SlideShare ist ein Scribd-Unternehmen logo
1 von 64
PROJECT TIME MANAGEMENT
Lecture 5 & 6
PROJECT TIME MANAGEMENT
Content of Presentation
 PMI approach of Time Management
 WBS/ Activity Definition
 Estimation
o [Purpose of Estimation
o Factors influencing Estimates
o Methods of Estimation
o Problems in Estimation
o Accuracy in Estimation
o Importance of Accurate Estimates
 Scheduling (Planning and Scheduling)
o Objectives
o Techniques
o Critical Path Method (CPM)
 Basic Definition of CPM
 Activity
 Activity Duration
 Network Construction
 Example 1
o Histogram
 Resource Histogram
 Constructing Resource histogram
o Procedure for Resource Leveling
o PERT
o Example
 Use of software for planning,
scheduling & control of projects
o Process overview
o Software application
o EVMS
PROJECT TIME MANAGEMENT
6.1 ACTIVITY DEFINITION
1. Inputs
1. Enterprise
environmental factors .
2. Organizational process
assets
3. Project scope statement
4. Work Breakdown
structure
5. WBS Dictionary
6. Project management
plan
2. Tools and Techniques
1. Decomposition
2. Templates
3. Rolling wave planning
4. Expert judgment
5. Planning component
3. Outputs
1. Activity list
2. Activity attributes
3. Milestone list
4. Requested changes
6.2 ACTIVITY SEQUENCING
1. Inputs
.1 Project scope statement
.2 Activity list
.3 Activity attributes
.4 Milestone List
.5 Approved change requests
2 . Tools and Techniques
.1 Precedence Diagramming
Method (PDM)
.2 Arrow Diagramming
Method (ADM)
.3 Schedule network
templates
.4 Dependency determination
.5 Applying leads and lags
3. Outputs
.1 Project schedule network
diagrams
.2 Activity list (updates)
.3 Activity attributes
(updates)
.4 Requested changes
6.3 ACTIVITY RESOURCE
ESTIMATING
1. Inputs
.1 Enterprise environmental
factors
.2 Organizational process assets
.3 Activity list
.4 Activity attributes
.5 Resource availability
.6 Project management plan
2. Tools and Techniques
.1 Expert judgment
.2 Alternatives analysis
.3 Published estimating data
.4 Project management software
.5 bottom-up-estimating
3. Outputs
.1 Activity resource requirements
.2 Activity attributes (updates)
.3 Resource breakdown
structure
.4 Resource calendars (updates)
.5 Requested changes
Continue on
next slide
PMI Approach of Project Time Management (Cont..)
PMI Approach of Project Time Management (Cont..)
PROJECT TINE MANAGEMENT
6.4 ACTIVITY DURATION
ESTIMATING
1. Inputs
.1 Enterprise environmental
factors
.2 Organizational process assets
.3 Project scope statement
.4 Activity list
.5 Activity attributes
.6 Activity resource requirements
.7 Resource calendars
.8 Project Management plan
. Risk register
. Activity cost estimates
2. Tools and Techniques
.1 Expert judgment
.2 Analogous estimating
.3 Parametric estimating
.4 Three-point estimating
.5 Reserve analysis
3. Outputs
.1 Activity duration estimates
.2 Activity attributes (updates)
6.5 SCHEDULE DEVELOPMENT
1. Inputs
.1 Organizational process assets
.2 Project scope statement
.3 Activity list
.4 Activity attributes
.5 Project schedule network diagrams
.6 Activity resource requirements
.7 Resource calendars
.8 Activity duration estimates
.9 Project management plan
. Risk register
2. Tools and Techniques
.1 Schedule network analysis
.2 Critical path method
.3 Schedule compression
.4 What-if scenario analysis
.5 Resource leveling
.6 Critical chain method
.7 Project management software
.8 Applying calendars
.9 Adjusting leads & lags
10. Schedule model
3. Outputs
.1 Project schedule
.2 Schedule model data
.3 Schedule baseline
.4 resource requirements (Updates)
.5 Activity attributes (updates)
.6 Project calendars (updates)
.7 Requested changes
.8 Project management plan (updates)
. Schedule management plan (updates)
6.6 SCHEDULE CONTROL
1. Inputs
.1 Schedule management plan
.2 Schedule baseline
.3 Performance report
.4 Approved change request
2. Tools and Techniques
.1 Progress reporting
.2 Schedule change control
system
.3 Performance measurement
.4 Project management
software
.5 Variance analysis
.6 Schedule comparison bar
charts
3. Outputs
.1 Schedule model data
(updates)
.2 Schedule baseline (updates)
.3 Performance measurements
.4 Requested changes
.5 Recommended corrective
actions
.6 Organizational process
assets (updates)
.7 Activity list (updates)
.8 Activity attributes (updates)
.9 Project management plan
(updates)
Continue on
Previous slide
WORK BREAKDOWN
STRUCTURE (WBS)
PROJECT TIME MANAGEMENT
WORK BREAKDOWN STRUCTURE
(WBS)
 A WBS is “a hierarchical system that represents the
project in increasing levels of detail to define,
organise, and display the project work in measurable
and manageable components”.
 A WBS is a deliverable-oriented grouping of the work
involved in a project that defines the total scope of
the project
 WBS is a preliminary document that provides the
basis for planning and managing project schedules,
costs and resources
 Decomposition is subdividing project deliverables
into smaller pieces
 A work package is a task at the lowest level of the
WORK BREAKDOWN STRUCTURE
(WBS)
 The WBS consists of different
levels where level one is the least
detailed level often representing
the entire project. The number of
activities in the WBS grows quite
rapidly and it is not unusual that a
large construction project is
broken down into several
hundreds of activities. There is no
specific rule about which level of
detail a WBS should have but a
low level of detail may result in
insufficient detail for effective
planning, whereas a too high level
of detail may become
unmanageable and increase
planning costs. It is generally the
case that the WBS is poorly
detailed rather than too detailed.
According to Jackson (2004) the
level of detail should correlate with
the control level desired, i.e. to
have enough activities and just the
A proposed WBS for an infrastructure project (multi-storey building project).
Roles Played by the WBS
 Lays out the scope of project work
 All project tasks must be accounted
 Provides the foundation of all project estimates
 Times, costs, resource requirements, etc.
 Helps with the project’s organizational structure
 How tasks relate to one another, authority structure,
etc.
Roles Played by the WBS
9
ACTIVITY CODING
 The following procedure shall be adopted in
assigning ID to an activity let us take an example
of Procurement and take the values from the
above tables then to develop id for activity .
 Project - Nil
 Phases/Departments - P
 Sub Phases - F
 Area - 01
o Equipment - TK
• Discipline / Stages - O
 Then by combining all above we get the id as
• Activity No.1 - PF01TKO001
• Activity No. 2 - PF01TKX001
SAMPLE INTRANET WBS ORGANIZED BY
PHASE
13
INTRANET WBS IN TABULAR
FORM
14
1.0 Concept
1.1 Evaluate current systems
1.2 Define Requirements
1.2.1 Define user requirements
1.2.2 Define content requirements
1.2.3 Define system requirements
1.2.4 Define server owner requirements
1.3 Define specific functionality
1.4 Define risks and risk management approach
1.5 Develop project plan
1.6 Brief Web development team
2.0 Web Site Design
3.0 Web Site Development
4.0 Roll Out
5.0 Support
INTRANET WBS AND GANTT CHART IN
MICROSOFT PROJECT
15
WBS: The Compliance Project
Compliance
Project
1.0 Administration 4.0 Medical Care2.0 Physical
Therapy
3.0 Food /
Nutrition
3.1 Review State
Inspection Report
3.2 Review State
Compliance
Standards
3.3 Develop
Policies and
Procedures for
State
Compliance
3.4 Implement
Evaluation and
Correction
Procedures for
All Areas
3.3.2 Develop
Maintenance SOPs
3.3.1 Develop
Corrective
Procedures
3.3.2.1 Planning
3.3.2.2 Preparation
3.3.2.3 Delivery
1.1 Review State
Inspection Report
1.2 Review State
Compliance
Standards
1.3 Develop
Policies and
Procedures for
State
Compliance
1.4 Implement
Evaluation and
Correction
Procedures for
All Areas
1.3.2 Develop
Maintenance SOPs :
1.3.1 Develop
Corrective
Procedures:
1.3.2.1 Planning
1.3.2.2 Financial
1.3.2.3
Supervision
ESTIMATION
PROJECT TIME MANAGEMENT
ESTIMATION
 An estimate is a calculation of the quantities of various
items of work, and the expenses likely to be incurred there
on. The total of these probable expenses to be incurred on
the work is known as estimated cost of the work.
 The estimated cost of a work is a close approximation of its
actual cost. The agreement of the estimated cost with the
actual cost will depend on accurate use of estimating
methods and correct visualization of the work.
Importance of correct estimating is obvious.
 Estimating is the most important of the practical aspects of
Project Management. It is a comparatively simple subject
to understand; however, as it brings one up against
practical work, methods and procedure, knowledge of it
PURPOSE OF ESTIMATING
1. Estimating Materials
From the estimate of a work it is possible to determine the
quantity of materials required to complete work as per scope of
project and WBS.
2. Estimating Labor
The quantity and type of workers (man hours) of different
categories required to complete the work in the specified time.
3. Estimating Cost
An estimate is necessary to give an accurate idea of the cost of
work as per scope and WBS.
4. Estimating Time
It enables to estimate the time required to complete an item of
work or the work as a whole as per scope and WBS. Time
estimates are used in scheduling work, assigning resources
and determining delivery dates..
Estimation of cost, materials, labor and time is immensely
PROBLEMS IN ESTIMATION
a) There is no established project estimation process.
b) Inaccurate data is used, or historical data may not be
complete.
c) The forecasting techniques and tools are inefficient.
d) There is no ability to track actual project performance,
which can be used to refine estimates.
e) The project planners are inexperienced.
f) Deadlines and Time Constraints
g) Skill and Knowledge of Quantity Surveyor
h) Experience of Estimation
i) Productivity of labor and machinery
IMPORTANCE OF ACCURATE
ESTIMATES
 Inaccurate time estimates can result in inefficient
use of resources and hence impact on project
management.
 Inaccurate estimates can result in insufficient
budget being allocated, or excess budget being
set aside for the project when it could be used
for other projects.
 If the cost or benefits estimates are inaccurate
this can lead to incorrect decisions about
proceeding with the project being made.
WHEN ESTIMATES ARE REQUIRED
Project phase Estimates required
Initiation/Concep
t/
Inception Stage
Time, cost and benefit estimates in
project definition.
Planning Stage Time estimates in project schedule.
Cost estimates in project budget.
Cost and benefit estimates in
business case.
Execution For Project Management, to calculate
the Earned Value, Estimated time to
complete project, Quantities worked
out and billing of contractor.
24
PROJECT PLANNING AND
SCHEDULING
PROJECT TIME MANAGEMENT
PROJECT PLANNING AND
SCHEDULING
 Project Planning:
Process of identifying all the activities necessary to successfully
complete the project is called project planning.
 Project Scheduling:
Process of determining sequential order of planned activities,
assigning realistic duration, to each activity and determining start
and finish dates of each activity is called project scheduling.
Project planning is prerequisite to project scheduling because there
is no way to determine the sequential order of activities until they
are identified. However, the terms planning and scheduling are
often used synonymously because they are performed interactively.
E.g. when some schedule is reviewed, it may be decided that
additional activities may be added or rearranged in order to get the
best schedule of events of projects.
OBJECTIVES OF PROJECT PLANNING &
SCHEDULING
 Finish project on time.
 Continuous (uninterrupted) flow of work.
 Reduced amount of rework.
 Minimize confusion and misunderstanding.
 Increased knowledge of status of project to every
one (including management).
 Knowledge of distribution of costs of project.
 Accountability of people / defined responsibility and
clear understanding of who does what, when and
how much.
 Exploitation and optimum use of resources.
TECHNIQUES FOR PLANNING AND
SCHEDULING
Techniques used for scheduling depends upon the type, size,
complexity, duration, personal and owner requirement. It is
preferred to use a simpler technique which is simple to use and
easily interpreted by all project participants. There are two
general techniques which commonly used for planning and
scheduling.
 Bar Chart (Gantt Chart):
It is the graphical representation of Time (X-axis) and Activities
on Y-axis, so that the status of project may be visualized and
controlled.
 Net work analysis system (CPM and PERT):
It is the schematic representation of various activities. This
method calculates the minimum completion time for a project
along with start and finish time of project activities.
BAR
CHART
 Bar Chart was developed by Henery L. Gantt in 1917, which is the
most common planning tool even now and provided basis for
developing planning and scheduling software.
 Bar Charts are the easiest and most widely used form of scheduling in
project management. Even with other scheduling techniques the
eventual schedule is presented the form of a bar chart. The level of
detail of the activities depends on the intended use of the schedule.
The most commonly used bar chart for engineering works is called
Gantt chart.
 A Gantt chart is a type of bar chart that illustrates a project schedule,
start and finish dates of the terminal elements and summary elements
of civil engineering project. Terminal elements and summary elements
comprise the work breakdown structure of the project. Some Gantt
charts also show the dependency (i.e. precedence network)
relationships between activities. Gantt charts can be used to show
current schedule status using percent-complete shadings.
 Gantt charts have become a common technique for representing the
June
Week 1 Week-2 Week-3 Week-4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Activities
Planning
1
To formalize organizational Risk Management
Plan
Organizati
on
2 Risk Identification
Questionnairs and feedback from Procurement Deptt.
Questionnairs and feedback from Engineering Deptt.
Questionnairs and feedback from PMD Deptt.
Questionnairs and feedback from Contrac Deptt.
Questionnairs and feedback from Finance Deptt.
CRITICAL PATH METHOD (CPM)
The Critical Path Method is a method where activities are arranged
based on interrelationship. It is a planning and control technique that
provides an accurate, timely and easily understood picture of the
project. Its purpose is to allows effective scheduling and controlling,
after the project starts. One of the most important features of CPM is
the logic diagram. The logic diagram graphically portrays the
relationship between project activities.
 Critical path in a network is a longest path in terms of time unit, which
gives minimum overall duration to complete the project.
 CPM calls attention which activities must be completed before other
activities can begun.
A
B
D
F
G
E
C
H
BASIC DEFINITIONS OF CPM TERMS
 Activity:- The performance of a task required to complete the project e.g.
foundation design, contract document, RCC form work, pouring of
concrete.
 Network:- A diagram to represents the relationship of activities to complete
the project.
 Duration:- The estimated time required to perform an activity.
 Early Start (ES):- The earliest time an activity can be start.
 Early Finish (EF):- The earliest time an activity can be finished.
 Late Finish (LF):- The latest time an activity can be finished.
 Late Start (LS):- The latest time an activity can be started without delaying
the completion of project. (LS = LF – D)
 Total Float (TF):- The amount of time an activity may be delayed without
delaying the completion date of project.
Mathematically, TF = LF – EF = LS – ES.
 Critical Activity:- If total float for an activity is zero, activity is called critical
activity.
 Critical path is a longest path in terms of time unit in a network, which
ACTIVITY
A common technique used to understand and organize complex undertaking
is to break the project into smaller pieces. This technique is used both
planning and estimating. Each activity is a discrete task. Activities should be
only be specified as per level of management. The number and detail of
listed quality will vary from job to job and depend on the intended level of
control. Usually for planning purposes activity doesn’t exceed from 25 days,
if exceeds may be divided into further components. The activities must have
four characteristics.
1. Time consumption: An activity must consume time.
2. Use of resources: An activity usually consumes Labour, Material or
Equipment resources.
3. Definite Start and Finish time: An activity represents a definite scope of
work i.e. Starting and Ending point in time.
4. Activities are measurable. The progress towards completion of activity’s
scope of work must be measureable.
ACTIVITY DURATION
 One of the most important steps in planning a project is estimating
the time required to complete each activity. The duration of each
activity is a function of quantity of work and work production rate.
Work production rates are based on planned composition of labor
and equipment used to perform the task. Careless estimates of
production rates may cause un economical use of personnel,
materials, equipment and time.
 When the project bid estimate is prepared, the estimator calculates
the quantity of material that must be put in place and assumes a
production rate to get the cost of each work, which is based
construction method and technique. The bid preparation information
can be served as the tool for calculating g an activity duration.
 All Activities in a schedule should have same unit of time, which may
be in months, weeks, days and hours.
EXAMPLE
In estimating a three storey office building, it was
determined that 480 light fixtures would be installed on
each floor. The production rate of two fixture per man
hour may be used for installation. The company has five
electrician. The normal working day will be 8 hours. What
will be the duration (in days) to install all lights in the
building.SOLUTION:
Production Rate: 2 fixture x 5 electrician = 10 fixtures per man hour
1-man hour
Activity Duration = 480 fixture x 3 floors = 144 hours
10
Activity Duration = 144 hours = 18 day
8 hours
NETWORK CONSTRUCTION
Activity must have a specific duration except the dummy activity, having zero
duration. Each activity is represented as can arrow or node. Arrows are not
drawn according to scale. The brief description about activity is written over
arrow or node. Duration (hours, week, months) to complete that activity is
written under the arrow, where 1 and 2 are the event. Which are written
inside the circles or boxes. The starting event is masked at the tail and finish
event at the head of the arrow.
Rules:
1. Each activity should be represented by a separate arrow.
2. The arrow may be straight or inclined lines.
3. Dummy activity should be represented with dotted lines.
4. Critical path must be shown clearly with double line.
5. Intersection of activity is not allowed.
6. Boxes are provided for event times (ES, EF, LS, LF)
7. EST is some reference time, normally EST = 0 at the start of the project /
work. EFT = EST + Duration.
8. Each activity is followed by a predecessor and successor except start and
finish activities. Any starting activity must have predecessor none, or finish
activity must have no successor.
EXAMPLE 1. CPM
Activity Duration
(days)
Events Preceding
Activity
(Predecessor
)
A 4 1 – 2 None
B 6 2 – 3 A
C 8 2 – 4 A
D 10 3 – 6 B
E 5 3 – 5 B
F 7 4 – 5 C
G 12 6 – 7 D
H 8 5 – 7 E, F
I 3 7 – 8 G,H
1. Construct AOA network
2. Find ES, EF, LS and LF
of all activities
3. Find total float of all
activities (days)
4. Find the project
duration (days)
5. Mark critical path on
the network
EXAMPLE 2. CPM
Activity Duration Predecessor Resourc
e
Early
Start
(ES)
Early
Finish
(EF)
Late
Start
(LS)
Late
Finish
(LF)
Total
Float
(TF)
Remark
O 8 None 10
N 3 O 2
M 13 N 5
L 7 O 15
K 12 O 8
J 3 K 4
I 10 L 3
H 8 L 10
G 6 H,M 8
F 20 I 4
E 16 I 6
D 8 J 4
C 4 G, E 20
B 5 F 6
A 3 B, C,D 3
1. Construct AOA & AON networks
2. Find ES, EF, LS and LF of all
activities
3. Find total float of all activities (days)
4. Find the project duration (days)
5. Mark critical path on the network
EXAMPLE 3. CPM
Activity Duration Predecesso
r
Resourc
e
(ES) (EF) (LS) (LF) (TF) Remark
Q 8 None 5
P 10 Q 6
O 7 Q 10
N 6 O 2
M 9 Q 5
L 5 M 15
K 4 O 8
J 7 L, K 4
I 9 L, K 3
H 20 P 10
G 12 H 8
F 9 N 4
E 20 N 6
D 11 I 4
C 7 E, J 20
B 7 G, F 6
A 3 B, C,D 3
1. Construct AOA network
2. Find ES, EF, LS and LF of all
activities
Find total float of all activities (days)
4. Find the project duration (days)
5. Mark critical path on the network
EXAMPLE 4. CPM
1. Construct AOA network
2. Find ES, EF, LS and LF of all
activities
3. Find total float of all activities (days)
4. Find the project duration (days)
5. Mark critical path on the network
6. Resource Histogram
Solution: Critical Path = Q – P – H – G – B – A, Project Duration = 60 days
2nd Path = Q – O – N – F – B – A, Duration = 40 days
3rd Path = Q – O – N – E – C – A, Duration = 51days
4th Path = Q – O – K – J – C – A, Duration = 36 days
5th Path = Q – O – K – I – D – A, Duration = 42 days
6th Path = Q – M – L – J – C – A, Duration = 39 days
7th Path = Q – O – K – I – D – A, Duration = 45 days
RESOURCE HISTOGRAM
Project Time Management
HISTOGRAM
 A histogram is a graphical data analysis technique for summarizing
the distributional information of a variable. The response variable is
divided into equal sized intervals (or bins). The number of
occurrences of the response variable is calculated for each bin. The
histogram consists of:
 Vertical axis = frequencies or relative frequencies;
 Horizontal axis = response variable (i.e., the mid-point of each
interval).
 Histogram is a summary graph showing a count of data points falling
in various ranges. The histogram displays a single variable in a bar
form to indicate how often some event is likely to occur by showing
the pattern of variation (distribution) of data. A pattern of variation has
three aspects: the center (average), the shape of the curve, and the
width of the curve. Histograms are constructed with variables such
as time, weight, temperature and are not appropriate for attribute
RESOURCE HISTOGRAM
 It is a graphical
representation of time
on X-axis and resources
on Y-axis.
 It is a view of project
data in which resource
requirements, usage,
and availabilities are
shown against a time
scale. The personnel,
equipment, materials,
and services needed to
complete tasks in a
project are resources.
TYPES OF RESOURCE HISTOGRAM
1. Labor Resource Histogram
2. Material Resource Histogram
3. Equipment Resource
Histogram
4. Cost Histogram
In these resource histograms time
is taken on x axis and the resource
is taken on y axis. For a
construction project total resources
are mentioned according to that
particular time these histograms
also help us to calculate cost for a
particular resource of a project at a
particular time because resource
can be converted in terms of cost.
PROCEDURE FOR RESOURCE
LEVELING
1. Plan and Schedule project activities.
2. Construct a Network for the project.
3. Mark Critical Path (CP).
4. Construct the Bar Chart for the Project.
5. For each working day show resources of each activity at
their respective duration on Bar Chart.
6. Sum up the total resources vertically for each working day.
7. Plot the histogram for the resource.
8. Mark the sudden drop or rise in resource histogram.
9. Utilize the total float available for non critical activity to level
the resources by hit & trial method.
10. Recheck the leveled histogram and prepare a new schedule
of work / execution.
Activity Duratio
n
Pred. ES EF LS LF float
A 6 None 0 6 0 6 0
B 20 A 6 26 15 35 9
C 5 A 6 11 6 11 0
D 8 A 6 14 17 25 11
E 10 D 14 24 25 35 11
F 14 C 11 35 11 35 0
G 8 C 11 19 45 53 34
H 12 C 11 23 31 43 20
I 6 B, F 14 20 37 43 23
J 10 E, H 23 33 43 53 20
K 18 G, I, J 35 53 35 53 0
CONSTRUCTING RESOURCE
HISTOGRAM
CONSTRUCTING RESOURCE
HISTOGRAM
PROGRAMME EVALUATION
AND REVIEW TECHNIQUE
(PERT)
Project Time Management
PROGRAMME EVALUATION AND REVIEW
TECHNIQUE (PERT)
 PERT is a management tools process which ensures
accomplishment of a project with in planned schedule and
cost.
 PERT is an inherent planning technique forces the manager to
develop a comprehensive plan and allows realistic scheduling.
The procedure for monitoring, forecasting and simulating
allows the manager to respond quickly to unexpected changes
in the project, detect trouble areas early and evaluate
proposed alternative courses of action. PERT also helps to
evaluate alternatives at any time during projects duration by
looking effect of each change on its completion date. PERT
also helps to simulate the project time & cost and effects
of alternate decisions.
 In other words it can be defined as a planning & Control
techniques that precuts statistical information regarding the
DIFFERENCE BETWEEN PERT AND CPM
CPM PERT
CPM uses one time estimate that
represents the normal time.
PERT uses three time estimates (optimistic, most
likely, and pessimistic) to derive an expected time.
CPM is deterministic in nature. PERT is probabilistic in nature,
CPM is used for those projects where
percent complete can be determined with
reasonable accuracy such as construction.
PERT is used for R&D, where percent complete is
almost impossible to determine except a completed
milestones.
CPM is activity oriented and can be used as
an arrow diagram network.
PERT is event oriented rather than activity oriented
and can be used as an arrow diagram network.
CPM as a controlling device for the simple
reason that one must repeat the entire
evaluation of the project each time the
changes are introduced into the network
PERT serves a useful control device as it assist the
management in controlling a project by calling
attention through constant review to such delays in
activities which might lead to a delay in the project
completion date.
Cannot be used for risk analysis and
management
Can be used for risk analysis and management
CPM Gives Critical Path PERT gives probability in % to achieve critical path
May be used successfully for projects
without uncertainties and risks
May be used successfully for projects with
uncertainties and risks
a) Draw net work for PERT
b) Find Expected Time “te” for all
activities and “TE “
c) Find Variance “σ2” for all activities
d) Find “Z” value, when Ts= 40 days
e) Find the scheduled duration (Ts)
for project completion with 80%
probability
EXAMPLE: PERTActivit
y
Duration Pre
d.
Expected
Time
Varian
ce
O M P te σ2
A 4 8 15 Nil
B 8 10 20 Nil
C 11 12 15 Nil
D 13 15 20 C
E 2 3 4 B
F 2 3 5 A
G 3 4 8 A
H 1 2 3 G
I 5 8 12 D,E,
F
J 3 5 7 H,I
EXAMPLE: PERT
Activity Duration Pred
.
Expected
Time
Variance
O M P te σ2
A 8 10 15 Nil
B 8 10 12 A
C 11 12 13 B
D 18 20 26 B
E 1 2 4 B
F 1 2 5 C
G 3 4 7 E
H 1 2 3 F
I 10 15 21 D
J 3 5 7 G
K 32 40 56 H,I,J
L 4 8 13 K
(i)Draw net work for PERT
(ii)Find Expected Time “te” for all activities
(iii)Find Variance “σ2” for all activities
(iv)Find “Z” value, when Ts= 103
(v)What is the probability that project will finish
in 104 days?
(vi)What is the probability that activity “K” will
start on 55th day of project execution?
Calculations:
SOLUTION
Activity Duration Pred Expected
Time
Variance
O M P te σ2
A 8 10 15 Nil
B 8 10 12 A
C 11 12 13 B
D 18 20 26 B
E 1 2 4 B
F 1 2 5 C
G 3 4 7 E
H 1 2 3 F
I 10 15 21 D
J 3 5 7 G
K 32 40 56 H,I,J
L 4 8 13 K
= 10.5 days
= =
= 1.36
USE OF SOFTWARE FOR
PROJECT PLANNING &
SCHEDULING
Project Time Management
PLANNING, SCHEDULING AND
CONTROL
 MS Project
 Primavera (P3,
P6)
 Risky Project
 Pertmaster
Software application
Process Overview
1. Project Baseline Schedule
2. Project Baseline Budget
PROJECT STATUS AT MONTH 3
Progress at end of 3rd Month:
Project Budget (BAC): 37.22 lakhs
Funds Used (AC): 16.40 lakhs
Utilization = 44.1 %
Additional EV Parameters:
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Sh e e t 1 o f 1
A c ti v ity
ID
A c ti v ity
D e s c rip t io n
O ri g
D u r
B u d g e t
(B A C )
P la n n e d
(B C W S )
E a rn e d
(B C W P )
A c tu a l
(A C W P )
Rura l He a lth Cli nic
T o t a l 2 1 0 3 , 7 2 2 , 0 0 0 . 0 0 1 , 9 8 2 , 8 0 0 . 0 0 1 , 4 5 0 , 0 0 0 . 0 0 1 , 6 4 0 , 0 0 0 . 0 0
Ge n e ra l
S u b t o t a l 2 1 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 0 0 P ro j e c t S t a rt 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 1 1 0 P ro j e c t C o m p l e t e 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
F o u n da tio n
S u b t o t a l 5 4 8 5 0 , 0 0 0 . 0 0 8 5 0 , 0 0 0 . 0 0 8 5 0 , 0 0 0 . 0 0 9 5 0 , 0 0 0 . 0 0
1 0 1 0 E a rt h w o r k s 1 8 5 0 , 0 0 0 . 0 0 5 0 , 0 0 0 . 0 0 5 0 , 0 0 0 . 0 0 6 0 , 0 0 0 . 0 0
1 0 2 0 F o u n d a t i o n u p t o P l i n t h 2 4 8 0 0 , 0 0 0 . 0 0 8 0 0 , 0 0 0 . 0 0 8 0 0 , 0 0 0 . 0 0 8 9 0 , 0 0 0 . 0 0
Stru c tu re W o rk
S u b t o t a l 5 1 1 , 5 3 6 , 0 0 0 . 0 0 1 , 1 3 2 , 8 0 0 . 0 0 6 0 0 , 0 0 0 . 0 0 6 9 0 , 0 0 0 . 0 0
1 0 3 0 S u p e r-s t ru c t u r e 5 0 1 , 4 4 0 , 0 0 0 . 0 0 1 , 0 3 6 , 8 0 0 . 0 0 5 0 4 , 0 0 0 . 0 0 5 8 4 , 0 0 0 . 0 0
1 0 4 0 B l o c k M a s o n r y 1 5 9 6 , 0 0 0 . 0 0 9 6 , 0 0 0 . 0 0 9 6 , 0 0 0 . 0 0 1 0 6 , 0 0 0 . 0 0
F in i s he s
S u b t o t a l 1 0 5 1 , 3 3 6 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 5 0 P l a s t e r 4 0 1 9 2 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 1 0 0 P l u m b i n g 1 5 1 0 0 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 9 0 E l e c t ri c a l W o r k s 2 5 2 0 0 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 7 0 F l o o r i n g 4 5 3 0 0 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 6 0 P a i n t 4 0 1 4 4 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 8 0 W o o d W o rk 2 0 4 0 0 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
M o n t h s
1 2 3 4 5 6 7 8 9 1 0
P ro j e c t S t a rt
P ro j e c t C o m p l e te
E a rt h wo r k s
F o u n d a t io n u p t o P li n th
S u p e r-s t ru c t u r e
B lo c k M a s o n r y
P la s t e r
P lu m b i n g
E le c t ric a l W o r k s
F lo o r in g
P a in t
W o o d W o rk
Resour ce/ Cost Profi l e Legend
Pl anned val ue cur ve
Earned val ue curve
Curr ent est i m ate curve
Total earl y cost per M ont h (Curr ent Est i m ate)
Total of Al l Resour ces Detai l scal e (l ef t) : X 100000
Cum ul at i ve scal e ( ri ght ): X 100000
1 2 3 4 5 6 7 8 9 1 0
M o n t h s
1
2
3
4
5
6
7
8
9
1 0
4
8
1 2
1 6
2 0
2 4
2 8
3 2
3 6
4 0
x 100000 x 100000
Sh e e t 1 o f 1
PV
EV
AC
EAC
BAC
TIME
COST
SCHEDULE ANALYSIS BAC
Data Date
AC
EV
PV
Progress at end of 3rd Month:
Project Budget (BAC): 37.22 lakhs
Funds Used (AC): 16.40 lakhs
Utilization = 44.1 %
Additional EV Parameters:
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Schedule Performance
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Schedule Variance = EV-PV = -5.32
Schedule Performance Index = EV/PV = 0.73
SV
TIME
COST
Cost Analysis BAC
Data Date
AC
EV
PV
Progress at end of 3rd Month:
Project Budget (BAC): 37.22 lakhs
Funds Used (AC): 16.40 lakhs
Utilization = 44.1 %
Additional EV Parameters:
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Cost Performance
Actual Cost (AC): 16.40 lakhs
Earned (EV): 14.50 lakhs
Cost Variance = EV-AC = -1.90
Cost Performance Index = EV/AC = 0.88
CV
TIME
COST
ESTIMATE AT COMPLETIONBAC
Data Date
AC
EV
PV
Progress at end of 3rd Month:
Project Budget (BAC): 37.22 lakhs
Funds Used (AC): 16.40 lakhs
Utilization = 44.1 %
Additional EV Parameters:
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Estimate at Completion
Actual Cost (AC): 16.40 lakhs
Earned (EV): 14.50 lakhs
EAC = BAC/CPI = 42.3
Variance at Completion = BAC-EAC = -5.07
64
Thank You

Weitere ähnliche Inhalte

Was ist angesagt?

Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration ManagementBhuWan Khadka
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Scheduleshofiulalom
 
Project Time Management
Project Time Management Project Time Management
Project Time Management Waqar Ali
 
Project management planning
Project management planningProject management planning
Project management planningAlvin Niere
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2Anand Bobade
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational StructureBhuWan Khadka
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoringharoldtaylor1113
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTùng Trần Thanh
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 

Was ist angesagt? (20)

Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
Project Management
Project ManagementProject Management
Project Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
 
Project management planning
Project management planningProject management planning
Project management planning
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Project Management
Project ManagementProject Management
Project Management
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational Structure
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 

Ähnlich wie project time management

Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptxTecnicoItca
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptxHafixFarhan
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdfssuserc0e4e0
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Chapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).pptChapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).pptssuser8cd298
 
Tools & Techniques.pptx
Tools & Techniques.pptxTools & Techniques.pptx
Tools & Techniques.pptxAarthi393502
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint university(kust)
 
Managingtripleconstraint aam
Managingtripleconstraint aamManagingtripleconstraint aam
Managingtripleconstraint aamAldo Arecco
 

Ähnlich wie project time management (20)

Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Chapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).pptChapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).ppt
 
Tools & Techniques.pptx
Tools & Techniques.pptxTools & Techniques.pptx
Tools & Techniques.pptx
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 
Managingtripleconstraint aam
Managingtripleconstraint aamManagingtripleconstraint aam
Managingtripleconstraint aam
 
Project management
Project managementProject management
Project management
 

Kürzlich hochgeladen

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Kürzlich hochgeladen (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 

project time management

  • 1. PROJECT TIME MANAGEMENT Lecture 5 & 6 PROJECT TIME MANAGEMENT
  • 2. Content of Presentation  PMI approach of Time Management  WBS/ Activity Definition  Estimation o [Purpose of Estimation o Factors influencing Estimates o Methods of Estimation o Problems in Estimation o Accuracy in Estimation o Importance of Accurate Estimates  Scheduling (Planning and Scheduling) o Objectives o Techniques o Critical Path Method (CPM)  Basic Definition of CPM  Activity  Activity Duration  Network Construction  Example 1 o Histogram  Resource Histogram  Constructing Resource histogram o Procedure for Resource Leveling o PERT o Example  Use of software for planning, scheduling & control of projects o Process overview o Software application o EVMS
  • 3. PROJECT TIME MANAGEMENT 6.1 ACTIVITY DEFINITION 1. Inputs 1. Enterprise environmental factors . 2. Organizational process assets 3. Project scope statement 4. Work Breakdown structure 5. WBS Dictionary 6. Project management plan 2. Tools and Techniques 1. Decomposition 2. Templates 3. Rolling wave planning 4. Expert judgment 5. Planning component 3. Outputs 1. Activity list 2. Activity attributes 3. Milestone list 4. Requested changes 6.2 ACTIVITY SEQUENCING 1. Inputs .1 Project scope statement .2 Activity list .3 Activity attributes .4 Milestone List .5 Approved change requests 2 . Tools and Techniques .1 Precedence Diagramming Method (PDM) .2 Arrow Diagramming Method (ADM) .3 Schedule network templates .4 Dependency determination .5 Applying leads and lags 3. Outputs .1 Project schedule network diagrams .2 Activity list (updates) .3 Activity attributes (updates) .4 Requested changes 6.3 ACTIVITY RESOURCE ESTIMATING 1. Inputs .1 Enterprise environmental factors .2 Organizational process assets .3 Activity list .4 Activity attributes .5 Resource availability .6 Project management plan 2. Tools and Techniques .1 Expert judgment .2 Alternatives analysis .3 Published estimating data .4 Project management software .5 bottom-up-estimating 3. Outputs .1 Activity resource requirements .2 Activity attributes (updates) .3 Resource breakdown structure .4 Resource calendars (updates) .5 Requested changes Continue on next slide PMI Approach of Project Time Management (Cont..)
  • 4. PMI Approach of Project Time Management (Cont..) PROJECT TINE MANAGEMENT 6.4 ACTIVITY DURATION ESTIMATING 1. Inputs .1 Enterprise environmental factors .2 Organizational process assets .3 Project scope statement .4 Activity list .5 Activity attributes .6 Activity resource requirements .7 Resource calendars .8 Project Management plan . Risk register . Activity cost estimates 2. Tools and Techniques .1 Expert judgment .2 Analogous estimating .3 Parametric estimating .4 Three-point estimating .5 Reserve analysis 3. Outputs .1 Activity duration estimates .2 Activity attributes (updates) 6.5 SCHEDULE DEVELOPMENT 1. Inputs .1 Organizational process assets .2 Project scope statement .3 Activity list .4 Activity attributes .5 Project schedule network diagrams .6 Activity resource requirements .7 Resource calendars .8 Activity duration estimates .9 Project management plan . Risk register 2. Tools and Techniques .1 Schedule network analysis .2 Critical path method .3 Schedule compression .4 What-if scenario analysis .5 Resource leveling .6 Critical chain method .7 Project management software .8 Applying calendars .9 Adjusting leads & lags 10. Schedule model 3. Outputs .1 Project schedule .2 Schedule model data .3 Schedule baseline .4 resource requirements (Updates) .5 Activity attributes (updates) .6 Project calendars (updates) .7 Requested changes .8 Project management plan (updates) . Schedule management plan (updates) 6.6 SCHEDULE CONTROL 1. Inputs .1 Schedule management plan .2 Schedule baseline .3 Performance report .4 Approved change request 2. Tools and Techniques .1 Progress reporting .2 Schedule change control system .3 Performance measurement .4 Project management software .5 Variance analysis .6 Schedule comparison bar charts 3. Outputs .1 Schedule model data (updates) .2 Schedule baseline (updates) .3 Performance measurements .4 Requested changes .5 Recommended corrective actions .6 Organizational process assets (updates) .7 Activity list (updates) .8 Activity attributes (updates) .9 Project management plan (updates) Continue on Previous slide
  • 6. WORK BREAKDOWN STRUCTURE (WBS)  A WBS is “a hierarchical system that represents the project in increasing levels of detail to define, organise, and display the project work in measurable and manageable components”.  A WBS is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project  WBS is a preliminary document that provides the basis for planning and managing project schedules, costs and resources  Decomposition is subdividing project deliverables into smaller pieces  A work package is a task at the lowest level of the
  • 7. WORK BREAKDOWN STRUCTURE (WBS)  The WBS consists of different levels where level one is the least detailed level often representing the entire project. The number of activities in the WBS grows quite rapidly and it is not unusual that a large construction project is broken down into several hundreds of activities. There is no specific rule about which level of detail a WBS should have but a low level of detail may result in insufficient detail for effective planning, whereas a too high level of detail may become unmanageable and increase planning costs. It is generally the case that the WBS is poorly detailed rather than too detailed. According to Jackson (2004) the level of detail should correlate with the control level desired, i.e. to have enough activities and just the A proposed WBS for an infrastructure project (multi-storey building project).
  • 8. Roles Played by the WBS  Lays out the scope of project work  All project tasks must be accounted  Provides the foundation of all project estimates  Times, costs, resource requirements, etc.  Helps with the project’s organizational structure  How tasks relate to one another, authority structure, etc.
  • 9. Roles Played by the WBS 9
  • 10. ACTIVITY CODING  The following procedure shall be adopted in assigning ID to an activity let us take an example of Procurement and take the values from the above tables then to develop id for activity .  Project - Nil  Phases/Departments - P  Sub Phases - F  Area - 01 o Equipment - TK • Discipline / Stages - O  Then by combining all above we get the id as • Activity No.1 - PF01TKO001 • Activity No. 2 - PF01TKX001
  • 11.
  • 12.
  • 13. SAMPLE INTRANET WBS ORGANIZED BY PHASE 13
  • 14. INTRANET WBS IN TABULAR FORM 14 1.0 Concept 1.1 Evaluate current systems 1.2 Define Requirements 1.2.1 Define user requirements 1.2.2 Define content requirements 1.2.3 Define system requirements 1.2.4 Define server owner requirements 1.3 Define specific functionality 1.4 Define risks and risk management approach 1.5 Develop project plan 1.6 Brief Web development team 2.0 Web Site Design 3.0 Web Site Development 4.0 Roll Out 5.0 Support
  • 15. INTRANET WBS AND GANTT CHART IN MICROSOFT PROJECT 15
  • 16. WBS: The Compliance Project Compliance Project 1.0 Administration 4.0 Medical Care2.0 Physical Therapy 3.0 Food / Nutrition 3.1 Review State Inspection Report 3.2 Review State Compliance Standards 3.3 Develop Policies and Procedures for State Compliance 3.4 Implement Evaluation and Correction Procedures for All Areas 3.3.2 Develop Maintenance SOPs 3.3.1 Develop Corrective Procedures 3.3.2.1 Planning 3.3.2.2 Preparation 3.3.2.3 Delivery 1.1 Review State Inspection Report 1.2 Review State Compliance Standards 1.3 Develop Policies and Procedures for State Compliance 1.4 Implement Evaluation and Correction Procedures for All Areas 1.3.2 Develop Maintenance SOPs : 1.3.1 Develop Corrective Procedures: 1.3.2.1 Planning 1.3.2.2 Financial 1.3.2.3 Supervision
  • 17.
  • 18.
  • 20. ESTIMATION  An estimate is a calculation of the quantities of various items of work, and the expenses likely to be incurred there on. The total of these probable expenses to be incurred on the work is known as estimated cost of the work.  The estimated cost of a work is a close approximation of its actual cost. The agreement of the estimated cost with the actual cost will depend on accurate use of estimating methods and correct visualization of the work. Importance of correct estimating is obvious.  Estimating is the most important of the practical aspects of Project Management. It is a comparatively simple subject to understand; however, as it brings one up against practical work, methods and procedure, knowledge of it
  • 21. PURPOSE OF ESTIMATING 1. Estimating Materials From the estimate of a work it is possible to determine the quantity of materials required to complete work as per scope of project and WBS. 2. Estimating Labor The quantity and type of workers (man hours) of different categories required to complete the work in the specified time. 3. Estimating Cost An estimate is necessary to give an accurate idea of the cost of work as per scope and WBS. 4. Estimating Time It enables to estimate the time required to complete an item of work or the work as a whole as per scope and WBS. Time estimates are used in scheduling work, assigning resources and determining delivery dates.. Estimation of cost, materials, labor and time is immensely
  • 22. PROBLEMS IN ESTIMATION a) There is no established project estimation process. b) Inaccurate data is used, or historical data may not be complete. c) The forecasting techniques and tools are inefficient. d) There is no ability to track actual project performance, which can be used to refine estimates. e) The project planners are inexperienced. f) Deadlines and Time Constraints g) Skill and Knowledge of Quantity Surveyor h) Experience of Estimation i) Productivity of labor and machinery
  • 23. IMPORTANCE OF ACCURATE ESTIMATES  Inaccurate time estimates can result in inefficient use of resources and hence impact on project management.  Inaccurate estimates can result in insufficient budget being allocated, or excess budget being set aside for the project when it could be used for other projects.  If the cost or benefits estimates are inaccurate this can lead to incorrect decisions about proceeding with the project being made.
  • 24. WHEN ESTIMATES ARE REQUIRED Project phase Estimates required Initiation/Concep t/ Inception Stage Time, cost and benefit estimates in project definition. Planning Stage Time estimates in project schedule. Cost estimates in project budget. Cost and benefit estimates in business case. Execution For Project Management, to calculate the Earned Value, Estimated time to complete project, Quantities worked out and billing of contractor. 24
  • 26. PROJECT PLANNING AND SCHEDULING  Project Planning: Process of identifying all the activities necessary to successfully complete the project is called project planning.  Project Scheduling: Process of determining sequential order of planned activities, assigning realistic duration, to each activity and determining start and finish dates of each activity is called project scheduling. Project planning is prerequisite to project scheduling because there is no way to determine the sequential order of activities until they are identified. However, the terms planning and scheduling are often used synonymously because they are performed interactively. E.g. when some schedule is reviewed, it may be decided that additional activities may be added or rearranged in order to get the best schedule of events of projects.
  • 27. OBJECTIVES OF PROJECT PLANNING & SCHEDULING  Finish project on time.  Continuous (uninterrupted) flow of work.  Reduced amount of rework.  Minimize confusion and misunderstanding.  Increased knowledge of status of project to every one (including management).  Knowledge of distribution of costs of project.  Accountability of people / defined responsibility and clear understanding of who does what, when and how much.  Exploitation and optimum use of resources.
  • 28. TECHNIQUES FOR PLANNING AND SCHEDULING Techniques used for scheduling depends upon the type, size, complexity, duration, personal and owner requirement. It is preferred to use a simpler technique which is simple to use and easily interpreted by all project participants. There are two general techniques which commonly used for planning and scheduling.  Bar Chart (Gantt Chart): It is the graphical representation of Time (X-axis) and Activities on Y-axis, so that the status of project may be visualized and controlled.  Net work analysis system (CPM and PERT): It is the schematic representation of various activities. This method calculates the minimum completion time for a project along with start and finish time of project activities.
  • 29. BAR CHART  Bar Chart was developed by Henery L. Gantt in 1917, which is the most common planning tool even now and provided basis for developing planning and scheduling software.  Bar Charts are the easiest and most widely used form of scheduling in project management. Even with other scheduling techniques the eventual schedule is presented the form of a bar chart. The level of detail of the activities depends on the intended use of the schedule. The most commonly used bar chart for engineering works is called Gantt chart.  A Gantt chart is a type of bar chart that illustrates a project schedule, start and finish dates of the terminal elements and summary elements of civil engineering project. Terminal elements and summary elements comprise the work breakdown structure of the project. Some Gantt charts also show the dependency (i.e. precedence network) relationships between activities. Gantt charts can be used to show current schedule status using percent-complete shadings.  Gantt charts have become a common technique for representing the
  • 30. June Week 1 Week-2 Week-3 Week-4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Activities Planning 1 To formalize organizational Risk Management Plan Organizati on 2 Risk Identification Questionnairs and feedback from Procurement Deptt. Questionnairs and feedback from Engineering Deptt. Questionnairs and feedback from PMD Deptt. Questionnairs and feedback from Contrac Deptt. Questionnairs and feedback from Finance Deptt.
  • 31. CRITICAL PATH METHOD (CPM) The Critical Path Method is a method where activities are arranged based on interrelationship. It is a planning and control technique that provides an accurate, timely and easily understood picture of the project. Its purpose is to allows effective scheduling and controlling, after the project starts. One of the most important features of CPM is the logic diagram. The logic diagram graphically portrays the relationship between project activities.  Critical path in a network is a longest path in terms of time unit, which gives minimum overall duration to complete the project.  CPM calls attention which activities must be completed before other activities can begun. A B D F G E C H
  • 32. BASIC DEFINITIONS OF CPM TERMS  Activity:- The performance of a task required to complete the project e.g. foundation design, contract document, RCC form work, pouring of concrete.  Network:- A diagram to represents the relationship of activities to complete the project.  Duration:- The estimated time required to perform an activity.  Early Start (ES):- The earliest time an activity can be start.  Early Finish (EF):- The earliest time an activity can be finished.  Late Finish (LF):- The latest time an activity can be finished.  Late Start (LS):- The latest time an activity can be started without delaying the completion of project. (LS = LF – D)  Total Float (TF):- The amount of time an activity may be delayed without delaying the completion date of project. Mathematically, TF = LF – EF = LS – ES.  Critical Activity:- If total float for an activity is zero, activity is called critical activity.  Critical path is a longest path in terms of time unit in a network, which
  • 33. ACTIVITY A common technique used to understand and organize complex undertaking is to break the project into smaller pieces. This technique is used both planning and estimating. Each activity is a discrete task. Activities should be only be specified as per level of management. The number and detail of listed quality will vary from job to job and depend on the intended level of control. Usually for planning purposes activity doesn’t exceed from 25 days, if exceeds may be divided into further components. The activities must have four characteristics. 1. Time consumption: An activity must consume time. 2. Use of resources: An activity usually consumes Labour, Material or Equipment resources. 3. Definite Start and Finish time: An activity represents a definite scope of work i.e. Starting and Ending point in time. 4. Activities are measurable. The progress towards completion of activity’s scope of work must be measureable.
  • 34. ACTIVITY DURATION  One of the most important steps in planning a project is estimating the time required to complete each activity. The duration of each activity is a function of quantity of work and work production rate. Work production rates are based on planned composition of labor and equipment used to perform the task. Careless estimates of production rates may cause un economical use of personnel, materials, equipment and time.  When the project bid estimate is prepared, the estimator calculates the quantity of material that must be put in place and assumes a production rate to get the cost of each work, which is based construction method and technique. The bid preparation information can be served as the tool for calculating g an activity duration.  All Activities in a schedule should have same unit of time, which may be in months, weeks, days and hours.
  • 35. EXAMPLE In estimating a three storey office building, it was determined that 480 light fixtures would be installed on each floor. The production rate of two fixture per man hour may be used for installation. The company has five electrician. The normal working day will be 8 hours. What will be the duration (in days) to install all lights in the building.SOLUTION: Production Rate: 2 fixture x 5 electrician = 10 fixtures per man hour 1-man hour Activity Duration = 480 fixture x 3 floors = 144 hours 10 Activity Duration = 144 hours = 18 day 8 hours
  • 36. NETWORK CONSTRUCTION Activity must have a specific duration except the dummy activity, having zero duration. Each activity is represented as can arrow or node. Arrows are not drawn according to scale. The brief description about activity is written over arrow or node. Duration (hours, week, months) to complete that activity is written under the arrow, where 1 and 2 are the event. Which are written inside the circles or boxes. The starting event is masked at the tail and finish event at the head of the arrow. Rules: 1. Each activity should be represented by a separate arrow. 2. The arrow may be straight or inclined lines. 3. Dummy activity should be represented with dotted lines. 4. Critical path must be shown clearly with double line. 5. Intersection of activity is not allowed. 6. Boxes are provided for event times (ES, EF, LS, LF) 7. EST is some reference time, normally EST = 0 at the start of the project / work. EFT = EST + Duration. 8. Each activity is followed by a predecessor and successor except start and finish activities. Any starting activity must have predecessor none, or finish activity must have no successor.
  • 37.
  • 38. EXAMPLE 1. CPM Activity Duration (days) Events Preceding Activity (Predecessor ) A 4 1 – 2 None B 6 2 – 3 A C 8 2 – 4 A D 10 3 – 6 B E 5 3 – 5 B F 7 4 – 5 C G 12 6 – 7 D H 8 5 – 7 E, F I 3 7 – 8 G,H 1. Construct AOA network 2. Find ES, EF, LS and LF of all activities 3. Find total float of all activities (days) 4. Find the project duration (days) 5. Mark critical path on the network
  • 39. EXAMPLE 2. CPM Activity Duration Predecessor Resourc e Early Start (ES) Early Finish (EF) Late Start (LS) Late Finish (LF) Total Float (TF) Remark O 8 None 10 N 3 O 2 M 13 N 5 L 7 O 15 K 12 O 8 J 3 K 4 I 10 L 3 H 8 L 10 G 6 H,M 8 F 20 I 4 E 16 I 6 D 8 J 4 C 4 G, E 20 B 5 F 6 A 3 B, C,D 3 1. Construct AOA & AON networks 2. Find ES, EF, LS and LF of all activities 3. Find total float of all activities (days) 4. Find the project duration (days) 5. Mark critical path on the network
  • 40. EXAMPLE 3. CPM Activity Duration Predecesso r Resourc e (ES) (EF) (LS) (LF) (TF) Remark Q 8 None 5 P 10 Q 6 O 7 Q 10 N 6 O 2 M 9 Q 5 L 5 M 15 K 4 O 8 J 7 L, K 4 I 9 L, K 3 H 20 P 10 G 12 H 8 F 9 N 4 E 20 N 6 D 11 I 4 C 7 E, J 20 B 7 G, F 6 A 3 B, C,D 3 1. Construct AOA network 2. Find ES, EF, LS and LF of all activities Find total float of all activities (days) 4. Find the project duration (days) 5. Mark critical path on the network
  • 41. EXAMPLE 4. CPM 1. Construct AOA network 2. Find ES, EF, LS and LF of all activities 3. Find total float of all activities (days) 4. Find the project duration (days) 5. Mark critical path on the network 6. Resource Histogram Solution: Critical Path = Q – P – H – G – B – A, Project Duration = 60 days 2nd Path = Q – O – N – F – B – A, Duration = 40 days 3rd Path = Q – O – N – E – C – A, Duration = 51days 4th Path = Q – O – K – J – C – A, Duration = 36 days 5th Path = Q – O – K – I – D – A, Duration = 42 days 6th Path = Q – M – L – J – C – A, Duration = 39 days 7th Path = Q – O – K – I – D – A, Duration = 45 days
  • 43. HISTOGRAM  A histogram is a graphical data analysis technique for summarizing the distributional information of a variable. The response variable is divided into equal sized intervals (or bins). The number of occurrences of the response variable is calculated for each bin. The histogram consists of:  Vertical axis = frequencies or relative frequencies;  Horizontal axis = response variable (i.e., the mid-point of each interval).  Histogram is a summary graph showing a count of data points falling in various ranges. The histogram displays a single variable in a bar form to indicate how often some event is likely to occur by showing the pattern of variation (distribution) of data. A pattern of variation has three aspects: the center (average), the shape of the curve, and the width of the curve. Histograms are constructed with variables such as time, weight, temperature and are not appropriate for attribute
  • 44. RESOURCE HISTOGRAM  It is a graphical representation of time on X-axis and resources on Y-axis.  It is a view of project data in which resource requirements, usage, and availabilities are shown against a time scale. The personnel, equipment, materials, and services needed to complete tasks in a project are resources.
  • 45. TYPES OF RESOURCE HISTOGRAM 1. Labor Resource Histogram 2. Material Resource Histogram 3. Equipment Resource Histogram 4. Cost Histogram In these resource histograms time is taken on x axis and the resource is taken on y axis. For a construction project total resources are mentioned according to that particular time these histograms also help us to calculate cost for a particular resource of a project at a particular time because resource can be converted in terms of cost.
  • 46. PROCEDURE FOR RESOURCE LEVELING 1. Plan and Schedule project activities. 2. Construct a Network for the project. 3. Mark Critical Path (CP). 4. Construct the Bar Chart for the Project. 5. For each working day show resources of each activity at their respective duration on Bar Chart. 6. Sum up the total resources vertically for each working day. 7. Plot the histogram for the resource. 8. Mark the sudden drop or rise in resource histogram. 9. Utilize the total float available for non critical activity to level the resources by hit & trial method. 10. Recheck the leveled histogram and prepare a new schedule of work / execution.
  • 47. Activity Duratio n Pred. ES EF LS LF float A 6 None 0 6 0 6 0 B 20 A 6 26 15 35 9 C 5 A 6 11 6 11 0 D 8 A 6 14 17 25 11 E 10 D 14 24 25 35 11 F 14 C 11 35 11 35 0 G 8 C 11 19 45 53 34 H 12 C 11 23 31 43 20 I 6 B, F 14 20 37 43 23 J 10 E, H 23 33 43 53 20 K 18 G, I, J 35 53 35 53 0 CONSTRUCTING RESOURCE HISTOGRAM
  • 49. PROGRAMME EVALUATION AND REVIEW TECHNIQUE (PERT) Project Time Management
  • 50. PROGRAMME EVALUATION AND REVIEW TECHNIQUE (PERT)  PERT is a management tools process which ensures accomplishment of a project with in planned schedule and cost.  PERT is an inherent planning technique forces the manager to develop a comprehensive plan and allows realistic scheduling. The procedure for monitoring, forecasting and simulating allows the manager to respond quickly to unexpected changes in the project, detect trouble areas early and evaluate proposed alternative courses of action. PERT also helps to evaluate alternatives at any time during projects duration by looking effect of each change on its completion date. PERT also helps to simulate the project time & cost and effects of alternate decisions.  In other words it can be defined as a planning & Control techniques that precuts statistical information regarding the
  • 51. DIFFERENCE BETWEEN PERT AND CPM CPM PERT CPM uses one time estimate that represents the normal time. PERT uses three time estimates (optimistic, most likely, and pessimistic) to derive an expected time. CPM is deterministic in nature. PERT is probabilistic in nature, CPM is used for those projects where percent complete can be determined with reasonable accuracy such as construction. PERT is used for R&D, where percent complete is almost impossible to determine except a completed milestones. CPM is activity oriented and can be used as an arrow diagram network. PERT is event oriented rather than activity oriented and can be used as an arrow diagram network. CPM as a controlling device for the simple reason that one must repeat the entire evaluation of the project each time the changes are introduced into the network PERT serves a useful control device as it assist the management in controlling a project by calling attention through constant review to such delays in activities which might lead to a delay in the project completion date. Cannot be used for risk analysis and management Can be used for risk analysis and management CPM Gives Critical Path PERT gives probability in % to achieve critical path May be used successfully for projects without uncertainties and risks May be used successfully for projects with uncertainties and risks
  • 52. a) Draw net work for PERT b) Find Expected Time “te” for all activities and “TE “ c) Find Variance “σ2” for all activities d) Find “Z” value, when Ts= 40 days e) Find the scheduled duration (Ts) for project completion with 80% probability EXAMPLE: PERTActivit y Duration Pre d. Expected Time Varian ce O M P te σ2 A 4 8 15 Nil B 8 10 20 Nil C 11 12 15 Nil D 13 15 20 C E 2 3 4 B F 2 3 5 A G 3 4 8 A H 1 2 3 G I 5 8 12 D,E, F J 3 5 7 H,I
  • 53. EXAMPLE: PERT Activity Duration Pred . Expected Time Variance O M P te σ2 A 8 10 15 Nil B 8 10 12 A C 11 12 13 B D 18 20 26 B E 1 2 4 B F 1 2 5 C G 3 4 7 E H 1 2 3 F I 10 15 21 D J 3 5 7 G K 32 40 56 H,I,J L 4 8 13 K (i)Draw net work for PERT (ii)Find Expected Time “te” for all activities (iii)Find Variance “σ2” for all activities (iv)Find “Z” value, when Ts= 103 (v)What is the probability that project will finish in 104 days? (vi)What is the probability that activity “K” will start on 55th day of project execution? Calculations:
  • 54. SOLUTION Activity Duration Pred Expected Time Variance O M P te σ2 A 8 10 15 Nil B 8 10 12 A C 11 12 13 B D 18 20 26 B E 1 2 4 B F 1 2 5 C G 3 4 7 E H 1 2 3 F I 10 15 21 D J 3 5 7 G K 32 40 56 H,I,J L 4 8 13 K = 10.5 days = = = 1.36
  • 55.
  • 56. USE OF SOFTWARE FOR PROJECT PLANNING & SCHEDULING Project Time Management
  • 57. PLANNING, SCHEDULING AND CONTROL  MS Project  Primavera (P3, P6)  Risky Project  Pertmaster Software application
  • 59. 1. Project Baseline Schedule 2. Project Baseline Budget
  • 60. PROJECT STATUS AT MONTH 3 Progress at end of 3rd Month: Project Budget (BAC): 37.22 lakhs Funds Used (AC): 16.40 lakhs Utilization = 44.1 % Additional EV Parameters: Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Sh e e t 1 o f 1 A c ti v ity ID A c ti v ity D e s c rip t io n O ri g D u r B u d g e t (B A C ) P la n n e d (B C W S ) E a rn e d (B C W P ) A c tu a l (A C W P ) Rura l He a lth Cli nic T o t a l 2 1 0 3 , 7 2 2 , 0 0 0 . 0 0 1 , 9 8 2 , 8 0 0 . 0 0 1 , 4 5 0 , 0 0 0 . 0 0 1 , 6 4 0 , 0 0 0 . 0 0 Ge n e ra l S u b t o t a l 2 1 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 0 0 P ro j e c t S t a rt 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 1 1 0 P ro j e c t C o m p l e t e 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 F o u n da tio n S u b t o t a l 5 4 8 5 0 , 0 0 0 . 0 0 8 5 0 , 0 0 0 . 0 0 8 5 0 , 0 0 0 . 0 0 9 5 0 , 0 0 0 . 0 0 1 0 1 0 E a rt h w o r k s 1 8 5 0 , 0 0 0 . 0 0 5 0 , 0 0 0 . 0 0 5 0 , 0 0 0 . 0 0 6 0 , 0 0 0 . 0 0 1 0 2 0 F o u n d a t i o n u p t o P l i n t h 2 4 8 0 0 , 0 0 0 . 0 0 8 0 0 , 0 0 0 . 0 0 8 0 0 , 0 0 0 . 0 0 8 9 0 , 0 0 0 . 0 0 Stru c tu re W o rk S u b t o t a l 5 1 1 , 5 3 6 , 0 0 0 . 0 0 1 , 1 3 2 , 8 0 0 . 0 0 6 0 0 , 0 0 0 . 0 0 6 9 0 , 0 0 0 . 0 0 1 0 3 0 S u p e r-s t ru c t u r e 5 0 1 , 4 4 0 , 0 0 0 . 0 0 1 , 0 3 6 , 8 0 0 . 0 0 5 0 4 , 0 0 0 . 0 0 5 8 4 , 0 0 0 . 0 0 1 0 4 0 B l o c k M a s o n r y 1 5 9 6 , 0 0 0 . 0 0 9 6 , 0 0 0 . 0 0 9 6 , 0 0 0 . 0 0 1 0 6 , 0 0 0 . 0 0 F in i s he s S u b t o t a l 1 0 5 1 , 3 3 6 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 5 0 P l a s t e r 4 0 1 9 2 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 1 0 0 P l u m b i n g 1 5 1 0 0 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 9 0 E l e c t ri c a l W o r k s 2 5 2 0 0 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 7 0 F l o o r i n g 4 5 3 0 0 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 6 0 P a i n t 4 0 1 4 4 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 8 0 W o o d W o rk 2 0 4 0 0 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 M o n t h s 1 2 3 4 5 6 7 8 9 1 0 P ro j e c t S t a rt P ro j e c t C o m p l e te E a rt h wo r k s F o u n d a t io n u p t o P li n th S u p e r-s t ru c t u r e B lo c k M a s o n r y P la s t e r P lu m b i n g E le c t ric a l W o r k s F lo o r in g P a in t W o o d W o rk Resour ce/ Cost Profi l e Legend Pl anned val ue cur ve Earned val ue curve Curr ent est i m ate curve Total earl y cost per M ont h (Curr ent Est i m ate) Total of Al l Resour ces Detai l scal e (l ef t) : X 100000 Cum ul at i ve scal e ( ri ght ): X 100000 1 2 3 4 5 6 7 8 9 1 0 M o n t h s 1 2 3 4 5 6 7 8 9 1 0 4 8 1 2 1 6 2 0 2 4 2 8 3 2 3 6 4 0 x 100000 x 100000 Sh e e t 1 o f 1 PV EV AC EAC BAC
  • 61. TIME COST SCHEDULE ANALYSIS BAC Data Date AC EV PV Progress at end of 3rd Month: Project Budget (BAC): 37.22 lakhs Funds Used (AC): 16.40 lakhs Utilization = 44.1 % Additional EV Parameters: Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Schedule Performance Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Schedule Variance = EV-PV = -5.32 Schedule Performance Index = EV/PV = 0.73 SV
  • 62. TIME COST Cost Analysis BAC Data Date AC EV PV Progress at end of 3rd Month: Project Budget (BAC): 37.22 lakhs Funds Used (AC): 16.40 lakhs Utilization = 44.1 % Additional EV Parameters: Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Cost Performance Actual Cost (AC): 16.40 lakhs Earned (EV): 14.50 lakhs Cost Variance = EV-AC = -1.90 Cost Performance Index = EV/AC = 0.88 CV
  • 63. TIME COST ESTIMATE AT COMPLETIONBAC Data Date AC EV PV Progress at end of 3rd Month: Project Budget (BAC): 37.22 lakhs Funds Used (AC): 16.40 lakhs Utilization = 44.1 % Additional EV Parameters: Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Estimate at Completion Actual Cost (AC): 16.40 lakhs Earned (EV): 14.50 lakhs EAC = BAC/CPI = 42.3 Variance at Completion = BAC-EAC = -5.07