IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 10, Issue 6 (Jan. 2014), PP 14-19
www.iosrjournals.org
www.iosrjournals.org 14 | Page
Role of Project Management Consultancy in Construction
Project
Atul R Nikumbh1
, Dr. S.S. Pimplikar2
1
Post graduate student, 2
Prof & Head of Dept. of Civil Engineering,
2
MAEER’S Maharashtra Institute of Technology, Pune university, India.
Abstract : The construction industry generally deals with the various types of construction sectors viz Real
Estate & Infrastructure. Real Estate Sector is segmented in Residential, Industrial, Corporate, and
Commercial. Whereas Infrastructure sector in Roads, Railways, Urban Infrastructures, Ports, Airports and
Power. To manage such kind of unique projects requires an expertise with organizations and a thorough
body of knowledge. The purpose of this paper is to provide the analysis or breakdown of Role of Project
Management Consultancy and study the Problems faced by PMC for implementing the project. Project
Management Consultancy plays multifaceted part in such projects and provides the services from inception
to completion of projects. At every stage of project life cycle, the principles of pro-activeness and creating
the win-win situation is necessary keeping in mind the customer / client’s requirements. Use of Project
Management Consultancy (PMC) offers one of the effective management solution to increase and improve the
efficiency and outcome of a project in construction. A case study of construction of a Mega Industrial
Project which is dealt by PMC and Project consist of various type of buildings for Manufacturing unit,
Assembling unit , Logistic unit , Process unit with allied Infra of Electrical utilities, Services like Fire
fighting, Sewage line, Storm water arrangement and Road etc have been considered for this research work.
Keywords: Body of Knowledge, Industrial Buildings, Project Management Consultancy (PMC), Role &
Responsibility Matrix.
I. INTRODUCTION
The Project Management Consultancy has a wide variety of roles to play during the construction
process. Construction project gives benefits to the Customer / Client in terms of satisfaction and it consists of
business development, profit, resources utilization, etc. Because of this consultancy plays a multifaceted part
in the construction project, and is usually involved in the project from the project’s inception to its
completion. It is important to fully understand Project Management Consultancy and authority. Doing so
ensures that the Consultancy can be fully maximized on each construction project. Normally the job is
managed by the Project Manager and supervised by the Construction Manager, and allied team of design
engineer, construction engineer or project architect. Efficiency in Management is needed to gain a higher
level in competitiveness. Every construction project is different i.e. unique, every construction project
demands the full attention, professionalism and energy of its project team, every construction project
depends upon an experienced leader to make it happen. The construction industry in India has grown very
fast with the construction of new projects. Due to the rapid expansion in the construction industry, the
services provided by the Consultancy need to be improved in terms of performance and quality of work to
meet the construction project goals and objective and also the clients satisfaction.
Paper highlights the case study for research of dealing the Mega Industrial Projects by PMC through
their role and responsibility during project life cycle from Project Initiation Phase and A/E Selection -
Schematic Design Phase- Design Development Phase- Construction Documents Phase- Bidding and Award
Phase- Construction Phase - Closeout. In all phases PMC manage the project by various services like
Scheduling, Cost budgeting, Value engineering, Risk Identifying, Monitoring & controlling, Time line
optimization, Resources Allocations, etc.
II. NEED FOR CONSULTANCY :
1. Shortage of specialized staff with the Industry since at present the supervisory staff conversant
with latest construction technique is not available in bulk. 2. Also, in general, there is a shortage of
supervisors who can be associated with a single project. 3. Faster execution of projects in short time.
III. PMC ROLES AND RESPONSIBILITY MATRIX:
There is no specific definition of project consultant. Most definitions describe management
consultants by their roles and responsibility and services that they provide using tools and skills they have in
delivering a task assigned by the client or the owner of the project (Dzulkarnaen, 2005).
Role of Project Management Consultancy in Construction Project
www.iosrjournals.org 15 | Page
Project is a Temporary endeavor with a specific beginning and end (i.e. has limited life) and creates
a unique product, service or result (i.e. each project by definition is unique). Project management is the art of
directing and coordinating human and material resources throughout the life of a project by using modem
management techniques to achieve pre-determined objectives of scope, cost, time, quality and participation
satisfaction.
Consultation is happening if the clients seek expert knowledge or some opinions on some
engineering problems or anything that involves engineering matters. Consultation maybe brief or extended
which involves only few hours of time, with the clients sitting across the desk of the consultant. Other
consultation may require traveling, some period of substantial portion of a consultant’s time over a period of
several months, and repeated presentations and discussions with the client (Maxwell, 1982).
Table 1 shows the roles and responsibility matrix for the various stakeholders of the project at different
stages of construction.
Table: 1 Roles and Responsibility Matrix
(R- Responsibility, I- Participatory responsibility)
CodeDescription of Project Management Consultancy’s Roles and Responsibility Matrix @ Industrial Projects
ClientPMCArchitect
A. Pre-construction Stage:
A.1 Analyze Client’s project related requirements I R R
A.2 Prepare the Design Brief in terms of function ability, cost, time, quality and safety R R R
A.3 Develop project control systems I R I
A.4 Finalization of project organization chart. R R I
A.5 Establishment of project communication and reporting system I R I
A.6 Preparation of works breakdown structure I R I
A.7 Preparation of Project Master Schedule with base line I R I
A.8 Preparation of Design / Drawings deliverables schedule I R I
A.9 Feedback on the Master Budget of the project I R I
A10 Co-ordination and follow-up with Architect and other design consultants for their inputs I R I
A.11 To identify and suggest consultants/designers for specialized requirements I R I
A.12 Lead project meetings as necessary for review of progress I R I
A.13 To set up ,track, monitor a design deliverable schedule I R I
A.14 Checking & verification of designer’s submissions (design basis reports, value engineering, cost benefit
analysis, drawings etc)
I R I
A.15 Cost control during all stages of design and design development R R I
A.16 Preparation of procurement plan R R I
A.17 Review of technical specifications and Bill of Quantities (BOQ) I R R
A.18 Monitoring the statutory approvals process by follow-ups with liaison consultants and reporting the progress. R R R
A.19 Conducting Pre-bid meetings and feedback for completeness of tender specifications and technical
parameters.
R R I
A.20 comparative statements & techno-commercial evaluation reports R R I
A.21 Submitting Weekly and Monthly progress reports I R I
B. Construction Stage
B. 1 Full time supervision of All construction works / activities for the project I R I
B.2 On-site design co-ordination and issue of drawings / clarifications I R R
B.3 Organize approval to contractors shop drawings, product data sheets, samples, R R R
B.4 Refinement of works breakdown structure I R I
B.5 Monitoring the progress of work with the Master construction schedule I R I
B.6 Prior flagging of anticipated bottlenecks and analysis of its reasons I R I
B.6 Day to day correspondences including contractual issues I R I
B.7 Change order management for design changes and extra items I R I
B.8 Prepare QA/QC plan and Method Statement I R I
B.9 Quality assurance and control to ensure conformance to drawings and specifications. I R I
B.10 Establish EHS plan (Environment, Health and Safety) I R I
B.11 Issue GFC drawings to respective contractors and keep updated record issued. I R I
B.12 Scrutinize and check working drawings received from Architects /designer I R I
B.13 Organize Progress review meetings on weekly basis. I R I
B.14 Collect, review and maintain all the records of contractors’ daily progress reports. I R I
C. Post-Construction Stage:
C.1 Advice about probable date of Substantial Completion I R I
C.2 Preparing & addressing the schedule of defects / punch lists I R I
C.3 Provide assistance in Testing and commissioning of the facility I R I
C.4 Collection and integration of various O and M manuals, commissioning & test certificates I R I
C.5 Reconciliation and Certification of Final bills of contractors, suppliers, vendors and consultants I R I
C.6 Preparation of project close-out report including learning I R I
C.7 Collate and verify all As-built drawings I R I
C.8 Addressing any queries during defects liability period I R I
C.9 Co-ordination with the Contractors to rectify the defects during the defects liability period, I R I
Role of Project Management Consultancy in Construction Project
www.iosrjournals.org 16 | Page
IV. CASE STUDY:
Project Management Consultancy manages the Mega Industrial Project in Maharashtra, India.
Project land area of 90.00 Acre and proposed Industrial Buildings are 8 No ( 16.50 Lac sqft ) space with
supporting utilities building, other services like fire fighting, etc and whole project is bifurcated in to 3-
Phases with allied infra works as follow :
Table: 2 Overview of Industrial Project
Phase 1:
(Completed and Operational)
• Building B1
• Building B3
• Building B4 (B4A+B4D)
• Building B8
• Electrical Substation- 33
KVA
• Roads, STP, General
Infrastructure
Phase 2:
( Construction in Progress)
• Building B1A-
106,284 Sqft
• Building B5- 162,096
Sqft
• Building B2 - 58,056
Sqft
• PMO, Gatehouse-
12,086+2,968 Sqft
• Roads and
Infrastructure
Phase 3:
( Proposed construction)
• B
uilding B6
• B
uilding B7
4.1 Methodology:
The data of this research was collected from different sources. Literature and theoretical reviews have been
taken from books, articles and papers to describe main concepts about consultant service management in
construction project. The main methods are descriptive, explanatory and quantitative. In description, it starts by
providing information about the current situation on the field of the construction industry. The quantitative works
done by collecting data from field / Site. Also collecting data by some questionnaires from the case study.
Experiences shared by supervisor engineers, managers, in tackling problems at various levels in these projects
put forth during planning stage of a new project helps in over viewing the project and identifying the expected
expert judgments.
4.2 Project Scheduling –Phase-1:
Generally Industrial buildings are constructed and earlier ready in the form of Cold Shell, but it is very
difficult to completely make it 100 % ready for functional use. It is reflected from Table-2 data that the within
9-12 months Industrial building having built area 1.5 Lac (Appr.) Sqft can be completed with a slight delay with
satisfactorily functioning and commission in the presence of PMC. Table 3 gives the schedule actually achieved
for the completion for phase – I.
Table: 3 Project Schedule
Industrial Project- Phase- 1 Activity Building B3 Building B4A Building B4D Building B8
Concept Initiation 03.05.2012 20.01.2012 01.06.2012 28.03.2012
Civil Works 11 Months 06 Months 08 Months 07 Months
Structural Work (Pre-Engineered building) 09 Months 06 Months 07 Months 07 Months
Services 05 Months 03 Months 03 Months 05 Months
Allied Infra 06 Months 04 Months 05 Months 07 Months
Office Bldg. with Interior Works 08 Months 04 Months 07 Months 07 Months
Completion & Handing Over 22.05.2013 20.08.2012 26.03.2013 19.03.2013
Total Duration 12 Months 08 Months 09 Months 12 Months
The proposed project cash flows for the phase- II are shown in fig 01, whereas the projected
manpower requirements are indicated in fig 02. Fig 02 reflects the need for averaging out the resource
allocation, particularly in the period from April-14 to August -14.
Role of Project Management Consultancy in Construction Project
www.iosrjournals.org 17 | Page
4.3 Project Cash Flow –Phase-2
Fig-1 Cash-Flow
4.4 Resource Allocation -Project Total Manpower-Phase-II
Fig-2 Allocation of Total Manpower
4.5 Project Time Line Optimization:
PMC tried to optimize the time factor through various phases, where delays have occurred. These efforts are
mentioned in Table 4.
Table: 4 Time Line Optimization
Design Phase
1. Finalization of Building Elevation and sign off with concept
2. Addendums of Tenant Improvement finalization in early
design stage & sign off on concept & details
3. Incorporation of statutory requirements in design phase
4. Addition of Mezzanine structural works to PEB (pre-
engineered building) scope
5. Linking Building Schedule to Design delivery schedule
6. Finalization of Power requirements of End user
7. Introduction of Precast Waffle wall
Procurement Phase
1. Delinking of PEB (pre-engineered building) & civil package to
concept finalization
2. Linking Procurement schedule to building deliverables
3. Untimely processing per lead delivery of long lead items viz.
Dock leveler, Fire door, HT Cables, etc.
4. Soft copy approvals – Reduction in Hard copies turnaround
time
Construction Phase
1. Milestone linking to individual package delivery timelines, Set
points briefing & acceptance
2. Progress balancing per requirements through work scope
shuffling
3. Progress communication & running catch up plans for delays
4. Lesser turnaround time trough design communication in soft
forms
5. Identification & attention of snags through process
Role of Project Management Consultancy in Construction Project
www.iosrjournals.org 18 | Page
4.6 Project Governance Structure:
Fig-3 Project Governance Structure
1.Respond to escalation from project team
2.Provide guidance & way forward
3.Meet every month
4.Review & respond to escalated items from on site
project team
5.Escalate to senior management
6.Meet every day with PMC project team
7.Review delays, issues/risks with PMC project team
8.Meet every day with on site contractors, suppliers
9.Reports progress highlights ,delays through delay
logs
10.Review risks ,issues and key topics every week
with contractors through weekly review meetings
11.Schedule status review
12.Escalate risks/issues & related recommendations to
CLIENT project team as appropriate
13.Meet every day with team members
14.Review progress issues, review status of specific
areas & ensure common understanding of project
progress
15.Inform & escalate the issues
Project Governance structure is for easy communication through authorities to avoid the conflict and
the further delay. In order to channelize this structure smoothly various lines of actions need to be
implemented such as escalating any issue of contractor to PMC and further firm PMC to client and to the
Project Team. PMC also reports through dash board to higher management of client and provide the
direction to contractor as per feedback received. This is shown in Fig 3.
Table 5 reflects the key challenges faced by the project management consultant whereas, Table 6
indicates the various efforts undertaken by the PMC to overcome these challenges.
Table 5: Key Challenges faced by project management consultant
1. Constructability issues 2. Supply chain risk – material delays
3. Poor quality engineering process runs 4. Inter-Contractor Coordination Issues
5. Activity dependency structure 6. Lack of Safety Awareness & Unsafe work
methods
7. Meteorological limitations
Table 6 efforts done by PMC to overcome the Challenges
Coordination meetings, Services Coordinator right from design
phase
Activity sequencing to reduce idle man hours in Monsoon
Higher management reporting dashboard – issues & achievements
communication
Round table progress reviews, design – construction
interface
Planning sign off & adherence system Daily quality audits, quality diligence & delivery sessions in
team, calibrations & standardizations enforcement
Conversion of RCC to Composite structure – Mezzanine, Package
additions to pre engineered buildings
Safe working methodologies, Safety awareness programs,
Penalty enforcement on defaulters
Project Delivery – Material delivery interface & forecast
communications
V. KNOWLEDGE:
There is no unique solution to what knowledge areas are necessary for managing a project.
Knowledge needs to vary from project to project. Some of the knowledge needed to manage projects is
unique or nearly unique. Project management knowledge areas do overlap with disciplines in General
Management and Technology Management. The Project Management Institute in USA advocates 10
knowledge areas for managing projects in their ‘A guide to the project management body of knowledge –
Fifth Edition-2013. These are also supported by ISO 10006 and renowned project management institutions in
the world. These knowledge areas in construction project management can be broadly grouped as under:
1. Project Integration management
2. Project Scope Management
Role of Project Management Consultancy in Construction Project
www.iosrjournals.org 19 | Page
3. Project Time Management
4. Project Cost Management
5. Project Quality Management
6. Project Human Resource Management
7. Project Communications Management
8. Project Risk Management
9. Project Procurement / Contract Management
10. Project Stake holder Management
5.1 Dealing with the Risks:
Risk identification, proper analysis and scientific mitigation are essential for a successful project.
The PMC’s role as implemented on the project is as shown in Table 7.
Table 7: Role or PMC in dealing with project risk
Risks Identified M
I
T
I
G
A
T
I
O
N
P
L
A
N
a. Sign off on the tenants on all
concept layouts & scope sheets
b. Follow up meetings with A/E
every week
c. Identify long lead items & trace
those well in time
d. Participate & educate team in
training to all new techniques
e. Quality Assurance Plan
implementation
f. Adoptions of recommendations
by Liasioning agencies for future
development & compliances
g. To review the Risks & Issues
on Weekly basis, discuss more often
with client
1.Concept Plan finalization
2.Turnaround time of Design approvals
3.Alignment of scope sheet of tenants with
BOQ’s
4.Procurement system ambiguity
5.Vendors not on board
6.Modifications to Building Elevation
7.Market risks & supply chain factors
8. Adoption of new execution methodology
(Waffle wall, FM II floor etc)
9.Cash flow factors
10.Design errors & omissions
VI. CONCLUSION:
Project Management Consultants manage the Project by application of their Knowledge, Skills, and
Experience at various stages. However PMC has to face various challenges like Design Issues,
Constructability Issues, Long lead material Issues, Inter Contractor Coordination Issues, Engineering Issues,
Safety Issues, etc These issues could be tackled by a well organised approach of the PMC. This also
includes adopting the various types of tools of higher management like Reporting dashboard, Round table
progress Review and conduction of brainstorming sessions, training on various field, design – construction
interface, Daily quality audits, quality diligence & delivery sessions in team.
In addition to above Project Management Consultancy is effective and efficient only when it is involved in Total
Project Life Cycle from Conception to Closeout. Awareness of various Processes involved in Project
Management and detail study of multiple constraints of project like Time-Cost-Risk-Scope-Quality-Resource
are an integral part of any project management consultancy.
ACKNOWLEDGEMENT
The authors would like to thank to M/s client of Mega Industrial Project Pvt Ltd, India & Project Management Consultants for their
support and guidance in completing the research for the case study.
REFERENCES:
[1] Adnan Enshassi1, Sherif Mohamed2, Saleh Abushaban3 Factors affecting the performance of construction projects in Gaza
strips; Journal of civil Engineering and Management 2009, 15(3): 269–280
[2] Cheung, S.-O.; Suen, H. C. H.; Cheung, K. K. W. 2004. PPMS: a Web-based construction project performance monitoring
system, Automation in Construction 13: 361–376. doi:10.1016/j.autcon.2003.12.001.
[3] Project Management Institute, Inc. (2013): A Guide to Project Management Body of Knowledge, (PMBOK) Fifth Edition, Project
Management Institute, Inc. Pennsylvania 19073-3299 USA
[4] Bernard, W. T. (1985). Construction and Development. Selangor, Pelanduk Publication.
[5] K K Chitkara,(2000): Construction Project Management, Second Edition, Tata McGraw Hill Pvt Ltd. New Delhi.
[6] O P Khanna (1999): Industrial Engineering and Management Revised Edition, Dhanpat Rai Publications, New Delhi.
[7] P K Joy,(1994) : Total Project Management, Second Edition, Macmillan India Limited. New Delhi.
[8] Foxhall, W. (1976). Professional construction Management and project administration. New York: Architectural Record and the
American Institute of Architects.

Weitere ähnliche Inhalte

Was ist angesagt?

Construction process
Construction processConstruction process
Construction process
Mazen Al-Qadi
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction Project
Dr. Amarjeet Singh
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
shillier38
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 

Was ist angesagt? (20)

Contract management
Contract managementContract management
Contract management
 
Construction process
Construction processConstruction process
Construction process
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
 
Understanding The role of The Consultant
Understanding The role of The ConsultantUnderstanding The role of The Consultant
Understanding The role of The Consultant
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction Project
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Tender & bidding in construction projects
Tender  & bidding in construction projectsTender  & bidding in construction projects
Tender & bidding in construction projects
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk management
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.ppt
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management ppt
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in Construction
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 

Andere mochten auch

Andere mochten auch (20)

W01226143147
W01226143147W01226143147
W01226143147
 
C012541523
C012541523C012541523
C012541523
 
C010411218
C010411218C010411218
C010411218
 
F017253244
F017253244F017253244
F017253244
 
M012147074
M012147074M012147074
M012147074
 
Friction Stir Welding of steels: AReview Paper
Friction Stir Welding of steels: AReview PaperFriction Stir Welding of steels: AReview Paper
Friction Stir Welding of steels: AReview Paper
 
Characteristics analysis of silicon carbide based 1-D Photonic crystal with 2...
Characteristics analysis of silicon carbide based 1-D Photonic crystal with 2...Characteristics analysis of silicon carbide based 1-D Photonic crystal with 2...
Characteristics analysis of silicon carbide based 1-D Photonic crystal with 2...
 
Performance Analysis and Comparative Study of Cognitive Radio Spectrum Sensin...
Performance Analysis and Comparative Study of Cognitive Radio Spectrum Sensin...Performance Analysis and Comparative Study of Cognitive Radio Spectrum Sensin...
Performance Analysis and Comparative Study of Cognitive Radio Spectrum Sensin...
 
B1802021823
B1802021823B1802021823
B1802021823
 
Speech Recognized Automation System Using Speaker Identification through Wire...
Speech Recognized Automation System Using Speaker Identification through Wire...Speech Recognized Automation System Using Speaker Identification through Wire...
Speech Recognized Automation System Using Speaker Identification through Wire...
 
I010346366
I010346366I010346366
I010346366
 
Importance of Development of Quality Checklists
Importance of Development of Quality ChecklistsImportance of Development of Quality Checklists
Importance of Development of Quality Checklists
 
F017663344
F017663344F017663344
F017663344
 
I017525560
I017525560I017525560
I017525560
 
B1102010712
B1102010712B1102010712
B1102010712
 
R01232147152
R01232147152R01232147152
R01232147152
 
I017134347
I017134347I017134347
I017134347
 
A012470128
A012470128A012470128
A012470128
 
H017365863
H017365863H017365863
H017365863
 
I017355767
I017355767I017355767
I017355767
 

Ähnlich wie Role of Project Management Consultancy in Construction Project

Royce_Brown Resume-82115
Royce_Brown Resume-82115Royce_Brown Resume-82115
Royce_Brown Resume-82115
Royce Brown
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
Muhammad Daniyal
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
pisal3
 
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_ManagementPMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
Murari Thayi, PgMP, PMP
 
Updated CV of MUSA ELSHEIKH
Updated CV of MUSA ELSHEIKHUpdated CV of MUSA ELSHEIKH
Updated CV of MUSA ELSHEIKH
Musa Elsheikh
 

Ähnlich wie Role of Project Management Consultancy in Construction Project (20)

Architect as a project manager
Architect as a project managerArchitect as a project manager
Architect as a project manager
 
CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015
 
4
44
4
 
Q130302108111
Q130302108111Q130302108111
Q130302108111
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
Application of BIM
Application of BIMApplication of BIM
Application of BIM
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 
Role of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case StudyRole of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case Study
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
H1303055462
H1303055462H1303055462
H1303055462
 
Royce_Brown Resume-82115
Royce_Brown Resume-82115Royce_Brown Resume-82115
Royce_Brown Resume-82115
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
 
7 Design Phases in Architectural Design Process
7 Design Phases in Architectural Design Process7 Design Phases in Architectural Design Process
7 Design Phases in Architectural Design Process
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
Primavera trainer
Primavera trainerPrimavera trainer
Primavera trainer
 
Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01
 
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_ManagementPMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
 
Updated CV of MUSA ELSHEIKH
Updated CV of MUSA ELSHEIKHUpdated CV of MUSA ELSHEIKH
Updated CV of MUSA ELSHEIKH
 

Mehr von IOSR Journals

Mehr von IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Kürzlich hochgeladen

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 

Kürzlich hochgeladen (20)

Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 

Role of Project Management Consultancy in Construction Project

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 10, Issue 6 (Jan. 2014), PP 14-19 www.iosrjournals.org www.iosrjournals.org 14 | Page Role of Project Management Consultancy in Construction Project Atul R Nikumbh1 , Dr. S.S. Pimplikar2 1 Post graduate student, 2 Prof & Head of Dept. of Civil Engineering, 2 MAEER’S Maharashtra Institute of Technology, Pune university, India. Abstract : The construction industry generally deals with the various types of construction sectors viz Real Estate & Infrastructure. Real Estate Sector is segmented in Residential, Industrial, Corporate, and Commercial. Whereas Infrastructure sector in Roads, Railways, Urban Infrastructures, Ports, Airports and Power. To manage such kind of unique projects requires an expertise with organizations and a thorough body of knowledge. The purpose of this paper is to provide the analysis or breakdown of Role of Project Management Consultancy and study the Problems faced by PMC for implementing the project. Project Management Consultancy plays multifaceted part in such projects and provides the services from inception to completion of projects. At every stage of project life cycle, the principles of pro-activeness and creating the win-win situation is necessary keeping in mind the customer / client’s requirements. Use of Project Management Consultancy (PMC) offers one of the effective management solution to increase and improve the efficiency and outcome of a project in construction. A case study of construction of a Mega Industrial Project which is dealt by PMC and Project consist of various type of buildings for Manufacturing unit, Assembling unit , Logistic unit , Process unit with allied Infra of Electrical utilities, Services like Fire fighting, Sewage line, Storm water arrangement and Road etc have been considered for this research work. Keywords: Body of Knowledge, Industrial Buildings, Project Management Consultancy (PMC), Role & Responsibility Matrix. I. INTRODUCTION The Project Management Consultancy has a wide variety of roles to play during the construction process. Construction project gives benefits to the Customer / Client in terms of satisfaction and it consists of business development, profit, resources utilization, etc. Because of this consultancy plays a multifaceted part in the construction project, and is usually involved in the project from the project’s inception to its completion. It is important to fully understand Project Management Consultancy and authority. Doing so ensures that the Consultancy can be fully maximized on each construction project. Normally the job is managed by the Project Manager and supervised by the Construction Manager, and allied team of design engineer, construction engineer or project architect. Efficiency in Management is needed to gain a higher level in competitiveness. Every construction project is different i.e. unique, every construction project demands the full attention, professionalism and energy of its project team, every construction project depends upon an experienced leader to make it happen. The construction industry in India has grown very fast with the construction of new projects. Due to the rapid expansion in the construction industry, the services provided by the Consultancy need to be improved in terms of performance and quality of work to meet the construction project goals and objective and also the clients satisfaction. Paper highlights the case study for research of dealing the Mega Industrial Projects by PMC through their role and responsibility during project life cycle from Project Initiation Phase and A/E Selection - Schematic Design Phase- Design Development Phase- Construction Documents Phase- Bidding and Award Phase- Construction Phase - Closeout. In all phases PMC manage the project by various services like Scheduling, Cost budgeting, Value engineering, Risk Identifying, Monitoring & controlling, Time line optimization, Resources Allocations, etc. II. NEED FOR CONSULTANCY : 1. Shortage of specialized staff with the Industry since at present the supervisory staff conversant with latest construction technique is not available in bulk. 2. Also, in general, there is a shortage of supervisors who can be associated with a single project. 3. Faster execution of projects in short time. III. PMC ROLES AND RESPONSIBILITY MATRIX: There is no specific definition of project consultant. Most definitions describe management consultants by their roles and responsibility and services that they provide using tools and skills they have in delivering a task assigned by the client or the owner of the project (Dzulkarnaen, 2005).
  • 2. Role of Project Management Consultancy in Construction Project www.iosrjournals.org 15 | Page Project is a Temporary endeavor with a specific beginning and end (i.e. has limited life) and creates a unique product, service or result (i.e. each project by definition is unique). Project management is the art of directing and coordinating human and material resources throughout the life of a project by using modem management techniques to achieve pre-determined objectives of scope, cost, time, quality and participation satisfaction. Consultation is happening if the clients seek expert knowledge or some opinions on some engineering problems or anything that involves engineering matters. Consultation maybe brief or extended which involves only few hours of time, with the clients sitting across the desk of the consultant. Other consultation may require traveling, some period of substantial portion of a consultant’s time over a period of several months, and repeated presentations and discussions with the client (Maxwell, 1982). Table 1 shows the roles and responsibility matrix for the various stakeholders of the project at different stages of construction. Table: 1 Roles and Responsibility Matrix (R- Responsibility, I- Participatory responsibility) CodeDescription of Project Management Consultancy’s Roles and Responsibility Matrix @ Industrial Projects ClientPMCArchitect A. Pre-construction Stage: A.1 Analyze Client’s project related requirements I R R A.2 Prepare the Design Brief in terms of function ability, cost, time, quality and safety R R R A.3 Develop project control systems I R I A.4 Finalization of project organization chart. R R I A.5 Establishment of project communication and reporting system I R I A.6 Preparation of works breakdown structure I R I A.7 Preparation of Project Master Schedule with base line I R I A.8 Preparation of Design / Drawings deliverables schedule I R I A.9 Feedback on the Master Budget of the project I R I A10 Co-ordination and follow-up with Architect and other design consultants for their inputs I R I A.11 To identify and suggest consultants/designers for specialized requirements I R I A.12 Lead project meetings as necessary for review of progress I R I A.13 To set up ,track, monitor a design deliverable schedule I R I A.14 Checking & verification of designer’s submissions (design basis reports, value engineering, cost benefit analysis, drawings etc) I R I A.15 Cost control during all stages of design and design development R R I A.16 Preparation of procurement plan R R I A.17 Review of technical specifications and Bill of Quantities (BOQ) I R R A.18 Monitoring the statutory approvals process by follow-ups with liaison consultants and reporting the progress. R R R A.19 Conducting Pre-bid meetings and feedback for completeness of tender specifications and technical parameters. R R I A.20 comparative statements & techno-commercial evaluation reports R R I A.21 Submitting Weekly and Monthly progress reports I R I B. Construction Stage B. 1 Full time supervision of All construction works / activities for the project I R I B.2 On-site design co-ordination and issue of drawings / clarifications I R R B.3 Organize approval to contractors shop drawings, product data sheets, samples, R R R B.4 Refinement of works breakdown structure I R I B.5 Monitoring the progress of work with the Master construction schedule I R I B.6 Prior flagging of anticipated bottlenecks and analysis of its reasons I R I B.6 Day to day correspondences including contractual issues I R I B.7 Change order management for design changes and extra items I R I B.8 Prepare QA/QC plan and Method Statement I R I B.9 Quality assurance and control to ensure conformance to drawings and specifications. I R I B.10 Establish EHS plan (Environment, Health and Safety) I R I B.11 Issue GFC drawings to respective contractors and keep updated record issued. I R I B.12 Scrutinize and check working drawings received from Architects /designer I R I B.13 Organize Progress review meetings on weekly basis. I R I B.14 Collect, review and maintain all the records of contractors’ daily progress reports. I R I C. Post-Construction Stage: C.1 Advice about probable date of Substantial Completion I R I C.2 Preparing & addressing the schedule of defects / punch lists I R I C.3 Provide assistance in Testing and commissioning of the facility I R I C.4 Collection and integration of various O and M manuals, commissioning & test certificates I R I C.5 Reconciliation and Certification of Final bills of contractors, suppliers, vendors and consultants I R I C.6 Preparation of project close-out report including learning I R I C.7 Collate and verify all As-built drawings I R I C.8 Addressing any queries during defects liability period I R I C.9 Co-ordination with the Contractors to rectify the defects during the defects liability period, I R I
  • 3. Role of Project Management Consultancy in Construction Project www.iosrjournals.org 16 | Page IV. CASE STUDY: Project Management Consultancy manages the Mega Industrial Project in Maharashtra, India. Project land area of 90.00 Acre and proposed Industrial Buildings are 8 No ( 16.50 Lac sqft ) space with supporting utilities building, other services like fire fighting, etc and whole project is bifurcated in to 3- Phases with allied infra works as follow : Table: 2 Overview of Industrial Project Phase 1: (Completed and Operational) • Building B1 • Building B3 • Building B4 (B4A+B4D) • Building B8 • Electrical Substation- 33 KVA • Roads, STP, General Infrastructure Phase 2: ( Construction in Progress) • Building B1A- 106,284 Sqft • Building B5- 162,096 Sqft • Building B2 - 58,056 Sqft • PMO, Gatehouse- 12,086+2,968 Sqft • Roads and Infrastructure Phase 3: ( Proposed construction) • B uilding B6 • B uilding B7 4.1 Methodology: The data of this research was collected from different sources. Literature and theoretical reviews have been taken from books, articles and papers to describe main concepts about consultant service management in construction project. The main methods are descriptive, explanatory and quantitative. In description, it starts by providing information about the current situation on the field of the construction industry. The quantitative works done by collecting data from field / Site. Also collecting data by some questionnaires from the case study. Experiences shared by supervisor engineers, managers, in tackling problems at various levels in these projects put forth during planning stage of a new project helps in over viewing the project and identifying the expected expert judgments. 4.2 Project Scheduling –Phase-1: Generally Industrial buildings are constructed and earlier ready in the form of Cold Shell, but it is very difficult to completely make it 100 % ready for functional use. It is reflected from Table-2 data that the within 9-12 months Industrial building having built area 1.5 Lac (Appr.) Sqft can be completed with a slight delay with satisfactorily functioning and commission in the presence of PMC. Table 3 gives the schedule actually achieved for the completion for phase – I. Table: 3 Project Schedule Industrial Project- Phase- 1 Activity Building B3 Building B4A Building B4D Building B8 Concept Initiation 03.05.2012 20.01.2012 01.06.2012 28.03.2012 Civil Works 11 Months 06 Months 08 Months 07 Months Structural Work (Pre-Engineered building) 09 Months 06 Months 07 Months 07 Months Services 05 Months 03 Months 03 Months 05 Months Allied Infra 06 Months 04 Months 05 Months 07 Months Office Bldg. with Interior Works 08 Months 04 Months 07 Months 07 Months Completion & Handing Over 22.05.2013 20.08.2012 26.03.2013 19.03.2013 Total Duration 12 Months 08 Months 09 Months 12 Months The proposed project cash flows for the phase- II are shown in fig 01, whereas the projected manpower requirements are indicated in fig 02. Fig 02 reflects the need for averaging out the resource allocation, particularly in the period from April-14 to August -14.
  • 4. Role of Project Management Consultancy in Construction Project www.iosrjournals.org 17 | Page 4.3 Project Cash Flow –Phase-2 Fig-1 Cash-Flow 4.4 Resource Allocation -Project Total Manpower-Phase-II Fig-2 Allocation of Total Manpower 4.5 Project Time Line Optimization: PMC tried to optimize the time factor through various phases, where delays have occurred. These efforts are mentioned in Table 4. Table: 4 Time Line Optimization Design Phase 1. Finalization of Building Elevation and sign off with concept 2. Addendums of Tenant Improvement finalization in early design stage & sign off on concept & details 3. Incorporation of statutory requirements in design phase 4. Addition of Mezzanine structural works to PEB (pre- engineered building) scope 5. Linking Building Schedule to Design delivery schedule 6. Finalization of Power requirements of End user 7. Introduction of Precast Waffle wall Procurement Phase 1. Delinking of PEB (pre-engineered building) & civil package to concept finalization 2. Linking Procurement schedule to building deliverables 3. Untimely processing per lead delivery of long lead items viz. Dock leveler, Fire door, HT Cables, etc. 4. Soft copy approvals – Reduction in Hard copies turnaround time Construction Phase 1. Milestone linking to individual package delivery timelines, Set points briefing & acceptance 2. Progress balancing per requirements through work scope shuffling 3. Progress communication & running catch up plans for delays 4. Lesser turnaround time trough design communication in soft forms 5. Identification & attention of snags through process
  • 5. Role of Project Management Consultancy in Construction Project www.iosrjournals.org 18 | Page 4.6 Project Governance Structure: Fig-3 Project Governance Structure 1.Respond to escalation from project team 2.Provide guidance & way forward 3.Meet every month 4.Review & respond to escalated items from on site project team 5.Escalate to senior management 6.Meet every day with PMC project team 7.Review delays, issues/risks with PMC project team 8.Meet every day with on site contractors, suppliers 9.Reports progress highlights ,delays through delay logs 10.Review risks ,issues and key topics every week with contractors through weekly review meetings 11.Schedule status review 12.Escalate risks/issues & related recommendations to CLIENT project team as appropriate 13.Meet every day with team members 14.Review progress issues, review status of specific areas & ensure common understanding of project progress 15.Inform & escalate the issues Project Governance structure is for easy communication through authorities to avoid the conflict and the further delay. In order to channelize this structure smoothly various lines of actions need to be implemented such as escalating any issue of contractor to PMC and further firm PMC to client and to the Project Team. PMC also reports through dash board to higher management of client and provide the direction to contractor as per feedback received. This is shown in Fig 3. Table 5 reflects the key challenges faced by the project management consultant whereas, Table 6 indicates the various efforts undertaken by the PMC to overcome these challenges. Table 5: Key Challenges faced by project management consultant 1. Constructability issues 2. Supply chain risk – material delays 3. Poor quality engineering process runs 4. Inter-Contractor Coordination Issues 5. Activity dependency structure 6. Lack of Safety Awareness & Unsafe work methods 7. Meteorological limitations Table 6 efforts done by PMC to overcome the Challenges Coordination meetings, Services Coordinator right from design phase Activity sequencing to reduce idle man hours in Monsoon Higher management reporting dashboard – issues & achievements communication Round table progress reviews, design – construction interface Planning sign off & adherence system Daily quality audits, quality diligence & delivery sessions in team, calibrations & standardizations enforcement Conversion of RCC to Composite structure – Mezzanine, Package additions to pre engineered buildings Safe working methodologies, Safety awareness programs, Penalty enforcement on defaulters Project Delivery – Material delivery interface & forecast communications V. KNOWLEDGE: There is no unique solution to what knowledge areas are necessary for managing a project. Knowledge needs to vary from project to project. Some of the knowledge needed to manage projects is unique or nearly unique. Project management knowledge areas do overlap with disciplines in General Management and Technology Management. The Project Management Institute in USA advocates 10 knowledge areas for managing projects in their ‘A guide to the project management body of knowledge – Fifth Edition-2013. These are also supported by ISO 10006 and renowned project management institutions in the world. These knowledge areas in construction project management can be broadly grouped as under: 1. Project Integration management 2. Project Scope Management
  • 6. Role of Project Management Consultancy in Construction Project www.iosrjournals.org 19 | Page 3. Project Time Management 4. Project Cost Management 5. Project Quality Management 6. Project Human Resource Management 7. Project Communications Management 8. Project Risk Management 9. Project Procurement / Contract Management 10. Project Stake holder Management 5.1 Dealing with the Risks: Risk identification, proper analysis and scientific mitigation are essential for a successful project. The PMC’s role as implemented on the project is as shown in Table 7. Table 7: Role or PMC in dealing with project risk Risks Identified M I T I G A T I O N P L A N a. Sign off on the tenants on all concept layouts & scope sheets b. Follow up meetings with A/E every week c. Identify long lead items & trace those well in time d. Participate & educate team in training to all new techniques e. Quality Assurance Plan implementation f. Adoptions of recommendations by Liasioning agencies for future development & compliances g. To review the Risks & Issues on Weekly basis, discuss more often with client 1.Concept Plan finalization 2.Turnaround time of Design approvals 3.Alignment of scope sheet of tenants with BOQ’s 4.Procurement system ambiguity 5.Vendors not on board 6.Modifications to Building Elevation 7.Market risks & supply chain factors 8. Adoption of new execution methodology (Waffle wall, FM II floor etc) 9.Cash flow factors 10.Design errors & omissions VI. CONCLUSION: Project Management Consultants manage the Project by application of their Knowledge, Skills, and Experience at various stages. However PMC has to face various challenges like Design Issues, Constructability Issues, Long lead material Issues, Inter Contractor Coordination Issues, Engineering Issues, Safety Issues, etc These issues could be tackled by a well organised approach of the PMC. This also includes adopting the various types of tools of higher management like Reporting dashboard, Round table progress Review and conduction of brainstorming sessions, training on various field, design – construction interface, Daily quality audits, quality diligence & delivery sessions in team. In addition to above Project Management Consultancy is effective and efficient only when it is involved in Total Project Life Cycle from Conception to Closeout. Awareness of various Processes involved in Project Management and detail study of multiple constraints of project like Time-Cost-Risk-Scope-Quality-Resource are an integral part of any project management consultancy. ACKNOWLEDGEMENT The authors would like to thank to M/s client of Mega Industrial Project Pvt Ltd, India & Project Management Consultants for their support and guidance in completing the research for the case study. REFERENCES: [1] Adnan Enshassi1, Sherif Mohamed2, Saleh Abushaban3 Factors affecting the performance of construction projects in Gaza strips; Journal of civil Engineering and Management 2009, 15(3): 269–280 [2] Cheung, S.-O.; Suen, H. C. H.; Cheung, K. K. W. 2004. PPMS: a Web-based construction project performance monitoring system, Automation in Construction 13: 361–376. doi:10.1016/j.autcon.2003.12.001. [3] Project Management Institute, Inc. (2013): A Guide to Project Management Body of Knowledge, (PMBOK) Fifth Edition, Project Management Institute, Inc. Pennsylvania 19073-3299 USA [4] Bernard, W. T. (1985). Construction and Development. Selangor, Pelanduk Publication. [5] K K Chitkara,(2000): Construction Project Management, Second Edition, Tata McGraw Hill Pvt Ltd. New Delhi. [6] O P Khanna (1999): Industrial Engineering and Management Revised Edition, Dhanpat Rai Publications, New Delhi. [7] P K Joy,(1994) : Total Project Management, Second Edition, Macmillan India Limited. New Delhi. [8] Foxhall, W. (1976). Professional construction Management and project administration. New York: Architectural Record and the American Institute of Architects.