1. LOMA LINDA UNIVERSITY
CLINICAL LABS REMODEL
CONTRACTOR
Serfass and Company
SIZE
2,200 sq.ft.
PROJECT BUDGET
1.3 million
SCHEDULE
6 Months
Completed as scheduled in
September
OWNER REFERENCE
Kent Chow Financial Officer
School of Allied Health
Professions
ARCHITECT REFERENCE
Brad Glassick HMC
Architects
Located in the historical Nichol Hall of the
Loma Linda University Campus. This 1.3
million remodel included but was not limited
to renovations to upgrade and restore the
finishes and furnishings in the Clinical Sciences
Classroom, giving it new lighting, work
benches and an overall contemporary
aesthetic .
Challenges :
• Layout
• Flow
• Utilities
• Technology
• Casework
“Despite these challenges, he has demonstrated
leadership through problem solving and conflict
resolution and effective communication.” Kent
Chow
2. LOMA LINDA UNIVERSITY
SHEPARDSON STREET OVERFLOW PARKING AND SOCCER FIELD
CONTRACTOR
Tilden Coil
SIZE
340,000 sq.ft.
PROJECT BUDGET
3.6 million
SCHEDULE
7 months
Completed as scheduled
January
OWNER REFERENCE
Donald Sease
Director LLU Drayson Center
ARCHITECT REFERENCE
Ken Scofield
Onyx Architects
Develop LLUAHSC Overflow Parking
(563 spaces) with lighting, fence,
landscape and security systems (card
controlled gate, security cameras, etc.).
Develop soccer field expansion for
Drayson Center with artificial turf and
sprinkler pressurization pumps and a new
restroom building.
Challenges:
• Layout
• Permits & Requirements
• Lighting
• Drainage
3. LOMA LINDA UNIVERSITY
NICHOL HALL KITCHEN
CONTRACTOR
Capstone Inc.
SIZE
1,420 sq.ft.
PROJECT BUDGET
1.3 million
SCHEDULE
6 months
Completed as scheduled
September
OWNER REFERENCE
Kent Chow Financial Officer
School of Allied Health
Professions
ARCHITECT REFERENCE
Brad Glassick HMC
Architects
Located in the historical Nichol Hall of the
Loma Linda University Campus. This 1.3
million remodel included but was not limited
to renovations to upgrade and restore the
finishes and furnishings in the space and give
this kitchen a clean and elegant look.
Challenges:
• Layout
• Permits & Requirements
• Flexibility
• Structural
• HVAC & Exhaust
“The project was full of surprises and it was
managed as if they had never occurred.“ Chef
Corey Gheen SAHP
4. LOMA LINDA UNIVERSITY
LLUAHSC SERVICES BUILDING 101 – MOVE MANAGEMENT
MOVE CONTRACTOR
Tangram Interiors
People
600
PROJECT BUDGET
½ million
SCHEDULE
4 months
Completed on scheduled
May
OWNER REFERENCE
Kevin Fischer
Executive Director LLU Real
Estate Management
ARCHITECT REFERENCE
Troy Aday
Aday Architects
Move 600 people from various locations on
the Loma Linda University campus to the
newly constructed LLUAHSC Services
Building 101. Coo
Challenges:
• Scheduling
• Limited down time
• Coordination with
active construction
• IT , IS, and Desktop
coordination
• Space planning
5. LOMA LINDA UNIVERSITY
EVANS HALL AMPHITHEATER
CONTRACTOR
Capstone Inc.
SIZE
1,100 sq.ft.
PROJECT BUDGET
446,00
SCHEDULE
4 months
Completed as scheduled
December
OWNER REFERENCE
Kent Chow Financial Officer
School of Allied Health
Professions
ARCHITECT REFERENCE
Troy Aday
Aday Architects
Renovate the amphitheater in Evans Hall to
provide larger table tops and accessible
desk spaces using new fixed amphitheater
seating. New high efficiency lighting, carpet
and audiovisual for teaching.
Challenges:
• Layout
• Framing Risers
• Schedule
6. LOMA LINDA UNIVERSITY
EVANS HALL TENANT IMPROVEMENT – PHYSICIAN ASSISTANT
CONTRACTOR
Capstone Inc.
SIZE
1,100 sq.ft.
PROJECT BUDGET
446,00
SCHEDULE
4 months
Completed as scheduled
December
OWNER REFERENCE
Kent Chow Financial Officer
School of Allied Health
Professions
ARCHITECT REFERENCE
Troy Aday
Aday Architects
Renovate level 2 of Evans Hall for the
relocation of the Physician’s Assistant
program. Scope included move
management,
Challenges:
• Layout
• Schedule
• Asbestos/Lead Abatement
• Schedule
• Changes
7. LOMA LINDA UNIVERSITY
LINDSAY HALL KITCHEN
CONTRACTOR
Serfass and Company
SIZE
2,200 sq.ft.
PROJECT BUDGET
1.3 million
SCHEDULE
6 Months
Completed December
OWNER REFERENCE
Lynette Bates
ARCHITECT REFERENCE
Alfredo E. Neyra Architect
The Lindsay Hall Female dormitory
kitchen remodel the existing Kitchen
and expand it to provide room for all
the Health Department-required
kitchen facilities and equipment.
Challenges :
• Layout
• Permits & Requirements
• Flow
• Utilities
• Casework