PROJECTS
Figure out what could go wrong before it does: Project Manager.
Network Techniques
For
Project Management
By
Amit Dhyani
Ishan Gandhi
Development of Project Network
Step 1:
Network Diagram or Project Graph.
1
2
3 4
Send
Invitations
Prepare
Dinner
Take
Dinner
A Network Diagram shows the activities and
events of the project and their logical
relationships.
Receive
Guests
The Network Diagram can be developed by
using Forward Method or Backward
Method.
Development of Project Network
Rules for Network Construction
Each activity must have a preceding and succeeding event.
Each event should have a distinct number.
In previous example, the activity
of "Send Invitations" is
designated as (1-2)
There should be no Loops in the project network.
1
23
Not more than one activity can have the same preceding
and succeeding events.
2
1
Time Estimation
Step 2:
Time Estimates for each Activity
Three Time values are obtained from each activity:
1. Optimistic time t
2. Most likely time t
3. Pessimistic time t
o
m
p
it should be obtained by
skipping around the network
rather than by following a
specific path.
they should be defined
independent of one another.
time available for completing
the project should not
influence the estimates.
estimates should considered
allowances which are random
variables and not others.
Time Estimation
Network Diagram with average time estimates-
1
2
3 4
5
13
12
8
2
2
15
Time Estimation
Activity Optimistic Most Likely Pessimistic Average
t t t to m p e=
t + 4t + to m p
6
1-2
1-3
2-4
3-4
2-5
4-5
9
6
1
4
10
1
12
12
1.5
8.5
14
2
21
18
5
10
24
3
13
12
2
8
15
2
t is the expected value of
activity duration;
weighted arithmetic
average time.
e
1
2
3 4
5
13
12
8
2
2
15
Determination of the Critical Path
Step 3
Determining Critical Path/s, event slacks and activity floats.
3(1). Earliest Occurrence Time (EOT)
The EOT of an event is the duration of the longest path (from beginning event
whose EOT is set at 0) leading to that event.
Hence, EOT of the end event represents the minimum time required for completing
the project.
General formula for EOT is:
EOT (i) = Max [ EOT (k) + d(k, i) ] Where,
EOT (i)= EOT of i event;
EOT (k)= EOT of k event (k precedes i);
d (k, i)= duration of activity (k, i)
th
th
Determination of EOT
5
2
43 8
2
15
2
1
13
12
0
13
12
EOT (i) = Max [ EOT (k) + d(k, i)]
EOT (4)
= Max [ ]
[ EOT (3) + d(3, 4)] [ EOT (2) + d(2, 4)]
= [12 + 8] = [13 + 2]
= [20] = [15]
EOT (4) = 20
Determination of EOT
5
2
43 8
2
15
2
1
13
12
0
13
12 20
28
To obtain EOT we start from
beginning event and move
forward towards the end,
hence it is called forward
pass.
The upper half of the circle : Event Number;
The left quarter in lower half: EOT;
The right corner in lower half: LOT.
Determination of EOT
5
2
43 8
2
15
2
1
13
12
0
13
12 20
28
Earliest Starting Time (EST)
EST for any activity is EOT
of an event, which is
preceding the activity.
EST (i, j) = EOT (i)
For Example,
EST of activity (2-5) will be
EST (2, 5) = EOT (2)
EST (2, 5) = 13
Determination of EOT
5
2
43 8
2
15
2
1
13
12
0
13
12 20
28
Earliest Finishing Time (EFT)
EFT for any activity
is addition of EOT of an
event, which is preceding the
activity and duration of the
activity.
EFT (i, j) = EOT (i) + d(i, j)
For Example,
EFT of activity (2-5) will be
EFT (2, 5) = EOT (2) + d(2, 5)
= 13 + 15
= 28
Determination of the Critical Path
3(2). Latest Occurrence Time (LOT)
The EOT of an event is the latest allowable time by which the event can occur, given
the time that is allowed for completion of the project (occurence of end event).
Hence, LOT of the an event represents the latest time by which the event should
occur to enable the project to be completed in given time.
General formula for LOT is:
LOT (i) = Min [ LOT (j) - d(i, j) ] Where,
LOT (i)= LOT of i event;
LOT (j)= LOT of j event (j follows i);
d (i, j)= duration of activity (i, j)
th
th
Determination of LOT
5
2
43 8
2
15
2
1
13
12
28
LOT (i) = Min [ LOT (j) - d(i, j)]
LOT (2)
= MIN [ ]
[ LOT (4) - d(2, 4)] [ LOT (5) - d(2, 5)]
= [26 - 2] = [28 - 15]
= [24] = [13]
LOT (2) = 13
26
Determination of LOT
5
2
43 8
2
15
2
1
13
12
0
13
26
28
To obtain LOT we start
from end event and
move backward towards
the beginning, hence it is
called backward pass.
LOT for end event is the given time for the
project to be completed. Normally, EOT is
considered for project deadline.
28
18
0
Determination of LOT
5
2
43 8
2
15
2
1
13
12
0
13
26
28 28
18
0
LFT for any activity is LOT of
an event, which is followed by
that activity.
LFT (i, j) = LOT (j)
Latest Finishing Time (LFT)
For Example,
LFT of activity (2-5) will be
LFT (2, 5) = LOT (5)
= 28
Determination of LOT
5
2
43 8
2
15
2
1
13
12
0
13
26
28 28
18
0
For Example,
LST of activity (2-5) will be
LST (2, 5) = LFT (2,5) + d(2,5)
= 28 - 15
Latest Starting Time (LST)
LST for any activity
is difference between LFT
of that activity and duration for
that activity.
LST (i, j) = LFT (i, j) - d(i, j)
= 13
Determination of the Critical Path
3(3). Event Slack
The slack for an event is the difference between its LOT and EOT.
Event Slack
Event LOT EOT Slack = LOT - EOT
5
4
3
2
1
28
26
18
13
0
28
20
12
13
0
0
6
6
0
0
Determination of the Critical Path
3(4). Critical and Slack Paths
The critical path starts with the beginning event, terminates with the end event, and is
marked by events which have a zero slack.
5
2
43 8
2
1
12
0
12 20
28
2
0
13 13
28
2618
13
15
5
4
3
2
1
0
6
6
0
0
Activity Slack
Hence,
Critical Path for this
project is (1-2-5)
Determination of the Critical Path
3(5). Activity Floats
Given the estimates of activity time and event slacks, three measures of floats are
defined:
(i) Total Float;
(ii) Free Float;
(iii) Independent Float.
2
13 13
4
20 26
2
Given the following, determine the Floats
Determination of the Critical Path
(i) Total Float:
2
13 13
4
20 26
2
The total float of an activity is the extra time available to complete the activity if it is
started as early as possible, without delaying the completion of the project.
Total
Float
=
Latest occurrence
time for event 4
-
Earliest occurrence
time for event 2 -
Duration of activity
(2-4)
= 26 - 13 - 2
= 11 weeks
Activities which have a
Zero Total Float lie
on critical path.
Determination of the Critical Path
(ii) Free Float:
2
13 13
4
20 26
2
The free float of an activity is the extra time available to complete the activity when the
activity is started at EOT of its preceding event and completed by the EOT of its
succeeding events.
Free
Float
=
Earliest occurrence
time for event 4 -
Earliest occurrence
time for event 2
-
Duration of activity
(2-4)
= 20 - 13 - 2
= 5 weeks
Determination of the Critical Path
(iii) Independent Float:
2
13 13
4
20 26
2
The independent float of an activity is the extra time available to complete the
activity when the activity is started at LOT of its preceding event and completed by the
EOT of its succeeding events.
Independent
Float
=
Earliest occurrence
time for event 4 -
Latest occurrence
time for event 2
-
Duration of activity
(2-4)
= 20 - 13 - 2
= 5 weeks
It may be noted that
Independent float of an activity
may be negative.
Determination of the Critical Path
Activity Floats
Activity Duration EST(i,j) EFT(i,j) LST(i,j) LFT(i,j)
(1-2)
(1-3)
(2-4)
(3-4)
(2-5)
(4-5)
13
12
2
8
15
2
(i,j) =EST (i) =EFT (j) =LST (i) =LFT (j)
Total
Float
Free
Float
Independent
Float
0
0
13
12
13
20
13
12
15
20
28
22
0
6
24
18
13
26
13
18
26
26
28
28
0
6
11
6
0
6
0
0
5
0
0
6
0
0
5
(6)
0
0
Scheduling when Resources are Limited
The Bounding Schedules
(i) Early Start Schedule:
It refers to the schedule in which all activities start as early as possible-
(a) all activities occur at
their earliest i.e. EST and
EFT.
(b) there may be time lag
between completion of
certain activities and
occurrence of events.
(c) all activities emanating
from an event begins at
same time.
1
3
2
4
5
0 5 15 25 302010
Scheduling when Resources are Limited
The Bounding Schedules
(i) Late Start Schedule:
It refers to the schedule in which all activities start as late as possible-
(a) all activities occur at
their Latest i.e. LST
and LFT.
(b) some activities may start
after time lag subsequent to
occurrence of preceding
events.
(c) all activities leading to an
event are completed at
same time.
1
3
2
4
5
0 5 15 25 302010
Scheduling when Resources are Limited
Illustration: Scheduling to Match Availability of Manpower
Activity Duration and Manpower Requirements
1
2
3
4
5
2 Days
2
1 Day
10
2 Days
4
1 Day
63 Days5
2 Days
8
Only 12 men are available
for the project.
Scheduling when Resources are Limited
Scheduling to Match Availability of Manpower
Early Start Schedule
Doesn't match the
manpower resource
constraint of 12
Persons.
Scheduling when Resources are Limited
Scheduling to Match Availability of Manpower
A Feasible Schedule
PERT MODEL
Program Evaluation Review Technique (PERT) was originally developed to facilitate
the planning and scheduling of the Polaris Fleet Ballistic Missile project of the US
government.
PERT Model is designed to handle risk and uncertainty.
PERT Model is suitable for-
Introduction
- Research and Development programmes
- Aerospace Projects
- Other projects involving new technology
As in such projects time required for completing various jobs or activities can be highly
variable.
Hence, the orientation of PERT is 'Probabilistic'
PERT MODEL
Variability in PERT analysis is measured by variance or standard deviation.
Steps involved in calculating standard deviation of duration of critical path:
Measures of Variability
(i) Determine Standard Deviation of duration of each activity on the critical path.
(ii) Determine S.D. of total duration of critical path on basis of step (i).
=
t - tp o
6
Where,
is Standard Deviation,
t is pessimistic time,
t is optimistic time.
p
o
PERT MODEL
Standard Deviation and Variance of Activity Duration
on Critical Path
Activity t t = t - t /6 Variance =p po o
2
(1-2)
(2-5)
21
24
9
10
2
2.33
4.00
5.43
Variance
(critical path duration)
Sum of Variances of activity
durations on the critical path
=
Standard Deviation
(critical path duration)
= (Sum of Variances of activity
durations on the critical path )
1/2
= (4 + 5.43)1/2
= 3.07
PERT MODEL
Probability of Completion by a Specific Date
With information of mean (T) and standard deviation ( ) for critical path duration, we can
compute the probability of completion by a specified date (D) as follows:
Z =
D - T
Where,
Z is number of S.D by which D, exceeds T
D is the specified date
T mean critical path duration
PERT MODEL
Probability of Completion by a Specific Date
Illustration
Specified Date (D) Z Probability of Completion by D
20
25
30
20 - 28
3.07
= -2.6
25 - 28
3.07
= -1.0
30 - 28
3.07
= 0.6
0.005
0.159
0.726
CPM MODEL
Introduction
Critical Path Method (CPM) was developed independently by Du Pont Company to
solve scheduling problems in industrial settings.
CPM Model is primarily concerned with the trade-off between cost and time.
CPM Model is applied to projects that employ a fairly stable technology and are
relatively risk free.
The main thrust of CPM analysis is on time-cost relationships
and it seeks to determine the project schedule which
minimizes total cost.
CPM MODEL
Assumptions under CPM Model
1. Two types of costs are associated with the project: Direct Costs and
Indirect Costs.
2. Activities of projects can be expedited (sooner) by crashing which involves
employing more resources.
3. Crashing reduces time but enhances direct costs because of factors like
overtime payments, extra payments and wastage.
4. Indirect costs associated with project increase linearly with project duration.
CPM MODEL
Procedure of CPM Analysis
1. Obtain the critical path in the network model. Determine project duration
and direct cost.
2. Examine cost-time slope of activities on the critical path obtained and
crash the activity which has the least slope.
3. Construct the new critical path after crashing as per step 2. Determine
project duration and cost.
4. Repeat step 2 and 3 till activities on the critical path are crashed.
Time Estimation
Illustration:
1
2
3
4
5
8
6
9
5
3
5
6
7
7
10
9
Critical Path is (1-2-4-6-7)
CPM MODEL
Illustration of CPM Analysis
Time in Weeks Cost Cost to expedite
per week
Activity Normal Crash Normal Crash
Rs Rs Rs
1-2
1-3
2-4
3-5
2-5
4-6
5-6
6-7
5-7
8
5
9
7
5
3
6
10
9
4
3
6
5
1
2
2
7
5
1/2
3000
4000
4000
2000
8000
10,000
4000
6000
4200
6000
8000
5500
3900
12,000
11,200
6800
8700
9000
750
2000
500
950
1000
2400
700
900
1200
45,200 71,100
Lowest
Lowest in critical path
Time Estimation
Project Network
1
2
3
4
5
8
6
9
5
3
5
6
7
7
10
9
Activity 2-4 has lowest
expedite cost per week.
Hence it will be crashed.
Note: Critical Path is (1-2-4-6-7)
Time Estimation
Project Network
1
2
3
4
5
8
6
6
5
3
5
6
7
7
10
9
Note: Activity 2-4 has been
crashed (9 to 6 weeks)
New critical path is (1-2-5-6-7)
Total Direct Cost= Rs 49,500
CPM MODEL
Illustration of CPM Analysis
Time in Weeks Cost Cost to expedite
per week
Activity Normal Crash Normal Crash
Rs Rs Rs
1-2
1-3
2-4
3-5
2-5
4-6
5-6
6-7
5-7
8
5
9
7
5
3
6
10
9
4
3
6
5
1
2
2
7
5
1/2
3000
4000
4000
2000
8000
10,000
4000
6000
4200
6000
8000
5500
3900
12,000
11,200
6800
8700
9000
750
2000
500
950
1000
2400
700
900
1200
45,200 71,100
Lowest
Lowest
Time Estimation
Project Network
1
2
3
4
5
8
2
6
5
3
5
6
7
7
10
9
Note: Activity 5-6 has been
crashed (6 to 2 weeks)
New critical path is (1-2-4-6-7)
Total Direct Cost= Rs 52,500
CPM MODEL
Illustration of CPM Analysis
Time in Weeks Cost Cost to expedite
per week
Activity Normal Crash Normal Crash
Rs Rs Rs
1-2
1-3
2-4
3-5
2-5
4-6
5-6
6-7
5-7
8
5
9
7
5
3
6
10
9
4
3
6
5
1
2
2
7
5
1/2
3000
4000
4000
2000
8000
10,000
4000
6000
4200
6000
8000
5500
3900
12,000
11,200
6800
8700
9000
750
2000
500
950
1000
2400
700
900
1200
45,200 71,100
Lowest
Lowest
Lowest
CPM MODEL
Illustration of CPM Analysis
Time in Weeks Cost Cost to expedite
per week
Activity Normal Crash Normal Crash
Rs Rs Rs
1-2
1-3
2-4
3-5
2-5
4-6
5-6
6-7
5-7
8
5
9
7
5
3
6
10
9
4
3
6
5
1
2
2
7
5
1/2
3000
4000
4000
2000
8000
10,000
4000
6000
4200
6000
8000
5500
3900
12,000
11,200
6800
8700
9000
750
2000
500
950
1000
2400
700
900
1200
45,200 71,100
Lowest
Lowest
Lowest
Lowest
Time Estimation
Project Network
1
2
3
4
5
4
2
6
5
3
5
6
7
7
7
9
Note: After crashing activity 6-7.
Network diagram has 2 critical
paths- (1-3-5-6-7) and (1-3-5-7)
CPM MODEL
Illustration of CPM Analysis
Time in Weeks Cost Cost to expedite
per week
Activity Normal Crash Normal Crash
Rs Rs Rs
1-2
1-3
2-4
3-5
2-5
4-6
5-6
6-7
5-7
8
5
9
7
5
3
6
10
9
4
3
6
5
1
2
2
7
5
1/2
3000
4000
4000
2000
8000
10,000
4000
6000
4200
6000
8000
5500
3900
12,000
11,200
6800
8700
9000
750
2000
500
950
1000
2400
700
900
1200
45,200 71,100
Lowest
Lowest
Lowest
Lowest
Lowest- 2 CP
Time Estimation
Project Network
1
2
3
4
5
4
2
6
5
3
5
6
5
7
7
9
Note: Activity 3-5 which is
common to both the critical paths
is least costly to crash.
CPM MODEL
Illustration of CPM Analysis
Time in Weeks Cost Cost to expedite
per week
Activity Normal Crash Normal Crash
Rs Rs Rs
1-2
1-3
2-4
3-5
2-5
4-6
5-6
6-7
5-7
8
5
9
7
5
3
6
10
9
4
3
6
5
1
2
2
7
5
1/2
3000
4000
4000
2000
8000
10,000
4000
6000
4200
6000
8000
5500
3900
12,000
11,200
6800
8700
9000
750
2000
500
950
1000
2400
700
900
1200
45,200 71,100
Lowest
Lowest
Lowest
Lowest
Lowest- 2 CP
Lowest
Time Estimation
Project Network
1
2
3
4
5
4
2
6
5
2 1/2
5
6
5
7
7
9
Note: All activities on New critical
path is (1-2-4-6-7) are crashed.
Hence, no further possibility of
time reduction.
CPM MODEL
Activities Crashed
None
(2-4)
(2-4) and (5-6)
(1-2), (2-4) and (5-6)
(1-2), (2-4), (5-6) and (6-7)
(1-2), (2-4), (3-5), (5-6) and (6-7)
(1-2), (2-4), (3-5), (5-6), (4-6) and (6-7)
Project
Duration
In weeks
Total
Direct
Cost
Total
Indirect
Cost
Total Cost
30
29
27
24
21
20
19
1/2
45200
46700
49500
52500
55200
57100
58300
60000
58000
54000
48000
42000
40000
39000
105,200
104,700
103,500
100,500
97,200
97,100
97,300
Project Duration and Total Cost
Indirect Cost is Rs 2000 per week
Network Cost System
Introduction
Network Cost System was developed to provide vehicle for cost
planning and control of projects.
Basic principle is: Costs are planned, measured, analysed and
controlled in terms of project activities.
For cost projections it is assumed that the expenditure for any activity
is incurred evenly over the duration of activity.
Network Cost System
Analysis and Control of Costs
1. Cost incurred to date
In NCS, Cost are recorded activity wise. Costs incurred to date can be obtained by
summing up costs for various activities.
2. Budgeted cost to date
is the cost projections made at the beginning.
3. Value of work done to date
is equal to budgeted costs * percentage of work accomplished.
4. Cost over-run (under-run) to date
Actual Cost - Value of work completed
Vaue of work completed
* 100
Network Cost System
Analysis and Control of Costs
5. Time over-run (under-run) to date
Time over-run is usually defined in terms of months behind or months ahead.
THANK YOU

Weitere ähnliche Inhalte

Was ist angesagt?

Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
Critical path method
Critical path methodCritical path method
Critical path methodDushyant Nasit
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniquesupendar aavula
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 
Project management book for mba
Project management book for mbaProject management book for mba
Project management book for mbaBikramjit Singh
 
Ppt on project appraisal
Ppt on project appraisalPpt on project appraisal
Ppt on project appraisalHachnayen
 
Project management techniques
Project management techniquesProject management techniques
Project management techniquesRagjni Govindaraju
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
crashing of project
crashing of project crashing of project
crashing of project Mir Zafarullah
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Schedulingsaurabmi2
 
Project management planning
Project management planningProject management planning
Project management planningAlvin Niere
 

Was ist angesagt? (20)

Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Project management book for mba
Project management book for mbaProject management book for mba
Project management book for mba
 
Ppt on project appraisal
Ppt on project appraisalPpt on project appraisal
Ppt on project appraisal
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
crashing of project
crashing of project crashing of project
crashing of project
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Project management planning
Project management planningProject management planning
Project management planning
 

Ă„hnlich wie Network Techniques for Project Management

Networktechniques
NetworktechniquesNetworktechniques
NetworktechniquesAmitLokhande16
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementAKSHAYA0000
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptxHimanshuKaklotar1
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.pptNitin137794
 
MP assignment for printing
MP assignment for printingMP assignment for printing
MP assignment for printingHieu Pham
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpmIrtizaMalik
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptBetshaTizazu2
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptxLJay7
 
Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM maggieget
 
Project management
Project managementProject management
Project managementKwesi Kissiedu
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii referenceahsanrabbani
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review TechniqueRaymund Sanchez
 
Lecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdfLecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdflucky141651
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques Mohammad Younus
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfSalahudin Babar
 

Ă„hnlich wie Network Techniques for Project Management (20)

Networktechniques
NetworktechniquesNetworktechniques
Networktechniques
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagement
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
 
MP assignment for printing
MP assignment for printingMP assignment for printing
MP assignment for printing
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM
 
Project management
Project managementProject management
Project management
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
Lecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdfLecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdf
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
Lecture 5.pdf
Lecture 5.pdfLecture 5.pdf
Lecture 5.pdf
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 

KĂĽrzlich hochgeladen

B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Lucknow đź’‹ Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow đź’‹ Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow đź’‹ Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow đź’‹ Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | â‚ą5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | â‚ą5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | â‚ą5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | â‚ą5k To 25k Wit...Suhani Kapoor
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Trucks in Minnesota
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 

KĂĽrzlich hochgeladen (20)

B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Lucknow đź’‹ Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow đź’‹ Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow đź’‹ Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow đź’‹ Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | â‚ą5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | â‚ą5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | â‚ą5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | â‚ą5k To 25k Wit...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 

Network Techniques for Project Management

  • 1. PROJECTS Figure out what could go wrong before it does: Project Manager. Network Techniques For Project Management By Amit Dhyani Ishan Gandhi
  • 2. Development of Project Network Step 1: Network Diagram or Project Graph. 1 2 3 4 Send Invitations Prepare Dinner Take Dinner A Network Diagram shows the activities and events of the project and their logical relationships. Receive Guests The Network Diagram can be developed by using Forward Method or Backward Method.
  • 3. Development of Project Network Rules for Network Construction Each activity must have a preceding and succeeding event. Each event should have a distinct number. In previous example, the activity of "Send Invitations" is designated as (1-2) There should be no Loops in the project network. 1 23 Not more than one activity can have the same preceding and succeeding events. 2 1
  • 4. Time Estimation Step 2: Time Estimates for each Activity Three Time values are obtained from each activity: 1. Optimistic time t 2. Most likely time t 3. Pessimistic time t o m p it should be obtained by skipping around the network rather than by following a specific path. they should be defined independent of one another. time available for completing the project should not influence the estimates. estimates should considered allowances which are random variables and not others.
  • 5. Time Estimation Network Diagram with average time estimates- 1 2 3 4 5 13 12 8 2 2 15
  • 6. Time Estimation Activity Optimistic Most Likely Pessimistic Average t t t to m p e= t + 4t + to m p 6 1-2 1-3 2-4 3-4 2-5 4-5 9 6 1 4 10 1 12 12 1.5 8.5 14 2 21 18 5 10 24 3 13 12 2 8 15 2 t is the expected value of activity duration; weighted arithmetic average time. e 1 2 3 4 5 13 12 8 2 2 15
  • 7. Determination of the Critical Path Step 3 Determining Critical Path/s, event slacks and activity floats. 3(1). Earliest Occurrence Time (EOT) The EOT of an event is the duration of the longest path (from beginning event whose EOT is set at 0) leading to that event. Hence, EOT of the end event represents the minimum time required for completing the project. General formula for EOT is: EOT (i) = Max [ EOT (k) + d(k, i) ] Where, EOT (i)= EOT of i event; EOT (k)= EOT of k event (k precedes i); d (k, i)= duration of activity (k, i) th th
  • 8. Determination of EOT 5 2 43 8 2 15 2 1 13 12 0 13 12 EOT (i) = Max [ EOT (k) + d(k, i)] EOT (4) = Max [ ] [ EOT (3) + d(3, 4)] [ EOT (2) + d(2, 4)] = [12 + 8] = [13 + 2] = [20] = [15] EOT (4) = 20
  • 9. Determination of EOT 5 2 43 8 2 15 2 1 13 12 0 13 12 20 28 To obtain EOT we start from beginning event and move forward towards the end, hence it is called forward pass. The upper half of the circle : Event Number; The left quarter in lower half: EOT; The right corner in lower half: LOT.
  • 10. Determination of EOT 5 2 43 8 2 15 2 1 13 12 0 13 12 20 28 Earliest Starting Time (EST) EST for any activity is EOT of an event, which is preceding the activity. EST (i, j) = EOT (i) For Example, EST of activity (2-5) will be EST (2, 5) = EOT (2) EST (2, 5) = 13
  • 11. Determination of EOT 5 2 43 8 2 15 2 1 13 12 0 13 12 20 28 Earliest Finishing Time (EFT) EFT for any activity is addition of EOT of an event, which is preceding the activity and duration of the activity. EFT (i, j) = EOT (i) + d(i, j) For Example, EFT of activity (2-5) will be EFT (2, 5) = EOT (2) + d(2, 5) = 13 + 15 = 28
  • 12. Determination of the Critical Path 3(2). Latest Occurrence Time (LOT) The EOT of an event is the latest allowable time by which the event can occur, given the time that is allowed for completion of the project (occurence of end event). Hence, LOT of the an event represents the latest time by which the event should occur to enable the project to be completed in given time. General formula for LOT is: LOT (i) = Min [ LOT (j) - d(i, j) ] Where, LOT (i)= LOT of i event; LOT (j)= LOT of j event (j follows i); d (i, j)= duration of activity (i, j) th th
  • 13. Determination of LOT 5 2 43 8 2 15 2 1 13 12 28 LOT (i) = Min [ LOT (j) - d(i, j)] LOT (2) = MIN [ ] [ LOT (4) - d(2, 4)] [ LOT (5) - d(2, 5)] = [26 - 2] = [28 - 15] = [24] = [13] LOT (2) = 13 26
  • 14. Determination of LOT 5 2 43 8 2 15 2 1 13 12 0 13 26 28 To obtain LOT we start from end event and move backward towards the beginning, hence it is called backward pass. LOT for end event is the given time for the project to be completed. Normally, EOT is considered for project deadline. 28 18 0
  • 15. Determination of LOT 5 2 43 8 2 15 2 1 13 12 0 13 26 28 28 18 0 LFT for any activity is LOT of an event, which is followed by that activity. LFT (i, j) = LOT (j) Latest Finishing Time (LFT) For Example, LFT of activity (2-5) will be LFT (2, 5) = LOT (5) = 28
  • 16. Determination of LOT 5 2 43 8 2 15 2 1 13 12 0 13 26 28 28 18 0 For Example, LST of activity (2-5) will be LST (2, 5) = LFT (2,5) + d(2,5) = 28 - 15 Latest Starting Time (LST) LST for any activity is difference between LFT of that activity and duration for that activity. LST (i, j) = LFT (i, j) - d(i, j) = 13
  • 17. Determination of the Critical Path 3(3). Event Slack The slack for an event is the difference between its LOT and EOT. Event Slack Event LOT EOT Slack = LOT - EOT 5 4 3 2 1 28 26 18 13 0 28 20 12 13 0 0 6 6 0 0
  • 18. Determination of the Critical Path 3(4). Critical and Slack Paths The critical path starts with the beginning event, terminates with the end event, and is marked by events which have a zero slack. 5 2 43 8 2 1 12 0 12 20 28 2 0 13 13 28 2618 13 15 5 4 3 2 1 0 6 6 0 0 Activity Slack Hence, Critical Path for this project is (1-2-5)
  • 19. Determination of the Critical Path 3(5). Activity Floats Given the estimates of activity time and event slacks, three measures of floats are defined: (i) Total Float; (ii) Free Float; (iii) Independent Float. 2 13 13 4 20 26 2 Given the following, determine the Floats
  • 20. Determination of the Critical Path (i) Total Float: 2 13 13 4 20 26 2 The total float of an activity is the extra time available to complete the activity if it is started as early as possible, without delaying the completion of the project. Total Float = Latest occurrence time for event 4 - Earliest occurrence time for event 2 - Duration of activity (2-4) = 26 - 13 - 2 = 11 weeks Activities which have a Zero Total Float lie on critical path.
  • 21. Determination of the Critical Path (ii) Free Float: 2 13 13 4 20 26 2 The free float of an activity is the extra time available to complete the activity when the activity is started at EOT of its preceding event and completed by the EOT of its succeeding events. Free Float = Earliest occurrence time for event 4 - Earliest occurrence time for event 2 - Duration of activity (2-4) = 20 - 13 - 2 = 5 weeks
  • 22. Determination of the Critical Path (iii) Independent Float: 2 13 13 4 20 26 2 The independent float of an activity is the extra time available to complete the activity when the activity is started at LOT of its preceding event and completed by the EOT of its succeeding events. Independent Float = Earliest occurrence time for event 4 - Latest occurrence time for event 2 - Duration of activity (2-4) = 20 - 13 - 2 = 5 weeks It may be noted that Independent float of an activity may be negative.
  • 23. Determination of the Critical Path Activity Floats Activity Duration EST(i,j) EFT(i,j) LST(i,j) LFT(i,j) (1-2) (1-3) (2-4) (3-4) (2-5) (4-5) 13 12 2 8 15 2 (i,j) =EST (i) =EFT (j) =LST (i) =LFT (j) Total Float Free Float Independent Float 0 0 13 12 13 20 13 12 15 20 28 22 0 6 24 18 13 26 13 18 26 26 28 28 0 6 11 6 0 6 0 0 5 0 0 6 0 0 5 (6) 0 0
  • 24. Scheduling when Resources are Limited The Bounding Schedules (i) Early Start Schedule: It refers to the schedule in which all activities start as early as possible- (a) all activities occur at their earliest i.e. EST and EFT. (b) there may be time lag between completion of certain activities and occurrence of events. (c) all activities emanating from an event begins at same time. 1 3 2 4 5 0 5 15 25 302010
  • 25. Scheduling when Resources are Limited The Bounding Schedules (i) Late Start Schedule: It refers to the schedule in which all activities start as late as possible- (a) all activities occur at their Latest i.e. LST and LFT. (b) some activities may start after time lag subsequent to occurrence of preceding events. (c) all activities leading to an event are completed at same time. 1 3 2 4 5 0 5 15 25 302010
  • 26. Scheduling when Resources are Limited Illustration: Scheduling to Match Availability of Manpower Activity Duration and Manpower Requirements 1 2 3 4 5 2 Days 2 1 Day 10 2 Days 4 1 Day 63 Days5 2 Days 8 Only 12 men are available for the project.
  • 27. Scheduling when Resources are Limited Scheduling to Match Availability of Manpower Early Start Schedule Doesn't match the manpower resource constraint of 12 Persons.
  • 28. Scheduling when Resources are Limited Scheduling to Match Availability of Manpower A Feasible Schedule
  • 29. PERT MODEL Program Evaluation Review Technique (PERT) was originally developed to facilitate the planning and scheduling of the Polaris Fleet Ballistic Missile project of the US government. PERT Model is designed to handle risk and uncertainty. PERT Model is suitable for- Introduction - Research and Development programmes - Aerospace Projects - Other projects involving new technology As in such projects time required for completing various jobs or activities can be highly variable. Hence, the orientation of PERT is 'Probabilistic'
  • 30. PERT MODEL Variability in PERT analysis is measured by variance or standard deviation. Steps involved in calculating standard deviation of duration of critical path: Measures of Variability (i) Determine Standard Deviation of duration of each activity on the critical path. (ii) Determine S.D. of total duration of critical path on basis of step (i). = t - tp o 6 Where, is Standard Deviation, t is pessimistic time, t is optimistic time. p o
  • 31. PERT MODEL Standard Deviation and Variance of Activity Duration on Critical Path Activity t t = t - t /6 Variance =p po o 2 (1-2) (2-5) 21 24 9 10 2 2.33 4.00 5.43 Variance (critical path duration) Sum of Variances of activity durations on the critical path = Standard Deviation (critical path duration) = (Sum of Variances of activity durations on the critical path ) 1/2 = (4 + 5.43)1/2 = 3.07
  • 32. PERT MODEL Probability of Completion by a Specific Date With information of mean (T) and standard deviation ( ) for critical path duration, we can compute the probability of completion by a specified date (D) as follows: Z = D - T Where, Z is number of S.D by which D, exceeds T D is the specified date T mean critical path duration
  • 33. PERT MODEL Probability of Completion by a Specific Date Illustration Specified Date (D) Z Probability of Completion by D 20 25 30 20 - 28 3.07 = -2.6 25 - 28 3.07 = -1.0 30 - 28 3.07 = 0.6 0.005 0.159 0.726
  • 34. CPM MODEL Introduction Critical Path Method (CPM) was developed independently by Du Pont Company to solve scheduling problems in industrial settings. CPM Model is primarily concerned with the trade-off between cost and time. CPM Model is applied to projects that employ a fairly stable technology and are relatively risk free. The main thrust of CPM analysis is on time-cost relationships and it seeks to determine the project schedule which minimizes total cost.
  • 35. CPM MODEL Assumptions under CPM Model 1. Two types of costs are associated with the project: Direct Costs and Indirect Costs. 2. Activities of projects can be expedited (sooner) by crashing which involves employing more resources. 3. Crashing reduces time but enhances direct costs because of factors like overtime payments, extra payments and wastage. 4. Indirect costs associated with project increase linearly with project duration.
  • 36. CPM MODEL Procedure of CPM Analysis 1. Obtain the critical path in the network model. Determine project duration and direct cost. 2. Examine cost-time slope of activities on the critical path obtained and crash the activity which has the least slope. 3. Construct the new critical path after crashing as per step 2. Determine project duration and cost. 4. Repeat step 2 and 3 till activities on the critical path are crashed.
  • 38. CPM MODEL Illustration of CPM Analysis Time in Weeks Cost Cost to expedite per week Activity Normal Crash Normal Crash Rs Rs Rs 1-2 1-3 2-4 3-5 2-5 4-6 5-6 6-7 5-7 8 5 9 7 5 3 6 10 9 4 3 6 5 1 2 2 7 5 1/2 3000 4000 4000 2000 8000 10,000 4000 6000 4200 6000 8000 5500 3900 12,000 11,200 6800 8700 9000 750 2000 500 950 1000 2400 700 900 1200 45,200 71,100 Lowest Lowest in critical path
  • 39. Time Estimation Project Network 1 2 3 4 5 8 6 9 5 3 5 6 7 7 10 9 Activity 2-4 has lowest expedite cost per week. Hence it will be crashed. Note: Critical Path is (1-2-4-6-7)
  • 40. Time Estimation Project Network 1 2 3 4 5 8 6 6 5 3 5 6 7 7 10 9 Note: Activity 2-4 has been crashed (9 to 6 weeks) New critical path is (1-2-5-6-7) Total Direct Cost= Rs 49,500
  • 41. CPM MODEL Illustration of CPM Analysis Time in Weeks Cost Cost to expedite per week Activity Normal Crash Normal Crash Rs Rs Rs 1-2 1-3 2-4 3-5 2-5 4-6 5-6 6-7 5-7 8 5 9 7 5 3 6 10 9 4 3 6 5 1 2 2 7 5 1/2 3000 4000 4000 2000 8000 10,000 4000 6000 4200 6000 8000 5500 3900 12,000 11,200 6800 8700 9000 750 2000 500 950 1000 2400 700 900 1200 45,200 71,100 Lowest Lowest
  • 42. Time Estimation Project Network 1 2 3 4 5 8 2 6 5 3 5 6 7 7 10 9 Note: Activity 5-6 has been crashed (6 to 2 weeks) New critical path is (1-2-4-6-7) Total Direct Cost= Rs 52,500
  • 43. CPM MODEL Illustration of CPM Analysis Time in Weeks Cost Cost to expedite per week Activity Normal Crash Normal Crash Rs Rs Rs 1-2 1-3 2-4 3-5 2-5 4-6 5-6 6-7 5-7 8 5 9 7 5 3 6 10 9 4 3 6 5 1 2 2 7 5 1/2 3000 4000 4000 2000 8000 10,000 4000 6000 4200 6000 8000 5500 3900 12,000 11,200 6800 8700 9000 750 2000 500 950 1000 2400 700 900 1200 45,200 71,100 Lowest Lowest Lowest
  • 44. CPM MODEL Illustration of CPM Analysis Time in Weeks Cost Cost to expedite per week Activity Normal Crash Normal Crash Rs Rs Rs 1-2 1-3 2-4 3-5 2-5 4-6 5-6 6-7 5-7 8 5 9 7 5 3 6 10 9 4 3 6 5 1 2 2 7 5 1/2 3000 4000 4000 2000 8000 10,000 4000 6000 4200 6000 8000 5500 3900 12,000 11,200 6800 8700 9000 750 2000 500 950 1000 2400 700 900 1200 45,200 71,100 Lowest Lowest Lowest Lowest
  • 45. Time Estimation Project Network 1 2 3 4 5 4 2 6 5 3 5 6 7 7 7 9 Note: After crashing activity 6-7. Network diagram has 2 critical paths- (1-3-5-6-7) and (1-3-5-7)
  • 46. CPM MODEL Illustration of CPM Analysis Time in Weeks Cost Cost to expedite per week Activity Normal Crash Normal Crash Rs Rs Rs 1-2 1-3 2-4 3-5 2-5 4-6 5-6 6-7 5-7 8 5 9 7 5 3 6 10 9 4 3 6 5 1 2 2 7 5 1/2 3000 4000 4000 2000 8000 10,000 4000 6000 4200 6000 8000 5500 3900 12,000 11,200 6800 8700 9000 750 2000 500 950 1000 2400 700 900 1200 45,200 71,100 Lowest Lowest Lowest Lowest Lowest- 2 CP
  • 47. Time Estimation Project Network 1 2 3 4 5 4 2 6 5 3 5 6 5 7 7 9 Note: Activity 3-5 which is common to both the critical paths is least costly to crash.
  • 48. CPM MODEL Illustration of CPM Analysis Time in Weeks Cost Cost to expedite per week Activity Normal Crash Normal Crash Rs Rs Rs 1-2 1-3 2-4 3-5 2-5 4-6 5-6 6-7 5-7 8 5 9 7 5 3 6 10 9 4 3 6 5 1 2 2 7 5 1/2 3000 4000 4000 2000 8000 10,000 4000 6000 4200 6000 8000 5500 3900 12,000 11,200 6800 8700 9000 750 2000 500 950 1000 2400 700 900 1200 45,200 71,100 Lowest Lowest Lowest Lowest Lowest- 2 CP Lowest
  • 49. Time Estimation Project Network 1 2 3 4 5 4 2 6 5 2 1/2 5 6 5 7 7 9 Note: All activities on New critical path is (1-2-4-6-7) are crashed. Hence, no further possibility of time reduction.
  • 50. CPM MODEL Activities Crashed None (2-4) (2-4) and (5-6) (1-2), (2-4) and (5-6) (1-2), (2-4), (5-6) and (6-7) (1-2), (2-4), (3-5), (5-6) and (6-7) (1-2), (2-4), (3-5), (5-6), (4-6) and (6-7) Project Duration In weeks Total Direct Cost Total Indirect Cost Total Cost 30 29 27 24 21 20 19 1/2 45200 46700 49500 52500 55200 57100 58300 60000 58000 54000 48000 42000 40000 39000 105,200 104,700 103,500 100,500 97,200 97,100 97,300 Project Duration and Total Cost Indirect Cost is Rs 2000 per week
  • 51. Network Cost System Introduction Network Cost System was developed to provide vehicle for cost planning and control of projects. Basic principle is: Costs are planned, measured, analysed and controlled in terms of project activities. For cost projections it is assumed that the expenditure for any activity is incurred evenly over the duration of activity.
  • 52. Network Cost System Analysis and Control of Costs 1. Cost incurred to date In NCS, Cost are recorded activity wise. Costs incurred to date can be obtained by summing up costs for various activities. 2. Budgeted cost to date is the cost projections made at the beginning. 3. Value of work done to date is equal to budgeted costs * percentage of work accomplished. 4. Cost over-run (under-run) to date Actual Cost - Value of work completed Vaue of work completed * 100
  • 53. Network Cost System Analysis and Control of Costs 5. Time over-run (under-run) to date Time over-run is usually defined in terms of months behind or months ahead.