Levels. Fire Protection rough-in is ongoing on Concourse, Suite and Press Levels. Electrical rough-in is ongoing on Concourse, Suite and Press Levels. Field Level Area 1 – Subroof installation, 24” storm line installation and metal framing are ongoing. Building the Future
  • 2. Metal Stud Framing: Area 1 – Metal stud framing for Field, Concourse, Suite and Press Levels are ongoing. Exterior metal stud framing and sheathing installation is ongoing at Field, Suite, and Press Levels. Masonry: Area 1 Field Level – Masonry wall installation is ongoing in Areas E, F, G and H. Area 4 – Canopy Truss erection is complete in Sequence 3-6 from column lines 33-39. Area 2 and 3 Concourse Level – Masonry wall installation At Main Concourse Buildings are ongoing. Curtainwall: Area 1 – Curtainwall framing installation will continue at West Elevation. Installation of Curtainwall glass is ongoing. Projected Activities occurring next Week: Area 1 – Shot of the West Building Field Side Foundations: Elevation showing progress of Canopy Area 3/4 Field Level – Foundations for “infill” area between Decking and Suite Soffit installation. Column Lines 40-42 will be placed. Concrete Flatwork: Area 3 Field Level – Concrete placement for Slab-on Grade at lower dock area will begin. Area 3 and 4 Field Level – Installation of on-grade seating risers and intermediate stairs will continue. Structural Steel Erection: Area 3/4 – Structural steel erection for “infill” area will Concourse Level Area 3 – Filled and polished begin. CMU Block walls at the East Concourse Buildings. MEP Rough-in: MEP Rough-in at Concourse, Suite and Press Levels will continue. Ductwork installation on Concourse, Suite, and Press Level will continue. Fire Sprinkler installation will continue on Concourse, Suite and Press Levels. Building the Future
  • 3. Metal Stud Framing: Area 1 – Metal stud framing for Field, Concourse, Suite and Press Levels will continue. Exterior Framing and sheathing installation will continue. Curtainwall: Area 1 – Curtain Framing and Glass installation at West Elevation will continue. Curtainwall framing on Suite and Press Level balconies will continue. Curtainwall framing Area 1 – Sheathing installation is complete at Field Side of Main Concourse will begin. at south end of West Building. Area 1 – Shot of the west building showing the progress of the exterior envelope. Building the Future
  • 4. Additional Photos: Area 2/3 – Shot of truck dock area looking northwest from under the State Avenue Area 1 – Soffit framing and sheathing is Bridge. ongoing at all levels of the West Building. Shot of the Stadium from Village West Roof Level Area 1 – Installation of the Parkway and State Avenue showing permanent roof has started. elevation change of roof canopy. Area 1 – Shot of the West Building from the Field Level Area 1 – Metal stud framing, southeast concourse. drywall and in wall MEP rough-in is ongoing. Building the Future