3. Definition
It is the process required to supply
equipment , material , service and other
resources needed to carry out a project that
satisfy customer
3
4. Item Description Weight
1 Engineering 5%
2 Equipment / Material 65%
3 Construction 15%
4 Testing and Commissioning 10%
4
5. 1-Setting procurement process requires to supply
equipment , materials and other resources to
carry out in constructing industrial project
right the first time and every time.
2- Monitoring performance indictor to help
manager to prevent and reduce problem that
can affect the procurement process.
5
7. Begin
Planning
Documentation
Product Evaluation
Awarded
Inspection
Delivery
7
8. Input
1. Scope of work
2. Specification and drawings
3. Company resource
4. Signature mandate
5. Product estimated value
8
9. Output
1. Product list
2. Product supplier list
3. Type of procurement contract
1. Sole source
2. Single source
3. Competitive bids
4. Estimated product value
5. Approval to proceed with procurement
9
10. Tender documents
Standardized forms
Inquiry
Invitation letter
Purchase order
General terms and condition
Filing system
10
11. 1. Price
2. Delivery time
3. Financial capability of supplier
4. Type of product
5. Historical of supplier
6. Supplier approaches
7. Workload existing and anticipated
8. Customer feedback
Reference
Approval
11
12. 1. Notify successful tender and unsuccessfully
tender of outcome
2. Compile contract documents
3. Formally accepted tender offer
12
13. Monitor supplier progress
Inspection
Shipment and delivery
Payment
Check compliance with quality
13
14. 1. Cycle times
The different activities within PP
1. Milestone events
Issuing R.Q - PO
Approval of drawings
Inspection
Customs clearance
Delivery
1. Management
Project police
Project Organization
14
15. 4. Cost Indicator
No of days in warehouse
No of days in customs
No of days correction / repair
No of changes to air transportation
Time from arrival till installation
5. Referential values
Amount of PO
No and amount of change orders
Delivery / invoicing
15
19. Whether the procurement satisfied the stated
objective
Whether needs and expectation have be meets
Whether the procurement process should be
improve
How external factors such regulation , standard
component have change
Whether the process improve cost saving
19
20. Review of performance indicator
Review non conformity report
Effect analysis regarding delays
Costs and time cycles
20
22. 1. Improve company and project reputation name
2. Achieving customer satisfaction and increase market
share
3. Reduce rework and mistake
4. Standardized forms
5. Reduce warranty period
6. Increase profit
7. Lower insurance cost
8. Improve cash follow
22
23. The problem present on procurement are of different types and origins. The
most detected problem :
Planning
Delay on issuing specification for quotation
Delay on informing supplier
Supplier
To many obstacles and clauses delay negotiations
Poor explanation about items
Later purchase makes system expensive , air freight
and urgent
23
24. 1. Delay at delivery
2. Delay on ordering
3. Delay on engineering drawings ( errors)
4. Repair and replacement at job site
5. Poorly planned inspection
6. Lack of information on site about arrival for some supplier
7. Changes to air transportation to make faster delivery
Using PP indicator and periodical report is tools to monitor and
prevent delays
Using IT ( email , scheduling etc ) will help in reducing delay and
closely monitor the product progress for necessary action .
24