YANPET PRACTISE
ELIMINATE HIDDEN RISK OF CUI
Hamad Al-Alwani
AIM Department
NACE JUBAIL TECHNICAL WORKSHOP
CORROSION UNDER INSULATION (CUI)
10TH December, 2015
No. 2
• Carbon steel: (–12°C) - (175°C)
• Stainless steel: (60°C) - (205°C)
WHAT IS CORROSION UNDER INSULATION (CUI) ?
• CUI is an external corrosion that occurs under insulated carbon steel and SS
equipment.
CUI is promoted by:
• Water vapors condensation.
• Sweating service
• Temperature cycling.
• Poor condition of coating.
• Poor/broken insulation/cladding.
No. 3
AFTER REMOVE INSULATION
CUI GENERAL VIEW
BEFORE REMOVE INSULATION
No. 4
AFTER REMOVE INSULATION
CUI GENERAL VIEW
BEFORE REMOVE INSULATION
No. 5
INSPECTION STRATEGY
• Inspection Strategy is RBI based approach
• Priority – 1: Sweating (continuous or cyclic) lines – require 100% insulation
stripping and visual inspection and NDT.
• Priority – 2 : Non sweating service Inspect as per API standard (suspected
locations)
No. 6
CUI: PLANT CASES
Line H-14015-3”-C322 Leaking Drain Valve & Corroded Pipe (Hydrogen)
Line #
Line Associated
Equipment
Damage
Original
Thickness
mm
Remaining
Thickness
mm
Risk Level
Risk status
H-14015-3”-
C322
D-1451A localized pitting 5.54 2.5 2
Mitigated
Pipe replaced
No. 7
CUI: PLANT CASES
P-13099A-14”-C322 Process (vapour)
Line #
Line Associated
Equipment
Damage
Original
Thickness
mm
Remaining
Thickness
mm
Risk Level
Risk status
P-13099A-
14”-C322
Process
(vapour)
P-13064A-18-
C322
General
corrosion
9.53 5.45 2
Mitigated
Pipe replaced
No. 8
CUI: PLANT CASES
Line 2P-15166- C323
Line #
Line Associated
Equipment
Damage
Original
Thickness
mm
Remaining l
Thickness
mm
Risk Level
Risk status
2P-15166-
C323
D-1451A
Minor wall lost &
bolts severely
corroded
8.18 7.8 2
Mitigation is in
progress
No. 9
YANPET CUI MITIGATION STRATEGY
I. Inspect on time.
II. Watch insulation damage.
III. Restoration of CUI Coatings.
IV. Apply Thermal Spray Aluminum (TSA) on critical services.
V. Replace PP Insulation with grid metallic type.
BEFORE AFTER
No. 10
• Removed all PP insulation and replace it by metallic grid type.
• Personnel Protection (PP) insulation (Piping operating above 60 °C to 110 °C).
• Grid type eliminates the hidden Risk & Operator is still protected from hot surface.
• Grid type cost effective, easy to install, reuse and fast future inspection.
YANPET PRACTICE WITH PP INSULATION
No. 11
YANPET PRACTICE WITH PP INSULATION
Line covered with old PP
insulation
Same line after removing
the insulation.
The alternative idea after
the installation.
No. 12
PLEASE REMEMBER !!!
SAFETY FIRST
&
CORROSION UNDER INSULATION PROGRAM IS THE SAFE WAY.
CORROSION UNDER UNSULATION
 Always: AVOID DAMAGES TO THE INSULATION COVER
THANK YOU

Weitere ähnliche Inhalte

Was ist angesagt?

Asme pcc 2 repair leaks
Asme pcc 2 repair leaksAsme pcc 2 repair leaks
Asme pcc 2 repair leaksGreg Kilaton
 
100661266 cswip-3-1-2009
100661266 cswip-3-1-2009100661266 cswip-3-1-2009
100661266 cswip-3-1-2009Jithu John
 
Documents Governing Welding Inspection and Qualification
Documents Governing Welding Inspection and QualificationDocuments Governing Welding Inspection and Qualification
Documents Governing Welding Inspection and QualificationRandall Stremmel
 
Lining Track Records & Case Histories
Lining Track Records & Case HistoriesLining Track Records & Case Histories
Lining Track Records & Case HistoriesInternational Paint
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2Jithu John
 
Fatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker PennimentFatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker PennimentNSW Environment and Planning
 
Clearing up material traceability: Confusion and myths in oil and gas manufac...
Clearing up material traceability: Confusion and myths in oil and gas manufac...Clearing up material traceability: Confusion and myths in oil and gas manufac...
Clearing up material traceability: Confusion and myths in oil and gas manufac...Lloyd's Register Energy
 
Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Ramdani Diningrat
 
2. pipeline materials overview
2. pipeline materials overview2. pipeline materials overview
2. pipeline materials overviewWillam Le
 
Effect of boron content on steels and recommended practice for welding Sasank...
Effect of boron content on steels and recommended practice for welding Sasank...Effect of boron content on steels and recommended practice for welding Sasank...
Effect of boron content on steels and recommended practice for welding Sasank...NSW Environment and Planning
 
Fundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas EngineerFundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas EngineerVarun Patel
 
Pre-Insulated Pipe Supports Featuring Cryogenic and High Temperature Pipe Shoes
Pre-Insulated Pipe Supports Featuring Cryogenic and High Temperature Pipe Shoes Pre-Insulated Pipe Supports Featuring Cryogenic and High Temperature Pipe Shoes
Pre-Insulated Pipe Supports Featuring Cryogenic and High Temperature Pipe Shoes Piping Technology & Products, Inc.
 

Was ist angesagt? (18)

Corrosion Under Insulation
Corrosion Under InsulationCorrosion Under Insulation
Corrosion Under Insulation
 
Asme pcc 2 repair leaks
Asme pcc 2 repair leaksAsme pcc 2 repair leaks
Asme pcc 2 repair leaks
 
International paint surfaces 23
International paint surfaces 23International paint surfaces 23
International paint surfaces 23
 
Introduction to linings
Introduction to liningsIntroduction to linings
Introduction to linings
 
100661266 cswip-3-1-2009
100661266 cswip-3-1-2009100661266 cswip-3-1-2009
100661266 cswip-3-1-2009
 
Piping Design Engineering
Piping Design EngineeringPiping Design Engineering
Piping Design Engineering
 
Documents Governing Welding Inspection and Qualification
Documents Governing Welding Inspection and QualificationDocuments Governing Welding Inspection and Qualification
Documents Governing Welding Inspection and Qualification
 
Lining Track Records & Case Histories
Lining Track Records & Case HistoriesLining Track Records & Case Histories
Lining Track Records & Case Histories
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2
 
Fatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker PennimentFatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker Penniment
 
Khurshid WI cswip 3.1
Khurshid WI cswip 3.1Khurshid WI cswip 3.1
Khurshid WI cswip 3.1
 
Clearing up material traceability: Confusion and myths in oil and gas manufac...
Clearing up material traceability: Confusion and myths in oil and gas manufac...Clearing up material traceability: Confusion and myths in oil and gas manufac...
Clearing up material traceability: Confusion and myths in oil and gas manufac...
 
Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1
 
2. pipeline materials overview
2. pipeline materials overview2. pipeline materials overview
2. pipeline materials overview
 
Effect of boron content on steels and recommended practice for welding Sasank...
Effect of boron content on steels and recommended practice for welding Sasank...Effect of boron content on steels and recommended practice for welding Sasank...
Effect of boron content on steels and recommended practice for welding Sasank...
 
Fundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas EngineerFundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas Engineer
 
AWS Profile EN IR
AWS Profile EN IRAWS Profile EN IR
AWS Profile EN IR
 
Pre-Insulated Pipe Supports Featuring Cryogenic and High Temperature Pipe Shoes
Pre-Insulated Pipe Supports Featuring Cryogenic and High Temperature Pipe Shoes Pre-Insulated Pipe Supports Featuring Cryogenic and High Temperature Pipe Shoes
Pre-Insulated Pipe Supports Featuring Cryogenic and High Temperature Pipe Shoes
 

Andere mochten auch

Ndt fabrication inspection_tuv_rheinland
Ndt fabrication inspection_tuv_rheinlandNdt fabrication inspection_tuv_rheinland
Ndt fabrication inspection_tuv_rheinlandRodolfo Barbosa Young
 
Welding qualification a
Welding qualification aWelding qualification a
Welding qualification aJithu John
 
ASME PVP 2016 PCC-1 Appendix A session summary
ASME PVP 2016   PCC-1 Appendix A session summaryASME PVP 2016   PCC-1 Appendix A session summary
ASME PVP 2016 PCC-1 Appendix A session summaryClay D. Rodery
 
Flange Bolt Chart
Flange Bolt ChartFlange Bolt Chart
Flange Bolt ChartSHORTBUS101
 
Calibration service
Calibration serviceCalibration service
Calibration servicesigmatest21
 
Non destructive testing
Non destructive testing Non destructive testing
Non destructive testing sigmatest21
 
Pesticide testing
Pesticide testingPesticide testing
Pesticide testingsigmatest21
 

Andere mochten auch (10)

Ndt fabrication inspection_tuv_rheinland
Ndt fabrication inspection_tuv_rheinlandNdt fabrication inspection_tuv_rheinland
Ndt fabrication inspection_tuv_rheinland
 
Welding qualification a
Welding qualification aWelding qualification a
Welding qualification a
 
Inspection of-pressure-vessels
Inspection of-pressure-vesselsInspection of-pressure-vessels
Inspection of-pressure-vessels
 
AS 3788
AS 3788 AS 3788
AS 3788
 
ASME PVP 2016 PCC-1 Appendix A session summary
ASME PVP 2016   PCC-1 Appendix A session summaryASME PVP 2016   PCC-1 Appendix A session summary
ASME PVP 2016 PCC-1 Appendix A session summary
 
Ganapathy(composite)
Ganapathy(composite)Ganapathy(composite)
Ganapathy(composite)
 
Flange Bolt Chart
Flange Bolt ChartFlange Bolt Chart
Flange Bolt Chart
 
Calibration service
Calibration serviceCalibration service
Calibration service
 
Non destructive testing
Non destructive testing Non destructive testing
Non destructive testing
 
Pesticide testing
Pesticide testingPesticide testing
Pesticide testing
 

Ähnlich wie 2 eliminate hidden riskof cui

Inspecting Lead-Clad Pipes with Pulsed Eddy Current (PEC)
Inspecting Lead-Clad Pipes with Pulsed Eddy Current (PEC)Inspecting Lead-Clad Pipes with Pulsed Eddy Current (PEC)
Inspecting Lead-Clad Pipes with Pulsed Eddy Current (PEC)Eddyfi
 
G&W High Voltage Cable Accessories - Joints & Terminations
G&W High Voltage Cable Accessories - Joints & TerminationsG&W High Voltage Cable Accessories - Joints & Terminations
G&W High Voltage Cable Accessories - Joints & TerminationsThorne & Derrick International
 
Piping sample report
Piping sample reportPiping sample report
Piping sample reportram111eg
 
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...
Electrical safety presentation by jmv railway and invitation ireee2019 at ...Mahesh Chandra Manav
 
QT111 Cold Shrink Silicone Rubber 3M Cable Terminations For MV HV Cables
QT111 Cold Shrink Silicone Rubber 3M Cable Terminations For MV HV CablesQT111 Cold Shrink Silicone Rubber 3M Cable Terminations For MV HV Cables
QT111 Cold Shrink Silicone Rubber 3M Cable Terminations For MV HV CablesThorne & Derrick International
 
Galvanize_It_10_20_2022-2024-2024-----.ppt
Galvanize_It_10_20_2022-2024-2024-----.pptGalvanize_It_10_20_2022-2024-2024-----.ppt
Galvanize_It_10_20_2022-2024-2024-----.pptkhurshedlakho
 
Galvanize_It_10_20_08.ppt
Galvanize_It_10_20_08.pptGalvanize_It_10_20_08.ppt
Galvanize_It_10_20_08.pptdivya
 
Built-in Novel Insulation Monitoring Function for RIF Paperless Transformer B...
Built-in Novel Insulation Monitoring Function for RIF Paperless Transformer B...Built-in Novel Insulation Monitoring Function for RIF Paperless Transformer B...
Built-in Novel Insulation Monitoring Function for RIF Paperless Transformer B...Gururaj B Rawoor
 
Presentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsPresentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsMahesh Chandra Manav
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Mahesh Chandra Manav
 
Corrosion Under Insulation Inspection In Ammonia Urea Plant
Corrosion Under Insulation Inspection In Ammonia Urea PlantCorrosion Under Insulation Inspection In Ammonia Urea Plant
Corrosion Under Insulation Inspection In Ammonia Urea PlantAsirul Hoq
 
Customer webinar 5
Customer webinar 5Customer webinar 5
Customer webinar 5gbsdirect
 
3M Cold Shrink Joint 145 kV Inline (Straight Through) SS145-II
3M Cold Shrink Joint 145 kV Inline (Straight Through) SS145-II3M Cold Shrink Joint 145 kV Inline (Straight Through) SS145-II
3M Cold Shrink Joint 145 kV Inline (Straight Through) SS145-IIThorne & Derrick International
 
A process review of insulators manufacturing and application
A process review of insulators manufacturing and applicationA process review of insulators manufacturing and application
A process review of insulators manufacturing and applicationCyber4Tech
 
02 feam enclosures_eng
02 feam enclosures_eng02 feam enclosures_eng
02 feam enclosures_engHai Pham
 
OVM250 Stay Cable System.ppt
OVM250 Stay Cable System.pptOVM250 Stay Cable System.ppt
OVM250 Stay Cable System.pptSaritaJoshi5
 
330377138-Conf-Tested-Assemblies-Iec-61439.pdf
330377138-Conf-Tested-Assemblies-Iec-61439.pdf330377138-Conf-Tested-Assemblies-Iec-61439.pdf
330377138-Conf-Tested-Assemblies-Iec-61439.pdfNafir Anas
 

Ähnlich wie 2 eliminate hidden riskof cui (20)

Inspecting Lead-Clad Pipes with Pulsed Eddy Current (PEC)
Inspecting Lead-Clad Pipes with Pulsed Eddy Current (PEC)Inspecting Lead-Clad Pipes with Pulsed Eddy Current (PEC)
Inspecting Lead-Clad Pipes with Pulsed Eddy Current (PEC)
 
G&W High Voltage Cable Accessories - Joints & Terminations
G&W High Voltage Cable Accessories - Joints & TerminationsG&W High Voltage Cable Accessories - Joints & Terminations
G&W High Voltage Cable Accessories - Joints & Terminations
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
 
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
 
06 - MCCB & ACB - Fuji Electric
06 - MCCB & ACB - Fuji Electric06 - MCCB & ACB - Fuji Electric
06 - MCCB & ACB - Fuji Electric
 
QT111 Cold Shrink Silicone Rubber 3M Cable Terminations For MV HV Cables
QT111 Cold Shrink Silicone Rubber 3M Cable Terminations For MV HV CablesQT111 Cold Shrink Silicone Rubber 3M Cable Terminations For MV HV Cables
QT111 Cold Shrink Silicone Rubber 3M Cable Terminations For MV HV Cables
 
Galvanize_It_10_20_2022-2024-2024-----.ppt
Galvanize_It_10_20_2022-2024-2024-----.pptGalvanize_It_10_20_2022-2024-2024-----.ppt
Galvanize_It_10_20_2022-2024-2024-----.ppt
 
Galvanize_It_10_20_08.ppt
Galvanize_It_10_20_08.pptGalvanize_It_10_20_08.ppt
Galvanize_It_10_20_08.ppt
 
MENDT2015_44.pdf
MENDT2015_44.pdfMENDT2015_44.pdf
MENDT2015_44.pdf
 
Built-in Novel Insulation Monitoring Function for RIF Paperless Transformer B...
Built-in Novel Insulation Monitoring Function for RIF Paperless Transformer B...Built-in Novel Insulation Monitoring Function for RIF Paperless Transformer B...
Built-in Novel Insulation Monitoring Function for RIF Paperless Transformer B...
 
Presentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsPresentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lps
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)
 
Corrosion Under Insulation Inspection In Ammonia Urea Plant
Corrosion Under Insulation Inspection In Ammonia Urea PlantCorrosion Under Insulation Inspection In Ammonia Urea Plant
Corrosion Under Insulation Inspection In Ammonia Urea Plant
 
Customer webinar 5
Customer webinar 5Customer webinar 5
Customer webinar 5
 
3M Cold Shrink Joint 145 kV Inline (Straight Through) SS145-II
3M Cold Shrink Joint 145 kV Inline (Straight Through) SS145-II3M Cold Shrink Joint 145 kV Inline (Straight Through) SS145-II
3M Cold Shrink Joint 145 kV Inline (Straight Through) SS145-II
 
A process review of insulators manufacturing and application
A process review of insulators manufacturing and applicationA process review of insulators manufacturing and application
A process review of insulators manufacturing and application
 
Megger dc insulation resistance testers -seminario
Megger   dc insulation resistance testers -seminarioMegger   dc insulation resistance testers -seminario
Megger dc insulation resistance testers -seminario
 
02 feam enclosures_eng
02 feam enclosures_eng02 feam enclosures_eng
02 feam enclosures_eng
 
OVM250 Stay Cable System.ppt
OVM250 Stay Cable System.pptOVM250 Stay Cable System.ppt
OVM250 Stay Cable System.ppt
 
330377138-Conf-Tested-Assemblies-Iec-61439.pdf
330377138-Conf-Tested-Assemblies-Iec-61439.pdf330377138-Conf-Tested-Assemblies-Iec-61439.pdf
330377138-Conf-Tested-Assemblies-Iec-61439.pdf
 

Mehr von Jithu John

2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptxJithu John
 
Oil refinery processes
Oil refinery processesOil refinery processes
Oil refinery processesJithu John
 
Asme section ii c new
Asme section ii c newAsme section ii c new
Asme section ii c newJithu John
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010Jithu John
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 sJithu John
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standardsJithu John
 
61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gudJithu John
 
Weld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsWeld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsJithu John
 

Mehr von Jithu John (11)

2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx
 
my ppt.pptx
my ppt.pptxmy ppt.pptx
my ppt.pptx
 
Oil refinery processes
Oil refinery processesOil refinery processes
Oil refinery processes
 
Asme section ii c new
Asme section ii c newAsme section ii c new
Asme section ii c new
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 s
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
 
Alignment
AlignmentAlignment
Alignment
 
61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud
 
Weld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsWeld ability of the new generation stainless steels
Weld ability of the new generation stainless steels
 
Weld defects
Weld defectsWeld defects
Weld defects
 

Kürzlich hochgeladen

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Kürzlich hochgeladen (20)

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

2 eliminate hidden riskof cui

  • 1. YANPET PRACTISE ELIMINATE HIDDEN RISK OF CUI Hamad Al-Alwani AIM Department NACE JUBAIL TECHNICAL WORKSHOP CORROSION UNDER INSULATION (CUI) 10TH December, 2015
  • 2. No. 2 • Carbon steel: (–12°C) - (175°C) • Stainless steel: (60°C) - (205°C) WHAT IS CORROSION UNDER INSULATION (CUI) ? • CUI is an external corrosion that occurs under insulated carbon steel and SS equipment. CUI is promoted by: • Water vapors condensation. • Sweating service • Temperature cycling. • Poor condition of coating. • Poor/broken insulation/cladding.
  • 3. No. 3 AFTER REMOVE INSULATION CUI GENERAL VIEW BEFORE REMOVE INSULATION
  • 4. No. 4 AFTER REMOVE INSULATION CUI GENERAL VIEW BEFORE REMOVE INSULATION
  • 5. No. 5 INSPECTION STRATEGY • Inspection Strategy is RBI based approach • Priority – 1: Sweating (continuous or cyclic) lines – require 100% insulation stripping and visual inspection and NDT. • Priority – 2 : Non sweating service Inspect as per API standard (suspected locations)
  • 6. No. 6 CUI: PLANT CASES Line H-14015-3”-C322 Leaking Drain Valve & Corroded Pipe (Hydrogen) Line # Line Associated Equipment Damage Original Thickness mm Remaining Thickness mm Risk Level Risk status H-14015-3”- C322 D-1451A localized pitting 5.54 2.5 2 Mitigated Pipe replaced
  • 7. No. 7 CUI: PLANT CASES P-13099A-14”-C322 Process (vapour) Line # Line Associated Equipment Damage Original Thickness mm Remaining Thickness mm Risk Level Risk status P-13099A- 14”-C322 Process (vapour) P-13064A-18- C322 General corrosion 9.53 5.45 2 Mitigated Pipe replaced
  • 8. No. 8 CUI: PLANT CASES Line 2P-15166- C323 Line # Line Associated Equipment Damage Original Thickness mm Remaining l Thickness mm Risk Level Risk status 2P-15166- C323 D-1451A Minor wall lost & bolts severely corroded 8.18 7.8 2 Mitigation is in progress
  • 9. No. 9 YANPET CUI MITIGATION STRATEGY I. Inspect on time. II. Watch insulation damage. III. Restoration of CUI Coatings. IV. Apply Thermal Spray Aluminum (TSA) on critical services. V. Replace PP Insulation with grid metallic type. BEFORE AFTER
  • 10. No. 10 • Removed all PP insulation and replace it by metallic grid type. • Personnel Protection (PP) insulation (Piping operating above 60 °C to 110 °C). • Grid type eliminates the hidden Risk & Operator is still protected from hot surface. • Grid type cost effective, easy to install, reuse and fast future inspection. YANPET PRACTICE WITH PP INSULATION
  • 11. No. 11 YANPET PRACTICE WITH PP INSULATION Line covered with old PP insulation Same line after removing the insulation. The alternative idea after the installation.
  • 12. No. 12 PLEASE REMEMBER !!! SAFETY FIRST & CORROSION UNDER INSULATION PROGRAM IS THE SAFE WAY. CORROSION UNDER UNSULATION  Always: AVOID DAMAGES TO THE INSULATION COVER