SlideShare ist ein Scribd-Unternehmen logo
1 von 9
Progrès et Courbe d’avancement
001
EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ
1
What is Performance Measurement?
Performance measurement is the practice of analyzing project progress and understanding what it means within the context of the overall project plan and goals.
Performance measurement enables project professionals to compare task or project progress against trends and benchmarks, such as past performance and expected
progress. The practice of performance variance analysis allows them to pinpoint which areas of the project are behind or ahead and where their focus is needed.
The most common way to conduct performance measurement is through Earned Value Management (EVM). EVM compares cost and schedule progress against project
baselines, budgets, and expected future outcomes.
There are a number of formulas involved in EVM analysis. These include :
 Earned Value (EV): % complete (from progress measurement) x BAC (budget at completion) or the sum of PV of all completed tasks to date.
 Planned Value (PV): The authorized budget assigned to scheduled work (usually at the control account level).
 Cost Variance (CV): This is EV – AC. AC stands for actual cost.
 Schedule Variance (SV): Calculated as EV – PV.
 Schedule Performance Index (SPI): EV/PV.
 Cost Performance Index (CPI): EV/AC.
 Variance at Completion (VAC): BAC (Budget at Completion) – EAC (Estimate at completion).
 Estimate to Completion (ETC): Calculated as EAC – AC or by creating a new bottom-up estimate of all work remaining.
 Estimate at Completion (EAC): This value can be calculated many ways, including:
 AC (actual costs to date) + Bottom-up ETC (new estimates for costs remaining).
 BAC / Cumulative CPI, to forecast based on efficiency so far.
 AC + (BAC – EV), to calculate actual costs so far plus the remaining value of work to be completed.
 AC + (BAC – EV/ (Cumulative CPI * Cumulative SPI)), to find actual to date plus the remaining budget adjusted for project efficiency rates so far.
 Using simulation software to predict when a project will complete and how much it will cost based on performance so far and predictions about
whether performance may improve, drop, or stay on-trend.
 To Complete Performance Index (TCPI): TCPI is used to calculate the cost performance that must be achieved to hit the cost target. Using EAC the formula
is (BAC – EV) / (EAC – AC).
Progrès et Courbe d’avancement
001
EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ
2
Five Key Processes Involved with Progress &
Performance Measurement
The following five processes are required for successful progress and performance measurement:
1. Progress measurement planning: This process involves determining the level and type of progress measurement. It generally
includes answering the Following questions:
1. Will the project team measure progress at the task level, cost control level, or higher?
2. Which method will be used to assess progress on each aspect of the project? (e.g., cost-based, hours-based, etc.)
3. How often will progress be gathered? (e.g., weekly, bi-weekly, or monthly.)
4. Who will be responsible for reporting it? (e.g., team members, supervisors, department heads.)
5. What tools will they need? (Will it require actual-hours reports, do they need to visually inspect product completion, will
they input progress directly into the software or send it to someone else?)
2. Performance measurement planning: During this process, project managers will plan out how performance measurement is inputted,
analyzed, and reported on. It will often also include guidelines for action. Key aspects of this process are:
1. Determining how frequently performance will be analyzed and reported on
2. Deciding metrics to be analyzed and tracked (for example, measuring against benchmarks, only tracking CPI & SPI, etc.)
3. Setting guidelines around the level of analysis and reporting (CPI & SPI reported weekly, EAC updated monthly, etc.)
Progrès et Courbe d’avancement
001
EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ
3
4. Documenting criteria around acceptable and ideal performance metrics (If performance drops below a certain threshold,
will it trigger an action? I.e., if cumulative SPI dips below 0.75, will overtime be assigned to help catch up?)
3. Executing progress and performance measurement: In the execution process, the people in charge of tracking and reporting progress
(as per the plan) will follow the steps to assess and input the data. The person or people in charge of analysis will ensure all data is
provided, run analytics, and report on performance in accordance with the set plan.
4. Monitoring progress and performance and implementing control actions: In this process, project managers and other stakeholders
will review performance metrics and determine whether action is required. They may be required to manage expectations around
expected completion dates, request more funding or resources, or simply provide assurances that everything is on track. If there are
rewards tied to achieving targets, they would be provided as part of this process.
5. Closure of progress and performance measurement activities: At the end of the project, after the final progress and performance
results are reported, the project data may be analyzed for lessons learned. Then, as the project is closed, the data will be stored so
that teams can use it in the future to improve estimates and forecasts for similar projects.
Progrès et Courbe d’avancement
001
EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ
4
Key Tracking Metrics for Progress & Performance
Measurement
Key performance measurements, and their meanings, are :
Progrès et Courbe d’avancement
001
EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ
5
TCPI is often one of the more difficult ratios to grasp, so an illustration may be helpful:
If a TCPI of 1.20 is calculated, it means that in order to spend no more than the overall project budget, the project needs to earn a CPI of 1.20 for the
remainder of the project.
Then, compare this to the cumulative CPI so far to make predictions about whether this is feasible. For instance, if the cumulative CPI is 0.76, one may
determine the TCPI is unrealistic, and that more money will need to be requested in order to finish the project.
Note: CPI, SPI, and TCPI are more common than CV, SV, and VAC as they are more easily comparable across tasks, activities, and projects. A CV of -
$5,000 may be much worse than a CV of -$25,000 if the total budget for the task or cost control account is significantly lower. Therefore, dollar values alone
are only marginally useful when making comparisons.
The Importance of Progress Management & Performance
Measurement
Progress measurement enables project professionals to track and monitor how close to completion a job, activity, or project is. When this progress is
analyzed using performance measurement metrics, it provides insights into how the project is going.
Without these tools, it becomes difficult to predict whether a project will complete on-time or within budget. Project managers and executives will be reliant
on subjective judgment and their own experience, which limits the consistency, objectiveness, and accuracy of one’s progress management.
Progress and performance measurement also improve the project team’s knowledge of what is currently occurring and strengthens their ability to predict
what will occur in the future. It can act as an early warning sign for potential issues and provides data to help improve future project estimates and planning.
Performance measurement data also enables project managers and stakeholders to set key performance metrics (KPIs) and benchmarks to measure future
performance against.
Progrès et Courbe d’avancement
001
EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ
6
Benefits of Using Progress and Performance
Measurement
According to a survey by PMI, only slightly more than half of projects finish within their planned schedule (52%) and budget (57%). Leading causes of project
failure were inaccurate estimates, limited resources, poor forecasting, and a general lack of visibility and communication.
By measuring performance, project teams gain greater insights into what is required to complete their ongoing projects, thereby improving visibility and
forecasting.
By being able to see performance trends early on and monitor changes, project teams can become more proactive about communicating progress and
requesting additional resources that they may need. The forecasting for the remainder of the project will also improve, as it will be based upon quantitative
data, and not just subjective assessments.
Additionally, by measuring and storing progress data, project managers improve their ability to create more realistic project estimates in the future. This
practice will result in a greater chance of success for those projects and a better ability to proactively plan for the number of resources that will be needed
long-term.
In short, progress and performance measurement are essential tools that enable project teams to stay on top of project performance and improve future
project planning. In the long-term, this enables them to be more proactive and results in a higher project success rate.
Progrès et Courbe d’avancement
001
EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ
7
Progress Management & Performance Measurement Key
Takeaways
Progress and performance measurement are essential elements of the monitor and control phase of any project. Progress measurement enables key
stakeholders to understand how close to completion tasks, activities, and projects are. Performance measurement allows management to understand how
the project is performing in comparison to the project plan and other relevant targets.
Together, progress and performance information grant the ability to discover potential issues early and be proactive about ensuring deadlines and goals are
hit. Performance data also improves future project estimates and forecasts.
Robust project controls software such as ARES PRISM provides a centralized, easy-to-use database to input, store, analyze, and report on progress and
performance measurement.
Progrès et Courbe d’avancement
001
EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ
8
Pre-Progressing Project Setup Checklist
Ensure you setup these items in your project before you start your First Progressing cycle.
 Show Time of Day with dates
 Ensure Project Start isn’t 12:00 am
 Ensure Data Date isn’t 12:00 am
 Use Project -Level Calendar
 Calendar Time Periods are correct
 Calendar non-work days +24>PF
 Use project Level Activity codes
 Financial Periods/calendar set?
 Set Physical % Complete All Acts
 Set Fixed Duration & Units/Time All Acts
Progrès et Courbe d’avancement
001
EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ
9
Description
This course is so designed that it covers every aspect of implementation. If you are working in large scale firms then you will get a picture of how projects are managed there. This will
make you able to organize projects, control access to projects, organize and control resources and in effectively planning, monitoring and controlling of the project. Similarly, if you are
working in small or a medium scale firm, or if you are new to Project Management and Primavera, you will get to know all the required core concepts of Project Management along with
examples and you will learn their implementation in Primavera P6 from start to end.
What will you learn
 After successful completion of this course, you will be able to develop a Schedule, update and monitor the Schedule, control the Schedule, generate reports, allocate cost and
resources.
 You can develop cash flows and s-curves, monitor and control cost and resources.
 You Will also understand lots of interesting Project Management concepts.
Chapter: 1 Introduction About Primavera P6
Chapter: 2 About WBS Create WBS code To View WBS
Chapter: 3 Introduction About Activity to Create a New Activity Relationship – Predecessors Schedule
Chapter: 4 Introduction About Calendar Types of Calendar Assigning Calendar to Project
Chapter: 5 About Project Codes Creating Project Codes To View the Project
Chapter: 6 About EPS To Create a New EPS
Chapter: 7 Resource types To Create Resource Assigning Resources
Chapter: 8 Activity Codes to Create an Activity Codes Assigning Activity Codes to View the Codes
Chapter: 9 About Expense to Create Expenses to View the Cost of -the Project or Budgeted cost Work Products & Documents Thresholds Issues & Risks
Chapter: 10 To Create New Baselines to View Cost Variance
Chapter: 11 Critical Path Method Constraints
Chapter: 12 Schedule Progress Progress Lines Progress Spotlight
Chapter: 13 Reports Creating Reports Report Wizard Export
Chapter: 14 Project

Weitere ähnliche Inhalte

Ähnlich wie formation.docx

2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise
 
Project management
Project managementProject management
Project management
Ahmed Said
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
Shraddha PMP
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best Practices
Ricardo Leite
 

Ähnlich wie formation.docx (20)

IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project management
Project managementProject management
Project management
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Measuring in
Measuring inMeasuring in
Measuring in
 
Measuring in
Measuring inMeasuring in
Measuring in
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.ppt
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software Engineering
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best Practices
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 

Kürzlich hochgeladen

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 

Kürzlich hochgeladen (20)

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 

formation.docx

  • 1. Progrès et Courbe d’avancement 001 EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ 1 What is Performance Measurement? Performance measurement is the practice of analyzing project progress and understanding what it means within the context of the overall project plan and goals. Performance measurement enables project professionals to compare task or project progress against trends and benchmarks, such as past performance and expected progress. The practice of performance variance analysis allows them to pinpoint which areas of the project are behind or ahead and where their focus is needed. The most common way to conduct performance measurement is through Earned Value Management (EVM). EVM compares cost and schedule progress against project baselines, budgets, and expected future outcomes. There are a number of formulas involved in EVM analysis. These include :  Earned Value (EV): % complete (from progress measurement) x BAC (budget at completion) or the sum of PV of all completed tasks to date.  Planned Value (PV): The authorized budget assigned to scheduled work (usually at the control account level).  Cost Variance (CV): This is EV – AC. AC stands for actual cost.  Schedule Variance (SV): Calculated as EV – PV.  Schedule Performance Index (SPI): EV/PV.  Cost Performance Index (CPI): EV/AC.  Variance at Completion (VAC): BAC (Budget at Completion) – EAC (Estimate at completion).  Estimate to Completion (ETC): Calculated as EAC – AC or by creating a new bottom-up estimate of all work remaining.  Estimate at Completion (EAC): This value can be calculated many ways, including:  AC (actual costs to date) + Bottom-up ETC (new estimates for costs remaining).  BAC / Cumulative CPI, to forecast based on efficiency so far.  AC + (BAC – EV), to calculate actual costs so far plus the remaining value of work to be completed.  AC + (BAC – EV/ (Cumulative CPI * Cumulative SPI)), to find actual to date plus the remaining budget adjusted for project efficiency rates so far.  Using simulation software to predict when a project will complete and how much it will cost based on performance so far and predictions about whether performance may improve, drop, or stay on-trend.  To Complete Performance Index (TCPI): TCPI is used to calculate the cost performance that must be achieved to hit the cost target. Using EAC the formula is (BAC – EV) / (EAC – AC).
  • 2. Progrès et Courbe d’avancement 001 EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ 2 Five Key Processes Involved with Progress & Performance Measurement The following five processes are required for successful progress and performance measurement: 1. Progress measurement planning: This process involves determining the level and type of progress measurement. It generally includes answering the Following questions: 1. Will the project team measure progress at the task level, cost control level, or higher? 2. Which method will be used to assess progress on each aspect of the project? (e.g., cost-based, hours-based, etc.) 3. How often will progress be gathered? (e.g., weekly, bi-weekly, or monthly.) 4. Who will be responsible for reporting it? (e.g., team members, supervisors, department heads.) 5. What tools will they need? (Will it require actual-hours reports, do they need to visually inspect product completion, will they input progress directly into the software or send it to someone else?) 2. Performance measurement planning: During this process, project managers will plan out how performance measurement is inputted, analyzed, and reported on. It will often also include guidelines for action. Key aspects of this process are: 1. Determining how frequently performance will be analyzed and reported on 2. Deciding metrics to be analyzed and tracked (for example, measuring against benchmarks, only tracking CPI & SPI, etc.) 3. Setting guidelines around the level of analysis and reporting (CPI & SPI reported weekly, EAC updated monthly, etc.)
  • 3. Progrès et Courbe d’avancement 001 EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ 3 4. Documenting criteria around acceptable and ideal performance metrics (If performance drops below a certain threshold, will it trigger an action? I.e., if cumulative SPI dips below 0.75, will overtime be assigned to help catch up?) 3. Executing progress and performance measurement: In the execution process, the people in charge of tracking and reporting progress (as per the plan) will follow the steps to assess and input the data. The person or people in charge of analysis will ensure all data is provided, run analytics, and report on performance in accordance with the set plan. 4. Monitoring progress and performance and implementing control actions: In this process, project managers and other stakeholders will review performance metrics and determine whether action is required. They may be required to manage expectations around expected completion dates, request more funding or resources, or simply provide assurances that everything is on track. If there are rewards tied to achieving targets, they would be provided as part of this process. 5. Closure of progress and performance measurement activities: At the end of the project, after the final progress and performance results are reported, the project data may be analyzed for lessons learned. Then, as the project is closed, the data will be stored so that teams can use it in the future to improve estimates and forecasts for similar projects.
  • 4. Progrès et Courbe d’avancement 001 EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ 4 Key Tracking Metrics for Progress & Performance Measurement Key performance measurements, and their meanings, are :
  • 5. Progrès et Courbe d’avancement 001 EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ 5 TCPI is often one of the more difficult ratios to grasp, so an illustration may be helpful: If a TCPI of 1.20 is calculated, it means that in order to spend no more than the overall project budget, the project needs to earn a CPI of 1.20 for the remainder of the project. Then, compare this to the cumulative CPI so far to make predictions about whether this is feasible. For instance, if the cumulative CPI is 0.76, one may determine the TCPI is unrealistic, and that more money will need to be requested in order to finish the project. Note: CPI, SPI, and TCPI are more common than CV, SV, and VAC as they are more easily comparable across tasks, activities, and projects. A CV of - $5,000 may be much worse than a CV of -$25,000 if the total budget for the task or cost control account is significantly lower. Therefore, dollar values alone are only marginally useful when making comparisons. The Importance of Progress Management & Performance Measurement Progress measurement enables project professionals to track and monitor how close to completion a job, activity, or project is. When this progress is analyzed using performance measurement metrics, it provides insights into how the project is going. Without these tools, it becomes difficult to predict whether a project will complete on-time or within budget. Project managers and executives will be reliant on subjective judgment and their own experience, which limits the consistency, objectiveness, and accuracy of one’s progress management. Progress and performance measurement also improve the project team’s knowledge of what is currently occurring and strengthens their ability to predict what will occur in the future. It can act as an early warning sign for potential issues and provides data to help improve future project estimates and planning. Performance measurement data also enables project managers and stakeholders to set key performance metrics (KPIs) and benchmarks to measure future performance against.
  • 6. Progrès et Courbe d’avancement 001 EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ 6 Benefits of Using Progress and Performance Measurement According to a survey by PMI, only slightly more than half of projects finish within their planned schedule (52%) and budget (57%). Leading causes of project failure were inaccurate estimates, limited resources, poor forecasting, and a general lack of visibility and communication. By measuring performance, project teams gain greater insights into what is required to complete their ongoing projects, thereby improving visibility and forecasting. By being able to see performance trends early on and monitor changes, project teams can become more proactive about communicating progress and requesting additional resources that they may need. The forecasting for the remainder of the project will also improve, as it will be based upon quantitative data, and not just subjective assessments. Additionally, by measuring and storing progress data, project managers improve their ability to create more realistic project estimates in the future. This practice will result in a greater chance of success for those projects and a better ability to proactively plan for the number of resources that will be needed long-term. In short, progress and performance measurement are essential tools that enable project teams to stay on top of project performance and improve future project planning. In the long-term, this enables them to be more proactive and results in a higher project success rate.
  • 7. Progrès et Courbe d’avancement 001 EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ 7 Progress Management & Performance Measurement Key Takeaways Progress and performance measurement are essential elements of the monitor and control phase of any project. Progress measurement enables key stakeholders to understand how close to completion tasks, activities, and projects are. Performance measurement allows management to understand how the project is performing in comparison to the project plan and other relevant targets. Together, progress and performance information grant the ability to discover potential issues early and be proactive about ensuring deadlines and goals are hit. Performance data also improves future project estimates and forecasts. Robust project controls software such as ARES PRISM provides a centralized, easy-to-use database to input, store, analyze, and report on progress and performance measurement.
  • 8. Progrès et Courbe d’avancement 001 EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ 8 Pre-Progressing Project Setup Checklist Ensure you setup these items in your project before you start your First Progressing cycle.  Show Time of Day with dates  Ensure Project Start isn’t 12:00 am  Ensure Data Date isn’t 12:00 am  Use Project -Level Calendar  Calendar Time Periods are correct  Calendar non-work days +24>PF  Use project Level Activity codes  Financial Periods/calendar set?  Set Physical % Complete All Acts  Set Fixed Duration & Units/Time All Acts
  • 9. Progrès et Courbe d’avancement 001 EPC WORKS FOR XYZ PROJECT Prepare by : Hichem GUENDOUZ 9 Description This course is so designed that it covers every aspect of implementation. If you are working in large scale firms then you will get a picture of how projects are managed there. This will make you able to organize projects, control access to projects, organize and control resources and in effectively planning, monitoring and controlling of the project. Similarly, if you are working in small or a medium scale firm, or if you are new to Project Management and Primavera, you will get to know all the required core concepts of Project Management along with examples and you will learn their implementation in Primavera P6 from start to end. What will you learn  After successful completion of this course, you will be able to develop a Schedule, update and monitor the Schedule, control the Schedule, generate reports, allocate cost and resources.  You can develop cash flows and s-curves, monitor and control cost and resources.  You Will also understand lots of interesting Project Management concepts. Chapter: 1 Introduction About Primavera P6 Chapter: 2 About WBS Create WBS code To View WBS Chapter: 3 Introduction About Activity to Create a New Activity Relationship – Predecessors Schedule Chapter: 4 Introduction About Calendar Types of Calendar Assigning Calendar to Project Chapter: 5 About Project Codes Creating Project Codes To View the Project Chapter: 6 About EPS To Create a New EPS Chapter: 7 Resource types To Create Resource Assigning Resources Chapter: 8 Activity Codes to Create an Activity Codes Assigning Activity Codes to View the Codes Chapter: 9 About Expense to Create Expenses to View the Cost of -the Project or Budgeted cost Work Products & Documents Thresholds Issues & Risks Chapter: 10 To Create New Baselines to View Cost Variance Chapter: 11 Critical Path Method Constraints Chapter: 12 Schedule Progress Progress Lines Progress Spotlight Chapter: 13 Reports Creating Reports Report Wizard Export Chapter: 14 Project