SlideShare ist ein Scribd-Unternehmen logo
1 von 1
Downloaden Sie, um offline zu lesen
Date:
Salient Issues:
1) Resolution of ROW, team for 
resolution appointed consisting 
of MEPCO, FEL and ACC 
personnals.
03‐Sep‐15																																					Project	Pulse
FEL	Housing	Colony
Construction	Statistics
Quality	statistics
CIVIL
MECHANICAL
ELECTRICAL	&	INSTRUMENTATION
PRE‐COMMISSIONING
SPTL
Progress	Statistics
5
26
1
1
7
11
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36
Civil
Mech.
E&I
NCR	status
Close Open
1603 1530 1530
980 894 894
0
300
600
900
1200
1500
1800
Sampled Tested Passed Sampled Tested Passed
Concrete	Cylinder	testing
34000
30552
411
0
10000
20000
30000
40000
Concrete CM
Plant	total	concrete	status
Total concrete Completed concrete Last Week Concreting
212
182
99
171
77
33
0
88
0
20
40
60
80
100
120
140
160
180
200
220
SPTL	Construction Total towers
Tower PO placed
Material delivered
Profile issued
Foundations
Erection
Slinging
ROW issues
7 7
6
4
3
0
5
10
SPTL	procurement
Total items PO issued Ins. Call rec. FAT Delivery
0%
0%
0%
85%
95%
100%
100%
100%
100%
100%
95%
0% 50% 100%
FEL	colony	major	milestonesMaster plan finalization
Houses layout finalization
Boundary wall marking
Boundary wall bid package
Bidding ‐ Boundary wall
Infrastructure bid package
Bidding ‐ Infrastructure
BOQ, BEQ, MOQ bid package
Bidding ‐ BOQ, BEQ, MOQ
Balance colony bid package
Bidding ‐ balance colony
70%
40%
0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Foundations
Brick work
Finishing
works
Boundary	wall
0% 0% 0% 0% 0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Foundations
Brick work
Piping works
Electrical…
Finishing…
Infrastructure
0% 0% 0% 0% 0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Foundations
Brick work
Piping works
Electrical
works
Finishing
works
BOQ,	BEQ,	MOQs
0% 0% 0% 0% 0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Foundations
Brick work
Piping works
Electrical works
Finishing works
Balance	colony
50
10
0
10
20
30
40
50
60
70
WQT
Passed
Failed 80
20
0%
20%
40%
60%
80%
100%
Radiography	(RT)
Performed
Remaining
100
50
20 30
15
0
50
100
150
Test	Packs
Total Ready Flush/Blow Hydrotested Reinstated
18000
2000 2000 0 0
0
16000 16000 18000 18000
0
5000
10000
15000
20000
25000
Total Fitup Weld Testing Painting
Piping	Shop	Fab	Dia	Inches
4,486
2,467
0
2,019
0
1000
2000
3000
4000
5000
Total Erected
Steel	Structure	(Tons)
960 908
528
0 71
144 196
17.7 1135
0 0
526
00
300
600
900
1200
Boiler
1
Boiler
2
STG
hall
ESP Bagasse
hall
Water
treatment
Coal
Handling
Misc.
Tons
Structure	erection	detailed
778 771
520
0 100 50
326 333
25.7 1135
200 100
450
0
300
600
900
1200
Boiler… Boiler… STG… ESP Bagasse… Water… Coal…
Sq. M
Sheeting	details
1850
4500
0 0
13401400
3350
0 0
700
0
1000
2000
3000
4000
5000
Coal Silo Cooling Tower Bagasse yard Coal yard Fly Ash silo
CM
Major	Concrete	Status
Total Completed
21 16.8 11
0 0
6
0.9 6.6
80 80
0
20
40
60
80
Coal Silo Cooling Tower Ash Silo Stack 1 Stack 2
M
Completion‐High	Rise	Structures
Remaining Achieved
26000
3914 3914
0
22086 22086
18000
0
5000
10000
15000
20000
25000
Total Fitup Welding Testing
Piping	Erection	Dia	Inches
7 7 7 6
0
0 0 0 1
7
0
2
4
6
8
10
Foundation Rolling Fitup welding Painting
Tanks
5064
167 1081
3816
0
1000
2000
3000
4000
5000
6000
Total
shipped
packages
In sailing At port Delivered
at site
Equipment	shipment
42
0
42
0
10
20
30
40
50
Total Complete
System	Mechancial	
Completion
15000
80000
0
15000
80000
0
50000
100000
Cable tray Cable Laying
Electrical	cable
Total Layed Remaining
83000 83000 83000
0 0 0
83000 83000 83000
0
50000
100000
Terminations Hot loop testing Cold loop testing
Terminations
Total Complete Remaining
2700 2700
3500
410 1210 0 0 0 0
2700 2700
3500
410 121
0
2000
4000
Ins. Calibrated Ins. Installed Local JBs Actuators Control panels
Installation
Total Complete Remaining
500
400
500
200
150 180 190 170
350
220
310
30
0
100
200
300
400
500
600
Civil Mechanical Electrical Instrumentation
Punch	Lists‐Category	A
Total
Closed
Open
500
400
500
200
150 180 190 170
350
220
310
30
0
100
200
300
400
500
600
Civil Mechanical Electrical Instrumentation
Punch	Lists‐Category	B
Total
Closed
Open
1999 1928
71 20 28
0
1000
2000
3000
Transmittal
Received
Transmittal
Replied
T < 7days 7 < T < 14
days
T > 14 days
Transmittal	Status
28 days 7 days
83.4% 100.0% 100.0%
58.6%
78.5%
45.9% 52.6%
20.8%
73.9%
43.8%
56.5%
68.9%
98.8% 96.2%
26.7%
59.0%
17.3%
7.5% 0.1%
36.5% 29.2% 21.1%
0%
20%
40%
60%
80%
100%
Overall Engineering Procurement Construction Civil Mechanical Electrical Instrumentation STG Boiler BOP
Planned Actual
27
17.7 17.6
80 80

Weitere ähnliche Inhalte

Ähnlich wie Project Pulse sheet-3 Sep 15

Eme slide gioi thieu version tieng anh_2-01-2014
Eme  slide gioi thieu version tieng anh_2-01-2014Eme  slide gioi thieu version tieng anh_2-01-2014
Eme slide gioi thieu version tieng anh_2-01-2014
xncd
 
Eme slide gioi thieu version tieng anh_02-01-2014
Eme  slide gioi thieu version tieng anh_02-01-2014Eme  slide gioi thieu version tieng anh_02-01-2014
Eme slide gioi thieu version tieng anh_02-01-2014
xncd
 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptx
IrfanAwan25
 
Syllabuswise analyse of gate
Syllabuswise analyse of gate Syllabuswise analyse of gate
Syllabuswise analyse of gate
manish katara
 
2010 deep research report on china solar grade polysilcon industry
2010 deep research report on china solar grade polysilcon industry2010 deep research report on china solar grade polysilcon industry
2010 deep research report on china solar grade polysilcon industry
qyresearch
 
28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation
imaduddin91
 
2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry
qyresearch
 
2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry
smarter2011
 
2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry
smarter2011
 
2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry
smarter2011
 

Ähnlich wie Project Pulse sheet-3 Sep 15 (19)

Eme slide gioi thieu version tieng anh_2-01-2014
Eme  slide gioi thieu version tieng anh_2-01-2014Eme  slide gioi thieu version tieng anh_2-01-2014
Eme slide gioi thieu version tieng anh_2-01-2014
 
Eme slide gioi thieu version tieng anh_02-01-2014
Eme  slide gioi thieu version tieng anh_02-01-2014Eme  slide gioi thieu version tieng anh_02-01-2014
Eme slide gioi thieu version tieng anh_02-01-2014
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptx
 
Owen Barry NSW Trade & Investment Mine Safety - Electrical Engineering safety...
Owen Barry NSW Trade & Investment Mine Safety - Electrical Engineering safety...Owen Barry NSW Trade & Investment Mine Safety - Electrical Engineering safety...
Owen Barry NSW Trade & Investment Mine Safety - Electrical Engineering safety...
 
Syllabuswise analyse of gate
Syllabuswise analyse of gate Syllabuswise analyse of gate
Syllabuswise analyse of gate
 
Typical Project Format.pptx
Typical Project Format.pptxTypical Project Format.pptx
Typical Project Format.pptx
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptx
 
2010 deep research report on china solar grade polysilcon industry
2010 deep research report on china solar grade polysilcon industry2010 deep research report on china solar grade polysilcon industry
2010 deep research report on china solar grade polysilcon industry
 
28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation
 
presentation
presentationpresentation
presentation
 
2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry
 
2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry
 
2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry
 
2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry2011 deep research report on china solar grade polysilicon industry
2011 deep research report on china solar grade polysilicon industry
 
Egypt energy
Egypt energyEgypt energy
Egypt energy
 
FQUP PPT.pptx
FQUP PPT.pptxFQUP PPT.pptx
FQUP PPT.pptx
 

Project Pulse sheet-3 Sep 15

  • 1. Date: Salient Issues: 1) Resolution of ROW, team for  resolution appointed consisting  of MEPCO, FEL and ACC  personnals. 03‐Sep‐15 Project Pulse FEL Housing Colony Construction Statistics Quality statistics CIVIL MECHANICAL ELECTRICAL & INSTRUMENTATION PRE‐COMMISSIONING SPTL Progress Statistics 5 26 1 1 7 11 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 Civil Mech. E&I NCR status Close Open 1603 1530 1530 980 894 894 0 300 600 900 1200 1500 1800 Sampled Tested Passed Sampled Tested Passed Concrete Cylinder testing 34000 30552 411 0 10000 20000 30000 40000 Concrete CM Plant total concrete status Total concrete Completed concrete Last Week Concreting 212 182 99 171 77 33 0 88 0 20 40 60 80 100 120 140 160 180 200 220 SPTL Construction Total towers Tower PO placed Material delivered Profile issued Foundations Erection Slinging ROW issues 7 7 6 4 3 0 5 10 SPTL procurement Total items PO issued Ins. Call rec. FAT Delivery 0% 0% 0% 85% 95% 100% 100% 100% 100% 100% 95% 0% 50% 100% FEL colony major milestonesMaster plan finalization Houses layout finalization Boundary wall marking Boundary wall bid package Bidding ‐ Boundary wall Infrastructure bid package Bidding ‐ Infrastructure BOQ, BEQ, MOQ bid package Bidding ‐ BOQ, BEQ, MOQ Balance colony bid package Bidding ‐ balance colony 70% 40% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Foundations Brick work Finishing works Boundary wall 0% 0% 0% 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Foundations Brick work Piping works Electrical… Finishing… Infrastructure 0% 0% 0% 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Foundations Brick work Piping works Electrical works Finishing works BOQ, BEQ, MOQs 0% 0% 0% 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Foundations Brick work Piping works Electrical works Finishing works Balance colony 50 10 0 10 20 30 40 50 60 70 WQT Passed Failed 80 20 0% 20% 40% 60% 80% 100% Radiography (RT) Performed Remaining 100 50 20 30 15 0 50 100 150 Test Packs Total Ready Flush/Blow Hydrotested Reinstated 18000 2000 2000 0 0 0 16000 16000 18000 18000 0 5000 10000 15000 20000 25000 Total Fitup Weld Testing Painting Piping Shop Fab Dia Inches 4,486 2,467 0 2,019 0 1000 2000 3000 4000 5000 Total Erected Steel Structure (Tons) 960 908 528 0 71 144 196 17.7 1135 0 0 526 00 300 600 900 1200 Boiler 1 Boiler 2 STG hall ESP Bagasse hall Water treatment Coal Handling Misc. Tons Structure erection detailed 778 771 520 0 100 50 326 333 25.7 1135 200 100 450 0 300 600 900 1200 Boiler… Boiler… STG… ESP Bagasse… Water… Coal… Sq. M Sheeting details 1850 4500 0 0 13401400 3350 0 0 700 0 1000 2000 3000 4000 5000 Coal Silo Cooling Tower Bagasse yard Coal yard Fly Ash silo CM Major Concrete Status Total Completed 21 16.8 11 0 0 6 0.9 6.6 80 80 0 20 40 60 80 Coal Silo Cooling Tower Ash Silo Stack 1 Stack 2 M Completion‐High Rise Structures Remaining Achieved 26000 3914 3914 0 22086 22086 18000 0 5000 10000 15000 20000 25000 Total Fitup Welding Testing Piping Erection Dia Inches 7 7 7 6 0 0 0 0 1 7 0 2 4 6 8 10 Foundation Rolling Fitup welding Painting Tanks 5064 167 1081 3816 0 1000 2000 3000 4000 5000 6000 Total shipped packages In sailing At port Delivered at site Equipment shipment 42 0 42 0 10 20 30 40 50 Total Complete System Mechancial Completion 15000 80000 0 15000 80000 0 50000 100000 Cable tray Cable Laying Electrical cable Total Layed Remaining 83000 83000 83000 0 0 0 83000 83000 83000 0 50000 100000 Terminations Hot loop testing Cold loop testing Terminations Total Complete Remaining 2700 2700 3500 410 1210 0 0 0 0 2700 2700 3500 410 121 0 2000 4000 Ins. Calibrated Ins. Installed Local JBs Actuators Control panels Installation Total Complete Remaining 500 400 500 200 150 180 190 170 350 220 310 30 0 100 200 300 400 500 600 Civil Mechanical Electrical Instrumentation Punch Lists‐Category A Total Closed Open 500 400 500 200 150 180 190 170 350 220 310 30 0 100 200 300 400 500 600 Civil Mechanical Electrical Instrumentation Punch Lists‐Category B Total Closed Open 1999 1928 71 20 28 0 1000 2000 3000 Transmittal Received Transmittal Replied T < 7days 7 < T < 14 days T > 14 days Transmittal Status 28 days 7 days 83.4% 100.0% 100.0% 58.6% 78.5% 45.9% 52.6% 20.8% 73.9% 43.8% 56.5% 68.9% 98.8% 96.2% 26.7% 59.0% 17.3% 7.5% 0.1% 36.5% 29.2% 21.1% 0% 20% 40% 60% 80% 100% Overall Engineering Procurement Construction Civil Mechanical Electrical Instrumentation STG Boiler BOP Planned Actual 27 17.7 17.6 80 80