Project Schedule
Management
Knowledge Area
Project Management Processes
Overview of Schedule
Management Knowledge Area
• Ensuring Project Items are
Completed on Time
• Relationship of Activities
• Schedule of Performing of
Activities
Overview of
Schedule
Management
Knowledge
Area
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Duration
6.5 Develop Schedule
6.6 Control Schedule
Project Schedule
Management
• Schedule Management involves the
processes needed to manage completion of
the project on time
• The process is used to produce the Project
Schedule
6.1 Plan
Schedule
Management-Planning Process Group
The Plan Schedule
Management Process
Is the process concerned with
laying the framework for the other
five Schedule Management
Processes and defining how they
will be conducted.
6.1 Plan Schedule
Management
• Occurs in the Planning Process Group
• Concerned with establishing of
procedures, policies, planning, managing,
and documenting the project schedule
• Used to create the Schedule
Management Plan
Schedule
Management Plan
• Provides guidance in creation of the schedule
• What needs to be done to create the schedule?
• Lays out how planning the schedule will be done
• The methodology to be used, such as Critical Path
Method
• Defines the tools to create the schedule
• Indicates software tools that will be used
• Instructs on the managing and control of the project
• Managing the schedule compared to the
schedule baseline
• Methods for measuring performance of the schedule
• Variance management, schedule change control
6.2 Define
Activities-Planning Process Group
The Define Activities
Process
Is the process for identifying
activities that will be performed
during the project in order to
produce the project deliverables
and documenting those activities
6.2 Define Activities
• Occurs in the Planning Process Group
• The work packages from the WBS
(Created in Project Scope
Management) are broken down into
smaller activities
• Improves the estimating of scheduling
• Should include the project team to
help define the activities
Outputs of the Define
Activities List Process
• Activity List
• The project activities that need to be
performed
• Activity Attributes
• Details regarding the activity list
• Milestones
• Key events that occur in the project schedule
• They are not an activity and have no duration
• Change Requests
• If activities are defined through progressive
elaboration (or Rolling Wave Planning) it may
result in changes to the planned scope
6.3 Sequence
Activities-Planning Process Group
The Sequence
Activities Process
• Concerned with identifying the
relationships of the activities
defined in the Define Activities
process
6.3 Sequence
Activities
• Occurs in the Planning Process Group
• A Network Diagram should be created to
show the sequence of activities in a visual
way
• Work is conducted to identify relationships
between activities
Sequence
Activities -
Dependencies
• A requirement that must be considered before
another requirement can be worked on; the
nature of the work includes this dependency
Mandatory
Dependency:
• An optional dependency that can be removed or
altered at the discretion of the project team
Discretionary
Dependency:
• A dependency that is coming from outside of the
project such as organizational rules/processes or
government regulations
External
Dependency:
• The relationship between project activities that
may be include resource availability being able to
move to the next activitiy
Internal
Dependency:
Lead Time
The following activity starts before the preceding
activity finishes
Lag Time
The time between the start of the next activity
and the end of the previous activity
Precedence
Diagramming Method
(PDM)
A method to create a
Network Diagram
Precedence Diagramming Method
Boxes that
represent
activities
Arrows
indicating
dependencies
Similar to a
process flow
chart
PDM
Relationships
Finish to Start (FS)
Start to Start (SS)
Finish to Finish (FF)
Start to Finish (SF)
6.4 Estimate
Activity Duration-Planning Process Group
The Estimate Activity
Duration Process
• Process of estimating how long
activities will take to complete to
the required state
6.4 Estimate Activity
Duration
• Occurs in the Planning Process Group
• Determine approximately how long each
activity will take to complete
• More accurate estimations can occur
with activities that are clearly understood
• Unclear items may include padded time
to allow for future clarifications that may
take longer than expected – risk
management
Techniques of Activity
Estimations
• One-Point Estimation
• Each estimator submits an estimate for the activity
• Parametric Estimation
• Using historical records to collect average completion
times for activities and using that as a basis to
estimate current activities
• Analogous Estimation
• Similar activities are examined for their actual
completion times and used to estimate for the
current activity
Techniques of Activity
Estimations –
PERT Analysis
• Three estimates are provided for each activity
• Optimistic Estimate (O) – Best case scenario for
activity completion times
• Most Likely Estimate (M) - The most likely
completion time of the activity
• Pessimistic Estimate (P) – Worst case scenario
for activity completion duration
• Using the average of the estimates to estimate the
activity
• Triangular Distribution
• Beta Distribution
• Used for time and cost estimates
Managing Schedule Risks
Contingency Reserve:
Extra time placed in the schedule on an activity
in case a risk actualizes
Management Reserve:
Extra money/budget held for the purposes of
combating unforeseen or unexpected risk
actualization
6.5 Develop
Schedule-Planning Process Group
The Develop Schedule
Process
• Using the outputs of the prior
processes to develop the project
schedule with planned/estimated
start and completion dates
6.5 Develop
Schedule
• Occurs during the Planning Process
Group
• Create a model using the estimations of
the activities and the planned sequence
to create a model of the schedule
• Time based activities are laid out in
sequence and indicate the resource
responsible for completing the activity
Requirements to Complete A Schedule
Project Scope
Statement
Network Diagram Activity List
Time Estimates of
Activities
Resource
Requirements Needed
to Complete Activities
Resource Availability
Schedules
Critical Path Method (CPM)
• Popular schedule Network Analysis technique
• The longest path from the beginning to the end
through the schedule
• Gives an idea of how long the project should
take to be fully completed
Float/Slack
• The time an activity can be delayed without impacting
other activities or delays in the project
• Total Float is the time an activity can be delayed without
impact to the project duration
• Free Float is the time an activity can be delayed without
impacting the early start date of another activity
• Project Float is the time that an activity can be delayed
without impacting customer imposed project completion
date
Critical Path
Activities
Should be Zero
Float Days
Calculating Float
Late Start (LS) – Early Start (ES)
Late Finish(LF) – Early Finish (EF)
6.6 Control
Schedule-Monitoring & Controlling Process Group
The Control Schedule
Process
• The process of working to ensure
that the progress of the project
remains on track or changes
against the scheduled baseline
are managed appropriately
6.6 Control
Schedule
• Occurs during the Monitoring &
Controlling Process Group
• Current progress is measured against the
scheduled baseline
• Root causes of changes should be found
and eliminated if possible to prevent
excessive changes to the schedule
baseline
Controlling the
Schedule
• Activities may be re-estimated
• Unclear areas may be clarified and need to be
estimated again
• Review the schedule to determine if the project is on
schedule
• Distribute work to available resources
• Resource leveling
• Adjust the projects progress
• Prepare reports on the status of the project compared
to the schedule
• Manage the change control process regarding the
schedule
Sources
• A Guide to the Project Management Body of Knowledge – PMBOK 6th
Edition
• https://www.pmi.org/
Joshua Render
https://agile-mercurial.com

Weitere ähnliche Inhalte

Was ist angesagt?

Project integration management
Project  integration managementProject  integration management
Project integration managementdeep sharma
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTùng Trần Thanh
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaEdureka!
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration ManagementBhuWan Khadka
 
2.project lifecycle
2.project lifecycle2.project lifecycle
2.project lifecyclerlabsza
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsNishant Munjal
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project KnowledgeDavidMcLachlan1
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management OverviewDavidMcLachlan1
 
Agile Project Management for PMP's
Agile Project Management for PMP'sAgile Project Management for PMP's
Agile Project Management for PMP'sVersionOne
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Agus Suhanto
 
Project Closing Process
Project Closing ProcessProject Closing Process
Project Closing ProcessNishant Munjal
 

Was ist angesagt? (20)

2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
2.project lifecycle
2.project lifecycle2.project lifecycle
2.project lifecycle
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
 
Agile Project Management for PMP's
Agile Project Management for PMP'sAgile Project Management for PMP's
Agile Project Management for PMP's
 
Project management
Project managementProject management
Project management
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 
Project Closing Process
Project Closing ProcessProject Closing Process
Project Closing Process
 

Ähnlich wie Project Management: Project Schedule Management Knowledge Area

TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdfNabeel Ahmad
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Project Planning and Control
Project Planning and Control Project Planning and Control
Project Planning and Control drpvkhatrissn
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)anjalatchi
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process GroupsBhuWan Khadka
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfAnatole9
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4Qussay Karam
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxMohanadRabea1
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3Golam Bitonsir
 

Ähnlich wie Project Management: Project Schedule Management Knowledge Area (20)

TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Project Management
Project ManagementProject Management
Project Management
 
Project Planning and Control
Project Planning and Control Project Planning and Control
Project Planning and Control
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdf
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Time management
Time managementTime management
Time management
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3
 

Mehr von Joshua Render

Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Joshua Render
 
Alderfer's ERG theory of motivation
Alderfer's ERG theory of motivationAlderfer's ERG theory of motivation
Alderfer's ERG theory of motivationJoshua Render
 
MacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZMacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZJoshua Render
 
Big Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelBig Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelJoshua Render
 
Drexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelDrexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelJoshua Render
 
7 Core Concepts of Lean
7 Core Concepts of Lean7 Core Concepts of Lean
7 Core Concepts of LeanJoshua Render
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)Joshua Render
 
Guide to User Story Creation
Guide to User Story CreationGuide to User Story Creation
Guide to User Story CreationJoshua Render
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management ProcessesJoshua Render
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaJoshua Render
 
Procurement Management Knowledge Area
Procurement Management Knowledge AreaProcurement Management Knowledge Area
Procurement Management Knowledge AreaJoshua Render
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge AreaJoshua Render
 
Communication Management Knowledge Area
Communication Management Knowledge AreaCommunication Management Knowledge Area
Communication Management Knowledge AreaJoshua Render
 
Resource Management Knowledge Area
Resource Management Knowledge AreaResource Management Knowledge Area
Resource Management Knowledge AreaJoshua Render
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge AreaJoshua Render
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaJoshua Render
 
What is Osmotic Communication?
What is Osmotic Communication?What is Osmotic Communication?
What is Osmotic Communication?Joshua Render
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge AreaJoshua Render
 

Mehr von Joshua Render (20)

Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?
 
Alderfer's ERG theory of motivation
Alderfer's ERG theory of motivationAlderfer's ERG theory of motivation
Alderfer's ERG theory of motivation
 
MacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZMacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory Z
 
Big Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelBig Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor Model
 
Drexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelDrexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance Model
 
What is Kanban?
What is Kanban?What is Kanban?
What is Kanban?
 
7 Core Concepts of Lean
7 Core Concepts of Lean7 Core Concepts of Lean
7 Core Concepts of Lean
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
Guide to User Story Creation
Guide to User Story CreationGuide to User Story Creation
Guide to User Story Creation
 
Tuckman's Model
Tuckman's ModelTuckman's Model
Tuckman's Model
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge Area
 
Procurement Management Knowledge Area
Procurement Management Knowledge AreaProcurement Management Knowledge Area
Procurement Management Knowledge Area
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge Area
 
Communication Management Knowledge Area
Communication Management Knowledge AreaCommunication Management Knowledge Area
Communication Management Knowledge Area
 
Resource Management Knowledge Area
Resource Management Knowledge AreaResource Management Knowledge Area
Resource Management Knowledge Area
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge Area
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
What is Osmotic Communication?
What is Osmotic Communication?What is Osmotic Communication?
What is Osmotic Communication?
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
 

Kürzlich hochgeladen

Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 

Kürzlich hochgeladen (20)

Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 

Project Management: Project Schedule Management Knowledge Area

  • 2. Overview of Schedule Management Knowledge Area • Ensuring Project Items are Completed on Time • Relationship of Activities • Schedule of Performing of Activities
  • 3. Overview of Schedule Management Knowledge Area 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Duration 6.5 Develop Schedule 6.6 Control Schedule
  • 4. Project Schedule Management • Schedule Management involves the processes needed to manage completion of the project on time • The process is used to produce the Project Schedule
  • 6. The Plan Schedule Management Process Is the process concerned with laying the framework for the other five Schedule Management Processes and defining how they will be conducted.
  • 7. 6.1 Plan Schedule Management • Occurs in the Planning Process Group • Concerned with establishing of procedures, policies, planning, managing, and documenting the project schedule • Used to create the Schedule Management Plan
  • 8. Schedule Management Plan • Provides guidance in creation of the schedule • What needs to be done to create the schedule? • Lays out how planning the schedule will be done • The methodology to be used, such as Critical Path Method • Defines the tools to create the schedule • Indicates software tools that will be used • Instructs on the managing and control of the project • Managing the schedule compared to the schedule baseline • Methods for measuring performance of the schedule • Variance management, schedule change control
  • 10. The Define Activities Process Is the process for identifying activities that will be performed during the project in order to produce the project deliverables and documenting those activities
  • 11. 6.2 Define Activities • Occurs in the Planning Process Group • The work packages from the WBS (Created in Project Scope Management) are broken down into smaller activities • Improves the estimating of scheduling • Should include the project team to help define the activities
  • 12. Outputs of the Define Activities List Process • Activity List • The project activities that need to be performed • Activity Attributes • Details regarding the activity list • Milestones • Key events that occur in the project schedule • They are not an activity and have no duration • Change Requests • If activities are defined through progressive elaboration (or Rolling Wave Planning) it may result in changes to the planned scope
  • 14. The Sequence Activities Process • Concerned with identifying the relationships of the activities defined in the Define Activities process
  • 15. 6.3 Sequence Activities • Occurs in the Planning Process Group • A Network Diagram should be created to show the sequence of activities in a visual way • Work is conducted to identify relationships between activities
  • 16. Sequence Activities - Dependencies • A requirement that must be considered before another requirement can be worked on; the nature of the work includes this dependency Mandatory Dependency: • An optional dependency that can be removed or altered at the discretion of the project team Discretionary Dependency: • A dependency that is coming from outside of the project such as organizational rules/processes or government regulations External Dependency: • The relationship between project activities that may be include resource availability being able to move to the next activitiy Internal Dependency:
  • 17. Lead Time The following activity starts before the preceding activity finishes
  • 18. Lag Time The time between the start of the next activity and the end of the previous activity
  • 19. Precedence Diagramming Method (PDM) A method to create a Network Diagram
  • 20. Precedence Diagramming Method Boxes that represent activities Arrows indicating dependencies Similar to a process flow chart
  • 21. PDM Relationships Finish to Start (FS) Start to Start (SS) Finish to Finish (FF) Start to Finish (SF)
  • 23. The Estimate Activity Duration Process • Process of estimating how long activities will take to complete to the required state
  • 24. 6.4 Estimate Activity Duration • Occurs in the Planning Process Group • Determine approximately how long each activity will take to complete • More accurate estimations can occur with activities that are clearly understood • Unclear items may include padded time to allow for future clarifications that may take longer than expected – risk management
  • 25. Techniques of Activity Estimations • One-Point Estimation • Each estimator submits an estimate for the activity • Parametric Estimation • Using historical records to collect average completion times for activities and using that as a basis to estimate current activities • Analogous Estimation • Similar activities are examined for their actual completion times and used to estimate for the current activity
  • 26. Techniques of Activity Estimations – PERT Analysis • Three estimates are provided for each activity • Optimistic Estimate (O) – Best case scenario for activity completion times • Most Likely Estimate (M) - The most likely completion time of the activity • Pessimistic Estimate (P) – Worst case scenario for activity completion duration • Using the average of the estimates to estimate the activity • Triangular Distribution • Beta Distribution • Used for time and cost estimates
  • 27. Managing Schedule Risks Contingency Reserve: Extra time placed in the schedule on an activity in case a risk actualizes Management Reserve: Extra money/budget held for the purposes of combating unforeseen or unexpected risk actualization
  • 29. The Develop Schedule Process • Using the outputs of the prior processes to develop the project schedule with planned/estimated start and completion dates
  • 30. 6.5 Develop Schedule • Occurs during the Planning Process Group • Create a model using the estimations of the activities and the planned sequence to create a model of the schedule • Time based activities are laid out in sequence and indicate the resource responsible for completing the activity
  • 31. Requirements to Complete A Schedule Project Scope Statement Network Diagram Activity List Time Estimates of Activities Resource Requirements Needed to Complete Activities Resource Availability Schedules
  • 32. Critical Path Method (CPM) • Popular schedule Network Analysis technique • The longest path from the beginning to the end through the schedule • Gives an idea of how long the project should take to be fully completed
  • 33. Float/Slack • The time an activity can be delayed without impacting other activities or delays in the project • Total Float is the time an activity can be delayed without impact to the project duration • Free Float is the time an activity can be delayed without impacting the early start date of another activity • Project Float is the time that an activity can be delayed without impacting customer imposed project completion date
  • 35. Calculating Float Late Start (LS) – Early Start (ES) Late Finish(LF) – Early Finish (EF)
  • 36. 6.6 Control Schedule-Monitoring & Controlling Process Group
  • 37. The Control Schedule Process • The process of working to ensure that the progress of the project remains on track or changes against the scheduled baseline are managed appropriately
  • 38. 6.6 Control Schedule • Occurs during the Monitoring & Controlling Process Group • Current progress is measured against the scheduled baseline • Root causes of changes should be found and eliminated if possible to prevent excessive changes to the schedule baseline
  • 39. Controlling the Schedule • Activities may be re-estimated • Unclear areas may be clarified and need to be estimated again • Review the schedule to determine if the project is on schedule • Distribute work to available resources • Resource leveling • Adjust the projects progress • Prepare reports on the status of the project compared to the schedule • Manage the change control process regarding the schedule
  • 40. Sources • A Guide to the Project Management Body of Knowledge – PMBOK 6th Edition • https://www.pmi.org/ Joshua Render https://agile-mercurial.com