POWER
MUARA TAWAR 5 – Indonesia
234 MW – KA13E2
Combined-Cycle Power Plant
PROJECT FEATURES PROJECT HIGHLIGHTS
- This project involves extension of the existing power plant with a fifth block.
The new KA13E2 block adds an additional 234 MW to the current 1800 MW
plant, helping the country to cope with the current electricity crisis on the
Java/Bali grid.
- The Alstom-Marubeni consortium already built combined-cycle block 1 and gas
turbine peaking block 2 in 1995.
- Alstom has already been a key player in the Indonesian power generation
market since the 1960’s. It has supported the client PT PLN in meeting the
growing energy demand of the country through the construction of gas, coal
and hydro power plants.
CUSTOMER BENEFITS
- High availability and reliability thanks to the KA13E2 proven technology
- Optimised base load through Plant Integrator™ methodology
- High operational flexibility to meet the booming demand for power
- An environmentally-responsible power solution with low emissions
The power plant is located in Muara Tawar,
35 km from Jakarta, on the northern coast of
Java Island, Indonesia.
JAKARTA
Bandung Surabaya
Medan
Ujung Pandang
(Makassar)
Palembang
Semarang
Kupang
Padang
Yogyakarta
Banjarmasin
Manila
Koror
Bangkok
Kuala Lumpur
Davao
Darwin
Bam
We
Da Nang
Kuching
Ipoh
Dili
Zamboanga
Hô Chi Minh
(Saigon)
Phnom-Penh
Rangoon
Bandar Seri Begawan
Manado
Palu
GorontaloPekanbaru
Jambi
Bandar Lampung
Samarinda
Pontianak
Balikpapan
Surakarta
Malang
Kendari Ambon
Jayapura
Manokwari
Ternate
Banda Aceh
Bengkulu
Denpasar Mataram
Palangkaraya
Serang
Pangkalpinang
Tanjungpinang
Indonesia
Plant Integrator™ Factors Customer benefits
INVESTMENT Optimised capital investment
LEAD-TIME Shorter lead-times to produce electricity faster
Higher plant efficiency for increased power output at a wide range of operational modes
PERFORMANCE Reduced emissions to meet environmental concerns
Lower Operating & Maintenance (O&M) costs
AVAILABILITY & FLEXIBILITY Better reliability, availability and flexibility
RETROFIT Better power plant economics through Integrated Retrofit Solutions
LIFE EXTENSION Extended plant life options
Our Plant Integrator™ approach offers more value for customers
The Plant Integrator™ concept is Alstom’s unique way of creating more value
for customers. We combine outstanding expertise at a component and plant
level, as we are both an equipment designer and manufacturer. In addition, we
are an Engineering, Procurement and Construction (EPC) contractor with
extensive proven worldwide references. Through close collaboration, we
guarantee that our customers meet their business objectives and serve their
market more effectively. There are six Plant Integrator™ factors , which help
increase the Net Present Value for our customers.
Customer: Perusahan Listrik
Negara Limited (PT PLN)
Notice to proceed: June 2008
Fuel: gas / oil back-up
Cooling system: Seawater
Application: Power Generation
Unique Plant Integrator™ capabilities to deliver a highly
available and reliable power plant
POWER
PT-PE/BPROS/MRTWPS08/eng/PPS/04.08/FR/6473-allready-500385489RCSLyon
MUARA TAWAR 5 – Indonesia
234 MW – KA13E2 – Combined-Cycle Power Plant
ALSTOM’s SCOPE
• Turnkey Engineering Procurement Construction (EPC) contract for the power
island of a KA13E2 multi-shaft Combined-Cycle Power Plant including:
- overall plant engineering,
- global procurement & logistics,
- electrical and mechanical construction supervision,
- commissioning of the power plant.
• Alstom's proven equipment and mature technology is designed and
manufactured in-house:
- One highly reliable & clean power producing GT13E2 gas turbine with unique
EV (EnVironmental) burner technology,
- One horizontal dual pressure Heat Recovery Steam Generator,
- One COMAX steam turbine,
- One air-cooled TOPAIR turbogenerator for the gas turbine,
- One air-cooled TOPACK turbogenerator for the steam turbine,
- One seawater cooled condenser,
- ALSPA power control systems.
The Muara Tawar project benefits from superior integration through
Alstom’s project management skills, EPC capabilities and state-of-the-art
key components.
Meeting Perusahan Listrik
Negara Limited’s requirements
Demand for power has grown
considerably in Indonesia, stimulated
by economic recovery. This increase
in demand, combined with
decreasing generation capacities in
ageing existing power plants, could
have led to a deteriorating demand-
supply balance. To avoid such a
situation, an investment programme
was launched to develop the existing
Muara Tawar power plant. This
project will help the country to face
its present growth in power demand,
while protecting the environment
with clean power solutions.
With its environmental and economic advantages,
this plant is another example of Alstom capability
to deliver clean integrated power solutions.
www.power.alstom.com
MUARA TAWAR 5 PLANT ARRANGEMENT

Weitere ähnliche Inhalte

Andere mochten auch (11)

Ahorro energético2
Ahorro energético2Ahorro energético2
Ahorro energético2
 
Bi osingle(sbs series)
Bi osingle(sbs series)Bi osingle(sbs series)
Bi osingle(sbs series)
 
LinkedIn Document eSCAPE
LinkedIn Document eSCAPELinkedIn Document eSCAPE
LinkedIn Document eSCAPE
 
Vast net
Vast netVast net
Vast net
 
Zmrakování pružné včely
Zmrakování pružné včelyZmrakování pružné včely
Zmrakování pružné včely
 
Marco legal
Marco legalMarco legal
Marco legal
 
Diocese de ilhéus programação da festa em louvor a são francisco de assis
Diocese de ilhéus  programação da festa em louvor a são francisco de  assisDiocese de ilhéus  programação da festa em louvor a são francisco de  assis
Diocese de ilhéus programação da festa em louvor a são francisco de assis
 
What is CRAFT?
What is CRAFT?What is CRAFT?
What is CRAFT?
 
Romantic Comedy genre conventions
Romantic Comedy genre conventionsRomantic Comedy genre conventions
Romantic Comedy genre conventions
 
Brain implants
Brain implantsBrain implants
Brain implants
 
Encuentro 2 Evaluar con tic
Encuentro 2 Evaluar con ticEncuentro 2 Evaluar con tic
Encuentro 2 Evaluar con tic
 

MT05 fact sheet

  • 1. POWER MUARA TAWAR 5 – Indonesia 234 MW – KA13E2 Combined-Cycle Power Plant PROJECT FEATURES PROJECT HIGHLIGHTS - This project involves extension of the existing power plant with a fifth block. The new KA13E2 block adds an additional 234 MW to the current 1800 MW plant, helping the country to cope with the current electricity crisis on the Java/Bali grid. - The Alstom-Marubeni consortium already built combined-cycle block 1 and gas turbine peaking block 2 in 1995. - Alstom has already been a key player in the Indonesian power generation market since the 1960’s. It has supported the client PT PLN in meeting the growing energy demand of the country through the construction of gas, coal and hydro power plants. CUSTOMER BENEFITS - High availability and reliability thanks to the KA13E2 proven technology - Optimised base load through Plant Integrator™ methodology - High operational flexibility to meet the booming demand for power - An environmentally-responsible power solution with low emissions The power plant is located in Muara Tawar, 35 km from Jakarta, on the northern coast of Java Island, Indonesia. JAKARTA Bandung Surabaya Medan Ujung Pandang (Makassar) Palembang Semarang Kupang Padang Yogyakarta Banjarmasin Manila Koror Bangkok Kuala Lumpur Davao Darwin Bam We Da Nang Kuching Ipoh Dili Zamboanga Hô Chi Minh (Saigon) Phnom-Penh Rangoon Bandar Seri Begawan Manado Palu GorontaloPekanbaru Jambi Bandar Lampung Samarinda Pontianak Balikpapan Surakarta Malang Kendari Ambon Jayapura Manokwari Ternate Banda Aceh Bengkulu Denpasar Mataram Palangkaraya Serang Pangkalpinang Tanjungpinang Indonesia Plant Integrator™ Factors Customer benefits INVESTMENT Optimised capital investment LEAD-TIME Shorter lead-times to produce electricity faster Higher plant efficiency for increased power output at a wide range of operational modes PERFORMANCE Reduced emissions to meet environmental concerns Lower Operating & Maintenance (O&M) costs AVAILABILITY & FLEXIBILITY Better reliability, availability and flexibility RETROFIT Better power plant economics through Integrated Retrofit Solutions LIFE EXTENSION Extended plant life options Our Plant Integrator™ approach offers more value for customers The Plant Integrator™ concept is Alstom’s unique way of creating more value for customers. We combine outstanding expertise at a component and plant level, as we are both an equipment designer and manufacturer. In addition, we are an Engineering, Procurement and Construction (EPC) contractor with extensive proven worldwide references. Through close collaboration, we guarantee that our customers meet their business objectives and serve their market more effectively. There are six Plant Integrator™ factors , which help increase the Net Present Value for our customers. Customer: Perusahan Listrik Negara Limited (PT PLN) Notice to proceed: June 2008 Fuel: gas / oil back-up Cooling system: Seawater Application: Power Generation Unique Plant Integrator™ capabilities to deliver a highly available and reliable power plant
  • 2. POWER PT-PE/BPROS/MRTWPS08/eng/PPS/04.08/FR/6473-allready-500385489RCSLyon MUARA TAWAR 5 – Indonesia 234 MW – KA13E2 – Combined-Cycle Power Plant ALSTOM’s SCOPE • Turnkey Engineering Procurement Construction (EPC) contract for the power island of a KA13E2 multi-shaft Combined-Cycle Power Plant including: - overall plant engineering, - global procurement & logistics, - electrical and mechanical construction supervision, - commissioning of the power plant. • Alstom's proven equipment and mature technology is designed and manufactured in-house: - One highly reliable & clean power producing GT13E2 gas turbine with unique EV (EnVironmental) burner technology, - One horizontal dual pressure Heat Recovery Steam Generator, - One COMAX steam turbine, - One air-cooled TOPAIR turbogenerator for the gas turbine, - One air-cooled TOPACK turbogenerator for the steam turbine, - One seawater cooled condenser, - ALSPA power control systems. The Muara Tawar project benefits from superior integration through Alstom’s project management skills, EPC capabilities and state-of-the-art key components. Meeting Perusahan Listrik Negara Limited’s requirements Demand for power has grown considerably in Indonesia, stimulated by economic recovery. This increase in demand, combined with decreasing generation capacities in ageing existing power plants, could have led to a deteriorating demand- supply balance. To avoid such a situation, an investment programme was launched to develop the existing Muara Tawar power plant. This project will help the country to face its present growth in power demand, while protecting the environment with clean power solutions. With its environmental and economic advantages, this plant is another example of Alstom capability to deliver clean integrated power solutions. www.power.alstom.com MUARA TAWAR 5 PLANT ARRANGEMENT