PROJECT DEMONSTRATES SEVERAL CLASSICAL
ADVANTAGES OF HELICAL PILES
SPEED: Total foundation install time was 4 days. Day 1: Survey in pile loca-
tions and install batter boards. Day 2: Hydro excavate to look for under-
ground obstructions. Day 3: Install helical piles. Day 4: Poured concrete to
fill in hydro excavated holes.
UNINTRUSIVE: Small equipment and crew were able to stay out of truck
lanes. No excavation for foundations. No need to reroute existing lines or
conduit. No soil spoils requiring disposal.
Unaffected by weather: Hydro-excavation occurred during heavy rains.
Helical piles installed the next day in wet conditions.
Immediate load bearing capability: Canopy base plates were attached di-
rectly to the pile cap.
Cost Savings: Helical piles not only met the schedule and access require-
ments; they were much cheaper than spread footers.
CANOPY
Customer needed a new can-
opy over an existing truck
unloading rack. Operation
needed to continue as unin-
terrupted as possible. Above
picture taken four weeks
after project was started.
Includes paving and installa-
tion of lights. Truck unload-
ing was never stopped or di-
verted.
SPREAD FOOTER OPTION
Spread footers were estimat-
ed to take at least 3 1/2
weeks to install. Truck lanes
would have to be closed
while footers were dug,
formed, poured, and allowed
to cure.
Helical Pile Case Study
Canopy over Truck Unloading Rack
Cheaper, Faster, and more Flexible than Spread footers
NO RACK INTERRUPTION
SOUTHERN INDUSTRIAL PILING, LLC
3670 Haynesville Hwy.
EL Dorado, AR 71730
870.866.9002 ph.
info@SIPiling.com email
www.sipiling.com
FAST INSTALLATION
Piles need small cross sectional area so could
be installed close to existing underground lines
without the need to reroute.
HIGH CAPACITY IN A SMALL
FOOT PRINT
Trucks were able to unload in all lanes during
pile installation.
ADVANTAGES OVER SPREAD FOOTERS
Fast installation with small crew and equip-
ment requirements made helical piles the
quickest and most economical choice.
Faster installation with smaller crew and
equipment. No excavation spoils to handle or
dispose. No need for wreck forms and back
fill. Immediately loadable. More economical.
Hydro-excavation was performed to 5’ deep.
This assured no underground pipelines or con-
duit were in the way of the piles. The deep
narrow holes left after pile installation were
back filled with concrete. This assured that no
voids were left and increased lateral load ca-
pacity.
Pile caps can be imbedded in concrete. Or can
be used in a welded or bolted concrete-free
foundation system. In this application the can-
opy contractor welded the base plates directly
to the pile cap.
INNOVATIVE DESIGN

Weitere ähnliche Inhalte

Was ist angesagt?

Thrasher Commercial Group
Thrasher Commercial GroupThrasher Commercial Group
Thrasher Commercial GroupJill Reeves
 
Tilt up-concrete-06a
Tilt up-concrete-06aTilt up-concrete-06a
Tilt up-concrete-06aMazhar Syed
 
OneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckOneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckAMSYSCO Inc.
 
Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport ConstructionDavid H Moloney
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures ConstructionDavid H Moloney
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionDavid H Moloney
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanJames Zhang (Chi, Zhang)
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck finalCrosstown TO
 
A 1 Concrete Leveling Pittsburgh Overview
A 1 Concrete Leveling Pittsburgh OverviewA 1 Concrete Leveling Pittsburgh Overview
A 1 Concrete Leveling Pittsburgh Overviewryperk1
 
Topsides installation options for semi-submersible floating production systems
Topsides installation options for semi-submersible floating production systemsTopsides installation options for semi-submersible floating production systems
Topsides installation options for semi-submersible floating production systemsNiels Haakman
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingDavid H Moloney
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanDavid H Moloney
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanDavid H Moloney
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 

Was ist angesagt? (20)

Thrasher Commercial Group
Thrasher Commercial GroupThrasher Commercial Group
Thrasher Commercial Group
 
Tilt up-concrete-06a
Tilt up-concrete-06aTilt up-concrete-06a
Tilt up-concrete-06a
 
OneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckOneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deck
 
Sky View Parc
Sky View ParcSky View Parc
Sky View Parc
 
Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport Construction
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution Plan
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck final
 
A 1 Concrete Leveling Pittsburgh Overview
A 1 Concrete Leveling Pittsburgh OverviewA 1 Concrete Leveling Pittsburgh Overview
A 1 Concrete Leveling Pittsburgh Overview
 
Topsides installation options for semi-submersible floating production systems
Topsides installation options for semi-submersible floating production systemsTopsides installation options for semi-submersible floating production systems
Topsides installation options for semi-submersible floating production systems
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution Plan
 
2201 Westlake/Enso
2201 Westlake/Enso2201 Westlake/Enso
2201 Westlake/Enso
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 

Andere mochten auch

Tecnología + Conocimiento para potenciar el crecimiento de su negocio
Tecnología + Conocimiento para potenciar el crecimiento de su negocioTecnología + Conocimiento para potenciar el crecimiento de su negocio
Tecnología + Conocimiento para potenciar el crecimiento de su negocioRafa Liñán Vega
 
Lance Reynolds Portfolio 2016 (1)
Lance Reynolds Portfolio  2016 (1)Lance Reynolds Portfolio  2016 (1)
Lance Reynolds Portfolio 2016 (1)Lance Reynolds
 
APLS certificate 2015
APLS certificate 2015APLS certificate 2015
APLS certificate 2015John Woodall
 
material audiovisual y como se descarga
material audiovisual y como se descarga material audiovisual y como se descarga
material audiovisual y como se descarga Ronald Marroquin
 
150812_North Grady
150812_North Grady150812_North Grady
150812_North GradyJason Braga
 
Sinteza saptamanii (8 - 10 feb)
Sinteza saptamanii (8 - 10 feb) Sinteza saptamanii (8 - 10 feb)
Sinteza saptamanii (8 - 10 feb) AliantaSEDLEX
 
Giurisdizione italiana
Giurisdizione italianaGiurisdizione italiana
Giurisdizione italianaPaolo Porcaro
 
Proyecto de-informatica (1)
Proyecto de-informatica (1)Proyecto de-informatica (1)
Proyecto de-informatica (1)Diana_Medina
 
Plugged in at Rio
Plugged in at RioPlugged in at Rio
Plugged in at Rioaenright
 

Andere mochten auch (16)

2015 cert
2015 cert2015 cert
2015 cert
 
Arbol
ArbolArbol
Arbol
 
Tecnología + Conocimiento para potenciar el crecimiento de su negocio
Tecnología + Conocimiento para potenciar el crecimiento de su negocioTecnología + Conocimiento para potenciar el crecimiento de su negocio
Tecnología + Conocimiento para potenciar el crecimiento de su negocio
 
Lance Reynolds Portfolio 2016 (1)
Lance Reynolds Portfolio  2016 (1)Lance Reynolds Portfolio  2016 (1)
Lance Reynolds Portfolio 2016 (1)
 
APLS certificate 2015
APLS certificate 2015APLS certificate 2015
APLS certificate 2015
 
material audiovisual y como se descarga
material audiovisual y como se descarga material audiovisual y como se descarga
material audiovisual y como se descarga
 
150812_North Grady
150812_North Grady150812_North Grady
150812_North Grady
 
osha 30
osha 30osha 30
osha 30
 
Sinteza saptamanii (8 - 10 feb)
Sinteza saptamanii (8 - 10 feb) Sinteza saptamanii (8 - 10 feb)
Sinteza saptamanii (8 - 10 feb)
 
Giurisdizione italiana
Giurisdizione italianaGiurisdizione italiana
Giurisdizione italiana
 
Proyecto de-informatica (1)
Proyecto de-informatica (1)Proyecto de-informatica (1)
Proyecto de-informatica (1)
 
Copper Bracelets
Copper  BraceletsCopper  Bracelets
Copper Bracelets
 
Plugged in at Rio
Plugged in at RioPlugged in at Rio
Plugged in at Rio
 
Presentation_NEW.PPTX
Presentation_NEW.PPTXPresentation_NEW.PPTX
Presentation_NEW.PPTX
 
gleichwertigkeit
gleichwertigkeitgleichwertigkeit
gleichwertigkeit
 
CV
CVCV
CV
 

Ähnlich wie Canopy Case Study 2

SEAoAR 2015 Conference
SEAoAR 2015 ConferenceSEAoAR 2015 Conference
SEAoAR 2015 ConferenceJames Parrish
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptxAnanthakumar75
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
Site Report for CT! MEASUREMENT AND BM
Site Report for CT! MEASUREMENT AND BMSite Report for CT! MEASUREMENT AND BM
Site Report for CT! MEASUREMENT AND BMcheeweishan
 
25 herold 20160830 retrieval final
25 herold 20160830 retrieval final25 herold 20160830 retrieval final
25 herold 20160830 retrieval finalleann_mays
 
101under water conustrution.pptx
101under water conustrution.pptx101under water conustrution.pptx
101under water conustrution.pptxMEHALAS3
 
The Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdfThe Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdffreezefreeze2
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and CaissonsRizwan Samor
 
The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsChris Bridges
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptxAkshayGhorpade19
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2David Matthew
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - FletcherJade Keswick
 

Ähnlich wie Canopy Case Study 2 (20)

SEAoAR 2015 Conference
SEAoAR 2015 ConferenceSEAoAR 2015 Conference
SEAoAR 2015 Conference
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptx
 
Construction site
Construction siteConstruction site
Construction site
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Shib
ShibShib
Shib
 
Site Report for CT! MEASUREMENT AND BM
Site Report for CT! MEASUREMENT AND BMSite Report for CT! MEASUREMENT AND BM
Site Report for CT! MEASUREMENT AND BM
 
Drainage Salvation-JRiopelle
Drainage Salvation-JRiopelleDrainage Salvation-JRiopelle
Drainage Salvation-JRiopelle
 
25 herold 20160830 retrieval final
25 herold 20160830 retrieval final25 herold 20160830 retrieval final
25 herold 20160830 retrieval final
 
Adarsh P1.pptx
Adarsh P1.pptxAdarsh P1.pptx
Adarsh P1.pptx
 
101under water conustrution.pptx
101under water conustrution.pptx101under water conustrution.pptx
101under water conustrution.pptx
 
The Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdfThe Great Leap Theory, Donald Bruce.pdf
The Great Leap Theory, Donald Bruce.pdf
 
Brick1
Brick1Brick1
Brick1
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankments
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2
 
Pile footing
Pile footingPile footing
Pile footing
 
UNderpinning.pptx.pdf
UNderpinning.pptx.pdfUNderpinning.pptx.pdf
UNderpinning.pptx.pdf
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - Fletcher
 

Canopy Case Study 2

  • 1. PROJECT DEMONSTRATES SEVERAL CLASSICAL ADVANTAGES OF HELICAL PILES SPEED: Total foundation install time was 4 days. Day 1: Survey in pile loca- tions and install batter boards. Day 2: Hydro excavate to look for under- ground obstructions. Day 3: Install helical piles. Day 4: Poured concrete to fill in hydro excavated holes. UNINTRUSIVE: Small equipment and crew were able to stay out of truck lanes. No excavation for foundations. No need to reroute existing lines or conduit. No soil spoils requiring disposal. Unaffected by weather: Hydro-excavation occurred during heavy rains. Helical piles installed the next day in wet conditions. Immediate load bearing capability: Canopy base plates were attached di- rectly to the pile cap. Cost Savings: Helical piles not only met the schedule and access require- ments; they were much cheaper than spread footers. CANOPY Customer needed a new can- opy over an existing truck unloading rack. Operation needed to continue as unin- terrupted as possible. Above picture taken four weeks after project was started. Includes paving and installa- tion of lights. Truck unload- ing was never stopped or di- verted. SPREAD FOOTER OPTION Spread footers were estimat- ed to take at least 3 1/2 weeks to install. Truck lanes would have to be closed while footers were dug, formed, poured, and allowed to cure. Helical Pile Case Study Canopy over Truck Unloading Rack Cheaper, Faster, and more Flexible than Spread footers
  • 2. NO RACK INTERRUPTION SOUTHERN INDUSTRIAL PILING, LLC 3670 Haynesville Hwy. EL Dorado, AR 71730 870.866.9002 ph. info@SIPiling.com email www.sipiling.com FAST INSTALLATION Piles need small cross sectional area so could be installed close to existing underground lines without the need to reroute. HIGH CAPACITY IN A SMALL FOOT PRINT Trucks were able to unload in all lanes during pile installation. ADVANTAGES OVER SPREAD FOOTERS Fast installation with small crew and equip- ment requirements made helical piles the quickest and most economical choice. Faster installation with smaller crew and equipment. No excavation spoils to handle or dispose. No need for wreck forms and back fill. Immediately loadable. More economical. Hydro-excavation was performed to 5’ deep. This assured no underground pipelines or con- duit were in the way of the piles. The deep narrow holes left after pile installation were back filled with concrete. This assured that no voids were left and increased lateral load ca- pacity. Pile caps can be imbedded in concrete. Or can be used in a welded or bolted concrete-free foundation system. In this application the can- opy contractor welded the base plates directly to the pile cap. INNOVATIVE DESIGN