2
Study focus
Development Theme
Driver for national industry and
services provision
Economic centres
Jakarta
Bandung
Semarang
Yogyakarta
Surabaya
Main economic activity
Food and beverage
Textile
Transportation Equipment
Shipping
ICT
Defence Equipment
Greater Jakarta Area
“to ensure that the infrastructure, services and facilities that are
provided in the Corridor meet the needs of the users of the
transport system, and especially the needs of main economic
activities of the corridor as identified in the MP3EI”
3
Study context
National Logistics System
Multimodal Transport StrategyNRMP NPMP
Road system plans
4
Mode choice in principle
Distance
Flow concentration
Cargo value
Cargo perishability/fragility
Cargo density
Road Rail Sea
Low
Low
High
High
Low
High
High
Low
Low
High
5
Domestic container movements by sea (Java)
6
Geographical Pattern of Intra-Java Freight Flows
0 1000 2000 3000 4000
Banten
DIY
DKI
Jawa Barat
Jawa Tengah
Jawa Timur
Destination
Milliontonnes
Origin
Banten DIY DKI Jawa Barat Jawa Tengah Jawa Timur
7
Fertiliser,600,000
Silica, 7,874
Iron Ore, 180000
Petroleum,496,000
Cement, 450,000
Container, 400,810
Parcel (multiproduct),
110,854
Antaboga
(multiproduct),
243,000
Other multiproduct,
130,792 Steel,25,731
Existing rail freight task (Java) – excl coal.
Source: KTPA, 2012
8
Key Obstacles to Efficient Multimodal Freight
Transport in the Java Corridor
GROUP KEY ISSUES
ROAD ISSUES Slow delivery of expressway system
Overloading
Congestion
Suboptimal road investment prioritisation
Distortion due to fuel subsidies
RAIL ISSUES Lack of network capacity
Limitations on train weights and dimensions
Lack of competition
MARITIME ISSUES Limited port capacity
High port access costs
Unreliable port performance
High cost and unreliability of domestic shipping services
MODAL
INTERCONNECTIVIT
Y ISSUES
Poor rail access to port terminals
Scarcity and poor performance of intermodal terminals
Lack of intermodal focus in planning and system management
9
Some surprises
• Truck costs are not as high as expected relative to other
modes. This reflects fuel subsidy, lack of RUC and probably
high level of overloading
• Truck travel times are not as low relative to other modes as in
other places. This appears to reflect traffic congestion and
restrictions on truck operation in cities.
• Some high value goods which we would normally expect to
travel by truck are shipped using sea mode (for security
reason), i. e.: electronics and car
• Some low value goods that seem natural targets for rail travel
by road: for example, around 300 trucks each carry 30 tons of
coal daily from Cirebon to Bandung for textile factories around
Bandung.
10
Targeting the right cargoes
Commodity Comments
Existing bulk traffics Need to avoid complacency
Steel Krakatau steel already sends cargo by both rail and sea, and is
interested in increasing non-road share. Also significant growth
with the Posco Krakatau steel development.
Port-related
containers
Pressure on landside access to ports will make increased use of rail
imperative. Also port-related movement tend to be better suited
to rail because there is not – or need not be – a truck distribution
leg at the port end.
Niche bulks Rail already has a position in many bulks, but some customers –
e.g. cement – have an interest in increasing their use of rail
Java-Sumatra
freight
The need to make the Straits crossing, congestion at the ferry and
relatively long distances make this trade a priority target for ro-ro
shipping services
Automotive A more difficult target for rail, but at least one major manufacturer
is interested in considering and rail is quite widely used in other
countries.
Jakarta-Surabaya
general cargo
It will be difficult for rail or sea to be sustainably profitable in these
cargoes, but both rail and sea currently play a minor role in the
carriage of these cargoes. Double-tracking should improve
competitive position of rail.
Low
hanging
fruit
More
difficult
11
RIGHT infrastructure and services
Immediate
(before
2014)
Complete Jakarta-Surabaya double-tracking
Improve access links to major ports
Improve facilities for handling motor vehicles at T Priok
Promote use of full potential of existing intermodal terminals
Develop common user terminal at Cilegon
Develop Cikarang-Surabaya rail services
Medium
term
(2015-2019)
Provide additional container capacity at T Priok and T Perak
Ensure all new terminal developments have high quality road
and rail access
Create network of intermodal terminals/dry ports
Expand ro-ro services between Sumatra and Java
Develop specialist rail services for automotive industry
Longer term
(2020 and
beyond)
Create freight only rail links in congested section of the
network
Increase structural strength of key rail freight links
12
The RIGHT supporting policies
Immediate
(before
2014)
Set and monitor KPIs for cargo handling performance at key ports
Adopt new road design standards for all of strategic freight network
Formally establish peak logistics industry consultative body
Remove fuel subsidy for heavy diesel fuels
Define and implement rail track access charge
Foster competition in container terminal services
Modernise PTKAI rolling stock (commence)
Adopt point-of-origin approach to enforcement of vehicle limits
Further streamline customs clearance procedures
Intensify congestion management efforts in major cities
Include multi-modal transport priority actions in Renstra
Medium
term
(2015-2019)
Restructure government institutions to better support multimodal transport
Develop national road freight strategy
Progressively introduce road pricing scheme
Trial new approaches to expressway delivery
Revise procedures for prioritising road capacity improvements
Restructure PKAI on business lines
Provide customs clearance at all dry ports
Integrate transport considerations into industrial estate planning
Longer term Introduce vehicle booking systems at T Priok and T Perak
13
Reform Themes and Supporting Actions
THEME ACTION ITEM
Improving land transport
access to ports
1: Construct Tanjung Priok rail link
2: Complete Tanjung Priok access road
3: Activate Tanjung Perak rail connection
4: Accelerate proposed expressway links to Tanjung Perak
5: Ensure high quality access road to Kalibaru
6: Incorporate planning for rail links in new terminal developments
Delivering increased port
capacity
7: Set and monitor Key Performance Indicators (KPIs) for cargo handling performance at key ports
8: Promptly deliver increased container port capacity
9: Improve facilities for handling motor vehicles at Tanjung Priok
10: Introduce a vehicle booking system at the main container terminals
Developing freight rail
infrastructure and terminals
11: Complete double tracking Jakarta–Surabaya
12: Develop selected freight only rail links
13: Selectively improve rail track strength
14: Promote use of the full potential of existing intermodal terminals
15: Construct a common user rail terminal at Cilegon
16: Develop a network of new intermodal terminals
Strengthening the freight
capability of road network
17: Develop a national road freight strategy
18: Adopt new road design standards for all roads in strategic freight network
19: Trial new approaches to expressway delivery
20: Change the way in which road capacity projects are prioritised
Fostering a more
competitive environment
21: Remove fuel subsidy on diesel fuel
22: Progressively introduce a road pricing regime
23: Define and implement track access charges
24: Adopt point-of-origin approach to enforcement of weight limits
25: Foster competition in the provision of container terminal services
26: Modernise PT Kereta Api Indonesia (PTKAI) freight operations
Introducing new service
models
27: Promote Cikarang–Surabaya rail services
28: Expand Ro-Ro shipping services between Java and Sumatera
29: Develop specialised rail services for automobiles
Improving planning and
trade facilitation
30: Formally establish peak logistics industry consultative body
31: Restructure government institutions to support multimodal approach
32: Integrate transport considerations into planning of industrial estates
33: Intensify congestion reduction efforts in major urban centres
34: Further streamline cargo clearance procedures
35: Provide customs clearance at inland terminals
14
Indicative Timing for Recommended Actions..1/2
Short Term
(before
2014)
Medium
Term (2015–
2019)
Long Term
(2020 and
beyond)
In Progress
Action 2: Complete Tanjung Priok access road
Action 4: Accelerate proposed expressway links to Tanjung Perak
Action 9: Improve facilities for handling motor vehicles at Tanjung Priok
Action 11: Complete double tracking Jakarta–Surabaya
Committed
Action 1: Construct Tanjung Priok rail link
Action 5: Ensure high quality access road to Kalibaru
Action 8: Promptly deliver increased container port capacity
Action 18: Adopt new road design standards for all roads in strategic freight
network
Action 23: Define and implement track access charges
Action 25: Foster competition in the provision of container terminal services
Action 33: Intensify congestion reduction efforts in major urban centres
Planned
Action 3: Activate Tanjung Perak rail connection
Action 6: Incorporate planning for rail links in new terminal developments
Action 34: Further streamline cargo clearance procedures
Previously recommended
Action 26: Modernise PT KAI freight operations
Action 13: Selectively improve rail track strength
Action 14: Promote use of the full potential of existing intermodal terminals
Action 15: Construct a common user rail terminal at Cilegon
Investigation and preparation
Implementation
15
Indicative Timing for Recommended Actions..2/2
Short Term
(before
2014)
Medium
Term (2015–
2019)
Long Term
(2020 and
beyond)
Action 16: Develop a network of new intermodal terminals
Action 17: Develop a national road freight strategy
Action 19: Trial new approaches to expressway delivery
Action 20: Change the way in which road capacity projects are prioritised
Action 21: Remove fuel subsidy on diesel fuel
Action 22: Progressively introduce a road pricing regime
Action 28: Expand Ro-Ro shipping services between Java and Sumatera
Action 31: Restructure government institutions to support multimodal
approach
Action 32: Integrate transport considerations into planning of industrial estates
Action 35: Provide customs clearance at inland terminals
New initiatives
Action 7: Set and monitor KPIs for cargo handling performance at key ports
Action 10: Introduce a vehicle booking system at the main container terminals
Action 12: Develop selected freight only rail links
Action 24: Adopt point-of-origin approach to enforcement of weight limits
Action 27: Promote Cikarang–Surabaya rail services
Action 29: Develop specialised rail services for automobiles
Action 30: Formally establish peak logistics industry consultative body
Investigation and preparation
Implementation
16
Options for Next Step
No Initiative Justification Activity Outputs
1. Detailedanalysisof
specific commodity
supply chains
(automotive, steel
andcement)
Tounderstand what needs to
bedone for potential
commodity to divertto rail,
andto provide a basis for
estimating thepotential sizeof
modechange
Detailedsurveyon the movement of
rawmaterial to final product
deliveryofspecific to improvethe
understanding on existing
commodity movement and its
transportsystem
• Tradeandsupply chainpattern
analysisfor eachcommodity
• Costand tariff structures
• Understanding of barrierstomodal
shiftin eachchain
• Estimatesofmodal shareexisting and
future
2. Diagnosticauditof
dryport performance
Touse the experienceof
Gedebageand Cikarang Dry
Portsto understand what
needs to be done to support
development of successful dry
ports inIndonesia
Diagnostic auditof factorsthat
currentlyinhibituse of the
Gedebageand Cikarang dryports
andanalysisof what canbe done to
removeobstaclesto improved
performanceofthese ports and
identifylessons learnedfor future
dryport development
• Factfinding problems and constraintin
Gedebageand Cikarang
• Detailedrecommendationsfor what
canbedone to improvesituation at
these facilities
• Criteria for theselectionand
development of future dryports.
3. Assessment of
potential intermodal
terminal markets
(IMT)andlocations
Support planning to develop
container yardconnected to
railwaytoincreasethe
flexibilityof freightrail
Asses both demand and supply
conditions at previously identified
potential IMT locations, including
working with PTKAI on potential for
development inseveral stations.
Identifythe possibility of further
development of those container yard
• Potential location
• Potential market
• Potential development as
“consolidation freightcentre”
• Operational andbusiness scheme
4. Explorationof
potential for Java-
Sumatra ro-ro
services
Needto develop alternativesin
Java-Sumatera corridor to
decreaseroad trafficload
Detailedsurveyon ro-roJakarta–
Belawan.Inititalizing assesmentto
potential demand from Central/East
Java –Sumatera corridor
• Potential demand/commoodity
(Semarang/Surabaya –Sumatera)
• Lesson learnedto Jakarta-Belawan
5. Developmentof
Cikarang-Tanjung
Perakserviceoptions
Morepromising (double trackvs
Pasoso). Support to
development freightrail inJava
North Corridor
Assess size of potential market and
key determinantsof mode choice for
thismovement. Theanalysis could
alsoincorporatean assessment of
thefeasibilityof higher priorityfor
freighttrainsonthe double tracked
section of the northern route.
• Potential market Cikarang toEast
Indonesia
• Problemsand constraint to
development (includeaccessibility to
Tjg.PerakPort)
• Modal shareexisting and future
17
Terima Kasih

Weitere ähnliche Inhalte

Was ist angesagt?

VET 4093- Pengurusan Stor, Harta Modal dan Inventori
VET 4093- Pengurusan Stor, Harta Modal dan InventoriVET 4093- Pengurusan Stor, Harta Modal dan Inventori
VET 4093- Pengurusan Stor, Harta Modal dan Inventori
Zuzan Michael Japang
 
Penerapan manajemen risiko djpbn
Penerapan manajemen risiko djpbnPenerapan manajemen risiko djpbn
Penerapan manajemen risiko djpbn
Ahmad Abdul Haq
 
8001 kehilangan
8001 kehilangan8001 kehilangan
8001 kehilangan
aimm reka
 
Market opportunity analysis in indonesia logistic 1.3 (1)
Market opportunity analysis in indonesia logistic 1.3 (1)Market opportunity analysis in indonesia logistic 1.3 (1)
Market opportunity analysis in indonesia logistic 1.3 (1)
CCN
 
dfdaMengukur keberkesanan sekolah
dfdaMengukur keberkesanan sekolahdfdaMengukur keberkesanan sekolah
dfdaMengukur keberkesanan sekolah
nathanheman
 
Borang soal selidik pengurusan pentadbiran prasekolah (1)
Borang soal selidik pengurusan pentadbiran prasekolah (1)Borang soal selidik pengurusan pentadbiran prasekolah (1)
Borang soal selidik pengurusan pentadbiran prasekolah (1)
ctalin2002
 
Tatacara Kaedah Sebut Harga
Tatacara Kaedah Sebut HargaTatacara Kaedah Sebut Harga
Tatacara Kaedah Sebut Harga
Iszwan Shah
 
Proton Strategic Analysis Presentation
Proton Strategic Analysis PresentationProton Strategic Analysis Presentation
Proton Strategic Analysis Presentation
Rasha Adi
 
Performance Measurement System Of Telekom Malaysia
Performance Measurement System Of Telekom MalaysiaPerformance Measurement System Of Telekom Malaysia
Performance Measurement System Of Telekom Malaysia
Husen Amr
 

Was ist angesagt? (20)

VET 4093- Pengurusan Stor, Harta Modal dan Inventori
VET 4093- Pengurusan Stor, Harta Modal dan InventoriVET 4093- Pengurusan Stor, Harta Modal dan Inventori
VET 4093- Pengurusan Stor, Harta Modal dan Inventori
 
TATAKELAKUAN DAN TATATERTIB.pptx
TATAKELAKUAN DAN TATATERTIB.pptxTATAKELAKUAN DAN TATATERTIB.pptx
TATAKELAKUAN DAN TATATERTIB.pptx
 
Penerapan manajemen risiko djpbn
Penerapan manajemen risiko djpbnPenerapan manajemen risiko djpbn
Penerapan manajemen risiko djpbn
 
Blue Ocean Strategy
Blue Ocean StrategyBlue Ocean Strategy
Blue Ocean Strategy
 
8001 kehilangan
8001 kehilangan8001 kehilangan
8001 kehilangan
 
Market opportunity analysis in indonesia logistic 1.3 (1)
Market opportunity analysis in indonesia logistic 1.3 (1)Market opportunity analysis in indonesia logistic 1.3 (1)
Market opportunity analysis in indonesia logistic 1.3 (1)
 
Peningkatan Kapasitas SDM Dalam Sektor Logistik
Peningkatan Kapasitas SDM Dalam Sektor LogistikPeningkatan Kapasitas SDM Dalam Sektor Logistik
Peningkatan Kapasitas SDM Dalam Sektor Logistik
 
PANDUAN MENGISI MYPORTFOLIO DALAM SISTEM HRMIS_2022.pdf
PANDUAN MENGISI MYPORTFOLIO DALAM SISTEM HRMIS_2022.pdfPANDUAN MENGISI MYPORTFOLIO DALAM SISTEM HRMIS_2022.pdf
PANDUAN MENGISI MYPORTFOLIO DALAM SISTEM HRMIS_2022.pdf
 
dfdaMengukur keberkesanan sekolah
dfdaMengukur keberkesanan sekolahdfdaMengukur keberkesanan sekolah
dfdaMengukur keberkesanan sekolah
 
Borang soal selidik pengurusan pentadbiran prasekolah (1)
Borang soal selidik pengurusan pentadbiran prasekolah (1)Borang soal selidik pengurusan pentadbiran prasekolah (1)
Borang soal selidik pengurusan pentadbiran prasekolah (1)
 
PETA PANDUAN (ROAD MAP) DAN RENCANA AKSI SISTEM LOGISTIK NASIONAL
PETA PANDUAN (ROAD MAP) DAN RENCANA AKSI SISTEM LOGISTIK NASIONALPETA PANDUAN (ROAD MAP) DAN RENCANA AKSI SISTEM LOGISTIK NASIONAL
PETA PANDUAN (ROAD MAP) DAN RENCANA AKSI SISTEM LOGISTIK NASIONAL
 
Rencana Aksi Jangka Menengah Ekonomi Ereatif 2015-2019
Rencana Aksi Jangka Menengah Ekonomi Ereatif 2015-2019Rencana Aksi Jangka Menengah Ekonomi Ereatif 2015-2019
Rencana Aksi Jangka Menengah Ekonomi Ereatif 2015-2019
 
2018_05_03 Presentasi Ekonomi Kreatif FEB UI
2018_05_03 Presentasi Ekonomi Kreatif FEB UI2018_05_03 Presentasi Ekonomi Kreatif FEB UI
2018_05_03 Presentasi Ekonomi Kreatif FEB UI
 
NPV table
NPV tableNPV table
NPV table
 
Tatacara Kaedah Sebut Harga
Tatacara Kaedah Sebut HargaTatacara Kaedah Sebut Harga
Tatacara Kaedah Sebut Harga
 
Senarai semak aset_dan_stor
Senarai semak aset_dan_storSenarai semak aset_dan_stor
Senarai semak aset_dan_stor
 
Borang soal selidik kepimpinan guru besar
Borang soal selidik kepimpinan guru besarBorang soal selidik kepimpinan guru besar
Borang soal selidik kepimpinan guru besar
 
Proton Strategic Analysis Presentation
Proton Strategic Analysis PresentationProton Strategic Analysis Presentation
Proton Strategic Analysis Presentation
 
Tatacara pengurusan aset kerajaan>>>>
Tatacara pengurusan aset kerajaan>>>>Tatacara pengurusan aset kerajaan>>>>
Tatacara pengurusan aset kerajaan>>>>
 
Performance Measurement System Of Telekom Malaysia
Performance Measurement System Of Telekom MalaysiaPerformance Measurement System Of Telekom Malaysia
Performance Measurement System Of Telekom Malaysia
 

Andere mochten auch

StateofLogisticsIndonesia2015
StateofLogisticsIndonesia2015StateofLogisticsIndonesia2015
StateofLogisticsIndonesia2015
Hafida Fahmiasari
 
Dedicated freight corridor
Dedicated freight corridorDedicated freight corridor
Dedicated freight corridor
Harshad Joshi
 
Startup Asia Jakarta 2013: State of e-commerce in Indonesia
Startup Asia Jakarta 2013: State of e-commerce in IndonesiaStartup Asia Jakarta 2013: State of e-commerce in Indonesia
Startup Asia Jakarta 2013: State of e-commerce in Indonesia
Tech in Asia
 
Overview on Roadmap for the Development of the Freight Logistics Services Sector
Overview on Roadmap for the Development of the Freight Logistics Services SectorOverview on Roadmap for the Development of the Freight Logistics Services Sector
Overview on Roadmap for the Development of the Freight Logistics Services Sector
Technopreneurs Association of Malaysia
 
Cracking the Facebook Coding Interview
Cracking the Facebook Coding InterviewCracking the Facebook Coding Interview
Cracking the Facebook Coding Interview
Gayle McDowell
 
Management Presentation 2016_Update 1Q-16_v20
Management Presentation 2016_Update 1Q-16_v20Management Presentation 2016_Update 1Q-16_v20
Management Presentation 2016_Update 1Q-16_v20
Adrianto Januri
 

Andere mochten auch (20)

StateofLogisticsIndonesia2015
StateofLogisticsIndonesia2015StateofLogisticsIndonesia2015
StateofLogisticsIndonesia2015
 
Great Smart Green Silk Road: One Belt, One Road
Great Smart Green Silk Road: One Belt, One RoadGreat Smart Green Silk Road: One Belt, One Road
Great Smart Green Silk Road: One Belt, One Road
 
Dedicated freight corridor
Dedicated freight corridorDedicated freight corridor
Dedicated freight corridor
 
Startup Asia Jakarta 2013: State of e-commerce in Indonesia
Startup Asia Jakarta 2013: State of e-commerce in IndonesiaStartup Asia Jakarta 2013: State of e-commerce in Indonesia
Startup Asia Jakarta 2013: State of e-commerce in Indonesia
 
Mobile Malaysia - ahead of the south-east Asia pack
Mobile Malaysia - ahead of the south-east Asia packMobile Malaysia - ahead of the south-east Asia pack
Mobile Malaysia - ahead of the south-east Asia pack
 
Overview on Roadmap for the Development of the Freight Logistics Services Sector
Overview on Roadmap for the Development of the Freight Logistics Services SectorOverview on Roadmap for the Development of the Freight Logistics Services Sector
Overview on Roadmap for the Development of the Freight Logistics Services Sector
 
Indonesia social media trend 2016 jakpat
Indonesia social media trend 2016 jakpatIndonesia social media trend 2016 jakpat
Indonesia social media trend 2016 jakpat
 
SparkLabs Global Asia E-Commerce Report 2015
SparkLabs Global Asia E-Commerce Report 2015SparkLabs Global Asia E-Commerce Report 2015
SparkLabs Global Asia E-Commerce Report 2015
 
What Would Steve Do? Lessons from the World's Most Captivating Presenters
What Would Steve Do? Lessons from the World's Most Captivating PresentersWhat Would Steve Do? Lessons from the World's Most Captivating Presenters
What Would Steve Do? Lessons from the World's Most Captivating Presenters
 
Using Analytics To Make Smart HR Decisions
Using Analytics To Make Smart HR DecisionsUsing Analytics To Make Smart HR Decisions
Using Analytics To Make Smart HR Decisions
 
Cracking the Facebook Coding Interview
Cracking the Facebook Coding InterviewCracking the Facebook Coding Interview
Cracking the Facebook Coding Interview
 
Going Global: A Road Map for Bringing the World to Your Classroom
Going Global: A Road Map for Bringing the World to Your Classroom Going Global: A Road Map for Bringing the World to Your Classroom
Going Global: A Road Map for Bringing the World to Your Classroom
 
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
 
Presentation on dgh program to ind ii board 2012 04
Presentation on dgh program to ind ii board 2012 04Presentation on dgh program to ind ii board 2012 04
Presentation on dgh program to ind ii board 2012 04
 
Rob Bain - Toll Road Forecasting
Rob Bain - Toll Road ForecastingRob Bain - Toll Road Forecasting
Rob Bain - Toll Road Forecasting
 
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
 
Management Presentation 2016_Update 1Q-16_v20
Management Presentation 2016_Update 1Q-16_v20Management Presentation 2016_Update 1Q-16_v20
Management Presentation 2016_Update 1Q-16_v20
 
Toll road business opportunity in Jakarta & West Java
Toll road business opportunity in Jakarta & West JavaToll road business opportunity in Jakarta & West Java
Toll road business opportunity in Jakarta & West Java
 
Sistem pengelolaan jalan tol wilayah suramadu
Sistem pengelolaan jalan tol wilayah suramaduSistem pengelolaan jalan tol wilayah suramadu
Sistem pengelolaan jalan tol wilayah suramadu
 
Elitery The First Tier III Certified data center in South East Asia by Uptime...
Elitery The First Tier III Certified data center in South East Asia by Uptime...Elitery The First Tier III Certified data center in South East Asia by Uptime...
Elitery The First Tier III Certified data center in South East Asia by Uptime...
 

Ähnlich wie Development of multimodal transport in north java corridor

Malaysia Logistics
Malaysia LogisticsMalaysia Logistics
Malaysia Logistics
YAU MEE LIM
 

Ähnlich wie Development of multimodal transport in north java corridor (20)

Advancing Rail Transit Excellence in OBOR Countries
Advancing Rail Transit Excellence in OBOR CountriesAdvancing Rail Transit Excellence in OBOR Countries
Advancing Rail Transit Excellence in OBOR Countries
 
Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th
 
Top ideas for Infrastructure
Top ideas for InfrastructureTop ideas for Infrastructure
Top ideas for Infrastructure
 
2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG
 
Mohinder Singh - Gestión Institucional del Sistema de Transporte de Singapur
Mohinder Singh - Gestión Institucional del Sistema de Transporte de SingapurMohinder Singh - Gestión Institucional del Sistema de Transporte de Singapur
Mohinder Singh - Gestión Institucional del Sistema de Transporte de Singapur
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
 
Malaysia Logistics
Malaysia LogisticsMalaysia Logistics
Malaysia Logistics
 
Multimodal Transport in an Indian Perspective
Multimodal Transport in an Indian PerspectiveMultimodal Transport in an Indian Perspective
Multimodal Transport in an Indian Perspective
 
Railway infrastructure construction and upgrading in india and the middle eas...
Railway infrastructure construction and upgrading in india and the middle eas...Railway infrastructure construction and upgrading in india and the middle eas...
Railway infrastructure construction and upgrading in india and the middle eas...
 
Innovation in Transnet
Innovation in TransnetInnovation in Transnet
Innovation in Transnet
 
GCC Railway
GCC RailwayGCC Railway
GCC Railway
 
Regional Integrated Supply Chain Strategy for Rail
Regional Integrated Supply Chain  Strategy for Rail Regional Integrated Supply Chain  Strategy for Rail
Regional Integrated Supply Chain Strategy for Rail
 
Working in synergy with neighbouring countries to seamlessly transport coal o...
Working in synergy with neighbouring countries to seamlessly transport coal o...Working in synergy with neighbouring countries to seamlessly transport coal o...
Working in synergy with neighbouring countries to seamlessly transport coal o...
 
Optimising a multi-load container transport corridor in South Africa
Optimising a multi-load container transport corridor in South AfricaOptimising a multi-load container transport corridor in South Africa
Optimising a multi-load container transport corridor in South Africa
 
The role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in javaThe role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in java
 
The Need For Rail And Ports Integration Pmaesa
The Need For Rail And Ports Integration PmaesaThe Need For Rail And Ports Integration Pmaesa
The Need For Rail And Ports Integration Pmaesa
 
Qatar rail - Geoff Mee presentation
Qatar rail - Geoff Mee presentationQatar rail - Geoff Mee presentation
Qatar rail - Geoff Mee presentation
 
Metro Rail final.pptx
Metro Rail final.pptxMetro Rail final.pptx
Metro Rail final.pptx
 
Sustainable Cargo Transportation
Sustainable Cargo TransportationSustainable Cargo Transportation
Sustainable Cargo Transportation
 
Scarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 PresentationScarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 Presentation
 

Mehr von Indonesia Infrastructure Initiative

Mehr von Indonesia Infrastructure Initiative (20)

Presentasi Sanitasi INDII
Presentasi Sanitasi INDIIPresentasi Sanitasi INDII
Presentasi Sanitasi INDII
 
Balikpapan Public Diplomacy 25 May 2015
Balikpapan  Public Diplomacy 25 May 2015Balikpapan  Public Diplomacy 25 May 2015
Balikpapan Public Diplomacy 25 May 2015
 
World experience-in-railway-restructuring
World experience-in-railway-restructuringWorld experience-in-railway-restructuring
World experience-in-railway-restructuring
 
Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesian railways revitalisation   bambang susantono, vice minister for tra...Indonesian railways revitalisation   bambang susantono, vice minister for tra...
Indonesian railways revitalisation bambang susantono, vice minister for tra...
 
WS2 Infrastructure Issues
WS2 Infrastructure IssuesWS2 Infrastructure Issues
WS2 Infrastructure Issues
 
Railway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in javaRailway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in java
 
Government strategy in developing multimodal transportation
Government strategy in developing multimodal transportationGovernment strategy in developing multimodal transportation
Government strategy in developing multimodal transportation
 
The role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportationThe role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportation
 
Development of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiyDevelopment of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiy
 
Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)
 
Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)
 
Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)
 
Ws3 presentation
Ws3 presentationWs3 presentation
Ws3 presentation
 
Ws3 me
Ws3 meWs3 me
Ws3 me
 
Ws3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safetyWs3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safety
 
Ws3 gender and disability presentation
Ws3 gender and disability presentationWs3 gender and disability presentation
Ws3 gender and disability presentation
 
Ws2 introduction
Ws2 introductionWs2 introduction
Ws2 introduction
 
Workshop #2 safe system approach
Workshop #2 safe system approachWorkshop #2 safe system approach
Workshop #2 safe system approach
 
Workshop #2 safe system approach english
Workshop #2 safe system approach englishWorkshop #2 safe system approach english
Workshop #2 safe system approach english
 
Ws3 safe system approach (english version)
Ws3 safe system approach (english version)Ws3 safe system approach (english version)
Ws3 safe system approach (english version)
 

Kürzlich hochgeladen

Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
nehasharma67844
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Chandigarh Call girls 9053900678 Call girls in Chandigarh
 
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Kürzlich hochgeladen (20)

The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
 
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakurbest call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...
Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...
Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...
 
VIP Model Call Girls Baramati ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Baramati ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Baramati ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Baramati ( Pune ) Call ON 8005736733 Starting From 5K to...
 
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
 
1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
 

Development of multimodal transport in north java corridor

  • 1. Development of Multimodal Transport in North Java Corridor Scoping Study
  • 2. 2 Study focus Development Theme Driver for national industry and services provision Economic centres Jakarta Bandung Semarang Yogyakarta Surabaya Main economic activity Food and beverage Textile Transportation Equipment Shipping ICT Defence Equipment Greater Jakarta Area “to ensure that the infrastructure, services and facilities that are provided in the Corridor meet the needs of the users of the transport system, and especially the needs of main economic activities of the corridor as identified in the MP3EI”
  • 3. 3 Study context National Logistics System Multimodal Transport StrategyNRMP NPMP Road system plans
  • 4. 4 Mode choice in principle Distance Flow concentration Cargo value Cargo perishability/fragility Cargo density Road Rail Sea Low Low High High Low High High Low Low High
  • 6. 6 Geographical Pattern of Intra-Java Freight Flows 0 1000 2000 3000 4000 Banten DIY DKI Jawa Barat Jawa Tengah Jawa Timur Destination Milliontonnes Origin Banten DIY DKI Jawa Barat Jawa Tengah Jawa Timur
  • 7. 7 Fertiliser,600,000 Silica, 7,874 Iron Ore, 180000 Petroleum,496,000 Cement, 450,000 Container, 400,810 Parcel (multiproduct), 110,854 Antaboga (multiproduct), 243,000 Other multiproduct, 130,792 Steel,25,731 Existing rail freight task (Java) – excl coal. Source: KTPA, 2012
  • 8. 8 Key Obstacles to Efficient Multimodal Freight Transport in the Java Corridor GROUP KEY ISSUES ROAD ISSUES Slow delivery of expressway system Overloading Congestion Suboptimal road investment prioritisation Distortion due to fuel subsidies RAIL ISSUES Lack of network capacity Limitations on train weights and dimensions Lack of competition MARITIME ISSUES Limited port capacity High port access costs Unreliable port performance High cost and unreliability of domestic shipping services MODAL INTERCONNECTIVIT Y ISSUES Poor rail access to port terminals Scarcity and poor performance of intermodal terminals Lack of intermodal focus in planning and system management
  • 9. 9 Some surprises • Truck costs are not as high as expected relative to other modes. This reflects fuel subsidy, lack of RUC and probably high level of overloading • Truck travel times are not as low relative to other modes as in other places. This appears to reflect traffic congestion and restrictions on truck operation in cities. • Some high value goods which we would normally expect to travel by truck are shipped using sea mode (for security reason), i. e.: electronics and car • Some low value goods that seem natural targets for rail travel by road: for example, around 300 trucks each carry 30 tons of coal daily from Cirebon to Bandung for textile factories around Bandung.
  • 10. 10 Targeting the right cargoes Commodity Comments Existing bulk traffics Need to avoid complacency Steel Krakatau steel already sends cargo by both rail and sea, and is interested in increasing non-road share. Also significant growth with the Posco Krakatau steel development. Port-related containers Pressure on landside access to ports will make increased use of rail imperative. Also port-related movement tend to be better suited to rail because there is not – or need not be – a truck distribution leg at the port end. Niche bulks Rail already has a position in many bulks, but some customers – e.g. cement – have an interest in increasing their use of rail Java-Sumatra freight The need to make the Straits crossing, congestion at the ferry and relatively long distances make this trade a priority target for ro-ro shipping services Automotive A more difficult target for rail, but at least one major manufacturer is interested in considering and rail is quite widely used in other countries. Jakarta-Surabaya general cargo It will be difficult for rail or sea to be sustainably profitable in these cargoes, but both rail and sea currently play a minor role in the carriage of these cargoes. Double-tracking should improve competitive position of rail. Low hanging fruit More difficult
  • 11. 11 RIGHT infrastructure and services Immediate (before 2014) Complete Jakarta-Surabaya double-tracking Improve access links to major ports Improve facilities for handling motor vehicles at T Priok Promote use of full potential of existing intermodal terminals Develop common user terminal at Cilegon Develop Cikarang-Surabaya rail services Medium term (2015-2019) Provide additional container capacity at T Priok and T Perak Ensure all new terminal developments have high quality road and rail access Create network of intermodal terminals/dry ports Expand ro-ro services between Sumatra and Java Develop specialist rail services for automotive industry Longer term (2020 and beyond) Create freight only rail links in congested section of the network Increase structural strength of key rail freight links
  • 12. 12 The RIGHT supporting policies Immediate (before 2014) Set and monitor KPIs for cargo handling performance at key ports Adopt new road design standards for all of strategic freight network Formally establish peak logistics industry consultative body Remove fuel subsidy for heavy diesel fuels Define and implement rail track access charge Foster competition in container terminal services Modernise PTKAI rolling stock (commence) Adopt point-of-origin approach to enforcement of vehicle limits Further streamline customs clearance procedures Intensify congestion management efforts in major cities Include multi-modal transport priority actions in Renstra Medium term (2015-2019) Restructure government institutions to better support multimodal transport Develop national road freight strategy Progressively introduce road pricing scheme Trial new approaches to expressway delivery Revise procedures for prioritising road capacity improvements Restructure PKAI on business lines Provide customs clearance at all dry ports Integrate transport considerations into industrial estate planning Longer term Introduce vehicle booking systems at T Priok and T Perak
  • 13. 13 Reform Themes and Supporting Actions THEME ACTION ITEM Improving land transport access to ports 1: Construct Tanjung Priok rail link 2: Complete Tanjung Priok access road 3: Activate Tanjung Perak rail connection 4: Accelerate proposed expressway links to Tanjung Perak 5: Ensure high quality access road to Kalibaru 6: Incorporate planning for rail links in new terminal developments Delivering increased port capacity 7: Set and monitor Key Performance Indicators (KPIs) for cargo handling performance at key ports 8: Promptly deliver increased container port capacity 9: Improve facilities for handling motor vehicles at Tanjung Priok 10: Introduce a vehicle booking system at the main container terminals Developing freight rail infrastructure and terminals 11: Complete double tracking Jakarta–Surabaya 12: Develop selected freight only rail links 13: Selectively improve rail track strength 14: Promote use of the full potential of existing intermodal terminals 15: Construct a common user rail terminal at Cilegon 16: Develop a network of new intermodal terminals Strengthening the freight capability of road network 17: Develop a national road freight strategy 18: Adopt new road design standards for all roads in strategic freight network 19: Trial new approaches to expressway delivery 20: Change the way in which road capacity projects are prioritised Fostering a more competitive environment 21: Remove fuel subsidy on diesel fuel 22: Progressively introduce a road pricing regime 23: Define and implement track access charges 24: Adopt point-of-origin approach to enforcement of weight limits 25: Foster competition in the provision of container terminal services 26: Modernise PT Kereta Api Indonesia (PTKAI) freight operations Introducing new service models 27: Promote Cikarang–Surabaya rail services 28: Expand Ro-Ro shipping services between Java and Sumatera 29: Develop specialised rail services for automobiles Improving planning and trade facilitation 30: Formally establish peak logistics industry consultative body 31: Restructure government institutions to support multimodal approach 32: Integrate transport considerations into planning of industrial estates 33: Intensify congestion reduction efforts in major urban centres 34: Further streamline cargo clearance procedures 35: Provide customs clearance at inland terminals
  • 14. 14 Indicative Timing for Recommended Actions..1/2 Short Term (before 2014) Medium Term (2015– 2019) Long Term (2020 and beyond) In Progress Action 2: Complete Tanjung Priok access road Action 4: Accelerate proposed expressway links to Tanjung Perak Action 9: Improve facilities for handling motor vehicles at Tanjung Priok Action 11: Complete double tracking Jakarta–Surabaya Committed Action 1: Construct Tanjung Priok rail link Action 5: Ensure high quality access road to Kalibaru Action 8: Promptly deliver increased container port capacity Action 18: Adopt new road design standards for all roads in strategic freight network Action 23: Define and implement track access charges Action 25: Foster competition in the provision of container terminal services Action 33: Intensify congestion reduction efforts in major urban centres Planned Action 3: Activate Tanjung Perak rail connection Action 6: Incorporate planning for rail links in new terminal developments Action 34: Further streamline cargo clearance procedures Previously recommended Action 26: Modernise PT KAI freight operations Action 13: Selectively improve rail track strength Action 14: Promote use of the full potential of existing intermodal terminals Action 15: Construct a common user rail terminal at Cilegon Investigation and preparation Implementation
  • 15. 15 Indicative Timing for Recommended Actions..2/2 Short Term (before 2014) Medium Term (2015– 2019) Long Term (2020 and beyond) Action 16: Develop a network of new intermodal terminals Action 17: Develop a national road freight strategy Action 19: Trial new approaches to expressway delivery Action 20: Change the way in which road capacity projects are prioritised Action 21: Remove fuel subsidy on diesel fuel Action 22: Progressively introduce a road pricing regime Action 28: Expand Ro-Ro shipping services between Java and Sumatera Action 31: Restructure government institutions to support multimodal approach Action 32: Integrate transport considerations into planning of industrial estates Action 35: Provide customs clearance at inland terminals New initiatives Action 7: Set and monitor KPIs for cargo handling performance at key ports Action 10: Introduce a vehicle booking system at the main container terminals Action 12: Develop selected freight only rail links Action 24: Adopt point-of-origin approach to enforcement of weight limits Action 27: Promote Cikarang–Surabaya rail services Action 29: Develop specialised rail services for automobiles Action 30: Formally establish peak logistics industry consultative body Investigation and preparation Implementation
  • 16. 16 Options for Next Step No Initiative Justification Activity Outputs 1. Detailedanalysisof specific commodity supply chains (automotive, steel andcement) Tounderstand what needs to bedone for potential commodity to divertto rail, andto provide a basis for estimating thepotential sizeof modechange Detailedsurveyon the movement of rawmaterial to final product deliveryofspecific to improvethe understanding on existing commodity movement and its transportsystem • Tradeandsupply chainpattern analysisfor eachcommodity • Costand tariff structures • Understanding of barrierstomodal shiftin eachchain • Estimatesofmodal shareexisting and future 2. Diagnosticauditof dryport performance Touse the experienceof Gedebageand Cikarang Dry Portsto understand what needs to be done to support development of successful dry ports inIndonesia Diagnostic auditof factorsthat currentlyinhibituse of the Gedebageand Cikarang dryports andanalysisof what canbe done to removeobstaclesto improved performanceofthese ports and identifylessons learnedfor future dryport development • Factfinding problems and constraintin Gedebageand Cikarang • Detailedrecommendationsfor what canbedone to improvesituation at these facilities • Criteria for theselectionand development of future dryports. 3. Assessment of potential intermodal terminal markets (IMT)andlocations Support planning to develop container yardconnected to railwaytoincreasethe flexibilityof freightrail Asses both demand and supply conditions at previously identified potential IMT locations, including working with PTKAI on potential for development inseveral stations. Identifythe possibility of further development of those container yard • Potential location • Potential market • Potential development as “consolidation freightcentre” • Operational andbusiness scheme 4. Explorationof potential for Java- Sumatra ro-ro services Needto develop alternativesin Java-Sumatera corridor to decreaseroad trafficload Detailedsurveyon ro-roJakarta– Belawan.Inititalizing assesmentto potential demand from Central/East Java –Sumatera corridor • Potential demand/commoodity (Semarang/Surabaya –Sumatera) • Lesson learnedto Jakarta-Belawan 5. Developmentof Cikarang-Tanjung Perakserviceoptions Morepromising (double trackvs Pasoso). Support to development freightrail inJava North Corridor Assess size of potential market and key determinantsof mode choice for thismovement. Theanalysis could alsoincorporatean assessment of thefeasibilityof higher priorityfor freighttrainsonthe double tracked section of the northern route. • Potential market Cikarang toEast Indonesia • Problemsand constraint to development (includeaccessibility to Tjg.PerakPort) • Modal shareexisting and future