INTEGRITY MANAGEMENT
   10 YEARS EXTERNAL
   CORROSION DIRECT
  ASSESSMENT (ECDA)

   Charlie Hall
Pipeline Integrity Actions


• Incident Overview                    • Bellingham
 June 10, 1999 a gasoline pipeline
  ruptured
                                         Washington
   – Gasoline leaked into two creeks
      in the City of Bellingham,
      Washington and ignited
   – Fireball killed three persons,
      injured eight other persons
   – Caused significant property
      damage
   – Released approximately 1/4
      million gallons of gasoline
      causing substantial
      environmental damage
El Paso Pipeline Incident
      August 19, 2000, 30-inch near Carlsbad, New Mexico.
El Paso Pipeline Incident
El Paso Pipeline Incident
Why Pipeline Integrity?




•“deterioration of a material, usually a metal, that results from a reaction
with its environment”
•Soil-side corrosion typically slow progressing
•Corrosion rate influenced by geological formations – “corrosive zones”
Why Pipeline Integrity?
Why Pipeline Integrity?
Congressional Intervention
Pipeline Integrity

 Issued Integrity Management (IM) Regulations
 12/15/2003

 Require Industry To:
    Conduct an Analysis of the Risks and Adopt a
      Written IM Program in High Consequence Areas
      (HCA’s) by 12/17/2004
    Begin Baseline Assessments: 06/17/2004
    Finish Baseline Assessments: 12/17/2012
    Reassess Covered Pipeline Every 7 Years
Gas Integrity Management Program


         Scope and
      Implementation               Remediation
    (901, 903, 907, 913)               (933)
     HCA Identification         Prevent/Mitigative
          (903, 905)                   (935)
      Threat Analysis        Continual Evaluation
            (917)              (937, 939, 941, 943)
  Baseline Assessment              Performance
          (919, 921)             Measures(947)
Direct Assessment           QA, Training, Comm.
        (923 through 921)         (915, 945, 949, 951)
Baseline Assessment Tool Selection
Based Upon Threat Assessment Analysis

  Smart Pigging Historical Information (Need
  Further Investigation to Find Root Cause)

  Hydrostatic Testing (PHMSA Gold Standard –
  Disrupts Service / Introduces Water)

  External Corrosion Direct Assessment (Major
  Challenge for Acceptance – Industry Worked Out
  Process ECDA)
ECDA – Four Step Process

                  Advantage

 “can locate areas where defects could form in
 the future rather than only areas were defects
              have already formed”
ECDA – Four Step Process

   1. Pre-Assessment

   2. Indirect Inspection

   3. Direct Examinations

   4. Post Assessments

      FAILURE TO FOLLOW PROCESS
       JEOPARDIZES PIPELINE SAFETY
ECDA – Four Step Process

                Pre-Assessment
   “Utilization of Operational and Historical
    Records to Assess Potential External
    Corrosion Locations and to Determine
          Feasibility of Applying ECDA”

   UNDERSTANDING PIPELINE THREATS
    AND THE NEED TO OVERCOME THE
  ACCEPTANCE THAT RECORDS REVIEW
              REQUIRED
ECDA – Four Step Process

                Pre-Assessment
Identify and Address Corrosion Activity

  Past or Old Corrosion Damage (Finds Old
  Damage after CP Problem Corrected)
  Present Activity (Yes)
  Future Corrosion Risks (Identifies Problem
  Areas)

Continuous Improvement Process (If Applied
Correctly)
ECDA – Four Step Process
                    Pre-Assessment
             ECDA Feasibility Assessment
         Integrate and Analyze Data Collected
 Coating Electrical Shielding (ECDA Feasibility NO)

 Backfill with Rock Content and Rock Ledges (Remain
 Problem)

 Ground Surface Hindrances, i.e. Pavements (Drilling/Traffic
 Control)

 Adjacent Buried Metallic Structures (Stray Current Influence)

 Inaccessible Areas (Difficult to Access – Casings Overcome)

 Situations That Prevent Aboveground Measurements in
 Reasonable Time-Frame (Planning and Execution)
ECDA – Four Step Process
                        Pre-Assessment
  Data Collection
    Data Elements: Pipe-related, Construction Related,
    Soils/environmental, Corrosion Control, Operational
    Historical Records – Better Understanding Pipeline
    Sufficient Data – Missing Records
    Subject Matter Experts - Retirements

  Determine ECDA Feasibility – (Missing Data)

  Establish ECDA Regions
     Similar Physical Characteristics – Role of Environment
     Similar Past, Present, Future Corrosion Behaviors
     Utilizes Similar IIT Tools

  Select Indirect Inspection Tools
ECDA – Four Step Process

             Indirect Inspection
 CIS     - Indicates CP Level

 DCVG/ACVG - Indicates Exposed Metal

 Soils   - Indicate Environment Corrosivity

 Depth   - Indicate Third Party Damage Risk

 PCM     - Indicate Current Attenuation
ECDA – Four Step Process

              Indirect Inspection
    “Equipment and Practices Used to Take
   Measurements at Ground Surface Above or
    Near a Pipeline to Locate or Characterize
  Corrosion Activity, Coating Holidays, or Other
                    Anomalies”

    Data Collection, Quality, Recognition,
 Current Interruption, Stray Current, Casings
              and AC Corrosion
ECDA – Four Step Process
                 Indirect Inspection
 Locate and define severity of coating faults where
 corrosion may occur or be occurring Discovery
 Coating Condition More Severe

 Conduct at least two indirect inspection tools (IIT) the
 entire length of the ECDA Region Casings and AC
 Corrosion

 Align and compare results from IIT tools More Stray
 Current Than Expected

 Identify, classify, and report results for Direct
 Examination step
ECDA – Four Step Process

            Direct Examination

 “Inspections and Measurements Made On the
     Pipe Surface at Excavations as Part of
     External Corrosion Direct Assessment
                   (ECDA)”

     Qualified Experienced Personnel
Data Integration Management Tools




 •INSERT INTEGRATED SURVEY GRAPH
ECDA – Four Step Process
           Direct Examination
ECDA – Four Step Process
           Direct Examination
ECDA – Four Step Process
              Post Assessment


   “Analysis of Indirect Inspections and Direct
    Examinations to Assess Pipeline Integrity,
   Prioritize Repairs, Redefine Reassessment
 Intervals and Assess the Overall Effectiveness
               of the ECDA Process”
ECDA – Four Step Process
               Direct Examination
 Process Validation

 Remaining Life Calculation

 Define Reassessment Interval

 Define Effectiveness Measures

 Continuous Improvement

 Reassess ECDA Feasibility
INTEGRITY MANAGEMENT
    10 YEARS ECDA




       Charlie Hall

Weitere ähnliche Inhalte

Was ist angesagt?

SCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity SolutionSCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity SolutionBrett Payton
 
The Importance of Risk Management in the Pipeline Industry
The Importance of Risk Management in the Pipeline IndustryThe Importance of Risk Management in the Pipeline Industry
The Importance of Risk Management in the Pipeline IndustryAudubon Engineering Company
 
Risk Assessment Hazardous Liquid Pipeline Integrity
Risk Assessment Hazardous Liquid Pipeline IntegrityRisk Assessment Hazardous Liquid Pipeline Integrity
Risk Assessment Hazardous Liquid Pipeline IntegrityAudubon Engineering Company
 
2. FDR-RAE Int Training 2015 - Pipeline Integrity - Copy
2. FDR-RAE Int Training 2015 - Pipeline Integrity - Copy2. FDR-RAE Int Training 2015 - Pipeline Integrity - Copy
2. FDR-RAE Int Training 2015 - Pipeline Integrity - CopyFranklin Del Rosario, P.Eng.
 
General Pulse Structural Monitoring
General Pulse Structural MonitoringGeneral Pulse Structural Monitoring
General Pulse Structural MonitoringBoQan
 
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid PipelinesPresentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid PipelinesAudubon Engineering Company
 
Identifying Casing Shorts With or Without Test Leads - Jim Walton
Identifying Casing Shorts With or Without Test Leads - Jim WaltonIdentifying Casing Shorts With or Without Test Leads - Jim Walton
Identifying Casing Shorts With or Without Test Leads - Jim Waltonnacetwincities
 
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines Audubon Engineering Company
 
external & internal corrosion monitoring
external & internal corrosion monitoringexternal & internal corrosion monitoring
external & internal corrosion monitoringsair ali khan
 
ADVANCED PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
ADVANCED  PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATIONADVANCED  PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
ADVANCED PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATIONpetroEDGE
 
Turnkey projects and services in Cage Aquaculture
Turnkey projects and services in Cage AquacultureTurnkey projects and services in Cage Aquaculture
Turnkey projects and services in Cage AquacultureAlessandro Ciattaglia
 
Presentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission PipelinesPresentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission PipelinesAudubon Engineering Company
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000daniel cobar
 

Was ist angesagt? (20)

AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion  AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion
 
External Corrosion Direct Assessment (ECDA)
External Corrosion Direct Assessment (ECDA) External Corrosion Direct Assessment (ECDA)
External Corrosion Direct Assessment (ECDA)
 
SCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity SolutionSCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity Solution
 
The Importance of Risk Management in the Pipeline Industry
The Importance of Risk Management in the Pipeline IndustryThe Importance of Risk Management in the Pipeline Industry
The Importance of Risk Management in the Pipeline Industry
 
Risk Assessment Hazardous Liquid Pipeline Integrity
Risk Assessment Hazardous Liquid Pipeline IntegrityRisk Assessment Hazardous Liquid Pipeline Integrity
Risk Assessment Hazardous Liquid Pipeline Integrity
 
2. FDR-RAE Int Training 2015 - Pipeline Integrity - Copy
2. FDR-RAE Int Training 2015 - Pipeline Integrity - Copy2. FDR-RAE Int Training 2015 - Pipeline Integrity - Copy
2. FDR-RAE Int Training 2015 - Pipeline Integrity - Copy
 
General Pulse Structural Monitoring
General Pulse Structural MonitoringGeneral Pulse Structural Monitoring
General Pulse Structural Monitoring
 
860686
860686860686
860686
 
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid PipelinesPresentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
 
Copy of HARDENBERGH JOBS
Copy of HARDENBERGH JOBSCopy of HARDENBERGH JOBS
Copy of HARDENBERGH JOBS
 
Pipeline repair techniques
Pipeline repair techniquesPipeline repair techniques
Pipeline repair techniques
 
Identifying Casing Shorts With or Without Test Leads - Jim Walton
Identifying Casing Shorts With or Without Test Leads - Jim WaltonIdentifying Casing Shorts With or Without Test Leads - Jim Walton
Identifying Casing Shorts With or Without Test Leads - Jim Walton
 
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
 
external & internal corrosion monitoring
external & internal corrosion monitoringexternal & internal corrosion monitoring
external & internal corrosion monitoring
 
ADVANCED PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
ADVANCED  PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATIONADVANCED  PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
ADVANCED PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
 
Turnkey projects and services in Cage Aquaculture
Turnkey projects and services in Cage AquacultureTurnkey projects and services in Cage Aquaculture
Turnkey projects and services in Cage Aquaculture
 
Presentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission PipelinesPresentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission Pipelines
 
3-Degradation
3-Degradation3-Degradation
3-Degradation
 
Dustin Marshall OQ Report (NCCER)
Dustin Marshall OQ Report (NCCER)Dustin Marshall OQ Report (NCCER)
Dustin Marshall OQ Report (NCCER)
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000
 

Andere mochten auch

Hands-Free Lifting & Hands-Off Safety Tools
 Hands-Free Lifting & Hands-Off Safety Tools Hands-Free Lifting & Hands-Off Safety Tools
Hands-Free Lifting & Hands-Off Safety ToolsProject Sales Corp
 
Direct Assessment ECDA Program Development
Direct Assessment ECDA Program DevelopmentDirect Assessment ECDA Program Development
Direct Assessment ECDA Program DevelopmentMTS Webmaster
 
PSC Hands free lifting and hands off tools 2015
PSC Hands free lifting and hands off tools 2015PSC Hands free lifting and hands off tools 2015
PSC Hands free lifting and hands off tools 2015Project Sales Corp India
 

Andere mochten auch (6)

Worldwide Distributors Finger Saver Tool
Worldwide Distributors Finger Saver ToolWorldwide Distributors Finger Saver Tool
Worldwide Distributors Finger Saver Tool
 
Hands-Free Lifting & Hands-Off Safety Tools
 Hands-Free Lifting & Hands-Off Safety Tools Hands-Free Lifting & Hands-Off Safety Tools
Hands-Free Lifting & Hands-Off Safety Tools
 
Direct Assessment ECDA Program Development
Direct Assessment ECDA Program DevelopmentDirect Assessment ECDA Program Development
Direct Assessment ECDA Program Development
 
PSC Hands free lifting and hands off tools 2015
PSC Hands free lifting and hands off tools 2015PSC Hands free lifting and hands off tools 2015
PSC Hands free lifting and hands off tools 2015
 
corrosion presentation
corrosion presentationcorrosion presentation
corrosion presentation
 
Corrosion control
Corrosion control Corrosion control
Corrosion control
 

Ähnlich wie 2012 FEPA Presentation: Charlie Hall

2-ecdaworkshoprlopeznov4ver3.ppt
2-ecdaworkshoprlopeznov4ver3.ppt2-ecdaworkshoprlopeznov4ver3.ppt
2-ecdaworkshoprlopeznov4ver3.pptTriWahono16
 
Pipeline Integrity Hazard Modelling & Mitigation - Internal Corrosion
Pipeline Integrity Hazard Modelling & Mitigation - Internal CorrosionPipeline Integrity Hazard Modelling & Mitigation - Internal Corrosion
Pipeline Integrity Hazard Modelling & Mitigation - Internal CorrosionDavid Richardson
 
Advanced Pipeline Risk Assessment vs. Simplified NACE Standards
Advanced Pipeline Risk Assessment vs. Simplified NACE StandardsAdvanced Pipeline Risk Assessment vs. Simplified NACE Standards
Advanced Pipeline Risk Assessment vs. Simplified NACE StandardsDavid Richardson
 
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...ASC-HRSC
 
Final Newea 9 09 10 Mh Rehab
Final Newea 9 09 10 Mh RehabFinal Newea 9 09 10 Mh Rehab
Final Newea 9 09 10 Mh Rehabmfrench62
 
White Paper Available from the PPIM Conference: Pipeline Regulation and Dire...
White Paper Available from the PPIM Conference:  Pipeline Regulation and Dire...White Paper Available from the PPIM Conference:  Pipeline Regulation and Dire...
White Paper Available from the PPIM Conference: Pipeline Regulation and Dire...Willbros Group, Inc.
 
Flywheel Safety - Richard thompson - Jan 2011
Flywheel Safety - Richard thompson - Jan 2011Flywheel Safety - Richard thompson - Jan 2011
Flywheel Safety - Richard thompson - Jan 2011cahouser
 
Improving Remedial Actions Through Integrated Use of Direct-Push HRSC Technol...
Improving Remedial Actions Through Integrated Use of Direct-Push HRSC Technol...Improving Remedial Actions Through Integrated Use of Direct-Push HRSC Technol...
Improving Remedial Actions Through Integrated Use of Direct-Push HRSC Technol...ASC-HRSC
 
Nace standards.pdf
Nace standards.pdfNace standards.pdf
Nace standards.pdfKLandry1
 
Developing Stone Test Programmes
Developing Stone Test ProgrammesDeveloping Stone Test Programmes
Developing Stone Test ProgrammesStone Initiatives
 
07 progress on inspection and evaluation of ciscc at canister of dry storage ...
07 progress on inspection and evaluation of ciscc at canister of dry storage ...07 progress on inspection and evaluation of ciscc at canister of dry storage ...
07 progress on inspection and evaluation of ciscc at canister of dry storage ...leann_mays
 
M.S. Thesis Defense
M.S. Thesis DefenseM.S. Thesis Defense
M.S. Thesis Defensepbecker1987
 
2004 January - Integrated Permit Planning
2004 January - Integrated Permit Planning2004 January - Integrated Permit Planning
2004 January - Integrated Permit PlanningShirley Rivera
 
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...ASC-HRSC
 
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...ascemiami-dade
 
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...Global CCS Institute
 

Ähnlich wie 2012 FEPA Presentation: Charlie Hall (20)

2-ecdaworkshoprlopeznov4ver3.ppt
2-ecdaworkshoprlopeznov4ver3.ppt2-ecdaworkshoprlopeznov4ver3.ppt
2-ecdaworkshoprlopeznov4ver3.ppt
 
Pipeline Integrity Hazard Modelling & Mitigation - Internal Corrosion
Pipeline Integrity Hazard Modelling & Mitigation - Internal CorrosionPipeline Integrity Hazard Modelling & Mitigation - Internal Corrosion
Pipeline Integrity Hazard Modelling & Mitigation - Internal Corrosion
 
Advanced Pipeline Risk Assessment vs. Simplified NACE Standards
Advanced Pipeline Risk Assessment vs. Simplified NACE StandardsAdvanced Pipeline Risk Assessment vs. Simplified NACE Standards
Advanced Pipeline Risk Assessment vs. Simplified NACE Standards
 
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
 
Final Newea 9 09 10 Mh Rehab
Final Newea 9 09 10 Mh RehabFinal Newea 9 09 10 Mh Rehab
Final Newea 9 09 10 Mh Rehab
 
FEA Based Level 3 Assessment of Deformed Tanks
FEA Based Level 3 Assessment of Deformed TanksFEA Based Level 3 Assessment of Deformed Tanks
FEA Based Level 3 Assessment of Deformed Tanks
 
White Paper Available from the PPIM Conference: Pipeline Regulation and Dire...
White Paper Available from the PPIM Conference:  Pipeline Regulation and Dire...White Paper Available from the PPIM Conference:  Pipeline Regulation and Dire...
White Paper Available from the PPIM Conference: Pipeline Regulation and Dire...
 
Flywheel Safety - Richard thompson - Jan 2011
Flywheel Safety - Richard thompson - Jan 2011Flywheel Safety - Richard thompson - Jan 2011
Flywheel Safety - Richard thompson - Jan 2011
 
Improving Remedial Actions Through Integrated Use of Direct-Push HRSC Technol...
Improving Remedial Actions Through Integrated Use of Direct-Push HRSC Technol...Improving Remedial Actions Through Integrated Use of Direct-Push HRSC Technol...
Improving Remedial Actions Through Integrated Use of Direct-Push HRSC Technol...
 
Nace standards.pdf
Nace standards.pdfNace standards.pdf
Nace standards.pdf
 
Integrating Laser Scan Data into FEA Model to Perform Level 3 FFS
Integrating Laser Scan Data into FEA Model to Perform Level 3 FFSIntegrating Laser Scan Data into FEA Model to Perform Level 3 FFS
Integrating Laser Scan Data into FEA Model to Perform Level 3 FFS
 
Developing Stone Test Programmes
Developing Stone Test ProgrammesDeveloping Stone Test Programmes
Developing Stone Test Programmes
 
Hazid & hazops
Hazid & hazopsHazid & hazops
Hazid & hazops
 
Deterioration of Concrete
Deterioration of ConcreteDeterioration of Concrete
Deterioration of Concrete
 
07 progress on inspection and evaluation of ciscc at canister of dry storage ...
07 progress on inspection and evaluation of ciscc at canister of dry storage ...07 progress on inspection and evaluation of ciscc at canister of dry storage ...
07 progress on inspection and evaluation of ciscc at canister of dry storage ...
 
M.S. Thesis Defense
M.S. Thesis DefenseM.S. Thesis Defense
M.S. Thesis Defense
 
2004 January - Integrated Permit Planning
2004 January - Integrated Permit Planning2004 January - Integrated Permit Planning
2004 January - Integrated Permit Planning
 
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
HRSC Technologies: Using MiHpt for Rapid In-Situ Contaminant and Hydrostratig...
 
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
 
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
 

Mehr von FloridaPipeTalk

2012 FEPA Presentation: Paul Smith
2012 FEPA Presentation: Paul Smith2012 FEPA Presentation: Paul Smith
2012 FEPA Presentation: Paul SmithFloridaPipeTalk
 
2012 FEPA Presentation: Peter Lidiak
2012 FEPA Presentation: Peter Lidiak2012 FEPA Presentation: Peter Lidiak
2012 FEPA Presentation: Peter LidiakFloridaPipeTalk
 
2012 FEPA Presentation: Mark Weise
2012 FEPA Presentation: Mark Weise2012 FEPA Presentation: Mark Weise
2012 FEPA Presentation: Mark WeiseFloridaPipeTalk
 
2012 FEPA Presentation: Larry Hjalmarson
2012 FEPA Presentation: Larry Hjalmarson2012 FEPA Presentation: Larry Hjalmarson
2012 FEPA Presentation: Larry HjalmarsonFloridaPipeTalk
 
2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald MorrisFloridaPipeTalk
 
2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik KirkpatrickFloridaPipeTalk
 
2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff DidasFloridaPipeTalk
 
2012 FEPA Presentation: Richard Musgrove
2012 FEPA Presentation: Richard Musgrove2012 FEPA Presentation: Richard Musgrove
2012 FEPA Presentation: Richard MusgroveFloridaPipeTalk
 
2012 FEPA Presentation: Stu Kogge
2012 FEPA Presentation: Stu Kogge2012 FEPA Presentation: Stu Kogge
2012 FEPA Presentation: Stu KoggeFloridaPipeTalk
 
2012 FEPA Presentation: Ted Huck
2012 FEPA Presentation: Ted Huck2012 FEPA Presentation: Ted Huck
2012 FEPA Presentation: Ted HuckFloridaPipeTalk
 
2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don ThornFloridaPipeTalk
 
2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny KilcollinsFloridaPipeTalk
 
2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne MosleyFloridaPipeTalk
 

Mehr von FloridaPipeTalk (13)

2012 FEPA Presentation: Paul Smith
2012 FEPA Presentation: Paul Smith2012 FEPA Presentation: Paul Smith
2012 FEPA Presentation: Paul Smith
 
2012 FEPA Presentation: Peter Lidiak
2012 FEPA Presentation: Peter Lidiak2012 FEPA Presentation: Peter Lidiak
2012 FEPA Presentation: Peter Lidiak
 
2012 FEPA Presentation: Mark Weise
2012 FEPA Presentation: Mark Weise2012 FEPA Presentation: Mark Weise
2012 FEPA Presentation: Mark Weise
 
2012 FEPA Presentation: Larry Hjalmarson
2012 FEPA Presentation: Larry Hjalmarson2012 FEPA Presentation: Larry Hjalmarson
2012 FEPA Presentation: Larry Hjalmarson
 
2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris
 
2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick
 
2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas
 
2012 FEPA Presentation: Richard Musgrove
2012 FEPA Presentation: Richard Musgrove2012 FEPA Presentation: Richard Musgrove
2012 FEPA Presentation: Richard Musgrove
 
2012 FEPA Presentation: Stu Kogge
2012 FEPA Presentation: Stu Kogge2012 FEPA Presentation: Stu Kogge
2012 FEPA Presentation: Stu Kogge
 
2012 FEPA Presentation: Ted Huck
2012 FEPA Presentation: Ted Huck2012 FEPA Presentation: Ted Huck
2012 FEPA Presentation: Ted Huck
 
2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn
 
2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins
 
2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley
 

Kürzlich hochgeladen

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLJAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Anamikakaur10
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noidadlhescort
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 

Kürzlich hochgeladen (20)

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLJAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 

2012 FEPA Presentation: Charlie Hall

  • 1. INTEGRITY MANAGEMENT 10 YEARS EXTERNAL CORROSION DIRECT ASSESSMENT (ECDA) Charlie Hall
  • 2. Pipeline Integrity Actions • Incident Overview • Bellingham  June 10, 1999 a gasoline pipeline ruptured Washington – Gasoline leaked into two creeks in the City of Bellingham, Washington and ignited – Fireball killed three persons, injured eight other persons – Caused significant property damage – Released approximately 1/4 million gallons of gasoline causing substantial environmental damage
  • 3. El Paso Pipeline Incident August 19, 2000, 30-inch near Carlsbad, New Mexico.
  • 4. El Paso Pipeline Incident
  • 5. El Paso Pipeline Incident
  • 6. Why Pipeline Integrity? •“deterioration of a material, usually a metal, that results from a reaction with its environment” •Soil-side corrosion typically slow progressing •Corrosion rate influenced by geological formations – “corrosive zones”
  • 10. Pipeline Integrity Issued Integrity Management (IM) Regulations 12/15/2003 Require Industry To:  Conduct an Analysis of the Risks and Adopt a Written IM Program in High Consequence Areas (HCA’s) by 12/17/2004  Begin Baseline Assessments: 06/17/2004  Finish Baseline Assessments: 12/17/2012  Reassess Covered Pipeline Every 7 Years
  • 11. Gas Integrity Management Program Scope and Implementation Remediation (901, 903, 907, 913) (933) HCA Identification Prevent/Mitigative (903, 905) (935) Threat Analysis Continual Evaluation (917) (937, 939, 941, 943) Baseline Assessment Performance (919, 921) Measures(947) Direct Assessment QA, Training, Comm. (923 through 921) (915, 945, 949, 951)
  • 12. Baseline Assessment Tool Selection Based Upon Threat Assessment Analysis Smart Pigging Historical Information (Need Further Investigation to Find Root Cause) Hydrostatic Testing (PHMSA Gold Standard – Disrupts Service / Introduces Water) External Corrosion Direct Assessment (Major Challenge for Acceptance – Industry Worked Out Process ECDA)
  • 13. ECDA – Four Step Process Advantage “can locate areas where defects could form in the future rather than only areas were defects have already formed”
  • 14. ECDA – Four Step Process 1. Pre-Assessment 2. Indirect Inspection 3. Direct Examinations 4. Post Assessments FAILURE TO FOLLOW PROCESS JEOPARDIZES PIPELINE SAFETY
  • 15. ECDA – Four Step Process Pre-Assessment “Utilization of Operational and Historical Records to Assess Potential External Corrosion Locations and to Determine Feasibility of Applying ECDA” UNDERSTANDING PIPELINE THREATS AND THE NEED TO OVERCOME THE ACCEPTANCE THAT RECORDS REVIEW REQUIRED
  • 16. ECDA – Four Step Process Pre-Assessment Identify and Address Corrosion Activity Past or Old Corrosion Damage (Finds Old Damage after CP Problem Corrected) Present Activity (Yes) Future Corrosion Risks (Identifies Problem Areas) Continuous Improvement Process (If Applied Correctly)
  • 17. ECDA – Four Step Process Pre-Assessment ECDA Feasibility Assessment Integrate and Analyze Data Collected Coating Electrical Shielding (ECDA Feasibility NO) Backfill with Rock Content and Rock Ledges (Remain Problem) Ground Surface Hindrances, i.e. Pavements (Drilling/Traffic Control) Adjacent Buried Metallic Structures (Stray Current Influence) Inaccessible Areas (Difficult to Access – Casings Overcome) Situations That Prevent Aboveground Measurements in Reasonable Time-Frame (Planning and Execution)
  • 18. ECDA – Four Step Process Pre-Assessment Data Collection Data Elements: Pipe-related, Construction Related, Soils/environmental, Corrosion Control, Operational Historical Records – Better Understanding Pipeline Sufficient Data – Missing Records Subject Matter Experts - Retirements Determine ECDA Feasibility – (Missing Data) Establish ECDA Regions Similar Physical Characteristics – Role of Environment Similar Past, Present, Future Corrosion Behaviors Utilizes Similar IIT Tools Select Indirect Inspection Tools
  • 19. ECDA – Four Step Process Indirect Inspection CIS - Indicates CP Level DCVG/ACVG - Indicates Exposed Metal Soils - Indicate Environment Corrosivity Depth - Indicate Third Party Damage Risk PCM - Indicate Current Attenuation
  • 20. ECDA – Four Step Process Indirect Inspection “Equipment and Practices Used to Take Measurements at Ground Surface Above or Near a Pipeline to Locate or Characterize Corrosion Activity, Coating Holidays, or Other Anomalies” Data Collection, Quality, Recognition, Current Interruption, Stray Current, Casings and AC Corrosion
  • 21. ECDA – Four Step Process Indirect Inspection Locate and define severity of coating faults where corrosion may occur or be occurring Discovery Coating Condition More Severe Conduct at least two indirect inspection tools (IIT) the entire length of the ECDA Region Casings and AC Corrosion Align and compare results from IIT tools More Stray Current Than Expected Identify, classify, and report results for Direct Examination step
  • 22. ECDA – Four Step Process Direct Examination “Inspections and Measurements Made On the Pipe Surface at Excavations as Part of External Corrosion Direct Assessment (ECDA)” Qualified Experienced Personnel
  • 23. Data Integration Management Tools •INSERT INTEGRATED SURVEY GRAPH
  • 24. ECDA – Four Step Process Direct Examination
  • 25. ECDA – Four Step Process Direct Examination
  • 26. ECDA – Four Step Process Post Assessment “Analysis of Indirect Inspections and Direct Examinations to Assess Pipeline Integrity, Prioritize Repairs, Redefine Reassessment Intervals and Assess the Overall Effectiveness of the ECDA Process”
  • 27. ECDA – Four Step Process Direct Examination Process Validation Remaining Life Calculation Define Reassessment Interval Define Effectiveness Measures Continuous Improvement Reassess ECDA Feasibility
  • 28. INTEGRITY MANAGEMENT 10 YEARS ECDA Charlie Hall

Hinweis der Redaktion

  1. As the pipeline ages, failures on the pipeline have become more frequent. Some years ago, the pipeline industry began to get extensive attention from regulators and legislators. Bellingham, WA incident Olympic Pipeline was implementing a new SCADA system and ignored a pipeline failure which pumped liquids into a stream. Some children playing with matches were killed when the water caught on fire. Some years later, an internal corrosion leak resulted in a group that had camped alongside a bridge to be killed. Gas leaked from the pipeline migrated over to a campfire and ignited. 12 people were involved in this incident. Congress legislated increased safety standards that resulted in the Pipeline Integrity Act.
  2. Code of Federal Regulations Title 49 Part 192 Pipeline Safety: Pipeline Integrity Management in High Consequence Areas (Gas Transmission Pipelines): Final rule
  3. Note implementation deadline dates
  4. Scope and Implementation: Develop and Follow a Written Integrity Management Plan Plan Contains All 16 Program Elements Specified in 192.911 HCA Identification, Baseline Assessment, Threat ID/Risk Assessment, DA Plan, Remediation, Continual Evaluation, Confirmatory DA, Preventative/Mitigative Measures, Performance Metrics, Recordkeeping, Management of Change, Quality Control, Communication Plan, Submittals to Regulators, Minimization of Environmental/Safety, Identification of New HCA’s Address the Risks on Each Covered Segment Collectively, a Set of Document(s) that Systematically Define, Control, and Implement Integrity Management Take Advantage of Existing Programs (e.g., O&M) Framework ( § 907) Minimal Process Detail Process for Implementing Each Program Element Describe How Relevant Decisions Will Be Made, By Whom, and Timeline Continual Incorporation of New Info Gained from Experience Evolve Into More Detailed and Comprehensive Program Continual Improvements Plans Certain Program Elements Described in Rule Refer to “Plans” Baseline Assessment Plan DA Plan (ECDA, ICDA, SCCDA) Performance Plan Communication Plan Why Have Written Plans? Accountability Compliance Record Portability (Asset Transfer) Consistent Implementation (Personnel Turnover) Progress (Performance) Standard Threat Analysis Prescriptive - 9 Categories 1. Internal Corrosion 2. External Corrosion 3. Stress Corrosion Cracking 4. Manufacturing-Related 5. Welding/Fabrication-Related 6. Equipment 7. Third Party/Mechanical Damage 8. Incorrect Operations 9. Weather-Related and Outside Force Data Gathering and Integration Minimum Data Per B31.8S, App A Past Incident History Corrosion Control Records Continuing Surveillance Records Patrolling Records Maintenance History Internal Inspection Records All Other Conditions Specific to Each Pipeline B31.8S Requires Systematic Effort Comprehensive Plan to Collect, Review & Analyze Data Validated and Documented Data and Assumptions Timely Consideration of New Information Data Integration Aimed At Putting Together Data from Different Sources for Better Understanding of Threats Combining Data from Integrity Assessments with Threat Assessment Requires ANALYSIS Continual Improvement “ Mature” Program is Not the End of Program Development Critical Self-Assessment Study Integrity Mgt Performance Identify Areas to Improve Risk Assessment Follow B31.8S, Section 5 Consider All Identified Threats Use Risk Assessment To: Prioritize Baseline Assessments Prioritize Reassessments Determine Additional Preventive and Mitigative Measures All Approaches Entail Identification of Relevant Threats for Each Covered Segment Characterization of Likelihood and Consequences of Pipeline Failure Likelihood and Consequences Combined to Calculate Risk References Standards Rule Invokes Industry Standards Documents (or Portions Thereof) Incorporated by Reference are Invoked in Subpart O as Though Set Out in Full in the CFR Re: 49 CFR 192.7 contains list NACE RP0502-2002 (ECDA) Entirety ASME B31.8S-2001 (IM) Specific (Most) Sections §§ 2, 4, 5, 6.2, 6.3, 6.4, 7, 9, 10, 11, 12, App A, App B.2
  5. Three Baseline Assessment Tools Can be Applied: 1- Smart Pigging 2- Hydrostatic Testing 3- External Corrosion Direct Assessment