NTPC has invited bid for the power procurement from 500 MW Solar Power projects in the state of Andhra Pradesh. Last date for BID submission is 30/06/2015. "EnvironmentFirst Energy Services (P) Ltd." is helping in complete BIDDING process, in case if you require any kind of know how you can contact us.
BRIEFING NOTE OF RFP BY NTPC FOR INSTALLATION OF 500 MW SOLAR POWER PROJECT IN ANDHRA PRADESH
1. EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: Environmentfirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Our Locations: Mumbai, Chennai, Ahmedabad, Jaipur, Panchkula Page 1
COMPETITIVE BIDDING BY NTPC FOR INSTALLATION OF 500 MW
SOLAR POWER PROJECT IN ANDHRA PRADESH
Summary
Bid Inviting Company NTPC
Contract Period/PPA 25 Years
Total Capacity of The Bid 500 MW
Project awarding Method Bidding
Capacity of each Project 50 MW each
Pre Bid Meeting On 16/06/2015 at 10:00 Hrs (IST)
at EOC, Noida
Downloading of RFS Document 01 May 2015 to 01 June 2015 till 17.00
Hrs
Submission Date 30.06.2015, Time: 17.00 Hrs
Performance Guarantee INR 30 Lakh/ MW in the Form of Bank
Guarantee valid for 19 months from the
date of PPA
Earnest Money Deposit INR 10 Lakh/ MW in the Form of Bank
Guarantee valid for 240 days from
technical Bid opening Date
Bid Processing fee Rs. 3 Lakh/Project (non refundable), in the
form of a demand draft / payable at and
10 Lakh for 2 or more projects Noida/New
Delhi Only in favour of NTPC Ltd
Technical Bid Bid Opening date 02 July 2015 10:00 am onwards
Financial Bid Opening Prior to Start of Reverse Auction
Date and time of Reverse auction To be announced for individually
2. EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: Environmentfirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Our Locations: Mumbai, Chennai, Ahmedabad, Jaipur, Panchkula Page 2
Summary
Location of Solar Park Village-Ghani, Distt. Kurnool, Andhra Pradesh
Contact person for the Park Mr. G. Adiseshu
AP Solar Power Corporation Ltd
House No 6-3-856/A3, Sadat Manzil Compound
Neeraj Public School Lane, Ameerpet, Hyd-16
Number of Bids by a company No upper limit for the Projects
Eligibility Net worth 1.5 Cr/MW
Benchmark Levellised Tariff Rs 7.04/Kwh to Rs 6.35 /Kwh with normal rate of
Depreciation
Documents to be submitted offline: Instrument Toward processing fee
Bank Guaranty Towards EMD
Original Power of Attorney
Original Integrity Pact signed by Authorized
Certificate of Compliance
Certificate toward compliance of fraud
protection
Envelope Enclosures First Envelope:
Technical Qualifying Documents and Excel
Sheet
Second Envelope:
First round Tariff Bid
3. EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: Environmentfirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Our Locations: Mumbai, Chennai, Ahmedabad, Jaipur, Panchkula Page 3
Other Information
Address for submission of Responses To
AGM(CS-RE)/Manager(CS-RE)
NTPC LTD, Renewable Energy Contract Services
Engineering Office Complex, NTPC Ltd
A 8A, Sec 24, Noida, UP 201301
Validity of Responses to RFS Valid for 180 Days from the date of Submission
Preparation Cost Bidder Shall be Responsible for all the document
and fee preparation cost
Additional Performance bank Guarantee Selected developers should have to provide
additional guarantee of 10 % that is Rs 3 Lakh/MW
Financial Closure Within 210 days from the signing of PPA after that
25,000/Day/MW penalty would be charged.
Commissioning 13 Months from signing PPA
Penalty:
NTPC will encash the PBG on per day
basis and 100% encashment on 5 month
delay.
After 5 months 1,00,000/MW for the
capacity which is not commissioned
Commercial operation Date 30 Days from the commissioning