Construction Update 08-18-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 8.18.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
8.16.2010
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating and foundations are
ongoing in Area 3.
Site Utilities:
Storm and Sanitary Sewer Installation is complete Area 3 – Installation of Storm and Sanitary
on the east side of France Family Drive. Lines are complete. Cleanup and repair of
France Family Drive has started.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site (Truck Dock Area).
Concrete Flatwork:
Area 2 – Prep work for next slab pour is underway from
Column Line 15 – 12.
Area 3 – Slab-on-Metal Deck is placed to Column Line 1.
Structural Steel Erection: Field Level Area 3 – Foundations are
Area 1 – Main Canopy Truss Erection are set to Column continuing on East side. Switchback ramp to
Line 20. Cauldron Club installation is ongoing.
Area 2 – South Scoreboard support steel is set between
Column Lines 15 – 18.
Precast Concrete:
Area 3 – Precast erection is ongoing and is currently set
to Column Line 7.
Underground MEP:
Electrical for Electrical Room 01.12.01 is ongoing. Deep
Plumbing has started in Area 3. Area 3 – Precast riser erection has turned
the corner is ongoing on the East side and is
currently to Column Line 7.
Building the Future
2. MEP Rough-in:
Area 2 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite and Press Levels
are ongoing. Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Suite Level.
Metal Stud Framing:
Area 1 – Metal stud framing for Concourse, Suite and Press Area 1 – South Scoreboard support steel is
Levels are ongoing. Metal stud framing has started at Field erected.
Level.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas F, G and H.
Area 3 Concourse Level – Picture framing has started
for south concourse buildings. Layout for north buildings
are ongoing.
Projected Activities occurring next Week:
Grading:
Area 4 – Grading for field wall foundations will continue. Area 1 – Shot of the West Building from the
east concourse.
Site Utilities:
Gas Service installation will begin.
Deep Underground MEP:
Deep Plumbing installation will continue in Area 3.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on Field Level Area 1 – Metal Stud Framing has
Grade between Column Lines 15 - 12. started at the Field Level.
Area 1, 2 and 3 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Building the Future
3. Structural Steel Erection:
Area 2 – Canopy installation at South side of Stadium will
continue.
Underground MEP:
Deep underground plumbing will continue in Area 3.
MEP Rough-in:
MEP Rough-in at Suite and Press Levels will continue.
Area 1 – Installation of curtainwall framing
Ductwork installation on Press Level will continue. Fire
at West Building has started.
Sprinkler installation will continue on Suite Level.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue.
Suite Level Area 1 – Stair 10 is installed at
Stadium Suite.
Building the Future
4. Additional Photos:
Suite Level Area 1 – Stair 6 installed to Press Press Level Area 1 – Shot of curtainwall
Level. framing from inside the Club.
Field Level Area 1 – Backfill for east side on- Field Level Area 3 – Dock Leveler concrete
grade seating is ongoing. bases are placed.
Mezzanine Level Area 1 – Masonry
Field Level Area 3 – Grease Interceptor Pit is
installation is ongoing at south mezzanine.
installed.