SlideShare ist ein Scribd-Unternehmen logo
1 von 11
Downloaden Sie, um offline zu lesen
STOP PROCRASTINATING! NPV IS DEAD:  USE RISK AS A KEY 
                       DECISION PARAMETER.

                                       Cesar Oboni1 and Franco Oboni2

    1
     Oboni Riskope Associates Inc. Vancouver, BC, Canada, V6Z 2A9 coboni@riskope.com 
                     2
                       Oboni Riskope International foboni@riskope.com


Abstract: Two case studies:  1) introducing an in­pit crushing & conveying system v.s. shovel & 
trucking in a large dump reclamation project and 2) long term pumping v.s. encapsulation of a 
very   large,  leaching,   underground  toxic  waste   storage,  are  presented   to  show  that  risks   as   a 
discriminant parameter should be used for successful long term planning at the inception of any 
project to manage rational decisions. One case is dealt with qualitatively at the pre­feasibility 
level and the other quantitatively at the preliminary design level. 

At  the  pre­feasibility   level   it   is   shown   that   graphic   methodologies   coupled   with   simple 
procedures   can   efficiently   pinpoint   weakness   areas,   leading   to   better   decisions  and  thus 
appropriate mitigations. At the preliminary design level we show innovative approaches, which 
eliminate the pitfalls of Net Present Value (NPV), a financial evaluator still used by many. The 
NPV is replaced by an analytical tool called  Comparative  Decision  Analysis/Economic  Safety 
Margin (CDA/ESM™), used to compare alternatives in financial terms including: a) life’s cycle 
balance   encompassing   internal   and   external   risks   over   a   selected   duration,   b)  project 
implementation and demobilization costs and risks. CDA/ESM has been successfully applied to: 
rope   v.s.   road   transportation,   surface   v.s.   underground   solutions,   environmental   projects, 
transportation networks and go/no­go decisions. 

Résumé: Deux études de cas sont présentées: 1) Introduction dans une mine à ciel ouvert d'un 
concasseur   couplé   à   une   courroie   transporteuse   en   remplacement   de   la   classique   solution 
excavatrice­camionnage pour la mise en demeure des stériles, 2) Pompage comparativement à 
l'encapsulation a long terme d'un très grand stockage souterrain des déchets toxiques. Le but est 
de montrer que les risques devraient être utilisés comme paramètre discriminant pour opérer des 
décisions rationnelles, conduisant à la réussite de la planification à long terme, et ceci depuis le 
début de n'importe quel projet. Le 1er cas est traité qualitativement au niveau de la pré­faisabilité, 
les autres quantitativement au niveau de la conception préliminaire.
Au   niveau   de   pré­faisabilité,   il   est   démontré   que   les   méthodes   graphiques   de   pair   avec   des 
procédures simples peuvent identifier efficacement les zones de faiblesse et de conduire à de 
meilleures   décisions,   ce   qui   permet   une   réduction   appropriée   des   risques.   Au   niveau   de   la 
conception préliminaire, nous montrons des approches novatrices qui permettent d'éliminer les 
pièges de la valeur actuelle nette (VAN), un outil financier encore généralement utilisé. La VAN 
est remplacée par un outil d'Analyse Comparative de  Decision / Marge de Sécurité Economique 
(CDA/ESM™), qui sert à comparer des alternatives en termes financiers, notamment: a) le cycle 
de vie englobant les risques internes et externes, au cours d'une durée sélectionnée, b) le coûts et 
les risques d'implémentation et de  démobilisation . La CDA/ESM™ a été appliquée avec succès 
au mode de transport par câble contre celui routier; aux solutions  de surfaces contre celles sous­
terraines, à des projets environnementaux , des réseaux de transport et des décisions oui/non.

Introduction

Two anonymous case studies taken from our day to day practice, thus covered by confidentiality, 
are presented in this paper to show: a) how risk can be used as a key decision parameter and b) 
how the commonly used Net Present Value (NPV), which is deterministic and generally does not 
include properly defined risk, can create distortions and biases when analyzing industrial (or 
other) alternatives. The two case studies are:

1) Introducing an in­pit crushing & conveying system (IPC&CS) v.s. shovel & trucking (S&T) in 
a large dump reclamation project we studied in 2008. 
2)  Long  term pumping v.s. encapsulation of a very large, leaching, underground toxic waste 
storage which we are currently reviewing.

Case Study 1: Introducing In­Pit Crushing & Conveying System v.s. Shovel & 
Trucking in a Large Dump Project.

A large coal mining company asked us to support their decision making related to a possible 
change   from   conventional   S&T   versus   IPC&CS   dumping.   The   operation   was   experiencing 
various critical personnel issues and difficulties with the ageing truck fleet which would require a 
large capital investment for renewal and maintenance (tire costs, etc.). Furthermore, in the long 
run, the cost of diesel will most certainly rise, again causing concern. 

In   order   to   alleviate   these   concerns,   and   reduce   costs,   future   emissions,   and   also   potential 
business   interruptions   due   to   shovelling   problems,   the   company   decided   to   develop   a   pre­
feasibility study exploring the possibility of implementing a IPC&CS. 
At the pre­feasibility level the aim of our actions was to identify situations that could hinder the 
performances of the project and define issues that needed to be immediately addressed. Our goal 
was also to identify issues that could generate high risks for an otherwise well designed plan, 
such as, rejection by the workforce or by nearby residents. The two main areas related to the 
possible implementation of IPC&CS at the mining operation were addressed by:

1) A preliminary qualitative comparison between the exposure­risk environment of the base case, 
i.e. S&T, vs. the IPC&CS. Risks can be upside (opportunities) or downside (the “classic” view of 
risk linked to mishaps).
2) A preliminary qualitative risk assessment of the project which identifies conditions that could 
adversely   impact   the   IPC&CS.   This   includes   qualitative   judgments   on   their   likelihood   of 
occurrence and consequences.

In the process of performing the qualitative risk assessment several hazardous conditions which 
could   be   easily   managed   by   design   solutions   were   flagged   in   the   first   step   of   a   proactive 
development   plan   where   risks   are   used   to   drive   the   better   design   of   projects   and   increased 
sustainability.

Hazard, Exposures, Advantages & Disadvantages Identification

Advantages and disadvantages of the IPC&CS over S&T (representing the Status Quo), were 
identified   in   a   facilitated   workshop   session   with   the   participation   of   key   stakeholders.   For 
example reduced diesel consumption was flagged as an obvious advantage for IPC&CS whereas 
necessary operational changes were considered a disadvantage. Advantages and disadvantages 
were defined at first for an “ideal perfect alternative” such as a perfectly functioning IPC&CS 
where obvious hazardous conditions and risk exposures would be mitigated to a satisfactory level 
(i.e. the design covers “good sense issues” and represents “good engineering,” as discussed later). 
The   advantage/disadvantage   session   was   immediately   followed­up   by   a   hazard   Identification 
session. Hazards were categorized and recorded in a specific table which included the Category 
of Hazard, Probability, Magnitude, Potential Target(s) and Qualitative Consequences.

Our pre­feasibility qualitative risk analysis goal was to reduce the chances of a fatal flaw in the 
design, by defining proper design parameters and bringing changes to the preliminary design 
geared towards increasing the chances that the future implementation would work and perform as 
intended. Of course the newly defined parameters and changes would have to be integrated in the 
costs estimates in order to avoid the project possibly becoming a “financial fiasco.”

A pre­feasibility study should cover a wide array of issues that could be seen as “good sense” or 
“good engineering” in addition to the classic issues of a risk assessment. “Good sense” issues do 
not generally require a detailed consequence analysis, to say it simply, if they are not somehow 
dealt with the system will not perform as intended. This type of study represents a first proactive 
step   in   the   direction   of   facility   risk   management   and   includes   risks  as   decision   making 
parameters. This  concept is better explained with a plot (Figure 1) depicting risk mitigation 
geared towards reaching specific levels of residual risks vs. mitigative investments.

In Figure 2 and 3, the black hexagon perimeter depicts the level of exposure of the base case. The 
green and red hexagons represent reduced and increased exposures levels, respectively, for the 
IPC&CS   at   this   operation.  The   term   “exposure”   is   used   here   to   make   clear   the   distinction 
between   a   standard   solution   for   the   IPC&CS   (one   that   is   not   customized   to   the   company’s 
particular conditions, thus is not mitigated to an appropriate level, and would most likely “not 
work as intended”) and the preliminary design generated after our pre­feasibility study (i.e. a 
IPC&CS mitigated to such a point that it is equivalent to S&T). Once mitigations actions are 
finally selected by the design team it becomes possible to develop a residual risk assessment 
which should be quantitative and not qualitative, to verify the pertinence and level of the selected 
mitigations alternatives (see Case Study 2).

Thus, Figure 2 depicts the comparison between IPC&CS and S&T at the considered coal mine 
with no specific mitigations implemented. As a result, in this example, the Fossil Fuel and Tire 
issues are depicted as lower exposures of the IPC&CS with respect to S&T, whereas extreme 
cold and winds are depicted as an increased exposure of the IPC&CS (as this graph does not yet 
take into account possible design mitigations). The Figure 3 concept is identical to the prior one, 
but it depicts a situation where all the possible design mitigations identified for the IPC&CS 
would   have   been   brought   into   the   design   in   order   to   at   least   equalize   the   exposures   of   the 
IPC&CS to the ones of S&T. 
                                                                                     The passage from the initial to 
                                                                                     the   mitigated   exposure 
                                                                                     landscape   requires   investment 
                                                                                     and   running   expenses   which 
                                                                                     have   to   be   integrated   in   the 
                                                                                     cost   estimates.   The   optimal 
                                                                                     solution   may   be   an 
                                                                                     intermediate   mitigation   level 
                                                                                     between   the   “green”   (fully 
                                                                                     mitigated) and the “red” (non 
                                                                                     mitigated) landscapes, i.e., the 
                                                                                     “yellow”   line   depicted   in 
                                                                                     Figure 4. 

                                                                   Consequences related to selec­
Figure 1.  Risk mitigation geared towards reaching specific levels ting an insufficient mitigation 
of residual risks vs. mitigative investments.                      level may range from high   to 
                                                                   catastrophic as the facility may 
                                                                   never   work   as   intended.   The 
                                                                   optimal   solution   will   be 
                                                                   somewhere   between   the 
                                                                   "green"   and   "red"   landscapes 
                                                                   presented   in   Figure   4   and   is 
                                                                   represented   by   the   "yellow" 
                                                                   line.   In the next phase of the 
                                                                   project we will start looking at 
                                                                   the   probabilities   and   residual 
                                                                   risks   (after   a   level   of 
                                                                   mitigation   has   been   selected 
                                                                   by   the   design   team   based   on 
                                                                   the   results   of   the   feasibility 
                                                                   study).

                                                                                   Preliminary Qualitative Risk 
                                                                                   Assessment

                                                                                   Once   the   appropriate   mitiga­
Figure 2.  Comparison between IPC&CS and S&T at the                                tion   level   for   the   issues 
considered coal mine with no specific mitigations implemented.                     described  in   the   prior  section 
are introduced in the design, the system will still be subject to two sets of risks: a) the residual 
risks derived from design mitigated hazards (which depend, as pointed out earlier, on the level of 
mitigation   selected   by   the   design   team)   and   b)   risks   linked   to   other   issues   which   may   be 
independent  from design mitigation   efforts  because  they find their roots  in  public/workforce 
perception:

                                                                                    ● Union/personnel unrest
                                                                                    ● Public outcry linked to 
                                                                                         dust   and   noise   and 
                                                                                         perceived   hazards   as 
                                                                                         the   new   operation   is 
                                                                                         implemented, etc.
                                                                                 If the design mitigation level 
                                                                                 are   not   sufficient,   then   the 
                                                                                 following   situations   may 
                                                                                 arise for the IPC&CS:
                                                                                 •  Refusal   to   accept   the 
                                                                                 changes   brought   by   the 
                                                                                 implementation
                                                                                 •  The system will not reach 
                                                                                 the   promised   performance 
                                                                                 level
                                                                                 •  The   company   will   not 
                                                                                 produce   the   appropriate 
                                                                                 product
 Figure 3.  Same as Fig. 2, but all the possible design mitigations  •Repeated serviceability pro­
 identified for the IPC&CS would have been brought into the design blems
 in order to at least equalize the exposures of the IPC&CS to the 
 ones of S&T.                                                                    All   of   the   last   four   points 
                                                                                 could   have   large   to 
                                                                                 catastrophic   consequences 
for the project, and probabilities that will depend on the mitigation levels defined by the design 
team. If the pre­feasibility level is passed by the IPC&CS, the next step will be to review all of 
the   proposed  mitigations,   define   the   residual   probabilities   of   failure   and   evaluate   mitigation 
alternatives.

As per the public/workforce perception issues, a well thought PR and information campaign, 
including   stakeholders   participation,   will   greatly   help   in   solving   any   arising   issue   before   it 
becomes a problem. Of course the criticality of the issues will be an inverse function of the 
design   mitigation   level,   and  will   directly  influence  the   effort  and   investment   directed  to  the 
PR/information campaign.
Figure. 4  The difference between the two 
  exposures landscapes requires investment.

Case   Study   2:  Long   Term   Pumping   v.s.   Encapsulation   of   a   Very   Large, 
Leaching, Underground Toxic Waste Storage.

This case considers a large underground storage of a toxic water soluble compound with the 
potential to leach into the water table. In order to prevent the leaching a pumping system has been 
installed. In the Status Quo, the permanent pumping system keeps the underground water level 
below the lower level of the storage. However, water percolates from the surface and some of the 
compound is dissolved, leading to the need to treat the pumped water. In the Status Quo, we will 
assume there is negligible risk to the ecosystem and human health. The “financial parameters” 
and risks linked to maintaining the Status Quo are summarized in Table 1 (in Million $, noted 
M).

Cause/Hazard for Status Quo alternative                                      Probability Cost M$
Capital investment will be necessary at start on the treatment plant         90%          5
Energy cost (diesel for the power plant) has a yearly chance of              30%          to double
Climate changes has a yearly chance of                                       15%          to triple
Table 1.  “Financial parameters” of the Status Quo alternative.

The alternative to the Status Quo would be a Rehabilitation of the site, i.e. Encapsulation of the 
underground storage (how that's done is not within the scope of this paper). The encapsulation 
would require a large capital investment (120M), but afterwards the permanent pumping and 
treatment would be reduced considerably. 
Cause/Hazard for Encapsulation alternative                                  Probability   Cost M$
Capital investment has a chance to double (additional 120M) of              10%           120
Energy cost (diesel for the power plant) has a yearly chance of             30%           to double
Climate changes can force to still pump like today despite the encapsulation  5%          3.6
work, with a chance of
Table 2.  “Financial parameters” of the Ecapsulation alternative.
As this encapsulation constitutes a “first in the world,” a Risk Assessment has been performed 
which has shown that there is a significant chance that the encapsulation may cost twice as 
foreseen.   The   “financial   parameters”   and   risks   linked   to   building   and   maintaining   the 
Rehabilitation are summarized in Table 2 (in Million $, noted M).

Finally, because of uncertainties (construction, long term climate change, etc.) there is also a 
chance that after developing the encapsulation as above (i.e. with the chance it may cost twice 
the initially foreseen amount), it may be necessary to maintain pumping as in the Status Quo. 
This means that despite investing in the encapsulation the project still does not work properly, 
which is an example of a failed rehabilitation case or a worst case scenario.




Figure 5.  Status Quo data sheet, as per the Riskope's CDA­ESM 
application

Traditional NPV Analysis

As usual in mining projects let's use a Rate of Return of 9% for this analysis and consider a life 
duration of forty years as an example. NB: the NPV are always marked as negative values in this 
study to stress the fact that the project generates only expenses and no profits.

         • Rehabilitation: 120M$ construction, then 0.3M$/yr, 40 years life span NPV: ­123.23M$
         • Status Quo: 3.6M$/yr, 40 years life span NPV: ­42.33M$

What makes this case study particularly strong in building an argument  against using NPV for 
alternative   selection   is   that   most   of  the   expense   in   Rehabilitation   is   upfront,   and   the   yearly 
expenses (as traditionally done, without the risks) are small, meanwhile the duration is very long
— in this case the NPV almost “nullifies” any expense coming after approximately 20 years.
It can be inferred by this simple analysis that the Status Quo has by far a better NPV value than 
the Rehabilitation which we will show later is a wrong estimation because of the long life of the 
project, and the risks that need to be included. There are two ways such an analysis could be 
altered to include risks. One would be to add the yearly risks as an additional cost and another 
would be to increase the rate of discount to “include uncertainties” as we have seen some do. 
Both these attempts would fail to yield pertinent results as we discuss below. Whenever used the 
NPV would strongly indicate the Status Quo as the most viable among the two alternatives in this 
case study.

Suppressing NPV and Using Risk as a Key Decision Parameter.

As with this case study, innovative approaches which eliminate the pitfalls of NPV have been 
used at the preliminary design level (Oboni and Oboni 2007, 2008; Oboni 1999­2000, 2005). The 
adopted replacement analytical tool is called CDA/ESM™ and is used to compare alternatives in 
financial terms, including: a) life’s cycle balance encompassing internal and external risks over a 
selected duration and b) project implementation and demobilization costs and risks. CDA/ESM 
has been successfully applied to: rope v.s. road transportation, surface v.s. underground solutions, 
environmental   projects,   water   treatments   alternatives,   transportation   networks   and   go/no­go 
decisions. Figure 5 displays the data sheet for the Status Quo alternative.

CDA/ESM   results   at   the   40   year   time   horizon   for   the   three   alternatives:   Status   Quo, 
Rehabilitation, and the Failed Rehabilitation case are displayed in Figure 6.  Figure 6 shows that 
the Status Quo alternative will cost cumulatively twice as much as the Rehabilitation in virtue of 
the risks afflicting each alternative, such as an increase in energy costs, which were included in 
this analysis with a chance of 30% (see Tables 1 & 2 and the sensitivity analysis below).  The 
cumulative   cost   analysis   eliminates   the   “zeroing   effect”   of   NPV   on   long   term   analyses.   As 
explained above, the Rehabilitation has potential for a worst case scenario failure which could 
lead to a financial fiasco: more studies should be devoted to understand the probability of such a 
scenario, and the possible mid­life mitigations of such risks. 

A residual Risk Assessment process can be used at this point to evaluate the probability that 
failures of the system of Rehabilitation will cost more than the Status Quo. Like in the coal mine 
case study the cost of the mitigative actions has to be introduced in the analysis before the next 
step of the design process. 

It is now interesting to try to explicitly consider risks in the NPV evaluations. It appears that, in 
this case study, the Rehabilitation CDA (average) result is roughly equal to the NPV with risks 
(Table 3) and not far from the “traditional” NPV.  This happens because the initial amount spent 
is very large compared to the yearly spending which seems, indeed, negligible. However, as we 
will   see  below  the  results  of both NPV  analyses  fail  to steer  decision  makers  in the  proper 
direction.

As we can now see the NPVs of the Status Quo with (Table 4) and without risks are lower than 
that of the Rehabilitation. NPVs are plain inadequate when integrating alternatives’ specific risks 
in the comparison process (see link in references) because their “discounted nature” annihilates 
the effects of long term expenditures, and makes it essentially impossible to consider risks in a 
proper way.

Table 3.  Evaluation of the NPV of the Rehabilitation modified with Expected Return values.
Financial Parameters              Costs              Probability        Expected Return
Construction                      120M$              N/A                132M$,   i.e   expected   fixed   initial 
Environmental Soundness           120M$              10.00%             expenses including “average risks”
Running Costs                     0.3M$              N/A
Energy Price                      2*0.3M$            30.00%             0.66M$/yr,   i.e.   expected   yearly 
                                                                        expenses  including “average risks”
Climate Changes                   3.6M$              5.00%

40 years life span NPV                                                  ­139M$




Figure 6.  For each analysis: min, max, average of 
the cumulative cost at forty years.

Table 4.  Evaluation of the NPV of the Status Quo modified with Expected Return values.
Financial Parameters              Costs              Probability        Expected Return
                                                                        11.88M$   i.e   expected   fixed   initial 
Items as listed in Table 3, with appropriate average values             expenses including “average risks”
                                                                        7.36M$/yr   i.e.   expected   yearly 
                                                                        expenses  including “average risks”
40 years life span NPV                                                  ­90.2M$


Furthermore,   as   depicted   in   Figure   7,   for   all   probabilities   of   energy   cost   increase,   the 
Rehabilitation (yellow bar) is more costs efficient than the Status Quo (blue bar), once all the 
three considered risks are included. So, again, if we consider the probabilities that the costs of 
energy might be triple or more at any value of energy, the Status Quo alternative is less appealing 
than Rehabilitation. Should more risk scenarios be included in the analysis, then we would see 
that the Status Quo alternative is even less attractive than depicted above.

Conclusions

Two Cases Studies taken from our day to day practice have been presented to show that risks 
should be used as a discriminant parameter from the beginning of any project for successful long 
term planning and to manage rational decisions. One case was dealt with qualitatively at the pre­
feasibility level, the other quantitatively at the preliminary design level. 

At the pre­feasibility level it has been shown that graphic methodologies coupled with simple 
procedures   can   efficiently   pinpoint   weaknesses   and   lead  to   better   decisions   and   appropriate 
mitigations.




Figure 7.  Sensitivity of  alternatives to variation in the probability of the raising costs of energy.

In the process of performing the qualitative risk assessment several hazardous conditions which 
could be easily managed by design solutions were flagged. Indeed a pre­feasibility qualitative 
risk   analysis   should   reduce   the   chances   of   a   fatal   flaw   of   the   design,   by   defining   design 
parameters and bringing changes to the preliminary design geared towards increasing the chances 
of the future implementation to work and perform as intended. Of course the newly defined 
parameters and changes have to be integrated in the preliminary implementation and running 
costs estimates in order to avoid the possibility the project becomes a “financial fiasco.”

The over­costs of these mitigations have to be integrated in the pre­feasibility construction and 
running cost estimates to verify the economic sense of the project. At that point the system will 
still be subject to two sets of risks:  a) residual risks deriving from design mitigated hazards 
(which will depend on the level of mitigation selected by the design team) and b) risks linked to 
hazards such as union/personnel unrest, public acceptance issues, etc., which may be independent 
from design mitigation, as based on public/workforce perceptions.
At the preliminary design level it was shown that this innovative approach eliminates the pitfalls 
of NPV, an obsolete financial concept still used by many. The evaluation of a project should of 
course include the annual risks potentially afflicting the project, construction risks, and risks of 
malfunctioning, and possibly also the demolition/reclamation costs. It has been shown that the 
NPV can lead to erroneous conclusions in terms of the overall cost of a project, in particular for 
very long term projects. Because of this the NPV is particularly dangerous when dealing with 
long term environmental rehabilitations.

The tool used to avoid the NPV pitfalls is called CDA/ESM™ and is used to compare alternatives 
in financial terms, including: a) life’s cycle balance encompassing internal and external risks over 
a selected duration and b) project implementation and demobilization costs and risks.

The approaches described above have been successfully applied to: rope v.s. road transportation, 
surface v.s. underground solutions, water treatments alternatives, transportation networks, go/no­
go decisions.

References

F. Oboni. 1999­2000. Risk/Crisis Management Systems Design, University of British Columbia
F. Oboni. 2005. Do Risk Assessments Really Add Value To Projects?. CIM, Ottawa
F. Oboni and C. Oboni. 2007. “Improving Sustainability through Reasonable Risk and Crisis 
Management”. ISBN 978­0­9784462­0­8
F. Oboni and C. Oboni.  2008. Oboni, Risk and Decision Making.  www.edumine.com 

Web Pages
Answers Corporation.  2009. http://www.answers.com/topic/net­present­value#Common_pitfalls

Weitere ähnliche Inhalte

Andere mochten auch

Mobile Leveraging The New New Media
Mobile Leveraging The New New MediaMobile Leveraging The New New Media
Mobile Leveraging The New New MediaRoshan Kumar
 
Chz Committed To Green Solar Tech 2009
Chz  Committed To Green Solar Tech 2009Chz  Committed To Green Solar Tech 2009
Chz Committed To Green Solar Tech 2009garykellmann
 
New Directions In Russian Private Equity
New Directions In Russian Private EquityNew Directions In Russian Private Equity
New Directions In Russian Private EquityThomas Nastas
 
2011 ebi industry workshop
2011 ebi industry workshop2011 ebi industry workshop
2011 ebi industry workshopMichel Dumontier
 
Ipsos store brands muscle in May 2012
Ipsos store brands muscle in May 2012Ipsos store brands muscle in May 2012
Ipsos store brands muscle in May 2012Damjana Kocjanc
 
Reputation snapshot for the banking industry, 2012, final
Reputation snapshot for the banking industry, 2012, finalReputation snapshot for the banking industry, 2012, final
Reputation snapshot for the banking industry, 2012, finalDamjana Kocjanc
 
Introduccion Al Movimiento Del Software Libre
Introduccion Al Movimiento Del Software LibreIntroduccion Al Movimiento Del Software Libre
Introduccion Al Movimiento Del Software LibreIsrael Zuñiga
 
Monica Cabbler - Profile
Monica Cabbler - ProfileMonica Cabbler - Profile
Monica Cabbler - ProfileMonica Cabbler
 
Android Bootcamp Santa Fe GTUG
Android Bootcamp Santa Fe GTUGAndroid Bootcamp Santa Fe GTUG
Android Bootcamp Santa Fe GTUGmatiasmolinas
 
Blerta Interpreter 1
Blerta Interpreter 1Blerta Interpreter 1
Blerta Interpreter 1Blerta
 
Part 5: Putting it all together
Part 5: Putting it all togetherPart 5: Putting it all together
Part 5: Putting it all togetherNAPWA
 
Rdash demo
Rdash demoRdash demo
Rdash demoJobs2web
 
Nastas Lecture Graduate School of Business Michgan State University
Nastas Lecture Graduate School of Business Michgan State UniversityNastas Lecture Graduate School of Business Michgan State University
Nastas Lecture Graduate School of Business Michgan State UniversityThomas Nastas
 
Tests & trials in the baha'i faith
Tests & trials in the baha'i faithTests & trials in the baha'i faith
Tests & trials in the baha'i faithBijan masumian
 
Powering Scientific Discovery with the Semantic Web (VanBUG 2014)
Powering Scientific Discovery with the Semantic Web (VanBUG 2014)Powering Scientific Discovery with the Semantic Web (VanBUG 2014)
Powering Scientific Discovery with the Semantic Web (VanBUG 2014)Michel Dumontier
 

Andere mochten auch (20)

Mobile Leveraging The New New Media
Mobile Leveraging The New New MediaMobile Leveraging The New New Media
Mobile Leveraging The New New Media
 
Chz Committed To Green Solar Tech 2009
Chz  Committed To Green Solar Tech 2009Chz  Committed To Green Solar Tech 2009
Chz Committed To Green Solar Tech 2009
 
New Directions In Russian Private Equity
New Directions In Russian Private EquityNew Directions In Russian Private Equity
New Directions In Russian Private Equity
 
Tolerability and Decision Making Discussion
Tolerability and Decision Making DiscussionTolerability and Decision Making Discussion
Tolerability and Decision Making Discussion
 
Long Term Data Storage 2007
Long Term Data Storage 2007Long Term Data Storage 2007
Long Term Data Storage 2007
 
2011 ebi industry workshop
2011 ebi industry workshop2011 ebi industry workshop
2011 ebi industry workshop
 
Ipsos store brands muscle in May 2012
Ipsos store brands muscle in May 2012Ipsos store brands muscle in May 2012
Ipsos store brands muscle in May 2012
 
CloudCoffee
CloudCoffeeCloudCoffee
CloudCoffee
 
Reputation snapshot for the banking industry, 2012, final
Reputation snapshot for the banking industry, 2012, finalReputation snapshot for the banking industry, 2012, final
Reputation snapshot for the banking industry, 2012, final
 
Introduccion Al Movimiento Del Software Libre
Introduccion Al Movimiento Del Software LibreIntroduccion Al Movimiento Del Software Libre
Introduccion Al Movimiento Del Software Libre
 
Monica Cabbler - Profile
Monica Cabbler - ProfileMonica Cabbler - Profile
Monica Cabbler - Profile
 
Android Bootcamp Santa Fe GTUG
Android Bootcamp Santa Fe GTUGAndroid Bootcamp Santa Fe GTUG
Android Bootcamp Santa Fe GTUG
 
Blerta Interpreter 1
Blerta Interpreter 1Blerta Interpreter 1
Blerta Interpreter 1
 
Part 5: Putting it all together
Part 5: Putting it all togetherPart 5: Putting it all together
Part 5: Putting it all together
 
Grupa Onet(2)
Grupa Onet(2)Grupa Onet(2)
Grupa Onet(2)
 
Rdash demo
Rdash demoRdash demo
Rdash demo
 
Nastas Lecture Graduate School of Business Michgan State University
Nastas Lecture Graduate School of Business Michgan State UniversityNastas Lecture Graduate School of Business Michgan State University
Nastas Lecture Graduate School of Business Michgan State University
 
Tests & trials in the baha'i faith
Tests & trials in the baha'i faithTests & trials in the baha'i faith
Tests & trials in the baha'i faith
 
Ishii presentation
Ishii presentationIshii presentation
Ishii presentation
 
Powering Scientific Discovery with the Semantic Web (VanBUG 2014)
Powering Scientific Discovery with the Semantic Web (VanBUG 2014)Powering Scientific Discovery with the Semantic Web (VanBUG 2014)
Powering Scientific Discovery with the Semantic Web (VanBUG 2014)
 

Ähnlich wie Comparing Alternatives Using CDA-ESM

IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET Journal
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisInSync Conference
 
Theoretical Risk Identification within the Nigeria East- West Coastal Highway...
Theoretical Risk Identification within the Nigeria East- West Coastal Highway...Theoretical Risk Identification within the Nigeria East- West Coastal Highway...
Theoretical Risk Identification within the Nigeria East- West Coastal Highway...civejjour
 
Risk management paper
Risk management paperRisk management paper
Risk management paperPMlynda17
 
2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_cls2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_clsDennis Doherty
 
APM Project magazine TEC Case Study
APM Project magazine TEC Case StudyAPM Project magazine TEC Case Study
APM Project magazine TEC Case StudyPatrick Watson
 
APM Project magazine TEC Case Study
APM Project magazine TEC Case StudyAPM Project magazine TEC Case Study
APM Project magazine TEC Case StudyPatrick Watson
 
megaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdfmegaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdfAdina Levin
 
Cda Esm Comparative Decision Analysis Economic Safety Margin
Cda Esm Comparative Decision Analysis   Economic Safety MarginCda Esm Comparative Decision Analysis   Economic Safety Margin
Cda Esm Comparative Decision Analysis Economic Safety Margincoboni
 
6 An Innovative Distributed Project Control
6 An Innovative Distributed Project Control6 An Innovative Distributed Project Control
6 An Innovative Distributed Project Controlpmb25
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Association for Project Management
 
Time-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithmTime-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithmVISHNU VIJAYAN
 
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Nicholas Phelan
 
ASCLME project management indicators
ASCLME project management indicatorsASCLME project management indicators
ASCLME project management indicatorsIwl Pcu
 
Carbon Credit Credibility.pdf
Carbon Credit Credibility.pdfCarbon Credit Credibility.pdf
Carbon Credit Credibility.pdfCalvinWong58696
 
Dr. saad ahmed al muhannadi 2015 - ph d - dba
Dr. saad ahmed al muhannadi    2015 - ph d - dbaDr. saad ahmed al muhannadi    2015 - ph d - dba
Dr. saad ahmed al muhannadi 2015 - ph d - dbafabdulkhadar
 
Screening of the project By Mr Allah Dad Khan Visiting Professor The Univers...
Screening of the project  By Mr Allah Dad Khan Visiting Professor The Univers...Screening of the project  By Mr Allah Dad Khan Visiting Professor The Univers...
Screening of the project By Mr Allah Dad Khan Visiting Professor The Univers...Mr.Allah Dad Khan
 
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Robert Byrd
 

Ähnlich wie Comparing Alternatives Using CDA-ESM (20)

IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
 
Theoretical Risk Identification within the Nigeria East- West Coastal Highway...
Theoretical Risk Identification within the Nigeria East- West Coastal Highway...Theoretical Risk Identification within the Nigeria East- West Coastal Highway...
Theoretical Risk Identification within the Nigeria East- West Coastal Highway...
 
Risk management paper
Risk management paperRisk management paper
Risk management paper
 
2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_cls2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_cls
 
APM Project magazine TEC Case Study
APM Project magazine TEC Case StudyAPM Project magazine TEC Case Study
APM Project magazine TEC Case Study
 
APM Project magazine TEC Case Study
APM Project magazine TEC Case StudyAPM Project magazine TEC Case Study
APM Project magazine TEC Case Study
 
megaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdfmegaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdf
 
Cda Esm Comparative Decision Analysis Economic Safety Margin
Cda Esm Comparative Decision Analysis   Economic Safety MarginCda Esm Comparative Decision Analysis   Economic Safety Margin
Cda Esm Comparative Decision Analysis Economic Safety Margin
 
6 An Innovative Distributed Project Control
6 An Innovative Distributed Project Control6 An Innovative Distributed Project Control
6 An Innovative Distributed Project Control
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
 
Time-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithmTime-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithm
 
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
 
ASCLME project management indicators
ASCLME project management indicatorsASCLME project management indicators
ASCLME project management indicators
 
Carbon Credit Credibility.pdf
Carbon Credit Credibility.pdfCarbon Credit Credibility.pdf
Carbon Credit Credibility.pdf
 
Dr. saad ahmed al muhannadi 2015 - ph d - dba
Dr. saad ahmed al muhannadi    2015 - ph d - dbaDr. saad ahmed al muhannadi    2015 - ph d - dba
Dr. saad ahmed al muhannadi 2015 - ph d - dba
 
Screening of the project By Mr Allah Dad Khan Visiting Professor The Univers...
Screening of the project  By Mr Allah Dad Khan Visiting Professor The Univers...Screening of the project  By Mr Allah Dad Khan Visiting Professor The Univers...
Screening of the project By Mr Allah Dad Khan Visiting Professor The Univers...
 
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
 
Chap 5.pdf
Chap 5.pdfChap 5.pdf
Chap 5.pdf
 
Chap 5.pdf
Chap 5.pdfChap 5.pdf
Chap 5.pdf
 

Mehr von Oboni Riskope Associates Inc.

Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...Oboni Riskope Associates Inc.
 
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...Oboni Riskope Associates Inc.
 
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, ColombiaOboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, ColombiaOboni Riskope Associates Inc.
 
Rims Metal and Mining Session talk by F+C Oboni, Riskope
Rims Metal and Mining Session talk by F+C Oboni, RiskopeRims Metal and Mining Session talk by F+C Oboni, Riskope
Rims Metal and Mining Session talk by F+C Oboni, RiskopeOboni Riskope Associates Inc.
 

Mehr von Oboni Riskope Associates Inc. (20)

Riskope new web site announcement
Riskope new web site announcementRiskope new web site announcement
Riskope new web site announcement
 
Rational Risk and Crisis Management Course
Rational Risk and Crisis Management CourseRational Risk and Crisis Management Course
Rational Risk and Crisis Management Course
 
Cim2013 oboni oboni_zabolotoniuk
Cim2013 oboni oboni_zabolotoniukCim2013 oboni oboni_zabolotoniuk
Cim2013 oboni oboni_zabolotoniuk
 
Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...
 
Riskope for christmas 2012
Riskope for christmas 2012Riskope for christmas 2012
Riskope for christmas 2012
 
Ore cockpit castellano
Ore cockpit castellanoOre cockpit castellano
Ore cockpit castellano
 
Mining 012 riskope is it true that pi_gs
Mining 012 riskope  is it true that pi_gsMining 012 riskope  is it true that pi_gs
Mining 012 riskope is it true that pi_gs
 
Bogota 02 10-011 Risk Management Mining Summit
Bogota 02 10-011 Risk Management Mining SummitBogota 02 10-011 Risk Management Mining Summit
Bogota 02 10-011 Risk Management Mining Summit
 
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
 
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, ColombiaOboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
 
Review ICS Guidelines
Review ICS GuidelinesReview ICS Guidelines
Review ICS Guidelines
 
Cassass presentation WLF2 Rome
Cassass presentation WLF2 RomeCassass presentation WLF2 Rome
Cassass presentation WLF2 Rome
 
Road Safety- Sicurezza Stradale
Road Safety- Sicurezza StradaleRoad Safety- Sicurezza Stradale
Road Safety- Sicurezza Stradale
 
Rims Metal and Mining Session talk by F+C Oboni, Riskope
Rims Metal and Mining Session talk by F+C Oboni, RiskopeRims Metal and Mining Session talk by F+C Oboni, Riskope
Rims Metal and Mining Session talk by F+C Oboni, Riskope
 
Rims Metals and Mining Session
Rims Metals and Mining Session Rims Metals and Mining Session
Rims Metals and Mining Session
 
Force Majeure: a Time Bomb
Force Majeure: a Time BombForce Majeure: a Time Bomb
Force Majeure: a Time Bomb
 
Oboni02 castellano
Oboni02 castellanoOboni02 castellano
Oboni02 castellano
 
Oboni01 castellano
Oboni01 castellanoOboni01 castellano
Oboni01 castellano
 
Cda esm waste oil disposal application part 2
Cda esm waste oil disposal application part 2Cda esm waste oil disposal application part 2
Cda esm waste oil disposal application part 2
 
Force Majeure Clause in Contracts
Force Majeure Clause in ContractsForce Majeure Clause in Contracts
Force Majeure Clause in Contracts
 

Kürzlich hochgeladen

Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noidadlhescort
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture conceptP&CO
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Sheetaleventcompany
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 

Kürzlich hochgeladen (20)

Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 

Comparing Alternatives Using CDA-ESM