SlideShare ist ein Scribd-Unternehmen logo
1 von 5
Downloaden Sie, um offline zu lesen
SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)
MGT60704 PROJECT MANAGEMENT
AUGUST 2018 SEMESTER
INDIVIDUAL ASSIGNMENT
NAME : PANG KAI YUN
STUDENT ID : 0319802
LECTURER : MR LEONG BOON TIK
SUBMISSION DATE : 27 NOVEMBER 2018
Assumption:
1. Working days excluding Saturday and Sunday.
2. Clear and grub the site before installing temporary electrical
connections and plumbing facilities. It takes 1 working day to complete.
3. Driving sheet piles is able to prevent any soil collapse and water
seepage. No additional support system is needed.
4. Before laying down the concrete of the mat foundation and the inverse
slab, the formwork and reinforcement bar is erect and placed within 12
days. After the concrete is poured, it is left for dry for 7 days. The
formwork of the foundation will take 8 days to dismantle.
5. The formwork of heavy wall will be dismantle within 2 days after the
concrete is cure.
* Assumption is highlighted in PURPLE in Gantt Chart
ID Task Mode Activity
ID
Task Name Duration
1 0 Water Pump Station 279 days
2 1000 Apply for Permits 27 days
3 1001 Secure city permit 5 days
4 1002 Secure building permit 21 days
5 1010 Site Work 6 days
6 1011 Clear and grub site 1 day
7 1012 Install temporary electrical connections 5 days
8 1013 Install plumbing utilities 5 days
9 1020 Geotechnical Investigation 4 days
10 1021 Subsurface exploration 4 days
11 2000 Piling 23 days
12 2001 Mobilize equipment and personnel 5 days
13 2002 Driving sheet piles 18 days
14 2010 Excavation 90 days
15 2011 Excavation & Tieback 90 days
16 2020 Foundation 68 days
17 2021 Formwork and reinforcement bar mat
foundation and inverse slab
10 days
18 2022 Pour Concrete mat foundation and inverse
slab
43 days
19 2023 Cure mat foundation and inverse slab 7 days
20 2024 Dismantle formwork 8 days
21 2030 Heavy wall (EL72 ro EL95) 28 days
22 2031 Construct wet well floor 4 days
23 2032 Formwork and Reinforcing stell Placement
(FRP) of heavy wall
5 days
24 2033 Pour concrete for heavy wall 8 days
25 2034 Cure heavy wall 7 days
26 2035 Dismantle formwork 2 days
27 2036 PVC waterproofing membrane 3 days
28 2037 Backfill up to EL95 with soil 3 days
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
March April May June July August September October November December January February March April
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 1
Project: 0319802 PANG KAI YU
Date: Tue 27/11/18
Secure building permit
Start: Tue 19/3/19ID: 4
Finish: Tue 16/4/19Dur: 21 days
Res:
Install plumbing utilities
Start: Tue 12/3/19ID: 8
Finish: Mon 18/3/19Dur: 5 days
Res:
Subsurface exploration
Start: Wed 17/4/19ID: 10
Finish: Mon 22/4/19Dur: 4 days
Res:
Mobilize equipment and personnel
Start: Mon 17/6/19ID: 12
Finish: Fri 21/6/19 Dur: 5 days
Res:
Driving sheet piles
Start: Mon 24/6/19ID: 13
Finish: Wed 17/7/19Dur: 18 days
Res:
Excavation & Tieback
Start: Thu 18/7/19ID: 15
Finish: Wed 20/11/19Dur: 90 days
Res:
Formwork and reinforcement bar mat foundation and inverse slab
Start: Thu 21/11/19ID: 17
Finish: Wed 4/12/19Dur: 10 days
Res:
Pour Concrete mat foundation and inverse slab
Start: Thu 5/12/19ID: 18
Finish: Mon 3/2/20Dur: 43 days
Res:
Cure mat foundation and inverse slab
Start: Tue 4/2/20 ID: 19
Finish: Wed 12/2/20Dur: 7 days
Res:
Dismantle formwork
Start: Thu 13/2/20ID: 20
Finish: Mon 24/2/20Dur: 8 days
Res:
Construct wet well floor
Start: Tue 25/2/20ID: 22
Finish: Fri 28/2/20 Dur: 4 days
Res:
Pour concrete for heavy wall
Start: Tue 3/3/20 ID: 24
Finish: Thu 12/3/20Dur: 8 days
Res:
Cure heavy wall
Start: Fri 13/3/20 ID: 25
Finish: Mon 23/3/20Dur: 7 days
Res:
Dismantle formwork
Start: Tue 24/3/20ID: 26
Finish: Wed 25/3/20Dur: 2 days
Res:
PVC waterproofing membrane
Start: Thu 26/3/20ID: 27
Finish: Mon 30/3/20Dur: 3 days
Res:
Backfill up to EL95 with soil
Start: Tue 31/3/20ID: 28
Finish: Thu 2/4/20 Dur: 3 days
Res:
Formwork and Reinforcing stell Placement (FRP) of heavy wall
Start: Tue 25/2/20ID: 23
Finish: Mon 2/3/20Dur: 5 days
Res:
Install temporary electrical connections
Start: Tue 12/3/19ID: 7
Finish: Mon 18/3/19Dur: 5 days
Res:
Clear and grub site
Start: Mon 11/3/19ID: 6
Finish: Mon 11/3/19Dur: 1 day
Res:
Secure city permit
Start: Mon 11/3/19ID: 3
Finish: Fri 15/3/19 Dur: 5 days
Res:
Page 1
Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Page 2
Project: 0319802 PANG KAI YU
Date: Tue 27/11/18

Weitere ähnliche Inhalte

Was ist angesagt?

estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingAnchit Agrawal
 
Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5Hari Krishna Shrestha
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 
Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projectsKapugantikapuganti Gupta
 
Apartment building construction project report
Apartment building construction project reportApartment building construction project report
Apartment building construction project reportHiska Chishi
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTIONMd Shadab
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Jamal Nelson, CCM
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity SSudhaVelan
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdfPPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdfTaufikkurrahman Upik Teler
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
Civil Engineering Internship Semester Presentation
Civil Engineering Internship Semester PresentationCivil Engineering Internship Semester Presentation
Civil Engineering Internship Semester PresentationShubham Pokharkar
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Industrial training presentation
Industrial training presentationIndustrial training presentation
Industrial training presentationNursyafiqah Ismail
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 

Was ist angesagt? (20)

estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projects
 
Apartment building construction project report
Apartment building construction project reportApartment building construction project report
Apartment building construction project report
 
Testing And Commissioning
Testing And CommissioningTesting And Commissioning
Testing And Commissioning
 
Ahmed -solar engineer-cv
Ahmed -solar engineer-cvAhmed -solar engineer-cv
Ahmed -solar engineer-cv
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTION
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdfPPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Viaduct
Viaduct Viaduct
Viaduct
 
Civil Engineering Internship Semester Presentation
Civil Engineering Internship Semester PresentationCivil Engineering Internship Semester Presentation
Civil Engineering Internship Semester Presentation
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Site Survey Report
Site Survey ReportSite Survey Report
Site Survey Report
 
Industrial training presentation
Industrial training presentationIndustrial training presentation
Industrial training presentation
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 

Ähnlich wie Assignment 1 - Water Pump Station

11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3Ahmad Basim Hamza
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposalkjanand
 
Nework digram .pdf
Nework digram .pdfNework digram .pdf
Nework digram .pdfdks
 
Final Report
Final Report Final Report
Final Report Jack Ng
 
Basic Civil Engineering by S S Bhavikatti.pdf
Basic Civil Engineering by S S Bhavikatti.pdfBasic Civil Engineering by S S Bhavikatti.pdf
Basic Civil Engineering by S S Bhavikatti.pdfmaheshreddy413
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdfabdo badr
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report finalShubham Parab
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential buildingShariful Haque Robin
 
Site visit report
Site visit reportSite visit report
Site visit reportJordon Wong
 
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...IRJET Journal
 
NARRATIVE-REPORT-JOHN-ZEDRICK-MISLANG.pdf
NARRATIVE-REPORT-JOHN-ZEDRICK-MISLANG.pdfNARRATIVE-REPORT-JOHN-ZEDRICK-MISLANG.pdf
NARRATIVE-REPORT-JOHN-ZEDRICK-MISLANG.pdfHEColladoDianaMaeY
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfGaluhWulandari10
 
Climate change video project plan
Climate change video project planClimate change video project plan
Climate change video project planvelgot
 
Site visit report
Site visit reportSite visit report
Site visit reportshensin1015
 

Ähnlich wie Assignment 1 - Water Pump Station (20)

Projec
ProjecProjec
Projec
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3
 
MS project Sample gantt chart
MS project Sample  gantt chartMS project Sample  gantt chart
MS project Sample gantt chart
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposal
 
Nework digram .pdf
Nework digram .pdfNework digram .pdf
Nework digram .pdf
 
Final Report
Final Report Final Report
Final Report
 
Site report 1
Site report 1Site report 1
Site report 1
 
Basic Civil Engineering by S S Bhavikatti.pdf
Basic Civil Engineering by S S Bhavikatti.pdfBasic Civil Engineering by S S Bhavikatti.pdf
Basic Civil Engineering by S S Bhavikatti.pdf
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdf
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Site visit report
Site visit reportSite visit report
Site visit report
 
P25
P25P25
P25
 
Shivam last.docx
Shivam last.docxShivam last.docx
Shivam last.docx
 
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
 
NARRATIVE-REPORT-JOHN-ZEDRICK-MISLANG.pdf
NARRATIVE-REPORT-JOHN-ZEDRICK-MISLANG.pdfNARRATIVE-REPORT-JOHN-ZEDRICK-MISLANG.pdf
NARRATIVE-REPORT-JOHN-ZEDRICK-MISLANG.pdf
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdf
 
Climate change video project plan
Climate change video project planClimate change video project plan
Climate change video project plan
 
Site visit report
Site visit reportSite visit report
Site visit report
 

Mehr von Kai Yun Pang

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiKai Yun Pang
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - ReportKai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial AppraisalKai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal Kai Yun Pang
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012Kai Yun Pang
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Kai Yun Pang
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S HotelKai Yun Pang
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study ReportKai Yun Pang
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - JournalKai Yun Pang
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service Kai Yun Pang
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - QuestionKai Yun Pang
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK LandKai Yun Pang
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial AnalysisKai Yun Pang
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Kai Yun Pang
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalKai Yun Pang
 

Mehr von Kai Yun Pang (20)

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - Report
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - Journal
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK Land
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial Analysis
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 

Kürzlich hochgeladen

Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 

Kürzlich hochgeladen (20)

Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 

Assignment 1 - Water Pump Station

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) MGT60704 PROJECT MANAGEMENT AUGUST 2018 SEMESTER INDIVIDUAL ASSIGNMENT NAME : PANG KAI YUN STUDENT ID : 0319802 LECTURER : MR LEONG BOON TIK SUBMISSION DATE : 27 NOVEMBER 2018
  • 2. Assumption: 1. Working days excluding Saturday and Sunday. 2. Clear and grub the site before installing temporary electrical connections and plumbing facilities. It takes 1 working day to complete. 3. Driving sheet piles is able to prevent any soil collapse and water seepage. No additional support system is needed. 4. Before laying down the concrete of the mat foundation and the inverse slab, the formwork and reinforcement bar is erect and placed within 12 days. After the concrete is poured, it is left for dry for 7 days. The formwork of the foundation will take 8 days to dismantle. 5. The formwork of heavy wall will be dismantle within 2 days after the concrete is cure. * Assumption is highlighted in PURPLE in Gantt Chart
  • 3. ID Task Mode Activity ID Task Name Duration 1 0 Water Pump Station 279 days 2 1000 Apply for Permits 27 days 3 1001 Secure city permit 5 days 4 1002 Secure building permit 21 days 5 1010 Site Work 6 days 6 1011 Clear and grub site 1 day 7 1012 Install temporary electrical connections 5 days 8 1013 Install plumbing utilities 5 days 9 1020 Geotechnical Investigation 4 days 10 1021 Subsurface exploration 4 days 11 2000 Piling 23 days 12 2001 Mobilize equipment and personnel 5 days 13 2002 Driving sheet piles 18 days 14 2010 Excavation 90 days 15 2011 Excavation & Tieback 90 days 16 2020 Foundation 68 days 17 2021 Formwork and reinforcement bar mat foundation and inverse slab 10 days 18 2022 Pour Concrete mat foundation and inverse slab 43 days 19 2023 Cure mat foundation and inverse slab 7 days 20 2024 Dismantle formwork 8 days 21 2030 Heavy wall (EL72 ro EL95) 28 days 22 2031 Construct wet well floor 4 days 23 2032 Formwork and Reinforcing stell Placement (FRP) of heavy wall 5 days 24 2033 Pour concrete for heavy wall 8 days 25 2034 Cure heavy wall 7 days 26 2035 Dismantle formwork 2 days 27 2036 PVC waterproofing membrane 3 days 28 2037 Backfill up to EL95 with soil 3 days B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B March April May June July August September October November December January February March April Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 1 Project: 0319802 PANG KAI YU Date: Tue 27/11/18
  • 4. Secure building permit Start: Tue 19/3/19ID: 4 Finish: Tue 16/4/19Dur: 21 days Res: Install plumbing utilities Start: Tue 12/3/19ID: 8 Finish: Mon 18/3/19Dur: 5 days Res: Subsurface exploration Start: Wed 17/4/19ID: 10 Finish: Mon 22/4/19Dur: 4 days Res: Mobilize equipment and personnel Start: Mon 17/6/19ID: 12 Finish: Fri 21/6/19 Dur: 5 days Res: Driving sheet piles Start: Mon 24/6/19ID: 13 Finish: Wed 17/7/19Dur: 18 days Res: Excavation & Tieback Start: Thu 18/7/19ID: 15 Finish: Wed 20/11/19Dur: 90 days Res: Formwork and reinforcement bar mat foundation and inverse slab Start: Thu 21/11/19ID: 17 Finish: Wed 4/12/19Dur: 10 days Res: Pour Concrete mat foundation and inverse slab Start: Thu 5/12/19ID: 18 Finish: Mon 3/2/20Dur: 43 days Res: Cure mat foundation and inverse slab Start: Tue 4/2/20 ID: 19 Finish: Wed 12/2/20Dur: 7 days Res: Dismantle formwork Start: Thu 13/2/20ID: 20 Finish: Mon 24/2/20Dur: 8 days Res: Construct wet well floor Start: Tue 25/2/20ID: 22 Finish: Fri 28/2/20 Dur: 4 days Res: Pour concrete for heavy wall Start: Tue 3/3/20 ID: 24 Finish: Thu 12/3/20Dur: 8 days Res: Cure heavy wall Start: Fri 13/3/20 ID: 25 Finish: Mon 23/3/20Dur: 7 days Res: Dismantle formwork Start: Tue 24/3/20ID: 26 Finish: Wed 25/3/20Dur: 2 days Res: PVC waterproofing membrane Start: Thu 26/3/20ID: 27 Finish: Mon 30/3/20Dur: 3 days Res: Backfill up to EL95 with soil Start: Tue 31/3/20ID: 28 Finish: Thu 2/4/20 Dur: 3 days Res: Formwork and Reinforcing stell Placement (FRP) of heavy wall Start: Tue 25/2/20ID: 23 Finish: Mon 2/3/20Dur: 5 days Res: Install temporary electrical connections Start: Tue 12/3/19ID: 7 Finish: Mon 18/3/19Dur: 5 days Res: Clear and grub site Start: Mon 11/3/19ID: 6 Finish: Mon 11/3/19Dur: 1 day Res: Secure city permit Start: Mon 11/3/19ID: 3 Finish: Fri 15/3/19 Dur: 5 days Res: Page 1
  • 5. Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical Page 2 Project: 0319802 PANG KAI YU Date: Tue 27/11/18