Project Pulse sheet-3 Sep 15
- 1. Date:
Salient Issues:
1) Resolution of ROW, team for
resolution appointed consisting
of MEPCO, FEL and ACC
personnals.
03‐Sep‐15 Project Pulse
FEL Housing Colony
Construction Statistics
Quality statistics
CIVIL
MECHANICAL
ELECTRICAL & INSTRUMENTATION
PRE‐COMMISSIONING
SPTL
Progress Statistics
5
26
1
1
7
11
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36
Civil
Mech.
E&I
NCR status
Close Open
1603 1530 1530
980 894 894
0
300
600
900
1200
1500
1800
Sampled Tested Passed Sampled Tested Passed
Concrete Cylinder testing
34000
30552
411
0
10000
20000
30000
40000
Concrete CM
Plant total concrete status
Total concrete Completed concrete Last Week Concreting
212
182
99
171
77
33
0
88
0
20
40
60
80
100
120
140
160
180
200
220
SPTL Construction Total towers
Tower PO placed
Material delivered
Profile issued
Foundations
Erection
Slinging
ROW issues
7 7
6
4
3
0
5
10
SPTL procurement
Total items PO issued Ins. Call rec. FAT Delivery
0%
0%
0%
85%
95%
100%
100%
100%
100%
100%
95%
0% 50% 100%
FEL colony major milestonesMaster plan finalization
Houses layout finalization
Boundary wall marking
Boundary wall bid package
Bidding ‐ Boundary wall
Infrastructure bid package
Bidding ‐ Infrastructure
BOQ, BEQ, MOQ bid package
Bidding ‐ BOQ, BEQ, MOQ
Balance colony bid package
Bidding ‐ balance colony
70%
40%
0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Foundations
Brick work
Finishing
works
Boundary wall
0% 0% 0% 0% 0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Foundations
Brick work
Piping works
Electrical…
Finishing…
Infrastructure
0% 0% 0% 0% 0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Foundations
Brick work
Piping works
Electrical
works
Finishing
works
BOQ, BEQ, MOQs
0% 0% 0% 0% 0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Foundations
Brick work
Piping works
Electrical works
Finishing works
Balance colony
50
10
0
10
20
30
40
50
60
70
WQT
Passed
Failed 80
20
0%
20%
40%
60%
80%
100%
Radiography (RT)
Performed
Remaining
100
50
20 30
15
0
50
100
150
Test Packs
Total Ready Flush/Blow Hydrotested Reinstated
18000
2000 2000 0 0
0
16000 16000 18000 18000
0
5000
10000
15000
20000
25000
Total Fitup Weld Testing Painting
Piping Shop Fab Dia Inches
4,486
2,467
0
2,019
0
1000
2000
3000
4000
5000
Total Erected
Steel Structure (Tons)
960 908
528
0 71
144 196
17.7 1135
0 0
526
00
300
600
900
1200
Boiler
1
Boiler
2
STG
hall
ESP Bagasse
hall
Water
treatment
Coal
Handling
Misc.
Tons
Structure erection detailed
778 771
520
0 100 50
326 333
25.7 1135
200 100
450
0
300
600
900
1200
Boiler… Boiler… STG… ESP Bagasse… Water… Coal…
Sq. M
Sheeting details
1850
4500
0 0
13401400
3350
0 0
700
0
1000
2000
3000
4000
5000
Coal Silo Cooling Tower Bagasse yard Coal yard Fly Ash silo
CM
Major Concrete Status
Total Completed
21 16.8 11
0 0
6
0.9 6.6
80 80
0
20
40
60
80
Coal Silo Cooling Tower Ash Silo Stack 1 Stack 2
M
Completion‐High Rise Structures
Remaining Achieved
26000
3914 3914
0
22086 22086
18000
0
5000
10000
15000
20000
25000
Total Fitup Welding Testing
Piping Erection Dia Inches
7 7 7 6
0
0 0 0 1
7
0
2
4
6
8
10
Foundation Rolling Fitup welding Painting
Tanks
5064
167 1081
3816
0
1000
2000
3000
4000
5000
6000
Total
shipped
packages
In sailing At port Delivered
at site
Equipment shipment
42
0
42
0
10
20
30
40
50
Total Complete
System Mechancial
Completion
15000
80000
0
15000
80000
0
50000
100000
Cable tray Cable Laying
Electrical cable
Total Layed Remaining
83000 83000 83000
0 0 0
83000 83000 83000
0
50000
100000
Terminations Hot loop testing Cold loop testing
Terminations
Total Complete Remaining
2700 2700
3500
410 1210 0 0 0 0
2700 2700
3500
410 121
0
2000
4000
Ins. Calibrated Ins. Installed Local JBs Actuators Control panels
Installation
Total Complete Remaining
500
400
500
200
150 180 190 170
350
220
310
30
0
100
200
300
400
500
600
Civil Mechanical Electrical Instrumentation
Punch Lists‐Category A
Total
Closed
Open
500
400
500
200
150 180 190 170
350
220
310
30
0
100
200
300
400
500
600
Civil Mechanical Electrical Instrumentation
Punch Lists‐Category B
Total
Closed
Open
1999 1928
71 20 28
0
1000
2000
3000
Transmittal
Received
Transmittal
Replied
T < 7days 7 < T < 14
days
T > 14 days
Transmittal Status
28 days 7 days
83.4% 100.0% 100.0%
58.6%
78.5%
45.9% 52.6%
20.8%
73.9%
43.8%
56.5%
68.9%
98.8% 96.2%
26.7%
59.0%
17.3%
7.5% 0.1%
36.5% 29.2% 21.1%
0%
20%
40%
60%
80%
100%
Overall Engineering Procurement Construction Civil Mechanical Electrical Instrumentation STG Boiler BOP
Planned Actual
27
17.7 17.6
80 80