2. Eyad Alhaj
1. More than 12 years of working in Syria, Iraq, and
online, in planning for projects of which some
exceeded $ 40 million.
2.More than 10 years of training in PMP, feasibility
study, M.S Project, and Primavera software for
various companies, NGOs, training centers in
Iraq, Syria, and online.
3.Speaker in conferences, publishing articles and
case studies in magazines about the benefits of
4D and 5D in BIM projects.
3. 2019
Egyptian Center
in Iraq/ Basra /
workshops for the
engineers of the South Oil
refineries company.
2020/2021
1.Sana Company
for construction in Nigeria,
Conducted an online
workshop on Zoom
platform for
Infrastructure project.
2.YSR Center
Workshops for
construction projects.
2011/2017
The General Company for
Engineering Studies
and Consultations
Workshops for practical
application to many
supervision projects.
Interactive workshops using Primavera software.
4. Content
Trainer: Eyad Alhaj
1. Introduction in Project management.
2. Introduction in Primavera software.
3. Link between PMBOK 6 guide and Primavera software.
4. Link between GAO guides, DCMA assessment and
Primavera software.
5.Training Standards
5. 1. Introduction in
Project management. 1
Trainer: Eyad Alhaj
Lecture: How to become professional planner on Primavera software? Chapter 1: Introduction in project management
6. Project or operation?
Overlap between project and operation
A Project is a temporary work undertaken to create a unique product, service or result .
Lecture: How to become professional planner on Primavera software? Chapter 1: Introduction in project management
Source: PMBOK
1-1
Trainer: Eyad Alhaj
7. Building
project
Planting
Project of 15
trees around
the building
Delivery of
the project
Ovelap between project
and operation
Watering
operations
of 15 trees
around the
building
Housing
operations in
the second
floor
Repair
project of
sanitary in
the second
floor
Lecture: How to become professional planner on Primavera software? Chapter 1: Introduction in project management
Trainer: Eyad Alhaj
1-2
8. When the project management
is unsuccessful ?
Failure story in
project management
Lecture: How to become professional planner on Primavera software? Chapter 1: Introduction in project management
1-3
Trainer: Eyad Alhaj
9. Success in project management
1) The project met scope, time and cost goals.
2) The project satisfied the customer/sponsor.
Source: PMI
Lecture: How to become professional planner on Primavera software? Chapter 1: Introduction in project management
1-4
Trainer: Eyad Alhaj
11. 81%
Primavera
16%
M-S Project 3%
None
The question posed to multiple groups in the field of project management software
Posted in: 22/08/2014
What software is most used?
Lecture: How to become professional planner on Primavera software? Chapter 2: Introduction in Primavera software
2-1
Trainer: Eyad Alhaj
12. First
issue
in 1983
History of Primavera software
Lecture: How to become professional planner on Primavera software? Chapter 2: Introduction in Primavera software
2-2
Trainer: Eyad Alhaj
13. Primavera software is used in the any project
Is Primavera software used only
in construction projects ?
Lecture: How to become professional planner on Primavera software? Chapter 2: Introduction in Primavera software
2-3
Trainer: Eyad Alhaj
14. Is Primavera software used only
during planning process ?
Primavera software used of during planning, executing,
monitoring and controlling process.
Lecture: How to become professional planner on Primavera software? Chapter 2: Introduction in Primavera software
2-4
Trainer: Eyad Alhaj
15. Is Primavera software used only
in scheduling of time?
Lecture: How to become professional planner on Primavera software? Chapter 2: Introduction in Primavera software
2-5
Trainer: Eyad Alhaj
Primavera software using of during time management.
16. Lecture: How to become professional planner on Primavera software? Chapter 2: Introduction in Primavera software
Is Primavera software used only
in scheduling of time?
2-6
Trainer: Eyad Alhaj
Primavera software using of during resources management.
17. Lecture: How to become professional planner on Primavera software? Chapter 2: Introduction in Primavera software
Is Primavera software used only
in scheduling of time?
2-7
Trainer: Eyad Alhaj
Primavera software using of during cost management.
18. Lecture: How to become professional planner on Primavera software? Chapter 2: Introduction in Primavera software
Is Primavera software used only
in scheduling of time?
Primavera software using of during risks management.
2-8
Trainer: Eyad Alhaj
19. Schedule
Scope
Resources
Costs
Risks
Lecture: How to become professional planner on Primavera software? Chapter 2: Introduction in Primavera software
Is Primavera software used only
in scheduling of time?
2-9
Trainer: Eyad Alhaj
20. 3.Link between PMBOK 6 guide
and Primavera software
Lecture: How to become professional planner on Primavera software? Chapter 3: Link between PMBOK 6 guide and Primavera software
3
Trainer: Eyad Alhaj Date prepared: 1/6/2019
21. Link between PMBOK 6 guide and Primavera software
Knowledge areas:
1. Scope Management
2. Schedule Management
3. Resource Management
4. Cost Management
5. Risks Management
6. Quality Management
7. Communication Management
8. Procurement Management
9.Stakeholders Management
10.Integration Management
Lecture: How to become professional planner on Primavera software? Chapter 3: Link between PMBOK 6 guide and Primavera software
3-1
Trainer: Eyad Alhaj Date prepared: 1/6/2019
22. Lecture: How to become professional planner on Primavera software? Chapter 3: Link between PMBOK 6 guide and Primavera software
Admin
Admin Categories
Units of Measure.
Explained how the link between PMBOK 6 guide and Primavera software during
course of (how to become professional planner on Primavera software)
Link between PMBOK 6 guide and Primavera software
Plan Cost Management : Output
Cost Management Plan (form), include :
1-Units of Measure
quantity measures
or lump sum in currency
3-2
Trainer: Eyad Alhaj Date prepared: 1/6/2019
23. Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
4. Link between GAO guides,
DCMA assessment and
Primavera software.
4
Trainer: Eyad Alhaj
24. GAO
Include of:
• Best practices for developing and maintaining high-quality schedules
• Contains text, illustrations, and detailed case studies
Link between GAO schedule assessment guide and Primavera software.
4-1
Trainer: Eyad Alhaj
Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
U.S. Government
Accountability Office
25. Explained how the link between GAO guides and Primavera software during course of
(How to become professional planner on Primavera software)
Develop Schedule: T & T
3. Critical Chain
The critical chain method adds duration buffers that are non-work
schedule activities to manage uncertainty.
Trainer: Eyad Alhaj
4-2
Link between GAO schedule assessment guide and Primavera software.
Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
26. Inflexible
Must Finish
On (MFO)
Task is scheduled to finish
on a specified date.
Must Start On
(MSO)
Task is scheduled to start on
a specified date
Develop Schedule: T & T
3. Critical Chain:
The critical chain method adds duration buffers that are non-work
schedule activities to manage uncertainty.
Link between GAO schedule assessment guide and Primavera software.
Source:
GAO schedule assessment
4-3
Explained how the link between GAO guides and Primavera software during course of
(how to become professional planner on Primavera software)
Trainer: Eyad Alhaj
Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
27. Develop Schedule: T & T
Link between GAO schedule assessment guide and Primavera software.
3. Critical Chain:
1- Finish On:
constraint, the constraint date is the date on which the activity must finish.
4-4
Explained how the link between GAO guides and Primavera software during course of
(how to become professional planner on Primavera software)
Trainer: Eyad Alhaj
Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
28. Link between GAO cost estimate guide and Primavera software.
Include of:
• The process of collecting and analyzing data and applying
• techniques, tools, and databases to predict the future cost of task.
4-5
Trainer: Eyad Alhaj
Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
29. Parametric cost estimates can be applied to a total project or to segments of
a project.
Estimate Costs: T & T
3. Parametric estimating
Source:
GAO cost estimate
Link between GAO cost estimate guide and Primavera software.
4-6
Explained how the link between GAO guides and Primavera software
during course of (how to become professional planner on Primavera software)
Trainer: Eyad Alhaj
Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
30. 3. Parametric estimating
3-2 Indirect cost
Estimate Costs: T & T
Link between GAO cost estimate guide and Primavera software.
4-7
Explained how the link between PMBOK 6 guide, GAO guides and Primavera software
during course of (how to become professional planner on Primavera software)
Trainer: Eyad Alhaj
Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
31. Link between DCMA Assessment and Primavera software.
Include of:
DCMA 14-point Schedule Assessment is a project management guideline
established on 14 metrics that provide the possibility to make a qualitative and
quantitative evaluation of the schedule.
4-8
Trainer: Eyad Alhaj
Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
Defense
Contract
Management
Agency
32. 2. Activity Duration Estimates:
Quantitative estimates of the likely duration of each activity
Estimate Activity Duration: Outputs
Important
note
Source:
DCMA
Link between DCMA Assessment and Primavera software.
Explained how the link between DCMAAssessment and Primavera software during
course of (how to become professional planner on Primavera software)
4-9
Trainer: Eyad Alhaj
Lecture: How to become professional planner on Primavera software? Chapter 4: Link between GAO guides, DCMA assessment and Primavera software
34. We train through interactive workshops for
a project that the attendees want.
1
2
3
Lecture: How to become professional planner on Primavera software? Chapter 5: Training Standards
5-1
35. We train through interactive workshops for
a project that the attendees want.
1
2 Reliance on international references
and standards.
3
Lecture: How to become professional planner on Primavera software? Chapter 5: Training Standards
5-2
36. We train through interactive workshops for
a project that the attendees want.
1
2 Reliance on international references
and standards.
3 The use of training methods suitable
for the attendees.
Lecture: How to become professional planner on Primavera software? Chapter 5: Training Standards
Attend a
workshop in
training of
trainers
(TOT)/2011
5-3
37. 1.You can communicate with us
Email: eyad.hajsa@gmail.com
WhatsApp:00963992023399
2. To follow the latest events and posts
https://www.facebook.com/EyadAlhaj1
https://www.linkedin.com/in/eyadalhaj/
For connection and follow-up