SlideShare ist ein Scribd-Unternehmen logo
1 von 9
Downloaden Sie, um offline zu lesen
IPM (INTEGRATED
PROJECT MANAGEMENT)
HADITOMO SUKSES PERDANA PMC IPM SPECIALIST
1
Project Planning & Control
 Part I - Scheduling Basics
 What is a Project Plan?
 A Project Plan is a group of tasks performed within a defined time schedule to meet a
specific set of objectives
 How to Create a Plan
 Establish Project Objectives and Scope Of Work
 Delineate Organization and Team
 Define the Work
 Determine the Timing
 Establish Resource Requirements and Availability
 Establish Man-Hour/Cost Budget
 Evaluate, Optimize, and Freeze Baseline Plan
 Distribute Information
12/24/2016
COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES
PERDANA
2
Project Planning & Control
 How to Control a Project
 Track Work Progress and Costs
 Compare Schedule and Cost Data to Baseline
 Use baseline to guide your decisions
 Update/modify the current project with realistic data
 Analyze and Evaluate Performance
 Recommend Action and Reforecast
 Communicate
 Building a Schedule
 Identify the Project Scope and Deliverables
 Identify Key Milestone Dates (Contract Milestones)
 Identify Resource Availability and Constraints
 Create a High-Level (Level 1) Master Schedule
 Create Detail Level (Level 3) Schedule
12/24/2016
COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES
PERDANA
3
Project Planning & Control
 Components of a Schedule
 Timescale - consistent units of time measurement (e.g., hours, days, work periods, etc.)
 Activities -
 Most Detailed Item Of Work
 Composed Of One Kind Of Action
 Measurable And Contiguous Duration
 Single Line Of Responsibility
 Set Of Resources And Costs Assigned
 Building a Master Schedule
 Analyze Project Scope
 Layout High Level Components
12/24/2016
COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES
PERDANA
4
Project Planning & Control
 Project Scope
 To Design, Procure, and Construct a Refinery Upgrade
 High Level Components
 Design / Engineer Refinery Upgrade
 Procure Equipment for Refinery Upgrade
 Construct Refinery Upgrade
 Refinery Upgrade “In Operation”
 Critical Path Method (CPM)
 A logical analysis of a schedule’s activities, calculating the effects of durations and
relationships, to determine the longest path to complete the project.
 Initially, calculations were done manually, and then overnight through mainframe computers.
Now, desktop PC’s perform the calculations.
 Various products: Open Plan, MS Project, P3, P6, Aurora, PRISM, Timeline, Harvard Project
Management, Artemis, Deltek Cobra Etc.
12/24/2016
COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES
PERDANA
5
Project Planning & Control
 CPM Key Terms
 Predecessor - an activity preceding another
 Successor - an activity that follows another
 Relationships -
 FS=Finish to Start: One activity must finish before the next activity can start
 SS=Start to Start: One activity must start before the next activity can start
 FF=Finish to Finish: The predecessor activity must be completed (finish) for specified period of time before
successor activity can finish
 Integrated Complexity:
 CPM Calculation variables now include:
 Relationships: FS = Finish to Start, SS = Start to Start, FF = Finish to Finish, Lags
 Float: Total, Free, Finish, Start, Most Critical
 Constraints: Start No Earlier, Finish No Earlier, Start No Later, Finish No Later, Expected, Mandatory, Float
 Activity Types: Task, Start Milestone, Finish Milestone, Hammock, Finish Flag, Start Flag, WBS, Meeting
 Calendars: Non-Work Periods, Holidays
 Schedule Calculation: Interruptible, Contiguous, Loops, Open Ends, Progress Override, Retained Logic
 Resources: Driving, Leveling, Unit Rates
12/24/2016
COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES
PERDANA
6
Project Planning & Control
 Planning / Scheduling
 “The plan is nothing… planning is everything.” - Dwight Eisenhower
 Engineers claim to not know how to plan, but will criticize your plan to shreds. Take the opportunity to
find out why they dislike your plan, thereby providing you with a valid plan.
 Progress Reporting
 Plan
 Status to Date
 Earned Value
 Forecast to Complete
 Forecast at Completion
12/24/2016
COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES
PERDANA
7
Project Planning & Control
 Forecasting
 Use Best Available Project Data
 Evaluate Against Project Plan
 Compare to Historical Points of Reference
 Forecast Ultimate Outcome
 Document Variance with a Deviation
 Incorporate into Cost Reporting
 Cost Reporting
 Typical Components of Cost Report:
 WBS Work Breakdown Structure
 Original Budget
 Current Budget
 (Original plus Client Approved Change Orders)
 Commitments and Expenditures
 Physical Progress
 Performance Factors on Labor
 Indicated Total Cost Forecast
12/24/2016
COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES
PERDANA
8
Project Planning & Control
 Change Management -Keys to Success
 Total Project Participation
 Early Identification
 Quick Assessment/Disposition
 ROM Estimate
 Engineer/Procure/Construct
 Schedule Impact
 Approval/Cancel
 Cost Savings or Impact
 Finalize Estimate/Final Approval
12/24/2016
COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES
PERDANA
9

Weitere ähnliche Inhalte

Was ist angesagt?

Features of project
Features of projectFeatures of project
Features of projectRaj Sampat
 
Project Termination
Project TerminationProject Termination
Project TerminationSajjad Sayed
 
Project management (1)
Project management (1)Project management (1)
Project management (1)Hetal Visaria
 
Project manager-roles and responsibilities
Project manager-roles and responsibilitiesProject manager-roles and responsibilities
Project manager-roles and responsibilitiescollege
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slidesdotesch
 
What is project management
What is project managementWhat is project management
What is project managementBilalChoudhary14
 
Project Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussionProject Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussionAbigail Pugal-Somera
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleAndrei Crăciun
 
Project Planning and Approval Process
Project Planning and Approval ProcessProject Planning and Approval Process
Project Planning and Approval ProcessAtif Nauman
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniquesTata Dinyuy
 
Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - PresentationHassan Rizwan
 
Basics of Project Planning
Basics of Project PlanningBasics of Project Planning
Basics of Project PlanningZilicus
 

Was ist angesagt? (20)

Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Features of project
Features of projectFeatures of project
Features of project
 
Project Termination
Project TerminationProject Termination
Project Termination
 
Project management tools
Project management toolsProject management tools
Project management tools
 
Project management
Project managementProject management
Project management
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Planning fundamentals - Project Management
Planning fundamentals - Project ManagementPlanning fundamentals - Project Management
Planning fundamentals - Project Management
 
Project manager-roles and responsibilities
Project manager-roles and responsibilitiesProject manager-roles and responsibilities
Project manager-roles and responsibilities
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slides
 
What is project management
What is project managementWhat is project management
What is project management
 
Project Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussionProject Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussion
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Project Planning and Approval Process
Project Planning and Approval ProcessProject Planning and Approval Process
Project Planning and Approval Process
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
 
Project/ Business life cycle methodology
Project/ Business life cycle methodologyProject/ Business life cycle methodology
Project/ Business life cycle methodology
 
Project Management
Project ManagementProject Management
Project Management
 
Project management-CH 4
Project management-CH 4Project management-CH 4
Project management-CH 4
 
Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - Presentation
 
Basics of Project Planning
Basics of Project PlanningBasics of Project Planning
Basics of Project Planning
 

Ähnlich wie IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1

The project plan
The project planThe project plan
The project planVatsalaPG
 
Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0niict
 
The Powerof One+Pmo Overview
The Powerof One+Pmo OverviewThe Powerof One+Pmo Overview
The Powerof One+Pmo OverviewDJ EVERETTE
 
Training pm jan 11 part b
Training pm jan 11 part bTraining pm jan 11 part b
Training pm jan 11 part bSiep Littooij
 
Planning_and_scheduling.pptx
Planning_and_scheduling.pptxPlanning_and_scheduling.pptx
Planning_and_scheduling.pptxKAhmedRehman
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodology5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodologyjmcmahon89
 
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docxBSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docxAASTHA76
 
Primavara
PrimavaraPrimavara
Primavaradanabl
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jimNASAPMC
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.pptTecnicoItca
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewDanielle Murphy
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidyNASAPMC
 

Ähnlich wie IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1 (20)

The project plan
The project planThe project plan
The project plan
 
Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0
 
Planning
PlanningPlanning
Planning
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
The Powerof One+Pmo Overview
The Powerof One+Pmo OverviewThe Powerof One+Pmo Overview
The Powerof One+Pmo Overview
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Project Management
Project ManagementProject Management
Project Management
 
Training pm jan 11 part b
Training pm jan 11 part bTraining pm jan 11 part b
Training pm jan 11 part b
 
Planning_and_scheduling.pptx
Planning_and_scheduling.pptxPlanning_and_scheduling.pptx
Planning_and_scheduling.pptx
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodology5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodology
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Management
Project ManagementProject Management
Project Management
 
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docxBSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
 
Primavara
PrimavaraPrimavara
Primavara
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.ppt
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overview
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
PMP Exam Preparation Course: 05 Project Time Management
PMP Exam Preparation Course: 05 Project Time ManagementPMP Exam Preparation Course: 05 Project Time Management
PMP Exam Preparation Course: 05 Project Time Management
 

IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1

  • 1. IPM (INTEGRATED PROJECT MANAGEMENT) HADITOMO SUKSES PERDANA PMC IPM SPECIALIST 1
  • 2. Project Planning & Control  Part I - Scheduling Basics  What is a Project Plan?  A Project Plan is a group of tasks performed within a defined time schedule to meet a specific set of objectives  How to Create a Plan  Establish Project Objectives and Scope Of Work  Delineate Organization and Team  Define the Work  Determine the Timing  Establish Resource Requirements and Availability  Establish Man-Hour/Cost Budget  Evaluate, Optimize, and Freeze Baseline Plan  Distribute Information 12/24/2016 COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES PERDANA 2
  • 3. Project Planning & Control  How to Control a Project  Track Work Progress and Costs  Compare Schedule and Cost Data to Baseline  Use baseline to guide your decisions  Update/modify the current project with realistic data  Analyze and Evaluate Performance  Recommend Action and Reforecast  Communicate  Building a Schedule  Identify the Project Scope and Deliverables  Identify Key Milestone Dates (Contract Milestones)  Identify Resource Availability and Constraints  Create a High-Level (Level 1) Master Schedule  Create Detail Level (Level 3) Schedule 12/24/2016 COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES PERDANA 3
  • 4. Project Planning & Control  Components of a Schedule  Timescale - consistent units of time measurement (e.g., hours, days, work periods, etc.)  Activities -  Most Detailed Item Of Work  Composed Of One Kind Of Action  Measurable And Contiguous Duration  Single Line Of Responsibility  Set Of Resources And Costs Assigned  Building a Master Schedule  Analyze Project Scope  Layout High Level Components 12/24/2016 COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES PERDANA 4
  • 5. Project Planning & Control  Project Scope  To Design, Procure, and Construct a Refinery Upgrade  High Level Components  Design / Engineer Refinery Upgrade  Procure Equipment for Refinery Upgrade  Construct Refinery Upgrade  Refinery Upgrade “In Operation”  Critical Path Method (CPM)  A logical analysis of a schedule’s activities, calculating the effects of durations and relationships, to determine the longest path to complete the project.  Initially, calculations were done manually, and then overnight through mainframe computers. Now, desktop PC’s perform the calculations.  Various products: Open Plan, MS Project, P3, P6, Aurora, PRISM, Timeline, Harvard Project Management, Artemis, Deltek Cobra Etc. 12/24/2016 COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES PERDANA 5
  • 6. Project Planning & Control  CPM Key Terms  Predecessor - an activity preceding another  Successor - an activity that follows another  Relationships -  FS=Finish to Start: One activity must finish before the next activity can start  SS=Start to Start: One activity must start before the next activity can start  FF=Finish to Finish: The predecessor activity must be completed (finish) for specified period of time before successor activity can finish  Integrated Complexity:  CPM Calculation variables now include:  Relationships: FS = Finish to Start, SS = Start to Start, FF = Finish to Finish, Lags  Float: Total, Free, Finish, Start, Most Critical  Constraints: Start No Earlier, Finish No Earlier, Start No Later, Finish No Later, Expected, Mandatory, Float  Activity Types: Task, Start Milestone, Finish Milestone, Hammock, Finish Flag, Start Flag, WBS, Meeting  Calendars: Non-Work Periods, Holidays  Schedule Calculation: Interruptible, Contiguous, Loops, Open Ends, Progress Override, Retained Logic  Resources: Driving, Leveling, Unit Rates 12/24/2016 COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES PERDANA 6
  • 7. Project Planning & Control  Planning / Scheduling  “The plan is nothing… planning is everything.” - Dwight Eisenhower  Engineers claim to not know how to plan, but will criticize your plan to shreds. Take the opportunity to find out why they dislike your plan, thereby providing you with a valid plan.  Progress Reporting  Plan  Status to Date  Earned Value  Forecast to Complete  Forecast at Completion 12/24/2016 COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES PERDANA 7
  • 8. Project Planning & Control  Forecasting  Use Best Available Project Data  Evaluate Against Project Plan  Compare to Historical Points of Reference  Forecast Ultimate Outcome  Document Variance with a Deviation  Incorporate into Cost Reporting  Cost Reporting  Typical Components of Cost Report:  WBS Work Breakdown Structure  Original Budget  Current Budget  (Original plus Client Approved Change Orders)  Commitments and Expenditures  Physical Progress  Performance Factors on Labor  Indicated Total Cost Forecast 12/24/2016 COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES PERDANA 8
  • 9. Project Planning & Control  Change Management -Keys to Success  Total Project Participation  Early Identification  Quick Assessment/Disposition  ROM Estimate  Engineer/Procure/Construct  Schedule Impact  Approval/Cancel  Cost Savings or Impact  Finalize Estimate/Final Approval 12/24/2016 COPYRIGHT OF UNDER LICENSED HADITOMO SUKSES PERDANA 9