Project Management
     Application and Concentration

                                          BUS XXX - 3 Units
                                                   Fall 2012


                                      Weekend 2 - Day 2




Project Management Certification – A Professional Commitment – A Responsibility
Reflecting on Last Class
     • Foundations
          o   What is a project?
          o   What is Project Management?
          o   Process Groups / Knowledge Areas / Processes
          o   Project Lifecycle and its characteristics
          o   Organizational Structure


     • Initiating
          o Project Charter – Why is it important; ITTO?
          o Identify Stakeholders – Why is this step important? ITTO?


     • Planning
          o Project Management Plan - Incorporates outputs from
              all other planning processes
          o Collect Requirements
              • Knowing the right questions
              • Knowing the right people
              • ITTO?
Project Management Certification – A Professional Commitment – A Responsibility
Learning Objectives for Today
 • Scope
     o Recognize how to Define Scope, so we know what we are delivering
     o Explain what is involved in Creating a WBS for project deliverables

 • Time
     o   Explain the processes leading up to Develop Schedule
     o   Breakdown all tasks to determine what the team should work on
     o   Determine the dependencies and what can be worked on concurrently
     o   Determine what / who / how many to use by Estimating activity resources
     o   Assess how long activities will take by Estimating activity durations
     o   Compile analysis into a schedule to determine a “target date”

 • Cost
     o Estimate how much each activity will costs
         • labor, service, equipment, and other items
     o Aggregate all costs to determine funding requirements and determine if
       scope needs adjustment when budget is a constraint
Project Management Certification – A Professional Commitment – A Responsibility
Weekend 2, Day 2 – Overview
                                                                  Process Groups
                                                                                                                                                                           Monitoring &
                                                                                   Initiating                  Planning                       Executing                                                     Closing
                                                                                                                                                                            Controlling
                                                             Knowledge Areas
                                                                                   Develop Project                                         Direct and Manage         Monitor & Control Project Work,     Close Project or
                                                              Integration          Charter
                                                                                                     Develop Project Management Plan
                                                                                                                                           Project Execution         Perform Integrated Change Control   Phase
F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t




                                                                                                     Collect Requirements,
                                                                                                                                                                     Verify Scope,
                                                              Scope                                  Define Scope,
                                                                                                                                                                     Control Scope
                                                                                                     Create WBS

                                                                                                     Define Activities,
                                                                                                     Sequence Activities,
                                                               Time                                  Estimate Activity Resources,                                    Control Schedule
                                                                                                     Estimate Activity Durations,
                                                                                                     Develop Schedule

                                                                                                     Estimate Cost,
                                                              Cost                                   Determine Budget
                                                                                                                                                                     Control Cost


                                                                                                                                           Perform Quality
                                                              Quality                                Plan Quality
                                                                                                                                           Assurance
                                                                                                                                                                     Perform Quality Control


                                                                                                                                           Acquire Project Team,
                                                              Human Resource                         Develop Human Resources Plan          Develop Project Team,
                                                                                                                                           Manage Project Team

                                                                                                                                           Distribute Information,
                                                                                   Identify
                                                              Communications       Stakeholders
                                                                                                     Plan Communications                   Manage Stakeholder        Report Performance
                                                                                                                                           Expectations

                                                                                                     Plan Risk Management,
                                                                                                     Identify Risks,
                                                              Risk                                   Perform Qualitative Risk Analysis,                              Monitor and Control Risks
                                                                                                     Perform Quantitative Risk Analysis,
                                                                                                     Plan Risk Responses

                                                              Procurement                            Plan Procurements                     Conduct Procurements      Administer Procurements             Close Procurement




                                                             Project Management Certification – A Professional Commitment – A Responsibility
Five Questions - Class Exercise




Project Management Certification – A Professional Commitment – A Responsibility
Define Scope



Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
     - Overview
 • What is Project Scope?

 • Why is it important to Define Scope?
     o Make sure everyone is on the right page
     o Baseline for changes


 • Who says what is in and what is out?

 • What about open ended projects?




Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
                                                                      - PMBOK Process 5.2
                                                                  Process Groups
                                                                                                                                                                           Monitoring &
                                                                                   Initiating                  Planning                       Executing                                                     Closing
                                                                                                                                                                            Controlling
                                                             Knowledge Areas
                                                                                   Develop Project                                         Direct and Manage         Monitor & Control Project Work,     Close Project or
                                                              Integration          Charter
                                                                                                     Develop Project Management Plan
                                                                                                                                           Project Execution         Perform Integrated Change Control   Phase
F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t




                                                                                                     Collect Requirements,
                                                                                                                                                                     Verify Scope,
                                                              Scope                                  Define Scope,
                                                                                                                                                                     Control Scope
                                                                                                     Create WBS

                                                                                                     Define Activities,
                                                                                                     Sequence Activities,
                                                               Time                                  Estimate Activity Resources,                                    Control Schedule
                                                                                                     Estimate Activity Durations,
                                                                                                     Develop Schedule

                                                                                                     Estimate Cost,
                                                              Cost                                   Determine Budget
                                                                                                                                                                     Control Cost


                                                                                                                                           Perform Quality
                                                              Quality                                Plan Quality
                                                                                                                                           Assurance
                                                                                                                                                                     Perform Quality Control


                                                                                                                                           Acquire Project Team,
                                                              Human Resource                         Develop Human Resources Plan          Develop Project Team,
                                                                                                                                           Manage Project Team

                                                                                                                                           Distribute Information,
                                                                                   Identify
                                                              Communications       Stakeholders
                                                                                                     Plan Communications                   Manage Stakeholder        Report Performance
                                                                                                                                           Expectations

                                                                                                     Plan Risk Management,
                                                                                                     Identify Risks,
                                                              Risk                                   Perform Qualitative Risk Analysis,                              Monitor and Control Risks
                                                                                                     Perform Quantitative Risk Analysis,
                                                                                                     Plan Risk Responses

                                                              Procurement                            Plan Procurements                     Conduct Procurements      Administer Procurements             Close Procurement




                                                             Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
     - Project vs. Product Scope


                          • Project Scope: measured against
                            project management plan


                          • Product Scope: measured against
                            product requirements




Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
            - Definition
1   2   3                              1   2   3   4                             1    2



                             • The process of developing a
                               detailed description of the project
                               and the product

                             • Defines what the project includes
                               and excludes




    Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
             - Inputs
1   2    3



        1) Project Charter
             o High-Level project description and requirements


        2) Requirements Documentation
             o Primary document used for scope definition


        3) Organizational Process Assets
             Examples:
             o Templates for a project scope statement
             o Files from previous projects
             o Lessons learned from previous projects




    Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
     - Tools & Techniques
                                   1   2   3   4



 1) Expert Judgment

 2) Product Analysis
     o Product breakdown, system analysis, requirement analysis, systems
       engineering, value engineering, and value analysis
     o Only for projects that have a product as a deliverable


 3) Alternative Identification
     o A technique used to generate different approaches to execute the
       project
     o Brainstorming, Lateral Thinking, Pair wise comparison


 4) Facilitated Workshops
     o Cross-functional



Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
     - Outputs
                                                                                1   2



 1) Project Scope Statement
     o Describes, in detail, project deliverables and work required to create
       these deliverables
     o Helps to create a common understanding among stakeholders (avoid
       scope creep)
     o Project team can perform detailed planning now
     o Components
         • Product Scope Description
         • Product Acceptance Criteria
         • Project Objectives
         • Project Deliverables
         • Project Exclusions
         • Project Constraints
         • Project Assumptions




Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
     - Moe’ Outputs
                                                                             1    2



 2) Project Document Updates
     o   Stakeholder Register
     o   Requirements documentation
     o   Requirements Traceability Matrix
     o   Etc.




Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
     - Top Reasons Why Projects Fail

 •   Unclear Project Objectives and Requirements
 •   Lack of Planning
 •   Scope Creep
 •   Lack of Stakeholder Involvement
 •   Gaps in Communication
 •   Resource Overload
 •   Etc.




Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
     - Data Flow Diagram




Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
     - Key Points
 • Scope definition is a joint effort between Project
   Manager , Project team, and business stakeholders
    (though the Project Manager may be the one writing the Scope Statement)

 • Scope Statement sets clear expectation and
   establish the basis for future change requests
 • Define Scope is a progressively elaborated process;
   may be adjusted as more details become known
 • A good idea to have Scope Statement approved
   and published
 • Scope Statement will later be used to measured
   against to determine if the project has been
   completed successfully

Project Management Certification – A Professional Commitment – A Responsibility
Define Scope
     - Key Points
 • Project constraints limit the options and restrict
   project team’s actions: Time, Budget, Scope,
   Quality, Schedule, Resource, Technology,
   Management Directives

 • Poorly written Scope Statement may lead to
   increased cost, longer duration, deliverables that
   do not meet business expectation, and ultimately
   unsatisfied stakeholders.

 • Meeting or exceeding stakeholder expectation
   doesn’t mean gold-plating

Project Management Certification – A Professional Commitment – A Responsibility
Create Work
Breakdown Structure


Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - Overview
 • What is the purpose?
     o More manageable components


 • Key is to break it down
     o Should include entire project scope


 • Multiple approaches
     o By Project Phases
     o By Deliverables
     o By Sub-projects




Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
                                                                      - PMBOK Process 5.3
                                                                  Process Groups
                                                                                                                                                                           Monitoring &
                                                                                   Initiating                  Planning                       Executing                                                     Closing
                                                                                                                                                                            Controlling
                                                             Knowledge Areas
                                                                                   Develop Project                                         Direct and Manage         Monitor & Control Project Work,     Close Project or
                                                              Integration          Charter
                                                                                                     Develop Project Management Plan
                                                                                                                                           Project Execution         Perform Integrated Change Control   Phase
F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t




                                                                                                     Collect Requirements,
                                                                                                                                                                     Verify Scope,
                                                              Scope                                  Define Scope,
                                                                                                                                                                     Control Scope
                                                                                                     Create WBS

                                                                                                     Define Activities,
                                                                                                     Sequence Activities,
                                                               Time                                  Estimate Activity Resources,                                    Control Schedule
                                                                                                     Estimate Activity Durations,
                                                                                                     Develop Schedule

                                                                                                     Estimate Cost,
                                                              Cost                                   Determine Budget
                                                                                                                                                                     Control Cost


                                                                                                                                           Perform Quality
                                                              Quality                                Plan Quality
                                                                                                                                           Assurance
                                                                                                                                                                     Perform Quality Control


                                                                                                                                           Acquire Project Team,
                                                              Human Resource                         Develop Human Resources Plan          Develop Project Team,
                                                                                                                                           Manage Project Team

                                                                                                                                           Distribute Information,
                                                                                   Identify
                                                              Communications       Stakeholders
                                                                                                     Plan Communications                   Manage Stakeholder        Report Performance
                                                                                                                                           Expectations

                                                                                                     Plan Risk Management,
                                                                                                     Identify Risks,
                                                              Risk                                   Perform Qualitative Risk Analysis,                              Monitor and Control Risks
                                                                                                     Perform Quantitative Risk Analysis,
                                                                                                     Plan Risk Responses

                                                              Procurement                            Plan Procurements                     Conduct Procurements      Administer Procurements             Close Procurement




                                                             Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - Definition
 • Definition: Deliverable – oriented hierarchical
   decomposition of the work to accomplish the
   project objectives and create required deliverables

 • Includes total scope of the project

 • Top down effort

 • Lowest Level = Work package, which can be
   scheduled, cost estimated, monitored, and
   controlled

 • Shall be revised if a major scope change occurs

Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
            - Definition
1   2   3                                  1                                1   2   3   4




    Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
             - Inputs
1   2    3




        1) Project Scope Statement
             o All the deliverables and work to create them
             o What type of work is not included


        2) Requirements Documentation

        3) Organization Process Assets
             o Policies, procedures, and templates for the WBS
             o Project files from previous projects
             o Lessons learned from previous projects




    Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - Tools & Techniques
                                         1



 1) Decomposition – Sample 5-step process
     a) Identify the deliverables and work
     b) Organize the WBS; structure can be organized by
         - Phases
         - Major deliverables
         - Subprojects (e.g. contracted work)
     c) Decompose the WBS into low-level components
     d) Assign identification codes
     e) Verify WBS




Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - Decomposition Guidelines
                                       1




 • Not a task list; excessive decomposition can have a
   detrimental effect by making WBS overly complex,
   confusing to view, and difficult to maintain

 • Rule of thumb for how far to break it down is to get
   to 8-80 hours of work per package

 • 100% Rule: Total of lowest levels must represents the
   total work of the project to ensure no work is left out
   or no extra work is added



Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - Outputs
                                                                        1   2   3   4



 1) The Work Breakdown Structure (WBS) itself

 • WBS is finalized by establishing control accounts for
   the work packages and a unique identifier from a
   code of accounts

 • Control Account - a management control point
   where scope, cost, and schedule are integrated
   and compared to the earned value

 • Each control account may have more than one
   work package but one work package shall only be
   linked to one control account
Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - Outputs
                                                                        1   2   3   4


 2) WBS Dictionary
     o   Code of account identifier
     o   Description of work
     o   Responsible person(s) or organization
     o   List of schedule milestones
     o   Resource and quality requirements
     o   Cost estimates
     o   Acceptance criteria
     o   Contract info and technical references


 3) Scope Baseline
     o Part of Project Management Plan
     o Consists of
        • Scope Statement
        • WBS
        • WBS Dictionary


 4) Project Document Updates
     o Requirements documentation, etc.

Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - Sample Diagram




Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - by Project Phases




Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - by Major Deliverables




Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - Data Flows




Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
     - Key Points

 • WBS is a deliverable-oriented structure

 • Work Package is the lowest level on WBS. Activities
   and tasks are not included in the WBS.

 • WBS should include 100% of the project scope

 • WBS Levels: Project Name = Level 1, Deliverables =
   Level 2

 • Scope Baseline includes Scope Statement, WBS,
   and WBS Dictionary

Project Management Certification – A Professional Commitment – A Responsibility
Define Activities



Project Management Certification – A Professional Commitment – A Responsibility
Define Activities
     - Overview

 • What’s the Purpose?
     o Further decompose the Work Packages into schedule activities as basis
       for estimating, scheduling, and monitoring
     o Working towards creating a project schedule


 • In what order should it be done – next steps
     o   Define Activity
     o   Sequence Activity
     o   Estimate Activity Resource
     o   Estimate Activity Duration
     o   Develop Schedule




Project Management Certification – A Professional Commitment – A Responsibility
Define Activities
                                                                      - PMBOK Process 6.1
                                                                  Process Groups
                                                                                                                                                                           Monitoring &
                                                                                   Initiating                  Planning                       Executing                                                     Closing
                                                                                                                                                                            Controlling
                                                             Knowledge Areas
                                                                                   Develop Project                                         Direct and Manage         Monitor & Control Project Work,     Close Project or
                                                              Integration          Charter
                                                                                                     Develop Project Management Plan
                                                                                                                                           Project Execution         Perform Integrated Change Control   Phase
F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t




                                                                                                     Collect Requirements,
                                                                                                                                                                     Verify Scope,
                                                              Scope                                  Define Scope,
                                                                                                                                                                     Control Scope
                                                                                                     Create WBS

                                                                                                     Define Activities,
                                                                                                            Activities
                                                                                                     Sequence Activities,
                                                               Time                                  Estimate Activity Resources,                                    Control Schedule
                                                                                                     Estimate Activity Durations,
                                                                                                     Develop Schedule

                                                                                                     Estimate Cost,
                                                              Cost                                   Determine Budget
                                                                                                                                                                     Control Cost


                                                                                                                                           Perform Quality
                                                              Quality                                Plan Quality
                                                                                                                                           Assurance
                                                                                                                                                                     Perform Quality Control


                                                                                                                                           Acquire Project Team,
                                                              Human Resource                         Develop Human Resources Plan          Develop Project Team,
                                                                                                                                           Manage Project Team

                                                                                                                                           Distribute Information,
                                                                                   Identify
                                                              Communications       Stakeholders
                                                                                                     Plan Communications                   Manage Stakeholder        Report Performance
                                                                                                                                           Expectations

                                                                                                     Plan Risk Management,
                                                                                                     Identify Risks,
                                                              Risk                                   Perform Qualitative Risk Analysis,                              Monitor and Control Risks
                                                                                                     Perform Quantitative Risk Analysis,
                                                                                                     Plan Risk Responses

                                                              Procurement                            Plan Procurements                     Conduct Procurements      Administer Procurements             Close Procurement




                                                             Project Management Certification – A Professional Commitment – A Responsibility
Define Activities
             - Definition
1   2    3                             1   2   3   4                           1   2   3




        • The process of identifying the specific actions to be
          performed

        • Project  Deliverables  Work Packages (WBS)
          Activities




    Project Management Certification – A Professional Commitment – A Responsibility
Define Activities
             - Inputs
1   2    3




        1) Scope Baseline
             o Deliverables, constraints, and assumptions


        2) Enterprise Environmental Factors
             o Project Management Information System used will affect the definition


        3) Organizational Process Assets
             o Existing formal and informal policies, procedures, and guidelines (e.g.
               Scheduling methodology)
             o Lessons learned/knowledge base from historical information




    Project Management Certification – A Professional Commitment – A Responsibility
Define Activities
     - Tools & Techniques
                                      1   2   3   4




 1) Decomposition
     o Involving teams in decomposition can lead to more accurate results


 2) Rolling Wave Planning
     o A progressive elaboration process where near-term activities are in great
       detail and longer-term activities are at a high level


 3) Templates
     o Organizational standard Activity List or Activity List from previous projects
     o Can also be used to identify typical schedule milestones


 4) Expert Judgment


Project Management Certification – A Professional Commitment – A Responsibility
Define Activities
     - Outputs
                                                                                  1   2   3




 1) Activity List (or Task List)
     o Detailed list of all activities required to complete the project


 2) Activity Attributes
     o Further defines the activity, such as Activity ID, WBS ID, activity name and
       description, predecessor, successor, leads and lags, person responsible,
       resource requirements, constraints, assumptions, level of effort, etc.
     o Activity attributes are used for schedule development and for selecting,
       ordering, and sorting the planned schedule activities in various ways
       within reports


 3) Milestone List
     o A list of significant points in a project




Project Management Certification – A Professional Commitment – A Responsibility
Create Work Breakdown Structure
          - Sample Milestone List
                                                  August                                                 September                                               October
                 Activity          Aug 13 - 17   Aug 20 - 24    Aug 27 - 31   Sep 3 - 7      Sep 10 - 14          Sep 17 - 21      Sep 24 - 28       Oct 1 - 5         Oct 8 - 12


  Offer Code Setup and BOM                                     8/24
  Forecast Mix                                                 8/24

  Packaging Design/Approval
  Packaging Arrived at FFC                                                                        9/10
  Collateral Arrived at FFC                                                                       9/10
  Assembly Specs                                                               8/31

  Call Routing and Training                                                                                  9/14
  IBTM and Testing Setup                                                                                     9/14

  Web Creative                                                                        9/5
  Web Development                                                                                         9/12
  Web Dependency Project                                                                                  9/12
  Complete
  Web QA Ready                                                                                               9/14
  Web Brand Setup
  Web End to End Testing                                                                                                        9/20
  Merchant ID Setup                                                                   9/5
                                                                                                  9/10
  FFC Brand Setup


  Planning Release                                                                                9/10
  Filled Intermediate Arrived at
  FFC                                                                                                                            9/21
  Kit Assembly
                                                                                            9/7
  QA Audit and Compliance
  QA Quality Agreement                                                                                           9/14
                                                                                                                                       Launch 9/24



Project Management Certification – A Professional Commitment – A Responsibility
Define Activities
     - Data Flows




Project Management Certification – A Professional Commitment – A Responsibility
Define Activities
     - Key Points

 • Define Activity process uses Scope Baseline as the
   primary input

 • WBS is further decomposed

 • Activity Lists, Activity Attributes and Milestone Lists
   are the outputs

 • May be progressive elaboration process

 • Rolling Wave Planning = define near-term work in
   greater detail than future work

Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities



Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Overview

 • Determine logical dependencies

 • Determine what can be done concurrently




Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
                                                                      - PMBOK Process 6.2
                                                                  Process Groups
                                                                                                                                                                           Monitoring &
                                                                                   Initiating                  Planning                       Executing                                                     Closing
                                                                                                                                                                            Controlling
                                                             Knowledge Areas
                                                                                   Develop Project                                         Direct and Manage         Monitor & Control Project Work,     Close Project or
                                                              Integration          Charter
                                                                                                     Develop Project Management Plan
                                                                                                                                           Project Execution         Perform Integrated Change Control   Phase
F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t




                                                                                                     Collect Requirements,
                                                                                                                                                                     Verify Scope,
                                                              Scope                                  Define Scope,
                                                                                                                                                                     Control Scope
                                                                                                     Create WBS

                                                                                                     Define Activities,
                                                                                                     Sequence Activities,
                                                               Time                                  Estimate Activity Resources,                                    Control Schedule
                                                                                                     Estimate Activity Durations,
                                                                                                     Develop Schedule

                                                                                                     Estimate Cost,
                                                              Cost                                   Determine Budget
                                                                                                                                                                     Control Cost


                                                                                                                                           Perform Quality
                                                              Quality                                Plan Quality
                                                                                                                                           Assurance
                                                                                                                                                                     Perform Quality Control


                                                                                                                                           Acquire Project Team,
                                                              Human Resource                         Develop Human Resources Plan          Develop Project Team,
                                                                                                                                           Manage Project Team

                                                                                                                                           Distribute Information,
                                                                                   Identify
                                                              Communications       Stakeholders
                                                                                                     Plan Communications                   Manage Stakeholder        Report Performance
                                                                                                                                           Expectations

                                                                                                     Plan Risk Management,
                                                                                                     Identify Risks,
                                                              Risk                                   Perform Qualitative Risk Analysis,                              Monitor and Control Risks
                                                                                                     Perform Quantitative Risk Analysis,
                                                                                                     Plan Risk Responses

                                                              Procurement                            Plan Procurements                     Conduct Procurements      Administer Procurements             Close Procurement




                                                             Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
             - Definition
1   2    3   4   5                     1   2   3   4                             1    2




        • Process of identifying and documenting
          relationships among project activities




    Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
             - Inputs
1   2    3   4   5




        1) Activity List

        2) Activity Attributes

        3) Milestone List

        4) Project Scope Statement
             o As double-check


        5) Organizational Process Assets
             o Example: Previous Project File




    Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Tools & Techniques
                                    1   2   3   4




 1) Precedence Diagramming Method (PDM)
     o A method used in Critical Path Methodology (CPM) to build a
       network diagram showing activity dependencies
     o Also known as activity on node (AON)


 • FYI - Arrow Diagramming Method (ADM)
     o A.K.A. Activity on Arrow (AOA) Network Diagram
     o Activities are represented by arrows; Nodes or circles are the starting and
       ending points of activities.
     o Only use Finish to Start dependency
     o Sometimes dummy activities must be inserted to accurately reflect
       dependency
     o Rarely used now




Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Tools & Techniques
                                       1   2   3   4




 • Four types of PDM relationships

     o Finish-to-start (FS): A must finish before B can start;
         sequential, most common

     o Finish-to-finish (FF): A must finish before B can finish

     o Start-to-start (SS): A must start before B can start

     o Start-to-finish (SF): A must start before B can finish; rarely used




Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Tools & Techniques
                                    1   2   3   4




 2) Dependency Determination
     o Mandatory (hard): Contractually required, physical limitations, etc.
     o Discretionary (soft): Preferred logic; only type PM has control over
     o External: outside the project team’s control




Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Tools & Techniques
                                     1   2   3   4




 3a) Lead
     o Starting work before the preceding activity finishes
     o allows acceleration of the schedule (fast-track)


          • ex 1: Start loading moving truck one day before packing finishes




          • Although possible to use lead with SS, difficult to understand




Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Tools & Techniques
                                    1   2   3   4




 3b) Lag: Delay
     o Example 1. Start honeymoon one day after the ceremony; wait one day
       for concrete to gain strength before putting on patio furniture




     o Example 2. QA team can start testing two days after Dev team starts dev




     o Leads and Lags can be applied to all four types of PDM relationships,
       although Leads are not common with SS, FF, and SF


 4) Schedule Network Templates

Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Outputs
                                                                             1    2




 1) Schedule Network Diagram
          A                  C              D

           B



 2) Project Document Updates may include
     o Activity List
     o Activity Attributes
     o Risk Register




Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Data Flows




Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Key Points

 • Sequence Activity: Tools and Techniques include
   Dependency Determination, PDM, Apply Leads and
   Lags, and Schedule Network Templates

 • Precedence Diagram Method (PDM or AON) has
   four types of logical relationships: FS, FF, SS, SF

 • Three types of PDM dependencies: Hard, Soft,
   External. Soft dependency is the only type Project
   Manager has control over.

 • Key output is Schedule Network Diagrams

Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity
          Resources


Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Resources
     - Overview

 • What’s the purpose
     o Determine the type and quantity of resource needed
     o Resources include people, equipment, material, hardware, software, etc.



 • What they don’t teach you in Kindergarten
     o Anything!




Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Resources
                                                                      - PMBOK Process 6.3
                                                                  Process Groups
                                                                                                                                                                           Monitoring &
                                                                                   Initiating                  Planning                       Executing                                                     Closing
                                                                                                                                                                            Controlling
                                                             Knowledge Areas
                                                                                   Develop Project                                         Direct and Manage         Monitor & Control Project Work,     Close Project or
                                                              Integration          Charter
                                                                                                     Develop Project Management Plan
                                                                                                                                           Project Execution         Perform Integrated Change Control   Phase
F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t




                                                                                                     Collect Requirements,
                                                                                                                                                                     Verify Scope,
                                                              Scope                                  Define Scope,
                                                                                                                                                                     Control Scope
                                                                                                     Create WBS

                                                                                                     Define Activities,
                                                                                                     Sequence Activities,
                                                               Time                                  Estimate Activity Resources,                                    Control Schedule
                                                                                                     Estimate Activity Durations,
                                                                                                     Develop Schedule

                                                                                                     Estimate Cost,
                                                              Cost                                   Determine Budget
                                                                                                                                                                     Control Cost


                                                                                                                                           Perform Quality
                                                              Quality                                Plan Quality
                                                                                                                                           Assurance
                                                                                                                                                                     Perform Quality Control


                                                                                                                                           Acquire Project Team,
                                                              Human Resource                         Develop Human Resources Plan          Develop Project Team,
                                                                                                                                           Manage Project Team

                                                                                                                                           Distribute Information,
                                                                                   Identify
                                                              Communications       Stakeholders
                                                                                                     Plan Communications                   Manage Stakeholder        Report Performance
                                                                                                                                           Expectations

                                                                                                     Plan Risk Management,
                                                                                                     Identify Risks,
                                                              Risk                                   Perform Qualitative Risk Analysis,                              Monitor and Control Risks
                                                                                                     Perform Quantitative Risk Analysis,
                                                                                                     Plan Risk Responses

                                                              Procurement                            Plan Procurements                     Conduct Procurements      Administer Procurements             Close Procurement




                                                             Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Resources
             - Definition
1   2    3   4   5                   1   2   3   4   5                         1   2   3




        • The process of estimating the type and quantity of
          material, people, equipment, or supplies required to
          perform each activity

        • Closely coordinated with Estimate Costs process




    Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Resources
             - Inputs
1   2    3   4   5




        1) Activity List

        2) Activity Attributes

        3) Resource Calendars
             o Output of “Acquire Team” in Executing progress group


        4) Enterprise Environmental Factors

        5) Organizational Process Assets



    Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Resources
     - Tools and Techniques
                                   1   2   3   4   5




 1) Expert Judgment

 2) Alternatives Analysis
     o Examples: resource skill levels, size and type of machinery,
       different tools and make-or-buy decisions


 3) Published Estimating Data
     o Examples: labor trades, material and equipment within the country and in
       other countries




Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Resources
     - Tools and Techniques
                                  1   2   3   4   5




 4) Bottom-up Estimating
     o If an activity cannot be confidently estimated, it is broken down
       to smaller parts for estimation; the estimates are then aggregated
       up to the activity level (PMBOK preferred method)


 5) PM Software
     o Examples: Primavera, MS Project, Clarity, etc.
     o Number of Resources usually influence activity duration; in some
       cases, having two resources will cut duration in half, in other
       cases it will not




Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Resources
     - Outputs
                                                                                              1   2   3



 1) Activity Resource Requirements
     o Identifies the types and quantities of resources required for each activity
       in a work package


 2) Resource Breakdown Structure
     o Hierarchical structure of the identified resources by resource category
       and resource type
     o Includes labor, materials, equipment, supplies, etc.
                               Software Project A


       Server          Developers           Business Analyst        Testers         Trainer

                Database           UI
                                                        Technical             Business
                Developer       Developer
                                                         Tester                Users

 3) Project Document Updates
     o May include: Activity List, Activity Attributes, Resource Calendars

Project Management Certification – A Professional Commitment – A Responsibility
Sequence Activities
     - Data Flows




Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Resources
     - Key Points

 • You should have paid attention in Kindergarten! 

 • The two processes that consider alternatives are
   Define Scope and Estimate Activity Resources

 • Bottom-up estimating performs estimates for each
   activity and rolls them up to higher levels




Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity
          Durations


Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
     - Overview

 • “How long will it take?”




Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
                                                                      - PMBOK Process 6.4
                                                                  Process Groups
                                                                                                                                                                           Monitoring &
                                                                                   Initiating                  Planning                       Executing                                                     Closing
                                                                                                                                                                            Controlling
                                                             Knowledge Areas
                                                                                   Develop Project                                         Direct and Manage         Monitor & Control Project Work,     Close Project or
                                                              Integration          Charter
                                                                                                     Develop Project Management Plan
                                                                                                                                           Project Execution         Perform Integrated Change Control   Phase
F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t




                                                                                                     Collect Requirements,
                                                                                                                                                                     Verify Scope,
                                                              Scope                                  Define Scope,
                                                                                                                                                                     Control Scope
                                                                                                     Create WBS

                                                                                                     Define Activities,
                                                                                                     Sequence Activities,
                                                               Time                                  Estimate Activity Resources,                                    Control Schedule
                                                                                                     Estimate Activity Durations,
                                                                                                     Develop Schedule

                                                                                                     Estimate Cost,
                                                              Cost                                   Determine Budget
                                                                                                                                                                     Control Cost


                                                                                                                                           Perform Quality
                                                              Quality                                Plan Quality
                                                                                                                                           Assurance
                                                                                                                                                                     Perform Quality Control


                                                                                                                                           Acquire Project Team,
                                                              Human Resource                         Develop Human Resources Plan          Develop Project Team,
                                                                                                                                           Manage Project Team

                                                                                                                                           Distribute Information,
                                                                                   Identify
                                                              Communications       Stakeholders
                                                                                                     Plan Communications                   Manage Stakeholder        Report Performance
                                                                                                                                           Expectations

                                                                                                     Plan Risk Management,
                                                                                                     Identify Risks,
                                                              Risk                                   Perform Qualitative Risk Analysis,                              Monitor and Control Risks
                                                                                                     Perform Quantitative Risk Analysis,
                                                                                                     Plan Risk Responses

                                                              Procurement                            Plan Procurements                     Conduct Procurements      Administer Procurements             Close Procurement




                                                             Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
     - Definition

 • The process of estimating the number of work
   periods needed to complete each activity with
   estimated resources

 • The duration estimate is progressively elaborated

 • In the real world, level of efforts (LOE) are estimated
   first and are used to calculate duration based on
   resource availability(80 hours / 0.5 head count = 160
   hours or 4 weeks of duration)



Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
            - Definition
1   2   3   4   5   6   7            1   2   3   4   5                           1    2




    Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
             - Inputs
1   2    3   4   5   6   7




        1) Activity List
             o Comprehensive List of all Scheduled Activities


        2) Activity Attributes
             o Identifies multiple components associated with each activity

        3) Activity Resource Requirements
             o Resources assigned and availability of those resources have a
               significant effect on an activity’s duration

        4) Resource Calendars
             o Type, Availability, & Capability of Human Resources (Sr. versus Jr.)
             o Type, Availability, & Capability of Equipment & Material Resources
               also affect duration

    Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
             - Inputs
1   2    3   4   5   6   7




        5) Project Scope Statement
             o Assumptions regarding Existing Conditions, Information availability, and
               Length of Reporting periods
             o Constraints of available resources and Contract Terms & Requirements


        6) Enterprise Environmental Factors
             o Duration Estimating databases
             o Productivity Metrics
             o Published Commercial Information


        7) Organizational Process Assets
             o   Historical Duration Information
             o   Product Calendars
             o   Scheduling Methodology
             o   Lessons Learned


    Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
     - Tools and Techniques
                                   1   2   3   4   5




 1) Expert Judgment
     o Team members who will perform activities will most
       accurately estimate them


 2) Analogous Estimating – lower accuracy
     o Use a similar previous project as a reference and adjust for known
       differences; Top-down approach relying on historical information
       and expert judgment
     o Can be used on activity duration or total project duration
     o Less costly, less time-consuming  less accurate;
       useful at early project stage


 3) Parametric Estimating – higher accuracy
     o Uses statistical relationship between historical data and other
       variables to quantitatively determine duration (= total units of
       work * labor hours per unit)


Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
     - Tools and Techniques
                                   1   2   3   4   5




 4) Three-Point Estimates (PERT) – higher accuracy
     o Expected Duration = [Optimistic + (4 x Most Likely) +
       Pessimistic] / 6
     o Weighted Average


 5) Reserve Analysis
     o Contingency reserves / time reserves / buffers to account
       for schedule uncertainty
     o A % or a fixed number of work periods




Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
     - Calculations
 • Class Exercise
     o Best case = 18 days, Most Likely = 25 days, Worse Case = 38 days
     o Assume 1 Sigma unless specified otherwise

 • Calculate the following
     o PERT or Expected Duration
     o Activity Standard Deviation = (Pessimistic – Optimistic) / 6
     o Range of Estimates = Expected Duration +/- Standard Deviation
        • Range needs to be widened if 2 Sigma (range = Expected Duration
           +/- Standard Deviation x 2)


 • FYI:
     o 1 Sigma = 68.3% confidence
     o 2 Sigma = 95.4% confidence
     o 3 Sigma = 99.7% confidence
                                           On this chart of a 'normal' distribution, showing the classic 'bell curve' shape,
                                           the mean (or average) is the vertical line at the center, and the vertical lines to
                                           either side represent intervals of one, two and three sigma. The percentage of
                                           data points that would lie within each segment of that distribution are shown.

Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
     - Results
 • Class Exercise
     o Best case = 18 days, Most Likely = 25 days, Worse Case = 38 days
     o Assume 1 Sigma unless specified otherwise

 • Calculate the following
     o PERT or Expected Duration
       = [Optimistic + (4 x Most Likely) + Pessimistic] / 6
       = (18 + 25x4 + 38)/6 = 26
     o Activity Standard Deviation
       = (Pessimistic – Optimistic) / 6
       = (38-18)/6 =3.33
     o Range of Estimates
       = Expected Duration +/- Standard Deviation
       = 26 +/- 3.33 = between 22.67 days and 29.33 days
         • if 2 Sigma (range = Expected Duration +/- Standard Deviation x 2)
           = 26 +/- 3.33x2 = between 19.34 to 32.66



Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
     - Outputs
                                                                                  1   2



 1) Activity Duration Estimates
     o Estimated time to complete each activity
     o Duration = Effort / Resources
     o This can be a range




 2) Project Document Updates
     o Activity attributes, Assumptions Log (e.g. skill level and availability)




Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
     - Data Flows




Project Management Certification – A Professional Commitment – A Responsibility
Estimate Activity Durations
     - Key Points
 • Analogous estimating is top-down approach and
   less accurate

 • Parametric estimating calculates duration/cost
   based on duration/cost per unit x total units.
   Duration/cost per unit can be from historical data.

 • PERT calculates a weighted average estimate by
   using optimistic, mostly likely, and pessimistic
   estimates.

 • Activity duration estimates include number of work
   periods including elapsed time.

Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule



Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
     - Overview

 • Why is it important?

 • Which time-related processes have been
   completed so far before building the schedule?




Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
                                                                      - PMBOK Process 6.5
                                                                  Process Groups
                                                                                                                                                                           Monitoring &
                                                                                   Initiating                  Planning                       Executing                                                     Closing
                                                                                                                                                                            Controlling
                                                             Knowledge Areas
                                                                                   Develop Project                                         Direct and Manage         Monitor & Control Project Work,     Close Project or
                                                              Integration          Charter
                                                                                                     Develop Project Management Plan
                                                                                                                                           Project Execution         Perform Integrated Change Control   Phase
F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t




                                                                                                     Collect Requirements,
                                                                                                                                                                     Verify Scope,
                                                              Scope                                  Define Scope,
                                                                                                                                                                     Control Scope
                                                                                                     Create WBS

                                                                                                     Define Activities,
                                                                                                     Sequence Activities,
                                                               Time                                  Estimate Activity Resources,                                    Control Schedule
                                                                                                     Estimate Activity Durations,
                                                                                                     Develop Schedule

                                                                                                     Estimate Cost,
                                                              Cost                                   Determine Budget
                                                                                                                                                                     Control Cost


                                                                                                                                           Perform Quality
                                                              Quality                                Plan Quality
                                                                                                                                           Assurance
                                                                                                                                                                     Perform Quality Control


                                                                                                                                           Acquire Project Team,
                                                              Human Resource                         Develop Human Resources Plan          Develop Project Team,
                                                                                                                                           Manage Project Team

                                                                                                                                           Distribute Information,
                                                                                   Identify
                                                              Communications       Stakeholders
                                                                                                     Plan Communications                   Manage Stakeholder        Report Performance
                                                                                                                                           Expectations

                                                                                                     Plan Risk Management,
                                                                                                     Identify Risks,
                                                              Risk                                   Perform Qualitative Risk Analysis,                              Monitor and Control Risks
                                                                                                     Perform Quantitative Risk Analysis,
                                                                                                     Plan Risk Responses

                                                              Procurement                            Plan Procurements                     Conduct Procurements      Administer Procurements             Close Procurement




                                                             Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
            - Definition
1   2   3   4   5   6   7   8   9   1   2   3   4   5   6   7   8           1   2   3   4




                                    • Process of analyzing sequences,
                                      durations, resources requirements,
                                      and schedule constraints to create
                                      the project schedule
                                    • Iterative process (schedule
                                      baseline vs. schedule revision)
    Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
             - Inputs
1   2    3   4   5   6   7   8   9




        1) Activity List
        2) Activity Attributes
        3) Project Schedule Network Diagrams
        4) Activity Resource Requirements
        5) Resource Calendars
        6) Activity Duration Estimates
        7) Project Scope Statement
        8) Enterprise Environmental Factors
        9) Organizational Process Assets


    Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
     - Tools and Techniques
                              1   2   3   4   5   6   7   8




 1) Schedule Network Analysis
     o Employs various analytical techniques, such as critical path
       method, critical chain method, what-if analysis, and resource
       leveling


 2) Critical Path Method (CPM)
     o A Schedule Network Analysis technique used to determine the
       schedule flexibility and determine the minimum project duration
     o Calculates the theoretical start and finish dates by using a
       forward pass and backward pass analysis;
     o No consideration of resource limitations


 3) Critical Chain Method
     o Critical Path Method + Resource constraints + Schedule Buffers


Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
     - Tools and Techniques
                             1   2   3   4   5   6   7   8




 4) Resource Leveling
     o A schedule network analysis technique applied to a schedule
       after critical path method
     o Necessary when required resources are over-allocated; often
       lets the schedule slip to smooth out resources
     o Can cause original Critical Path to change


 5) What-if Scenario Analysis
     o Change conditions to simulate different possible scenarios
     o A schedule network analysis is performed
     o Monte Carlo Analysis: Random and iterative computer model
       showing probability distributions




Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
     - Tools and Techniques
                              1   2   3   4   5   6   7   8




 6) Apply Leads and Lags
     o Leads – head start
     o Lags – delay, time elapses


 7) Schedule Compression
     o Shortens schedule with no change to project scope
     o Crashing: exchange higher costs for shorter schedule duration
       (eg. Add resources)
     o Fast tracking: converts sequential activities to parallel


 8) Scheduling Tool
     o Example: MS Project, Primavera P6




Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
      - Critical Path Method (ES, EF, LF, LS)
                                       1      2   3   4   5     6   7   8


    Forward Pass                                                    Forward Pass
                                                                    1. EF = ES + Duration
                                                                    2. ES of successor tasks = latest EF of predecessor tasks
    ES = 0          EF = 3
                                                                    Backward Pass
          Task A                                                    1. LS = LF – Duration
      Duration = 3 days                                             2. LF of predecessor tasks = earliest LS of successor tasks

    LS = 2          LF = 5         ES = 5             EF = 20

                                          Task D
    ES = 0          EF = 5           Duration = 15 days
           Task B                   LS = 5            LF = 20               ES = 20         EF = 26
      Duration = 5 days
                                                                                    Task F
    LS = 0          LF = 5                                                     Duration = 6 days

                   EF = 10                                                  LS = 20          LF = 26
    ES = 0                          ES = 10           EF = 15

          Task C                           Task E
                                                                                                  Backward Pass
     Duration = 10 days               Duration = 5 days

    LS = 5         LF = 15          LS = 15           LF = 20

    Note: Critical Path represents the path of the activities with the longest duration
    throughout the network diagram.


Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
     - Critical Path Method (ES, EF, LF, LS)
                               1   2   3   4   5   6   7   8




 • ES / EF (Forward-Pass)
     o Estimated Start / Estimated Finish
         • EF = ES + Activity Duration
         • ES of Successor tasks = latest EF of Predecessor tasks


 • LF / LS (Backward-Pass)
     o Latest Finish / Latest Start
         • LS = LF - Activity Duration
         • LF of Predecessor tasks = earliest LS of Successor tasks




Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
      - Critical Path Method (Float)
                                            1      2   3   4   5     6   7   8

                                                                         1. Float (AKA free float, slack) = LF – EF. The amount of
    Forward Pass                                                            time a task can be delayed without affecting
                                                                            successor’s earliest start.
                                                                         2. Total Float = The total amount of time that a schedule
    ES = 0          EF = 3                                                  activity may be delayed from its early start date
                                                                            without the project finish date or violating a schedule
          Task A             Float = 2                                      constraint
      Duration = 3 days                                                  3. The critical path is the path that has Total Float = 0
                                                                         4. Any delays along the critical path will delay the entire
    LS = 2          LF = 5               ES = 5           EF = 20           project
                                                                         5. The tasks that have float > 0 can be delayed maximum
                                                   Task D         Float = 0 by the amount of the float without delaying the project
    ES = 0          EF = 5                 Duration = 15 days
           Task B                         LS = 5           LF = 20               ES = 20       EF = 26
      Duration = 5 days      Float = 0
                                                                                        Task F
    LS = 0          LF = 5                                                                                Float = 0
                                                                                   Duration = 6 days

                   EF = 10                                                       LS = 20        LF = 26
    ES = 0                               ES = 10           EF = 15

          Task C             Float = 5           Task E
                                                                     Float = 5                       Backward Pass
     Duration = 10 days                     Duration = 5 days

    LS = 5         LF = 15               LS = 15           LF = 20


                                         What’s the total float of C-E-F?



Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
     - Critical Path Method (Float)
                             1   2   3   4   5   6   7   8


 • Float (AKA free float, slack) = LF – EF. Amount of time a
   task can be delayed without affecting successor’s
   earliest start.

 • Total Float = Total amount of time that a schedule
   activity may be delayed from its early start date without
   the project finish date or violating a schedule constraint

 • The critical path is the path that has Total Float = 0

 • Any delays along the critical path will delay the entire
   project

 • The tasks that have float > 0 can, at the most, be
   delayed by the amount of the float without delaying the
   project

Project Management Certification – A Professional Commitment – A Responsibility
Develop Schedule
        - Class Activity 1 – CPM
                                              1      2   3   4   5     6   7   8


    Forward Pass


    ES = 0            EF = 5

            Task A             Float = 8
        Duration = 5 days

    LS = 8          LF = 13                ES = 10           EF = 13

                                                 Task D                Float = 3
    ES = 0          EF = 10                  Duration = 3 days
              Task B                       LS = 13           LF = 16               ES = 16      EF = 31
        Duration = 10 days     Float = 3
                                                                                          Task F
    LS = 3          LF = 13                                                                               Float = 0
                                                                                    Duration = 15 days

                     EF = 8                                                        LS = 16      LF = 31
    ES = 0                                 ES = 8            EF = 16

             Task C            Float = 0          Task E
                                                                       Float = 0                     Backward Pass
        Duration = 8 days                    Duration = 8 days

    LS = 0           LF = 8                LS = 8            LF = 16

    -     Calculate the ES, EF, LS, and LF
    -     Calculate Floats
    -     Identify the Critical Path

Project Management Certification – A Professional Commitment – A Responsibility
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management
Project Management

Weitere ähnliche Inhalte

Was ist angesagt?

Project Organization and Structure
Project Organization and StructureProject Organization and Structure
Project Organization and Structure
haroldtaylor1113
 
Project management report document a medium size project.
Project management report document a medium size project. Project management report document a medium size project.
Project management report document a medium size project.
Weng Chuan
 
Project integration management
Project integration management Project integration management
Project integration management
KU Leuven
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
Mayur Rahangdale
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
341741357
 

Was ist angesagt? (20)

Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Project Organization and Structure
Project Organization and StructureProject Organization and Structure
Project Organization and Structure
 
Project Resource Management Techniques Organization Effective Planning Optimi...
Project Resource Management Techniques Organization Effective Planning Optimi...Project Resource Management Techniques Organization Effective Planning Optimi...
Project Resource Management Techniques Organization Effective Planning Optimi...
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Project management report document a medium size project.
Project management report document a medium size project. Project management report document a medium size project.
Project management report document a medium size project.
 
Project integration management
Project integration management Project integration management
Project integration management
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
King Abdullah Financial District, Riyadh, KSA
King Abdullah Financial District, Riyadh, KSAKing Abdullah Financial District, Riyadh, KSA
King Abdullah Financial District, Riyadh, KSA
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 
Project Management Centre of Excellence
Project Management Centre of ExcellenceProject Management Centre of Excellence
Project Management Centre of Excellence
 
Methodologies of Project Progress Measurement
Methodologies of Project Progress MeasurementMethodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
 
PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACE
 
Noe9e_PPT_ch01_accessible.pptx
Noe9e_PPT_ch01_accessible.pptxNoe9e_PPT_ch01_accessible.pptx
Noe9e_PPT_ch01_accessible.pptx
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 

Ähnlich wie Project Management

Project Management Professional (PMP) / 42 Processes
Project Management Professional (PMP) / 42 ProcessesProject Management Professional (PMP) / 42 Processes
Project Management Professional (PMP) / 42 Processes
edtichy
 
Porject Management Professional / 42 Processes
Porject Management Professional / 42 ProcessesPorject Management Professional / 42 Processes
Porject Management Professional / 42 Processes
kat_tichy
 
PMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesPMBOK 2008 Map of Processes
PMBOK 2008 Map of Processes
Murilo Juchem
 
Project management
Project managementProject management
Project management
Sameer Kumar
 
Pmbok 4th edition chapter 8 - Project Quality Management
Pmbok 4th edition   chapter 8 - Project Quality Management Pmbok 4th edition   chapter 8 - Project Quality Management
Pmbok 4th edition chapter 8 - Project Quality Management
Ahmad Maharma, PMP,RMP
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
Matilda Barbayanni
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach
Matilda Barbayanni
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach
Matilda Barbayanni
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
Matilda Barbayanni
 
Introduction project management
Introduction  project managementIntroduction  project management
Introduction project management
Hager Aamer
 
Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elements
haroldtaylor1113
 
NG BB 52 CONTROL Roadmap
NG BB 52 CONTROL RoadmapNG BB 52 CONTROL Roadmap
NG BB 52 CONTROL Roadmap
Leanleaders.org
 

Ähnlich wie Project Management (20)

Project Management Professional (PMP) / 42 Processes
Project Management Professional (PMP) / 42 ProcessesProject Management Professional (PMP) / 42 Processes
Project Management Professional (PMP) / 42 Processes
 
Porject Management Professional / 42 Processes
Porject Management Professional / 42 ProcessesPorject Management Professional / 42 Processes
Porject Management Professional / 42 Processes
 
Pmbok 4th edition chapter 6 - Project Time Management
Pmbok 4th edition   chapter 6 - Project Time Management Pmbok 4th edition   chapter 6 - Project Time Management
Pmbok 4th edition chapter 6 - Project Time Management
 
PMP Map Color Coded
PMP Map Color CodedPMP Map Color Coded
PMP Map Color Coded
 
Pmbok 4th edition chapter 5 - Project Scope Management
Pmbok 4th edition   chapter 5 - Project Scope Management Pmbok 4th edition   chapter 5 - Project Scope Management
Pmbok 4th edition chapter 5 - Project Scope Management
 
Pmbok 4th edition chapter 7 - Project Cost Management
Pmbok 4th edition   chapter 7 - Project Cost Management Pmbok 4th edition   chapter 7 - Project Cost Management
Pmbok 4th edition chapter 7 - Project Cost Management
 
PMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesPMBOK 2008 Map of Processes
PMBOK 2008 Map of Processes
 
Fr205 are you_agile_tk2012
Fr205 are you_agile_tk2012Fr205 are you_agile_tk2012
Fr205 are you_agile_tk2012
 
Agile Project Management for elearning development
Agile Project Management for elearning developmentAgile Project Management for elearning development
Agile Project Management for elearning development
 
Project management
Project managementProject management
Project management
 
Pmbok 4th edition chapter 10 - Project Communication Management
Pmbok 4th edition   chapter 10 - Project Communication ManagementPmbok 4th edition   chapter 10 - Project Communication Management
Pmbok 4th edition chapter 10 - Project Communication Management
 
Pmbok 4th edition chapter 3 - Project Management Processes for a Project
Pmbok 4th edition   chapter 3 - Project Management Processes for a Project Pmbok 4th edition   chapter 3 - Project Management Processes for a Project
Pmbok 4th edition chapter 3 - Project Management Processes for a Project
 
Pmbok 4th edition chapter 8 - Project Quality Management
Pmbok 4th edition   chapter 8 - Project Quality Management Pmbok 4th edition   chapter 8 - Project Quality Management
Pmbok 4th edition chapter 8 - Project Quality Management
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
Introduction project management
Introduction  project managementIntroduction  project management
Introduction project management
 
Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elements
 
NG BB 52 CONTROL Roadmap
NG BB 52 CONTROL RoadmapNG BB 52 CONTROL Roadmap
NG BB 52 CONTROL Roadmap
 

Kürzlich hochgeladen

Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
lizamodels9
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 

Kürzlich hochgeladen (20)

Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 

Project Management

  • 1. Project Management Application and Concentration BUS XXX - 3 Units Fall 2012 Weekend 2 - Day 2 Project Management Certification – A Professional Commitment – A Responsibility
  • 2. Reflecting on Last Class • Foundations o What is a project? o What is Project Management? o Process Groups / Knowledge Areas / Processes o Project Lifecycle and its characteristics o Organizational Structure • Initiating o Project Charter – Why is it important; ITTO? o Identify Stakeholders – Why is this step important? ITTO? • Planning o Project Management Plan - Incorporates outputs from all other planning processes o Collect Requirements • Knowing the right questions • Knowing the right people • ITTO? Project Management Certification – A Professional Commitment – A Responsibility
  • 3. Learning Objectives for Today • Scope o Recognize how to Define Scope, so we know what we are delivering o Explain what is involved in Creating a WBS for project deliverables • Time o Explain the processes leading up to Develop Schedule o Breakdown all tasks to determine what the team should work on o Determine the dependencies and what can be worked on concurrently o Determine what / who / how many to use by Estimating activity resources o Assess how long activities will take by Estimating activity durations o Compile analysis into a schedule to determine a “target date” • Cost o Estimate how much each activity will costs • labor, service, equipment, and other items o Aggregate all costs to determine funding requirements and determine if scope needs adjustment when budget is a constraint Project Management Certification – A Professional Commitment – A Responsibility
  • 4. Weekend 2, Day 2 – Overview Process Groups Monitoring & Initiating Planning Executing Closing Controlling Knowledge Areas Develop Project Direct and Manage Monitor & Control Project Work, Close Project or Integration Charter Develop Project Management Plan Project Execution Perform Integrated Change Control Phase F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t Collect Requirements, Verify Scope, Scope Define Scope, Control Scope Create WBS Define Activities, Sequence Activities, Time Estimate Activity Resources, Control Schedule Estimate Activity Durations, Develop Schedule Estimate Cost, Cost Determine Budget Control Cost Perform Quality Quality Plan Quality Assurance Perform Quality Control Acquire Project Team, Human Resource Develop Human Resources Plan Develop Project Team, Manage Project Team Distribute Information, Identify Communications Stakeholders Plan Communications Manage Stakeholder Report Performance Expectations Plan Risk Management, Identify Risks, Risk Perform Qualitative Risk Analysis, Monitor and Control Risks Perform Quantitative Risk Analysis, Plan Risk Responses Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurement Project Management Certification – A Professional Commitment – A Responsibility
  • 5. Five Questions - Class Exercise Project Management Certification – A Professional Commitment – A Responsibility
  • 6. Define Scope Project Management Certification – A Professional Commitment – A Responsibility
  • 7. Define Scope - Overview • What is Project Scope? • Why is it important to Define Scope? o Make sure everyone is on the right page o Baseline for changes • Who says what is in and what is out? • What about open ended projects? Project Management Certification – A Professional Commitment – A Responsibility
  • 8. Define Scope - PMBOK Process 5.2 Process Groups Monitoring & Initiating Planning Executing Closing Controlling Knowledge Areas Develop Project Direct and Manage Monitor & Control Project Work, Close Project or Integration Charter Develop Project Management Plan Project Execution Perform Integrated Change Control Phase F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t Collect Requirements, Verify Scope, Scope Define Scope, Control Scope Create WBS Define Activities, Sequence Activities, Time Estimate Activity Resources, Control Schedule Estimate Activity Durations, Develop Schedule Estimate Cost, Cost Determine Budget Control Cost Perform Quality Quality Plan Quality Assurance Perform Quality Control Acquire Project Team, Human Resource Develop Human Resources Plan Develop Project Team, Manage Project Team Distribute Information, Identify Communications Stakeholders Plan Communications Manage Stakeholder Report Performance Expectations Plan Risk Management, Identify Risks, Risk Perform Qualitative Risk Analysis, Monitor and Control Risks Perform Quantitative Risk Analysis, Plan Risk Responses Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurement Project Management Certification – A Professional Commitment – A Responsibility
  • 9. Define Scope - Project vs. Product Scope • Project Scope: measured against project management plan • Product Scope: measured against product requirements Project Management Certification – A Professional Commitment – A Responsibility
  • 10. Define Scope - Definition 1 2 3 1 2 3 4 1 2 • The process of developing a detailed description of the project and the product • Defines what the project includes and excludes Project Management Certification – A Professional Commitment – A Responsibility
  • 11. Define Scope - Inputs 1 2 3 1) Project Charter o High-Level project description and requirements 2) Requirements Documentation o Primary document used for scope definition 3) Organizational Process Assets Examples: o Templates for a project scope statement o Files from previous projects o Lessons learned from previous projects Project Management Certification – A Professional Commitment – A Responsibility
  • 12. Define Scope - Tools & Techniques 1 2 3 4 1) Expert Judgment 2) Product Analysis o Product breakdown, system analysis, requirement analysis, systems engineering, value engineering, and value analysis o Only for projects that have a product as a deliverable 3) Alternative Identification o A technique used to generate different approaches to execute the project o Brainstorming, Lateral Thinking, Pair wise comparison 4) Facilitated Workshops o Cross-functional Project Management Certification – A Professional Commitment – A Responsibility
  • 13. Define Scope - Outputs 1 2 1) Project Scope Statement o Describes, in detail, project deliverables and work required to create these deliverables o Helps to create a common understanding among stakeholders (avoid scope creep) o Project team can perform detailed planning now o Components • Product Scope Description • Product Acceptance Criteria • Project Objectives • Project Deliverables • Project Exclusions • Project Constraints • Project Assumptions Project Management Certification – A Professional Commitment – A Responsibility
  • 14. Define Scope - Moe’ Outputs 1 2 2) Project Document Updates o Stakeholder Register o Requirements documentation o Requirements Traceability Matrix o Etc. Project Management Certification – A Professional Commitment – A Responsibility
  • 15. Define Scope - Top Reasons Why Projects Fail • Unclear Project Objectives and Requirements • Lack of Planning • Scope Creep • Lack of Stakeholder Involvement • Gaps in Communication • Resource Overload • Etc. Project Management Certification – A Professional Commitment – A Responsibility
  • 16. Define Scope - Data Flow Diagram Project Management Certification – A Professional Commitment – A Responsibility
  • 17. Define Scope - Key Points • Scope definition is a joint effort between Project Manager , Project team, and business stakeholders (though the Project Manager may be the one writing the Scope Statement) • Scope Statement sets clear expectation and establish the basis for future change requests • Define Scope is a progressively elaborated process; may be adjusted as more details become known • A good idea to have Scope Statement approved and published • Scope Statement will later be used to measured against to determine if the project has been completed successfully Project Management Certification – A Professional Commitment – A Responsibility
  • 18. Define Scope - Key Points • Project constraints limit the options and restrict project team’s actions: Time, Budget, Scope, Quality, Schedule, Resource, Technology, Management Directives • Poorly written Scope Statement may lead to increased cost, longer duration, deliverables that do not meet business expectation, and ultimately unsatisfied stakeholders. • Meeting or exceeding stakeholder expectation doesn’t mean gold-plating Project Management Certification – A Professional Commitment – A Responsibility
  • 19. Create Work Breakdown Structure Project Management Certification – A Professional Commitment – A Responsibility
  • 20. Create Work Breakdown Structure - Overview • What is the purpose? o More manageable components • Key is to break it down o Should include entire project scope • Multiple approaches o By Project Phases o By Deliverables o By Sub-projects Project Management Certification – A Professional Commitment – A Responsibility
  • 21. Create Work Breakdown Structure - PMBOK Process 5.3 Process Groups Monitoring & Initiating Planning Executing Closing Controlling Knowledge Areas Develop Project Direct and Manage Monitor & Control Project Work, Close Project or Integration Charter Develop Project Management Plan Project Execution Perform Integrated Change Control Phase F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t Collect Requirements, Verify Scope, Scope Define Scope, Control Scope Create WBS Define Activities, Sequence Activities, Time Estimate Activity Resources, Control Schedule Estimate Activity Durations, Develop Schedule Estimate Cost, Cost Determine Budget Control Cost Perform Quality Quality Plan Quality Assurance Perform Quality Control Acquire Project Team, Human Resource Develop Human Resources Plan Develop Project Team, Manage Project Team Distribute Information, Identify Communications Stakeholders Plan Communications Manage Stakeholder Report Performance Expectations Plan Risk Management, Identify Risks, Risk Perform Qualitative Risk Analysis, Monitor and Control Risks Perform Quantitative Risk Analysis, Plan Risk Responses Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurement Project Management Certification – A Professional Commitment – A Responsibility
  • 22. Create Work Breakdown Structure - Definition • Definition: Deliverable – oriented hierarchical decomposition of the work to accomplish the project objectives and create required deliverables • Includes total scope of the project • Top down effort • Lowest Level = Work package, which can be scheduled, cost estimated, monitored, and controlled • Shall be revised if a major scope change occurs Project Management Certification – A Professional Commitment – A Responsibility
  • 23. Create Work Breakdown Structure - Definition 1 2 3 1 1 2 3 4 Project Management Certification – A Professional Commitment – A Responsibility
  • 24. Create Work Breakdown Structure - Inputs 1 2 3 1) Project Scope Statement o All the deliverables and work to create them o What type of work is not included 2) Requirements Documentation 3) Organization Process Assets o Policies, procedures, and templates for the WBS o Project files from previous projects o Lessons learned from previous projects Project Management Certification – A Professional Commitment – A Responsibility
  • 25. Create Work Breakdown Structure - Tools & Techniques 1 1) Decomposition – Sample 5-step process a) Identify the deliverables and work b) Organize the WBS; structure can be organized by - Phases - Major deliverables - Subprojects (e.g. contracted work) c) Decompose the WBS into low-level components d) Assign identification codes e) Verify WBS Project Management Certification – A Professional Commitment – A Responsibility
  • 26. Create Work Breakdown Structure - Decomposition Guidelines 1 • Not a task list; excessive decomposition can have a detrimental effect by making WBS overly complex, confusing to view, and difficult to maintain • Rule of thumb for how far to break it down is to get to 8-80 hours of work per package • 100% Rule: Total of lowest levels must represents the total work of the project to ensure no work is left out or no extra work is added Project Management Certification – A Professional Commitment – A Responsibility
  • 27. Create Work Breakdown Structure - Outputs 1 2 3 4 1) The Work Breakdown Structure (WBS) itself • WBS is finalized by establishing control accounts for the work packages and a unique identifier from a code of accounts • Control Account - a management control point where scope, cost, and schedule are integrated and compared to the earned value • Each control account may have more than one work package but one work package shall only be linked to one control account Project Management Certification – A Professional Commitment – A Responsibility
  • 28. Create Work Breakdown Structure - Outputs 1 2 3 4 2) WBS Dictionary o Code of account identifier o Description of work o Responsible person(s) or organization o List of schedule milestones o Resource and quality requirements o Cost estimates o Acceptance criteria o Contract info and technical references 3) Scope Baseline o Part of Project Management Plan o Consists of • Scope Statement • WBS • WBS Dictionary 4) Project Document Updates o Requirements documentation, etc. Project Management Certification – A Professional Commitment – A Responsibility
  • 29. Create Work Breakdown Structure - Sample Diagram Project Management Certification – A Professional Commitment – A Responsibility
  • 30. Create Work Breakdown Structure - by Project Phases Project Management Certification – A Professional Commitment – A Responsibility
  • 31. Create Work Breakdown Structure - by Major Deliverables Project Management Certification – A Professional Commitment – A Responsibility
  • 32. Create Work Breakdown Structure - Data Flows Project Management Certification – A Professional Commitment – A Responsibility
  • 33. Create Work Breakdown Structure - Key Points • WBS is a deliverable-oriented structure • Work Package is the lowest level on WBS. Activities and tasks are not included in the WBS. • WBS should include 100% of the project scope • WBS Levels: Project Name = Level 1, Deliverables = Level 2 • Scope Baseline includes Scope Statement, WBS, and WBS Dictionary Project Management Certification – A Professional Commitment – A Responsibility
  • 34. Define Activities Project Management Certification – A Professional Commitment – A Responsibility
  • 35. Define Activities - Overview • What’s the Purpose? o Further decompose the Work Packages into schedule activities as basis for estimating, scheduling, and monitoring o Working towards creating a project schedule • In what order should it be done – next steps o Define Activity o Sequence Activity o Estimate Activity Resource o Estimate Activity Duration o Develop Schedule Project Management Certification – A Professional Commitment – A Responsibility
  • 36. Define Activities - PMBOK Process 6.1 Process Groups Monitoring & Initiating Planning Executing Closing Controlling Knowledge Areas Develop Project Direct and Manage Monitor & Control Project Work, Close Project or Integration Charter Develop Project Management Plan Project Execution Perform Integrated Change Control Phase F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t Collect Requirements, Verify Scope, Scope Define Scope, Control Scope Create WBS Define Activities, Activities Sequence Activities, Time Estimate Activity Resources, Control Schedule Estimate Activity Durations, Develop Schedule Estimate Cost, Cost Determine Budget Control Cost Perform Quality Quality Plan Quality Assurance Perform Quality Control Acquire Project Team, Human Resource Develop Human Resources Plan Develop Project Team, Manage Project Team Distribute Information, Identify Communications Stakeholders Plan Communications Manage Stakeholder Report Performance Expectations Plan Risk Management, Identify Risks, Risk Perform Qualitative Risk Analysis, Monitor and Control Risks Perform Quantitative Risk Analysis, Plan Risk Responses Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurement Project Management Certification – A Professional Commitment – A Responsibility
  • 37. Define Activities - Definition 1 2 3 1 2 3 4 1 2 3 • The process of identifying the specific actions to be performed • Project  Deliverables  Work Packages (WBS) Activities Project Management Certification – A Professional Commitment – A Responsibility
  • 38. Define Activities - Inputs 1 2 3 1) Scope Baseline o Deliverables, constraints, and assumptions 2) Enterprise Environmental Factors o Project Management Information System used will affect the definition 3) Organizational Process Assets o Existing formal and informal policies, procedures, and guidelines (e.g. Scheduling methodology) o Lessons learned/knowledge base from historical information Project Management Certification – A Professional Commitment – A Responsibility
  • 39. Define Activities - Tools & Techniques 1 2 3 4 1) Decomposition o Involving teams in decomposition can lead to more accurate results 2) Rolling Wave Planning o A progressive elaboration process where near-term activities are in great detail and longer-term activities are at a high level 3) Templates o Organizational standard Activity List or Activity List from previous projects o Can also be used to identify typical schedule milestones 4) Expert Judgment Project Management Certification – A Professional Commitment – A Responsibility
  • 40. Define Activities - Outputs 1 2 3 1) Activity List (or Task List) o Detailed list of all activities required to complete the project 2) Activity Attributes o Further defines the activity, such as Activity ID, WBS ID, activity name and description, predecessor, successor, leads and lags, person responsible, resource requirements, constraints, assumptions, level of effort, etc. o Activity attributes are used for schedule development and for selecting, ordering, and sorting the planned schedule activities in various ways within reports 3) Milestone List o A list of significant points in a project Project Management Certification – A Professional Commitment – A Responsibility
  • 41. Create Work Breakdown Structure - Sample Milestone List August September October Activity Aug 13 - 17 Aug 20 - 24 Aug 27 - 31 Sep 3 - 7 Sep 10 - 14 Sep 17 - 21 Sep 24 - 28 Oct 1 - 5 Oct 8 - 12 Offer Code Setup and BOM 8/24 Forecast Mix 8/24 Packaging Design/Approval Packaging Arrived at FFC 9/10 Collateral Arrived at FFC 9/10 Assembly Specs 8/31 Call Routing and Training 9/14 IBTM and Testing Setup 9/14 Web Creative 9/5 Web Development 9/12 Web Dependency Project 9/12 Complete Web QA Ready 9/14 Web Brand Setup Web End to End Testing 9/20 Merchant ID Setup 9/5 9/10 FFC Brand Setup Planning Release 9/10 Filled Intermediate Arrived at FFC 9/21 Kit Assembly 9/7 QA Audit and Compliance QA Quality Agreement 9/14 Launch 9/24 Project Management Certification – A Professional Commitment – A Responsibility
  • 42. Define Activities - Data Flows Project Management Certification – A Professional Commitment – A Responsibility
  • 43. Define Activities - Key Points • Define Activity process uses Scope Baseline as the primary input • WBS is further decomposed • Activity Lists, Activity Attributes and Milestone Lists are the outputs • May be progressive elaboration process • Rolling Wave Planning = define near-term work in greater detail than future work Project Management Certification – A Professional Commitment – A Responsibility
  • 44. Sequence Activities Project Management Certification – A Professional Commitment – A Responsibility
  • 45. Sequence Activities - Overview • Determine logical dependencies • Determine what can be done concurrently Project Management Certification – A Professional Commitment – A Responsibility
  • 46. Sequence Activities - PMBOK Process 6.2 Process Groups Monitoring & Initiating Planning Executing Closing Controlling Knowledge Areas Develop Project Direct and Manage Monitor & Control Project Work, Close Project or Integration Charter Develop Project Management Plan Project Execution Perform Integrated Change Control Phase F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t Collect Requirements, Verify Scope, Scope Define Scope, Control Scope Create WBS Define Activities, Sequence Activities, Time Estimate Activity Resources, Control Schedule Estimate Activity Durations, Develop Schedule Estimate Cost, Cost Determine Budget Control Cost Perform Quality Quality Plan Quality Assurance Perform Quality Control Acquire Project Team, Human Resource Develop Human Resources Plan Develop Project Team, Manage Project Team Distribute Information, Identify Communications Stakeholders Plan Communications Manage Stakeholder Report Performance Expectations Plan Risk Management, Identify Risks, Risk Perform Qualitative Risk Analysis, Monitor and Control Risks Perform Quantitative Risk Analysis, Plan Risk Responses Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurement Project Management Certification – A Professional Commitment – A Responsibility
  • 47. Sequence Activities - Definition 1 2 3 4 5 1 2 3 4 1 2 • Process of identifying and documenting relationships among project activities Project Management Certification – A Professional Commitment – A Responsibility
  • 48. Sequence Activities - Inputs 1 2 3 4 5 1) Activity List 2) Activity Attributes 3) Milestone List 4) Project Scope Statement o As double-check 5) Organizational Process Assets o Example: Previous Project File Project Management Certification – A Professional Commitment – A Responsibility
  • 49. Sequence Activities - Tools & Techniques 1 2 3 4 1) Precedence Diagramming Method (PDM) o A method used in Critical Path Methodology (CPM) to build a network diagram showing activity dependencies o Also known as activity on node (AON) • FYI - Arrow Diagramming Method (ADM) o A.K.A. Activity on Arrow (AOA) Network Diagram o Activities are represented by arrows; Nodes or circles are the starting and ending points of activities. o Only use Finish to Start dependency o Sometimes dummy activities must be inserted to accurately reflect dependency o Rarely used now Project Management Certification – A Professional Commitment – A Responsibility
  • 50. Sequence Activities - Tools & Techniques 1 2 3 4 • Four types of PDM relationships o Finish-to-start (FS): A must finish before B can start; sequential, most common o Finish-to-finish (FF): A must finish before B can finish o Start-to-start (SS): A must start before B can start o Start-to-finish (SF): A must start before B can finish; rarely used Project Management Certification – A Professional Commitment – A Responsibility
  • 51. Sequence Activities - Tools & Techniques 1 2 3 4 2) Dependency Determination o Mandatory (hard): Contractually required, physical limitations, etc. o Discretionary (soft): Preferred logic; only type PM has control over o External: outside the project team’s control Project Management Certification – A Professional Commitment – A Responsibility
  • 52. Sequence Activities - Tools & Techniques 1 2 3 4 3a) Lead o Starting work before the preceding activity finishes o allows acceleration of the schedule (fast-track) • ex 1: Start loading moving truck one day before packing finishes • Although possible to use lead with SS, difficult to understand Project Management Certification – A Professional Commitment – A Responsibility
  • 53. Sequence Activities - Tools & Techniques 1 2 3 4 3b) Lag: Delay o Example 1. Start honeymoon one day after the ceremony; wait one day for concrete to gain strength before putting on patio furniture o Example 2. QA team can start testing two days after Dev team starts dev o Leads and Lags can be applied to all four types of PDM relationships, although Leads are not common with SS, FF, and SF 4) Schedule Network Templates Project Management Certification – A Professional Commitment – A Responsibility
  • 54. Sequence Activities - Outputs 1 2 1) Schedule Network Diagram A C D B 2) Project Document Updates may include o Activity List o Activity Attributes o Risk Register Project Management Certification – A Professional Commitment – A Responsibility
  • 55. Sequence Activities - Data Flows Project Management Certification – A Professional Commitment – A Responsibility
  • 56. Sequence Activities - Key Points • Sequence Activity: Tools and Techniques include Dependency Determination, PDM, Apply Leads and Lags, and Schedule Network Templates • Precedence Diagram Method (PDM or AON) has four types of logical relationships: FS, FF, SS, SF • Three types of PDM dependencies: Hard, Soft, External. Soft dependency is the only type Project Manager has control over. • Key output is Schedule Network Diagrams Project Management Certification – A Professional Commitment – A Responsibility
  • 57. Estimate Activity Resources Project Management Certification – A Professional Commitment – A Responsibility
  • 58. Estimate Activity Resources - Overview • What’s the purpose o Determine the type and quantity of resource needed o Resources include people, equipment, material, hardware, software, etc. • What they don’t teach you in Kindergarten o Anything! Project Management Certification – A Professional Commitment – A Responsibility
  • 59. Estimate Activity Resources - PMBOK Process 6.3 Process Groups Monitoring & Initiating Planning Executing Closing Controlling Knowledge Areas Develop Project Direct and Manage Monitor & Control Project Work, Close Project or Integration Charter Develop Project Management Plan Project Execution Perform Integrated Change Control Phase F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t Collect Requirements, Verify Scope, Scope Define Scope, Control Scope Create WBS Define Activities, Sequence Activities, Time Estimate Activity Resources, Control Schedule Estimate Activity Durations, Develop Schedule Estimate Cost, Cost Determine Budget Control Cost Perform Quality Quality Plan Quality Assurance Perform Quality Control Acquire Project Team, Human Resource Develop Human Resources Plan Develop Project Team, Manage Project Team Distribute Information, Identify Communications Stakeholders Plan Communications Manage Stakeholder Report Performance Expectations Plan Risk Management, Identify Risks, Risk Perform Qualitative Risk Analysis, Monitor and Control Risks Perform Quantitative Risk Analysis, Plan Risk Responses Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurement Project Management Certification – A Professional Commitment – A Responsibility
  • 60. Estimate Activity Resources - Definition 1 2 3 4 5 1 2 3 4 5 1 2 3 • The process of estimating the type and quantity of material, people, equipment, or supplies required to perform each activity • Closely coordinated with Estimate Costs process Project Management Certification – A Professional Commitment – A Responsibility
  • 61. Estimate Activity Resources - Inputs 1 2 3 4 5 1) Activity List 2) Activity Attributes 3) Resource Calendars o Output of “Acquire Team” in Executing progress group 4) Enterprise Environmental Factors 5) Organizational Process Assets Project Management Certification – A Professional Commitment – A Responsibility
  • 62. Estimate Activity Resources - Tools and Techniques 1 2 3 4 5 1) Expert Judgment 2) Alternatives Analysis o Examples: resource skill levels, size and type of machinery, different tools and make-or-buy decisions 3) Published Estimating Data o Examples: labor trades, material and equipment within the country and in other countries Project Management Certification – A Professional Commitment – A Responsibility
  • 63. Estimate Activity Resources - Tools and Techniques 1 2 3 4 5 4) Bottom-up Estimating o If an activity cannot be confidently estimated, it is broken down to smaller parts for estimation; the estimates are then aggregated up to the activity level (PMBOK preferred method) 5) PM Software o Examples: Primavera, MS Project, Clarity, etc. o Number of Resources usually influence activity duration; in some cases, having two resources will cut duration in half, in other cases it will not Project Management Certification – A Professional Commitment – A Responsibility
  • 64. Estimate Activity Resources - Outputs 1 2 3 1) Activity Resource Requirements o Identifies the types and quantities of resources required for each activity in a work package 2) Resource Breakdown Structure o Hierarchical structure of the identified resources by resource category and resource type o Includes labor, materials, equipment, supplies, etc. Software Project A Server Developers Business Analyst Testers Trainer Database UI Technical Business Developer Developer Tester Users 3) Project Document Updates o May include: Activity List, Activity Attributes, Resource Calendars Project Management Certification – A Professional Commitment – A Responsibility
  • 65. Sequence Activities - Data Flows Project Management Certification – A Professional Commitment – A Responsibility
  • 66. Estimate Activity Resources - Key Points • You should have paid attention in Kindergarten!  • The two processes that consider alternatives are Define Scope and Estimate Activity Resources • Bottom-up estimating performs estimates for each activity and rolls them up to higher levels Project Management Certification – A Professional Commitment – A Responsibility
  • 67. Estimate Activity Durations Project Management Certification – A Professional Commitment – A Responsibility
  • 68. Estimate Activity Durations - Overview • “How long will it take?” Project Management Certification – A Professional Commitment – A Responsibility
  • 69. Estimate Activity Durations - PMBOK Process 6.4 Process Groups Monitoring & Initiating Planning Executing Closing Controlling Knowledge Areas Develop Project Direct and Manage Monitor & Control Project Work, Close Project or Integration Charter Develop Project Management Plan Project Execution Perform Integrated Change Control Phase F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t Collect Requirements, Verify Scope, Scope Define Scope, Control Scope Create WBS Define Activities, Sequence Activities, Time Estimate Activity Resources, Control Schedule Estimate Activity Durations, Develop Schedule Estimate Cost, Cost Determine Budget Control Cost Perform Quality Quality Plan Quality Assurance Perform Quality Control Acquire Project Team, Human Resource Develop Human Resources Plan Develop Project Team, Manage Project Team Distribute Information, Identify Communications Stakeholders Plan Communications Manage Stakeholder Report Performance Expectations Plan Risk Management, Identify Risks, Risk Perform Qualitative Risk Analysis, Monitor and Control Risks Perform Quantitative Risk Analysis, Plan Risk Responses Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurement Project Management Certification – A Professional Commitment – A Responsibility
  • 70. Estimate Activity Durations - Definition • The process of estimating the number of work periods needed to complete each activity with estimated resources • The duration estimate is progressively elaborated • In the real world, level of efforts (LOE) are estimated first and are used to calculate duration based on resource availability(80 hours / 0.5 head count = 160 hours or 4 weeks of duration) Project Management Certification – A Professional Commitment – A Responsibility
  • 71. Estimate Activity Durations - Definition 1 2 3 4 5 6 7 1 2 3 4 5 1 2 Project Management Certification – A Professional Commitment – A Responsibility
  • 72. Estimate Activity Durations - Inputs 1 2 3 4 5 6 7 1) Activity List o Comprehensive List of all Scheduled Activities 2) Activity Attributes o Identifies multiple components associated with each activity 3) Activity Resource Requirements o Resources assigned and availability of those resources have a significant effect on an activity’s duration 4) Resource Calendars o Type, Availability, & Capability of Human Resources (Sr. versus Jr.) o Type, Availability, & Capability of Equipment & Material Resources also affect duration Project Management Certification – A Professional Commitment – A Responsibility
  • 73. Estimate Activity Durations - Inputs 1 2 3 4 5 6 7 5) Project Scope Statement o Assumptions regarding Existing Conditions, Information availability, and Length of Reporting periods o Constraints of available resources and Contract Terms & Requirements 6) Enterprise Environmental Factors o Duration Estimating databases o Productivity Metrics o Published Commercial Information 7) Organizational Process Assets o Historical Duration Information o Product Calendars o Scheduling Methodology o Lessons Learned Project Management Certification – A Professional Commitment – A Responsibility
  • 74. Estimate Activity Durations - Tools and Techniques 1 2 3 4 5 1) Expert Judgment o Team members who will perform activities will most accurately estimate them 2) Analogous Estimating – lower accuracy o Use a similar previous project as a reference and adjust for known differences; Top-down approach relying on historical information and expert judgment o Can be used on activity duration or total project duration o Less costly, less time-consuming  less accurate; useful at early project stage 3) Parametric Estimating – higher accuracy o Uses statistical relationship between historical data and other variables to quantitatively determine duration (= total units of work * labor hours per unit) Project Management Certification – A Professional Commitment – A Responsibility
  • 75. Estimate Activity Durations - Tools and Techniques 1 2 3 4 5 4) Three-Point Estimates (PERT) – higher accuracy o Expected Duration = [Optimistic + (4 x Most Likely) + Pessimistic] / 6 o Weighted Average 5) Reserve Analysis o Contingency reserves / time reserves / buffers to account for schedule uncertainty o A % or a fixed number of work periods Project Management Certification – A Professional Commitment – A Responsibility
  • 76. Estimate Activity Durations - Calculations • Class Exercise o Best case = 18 days, Most Likely = 25 days, Worse Case = 38 days o Assume 1 Sigma unless specified otherwise • Calculate the following o PERT or Expected Duration o Activity Standard Deviation = (Pessimistic – Optimistic) / 6 o Range of Estimates = Expected Duration +/- Standard Deviation • Range needs to be widened if 2 Sigma (range = Expected Duration +/- Standard Deviation x 2) • FYI: o 1 Sigma = 68.3% confidence o 2 Sigma = 95.4% confidence o 3 Sigma = 99.7% confidence On this chart of a 'normal' distribution, showing the classic 'bell curve' shape, the mean (or average) is the vertical line at the center, and the vertical lines to either side represent intervals of one, two and three sigma. The percentage of data points that would lie within each segment of that distribution are shown. Project Management Certification – A Professional Commitment – A Responsibility
  • 77. Estimate Activity Durations - Results • Class Exercise o Best case = 18 days, Most Likely = 25 days, Worse Case = 38 days o Assume 1 Sigma unless specified otherwise • Calculate the following o PERT or Expected Duration = [Optimistic + (4 x Most Likely) + Pessimistic] / 6 = (18 + 25x4 + 38)/6 = 26 o Activity Standard Deviation = (Pessimistic – Optimistic) / 6 = (38-18)/6 =3.33 o Range of Estimates = Expected Duration +/- Standard Deviation = 26 +/- 3.33 = between 22.67 days and 29.33 days • if 2 Sigma (range = Expected Duration +/- Standard Deviation x 2) = 26 +/- 3.33x2 = between 19.34 to 32.66 Project Management Certification – A Professional Commitment – A Responsibility
  • 78. Estimate Activity Durations - Outputs 1 2 1) Activity Duration Estimates o Estimated time to complete each activity o Duration = Effort / Resources o This can be a range 2) Project Document Updates o Activity attributes, Assumptions Log (e.g. skill level and availability) Project Management Certification – A Professional Commitment – A Responsibility
  • 79. Estimate Activity Durations - Data Flows Project Management Certification – A Professional Commitment – A Responsibility
  • 80. Estimate Activity Durations - Key Points • Analogous estimating is top-down approach and less accurate • Parametric estimating calculates duration/cost based on duration/cost per unit x total units. Duration/cost per unit can be from historical data. • PERT calculates a weighted average estimate by using optimistic, mostly likely, and pessimistic estimates. • Activity duration estimates include number of work periods including elapsed time. Project Management Certification – A Professional Commitment – A Responsibility
  • 81. Develop Schedule Project Management Certification – A Professional Commitment – A Responsibility
  • 82. Develop Schedule - Overview • Why is it important? • Which time-related processes have been completed so far before building the schedule? Project Management Certification – A Professional Commitment – A Responsibility
  • 83. Develop Schedule - PMBOK Process 6.5 Process Groups Monitoring & Initiating Planning Executing Closing Controlling Knowledge Areas Develop Project Direct and Manage Monitor & Control Project Work, Close Project or Integration Charter Develop Project Management Plan Project Execution Perform Integrated Change Control Phase F o u n d a t i o n s o f Pr o j e c t M a n a g e m e n t Collect Requirements, Verify Scope, Scope Define Scope, Control Scope Create WBS Define Activities, Sequence Activities, Time Estimate Activity Resources, Control Schedule Estimate Activity Durations, Develop Schedule Estimate Cost, Cost Determine Budget Control Cost Perform Quality Quality Plan Quality Assurance Perform Quality Control Acquire Project Team, Human Resource Develop Human Resources Plan Develop Project Team, Manage Project Team Distribute Information, Identify Communications Stakeholders Plan Communications Manage Stakeholder Report Performance Expectations Plan Risk Management, Identify Risks, Risk Perform Qualitative Risk Analysis, Monitor and Control Risks Perform Quantitative Risk Analysis, Plan Risk Responses Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurement Project Management Certification – A Professional Commitment – A Responsibility
  • 84. Develop Schedule - Definition 1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 1 2 3 4 • Process of analyzing sequences, durations, resources requirements, and schedule constraints to create the project schedule • Iterative process (schedule baseline vs. schedule revision) Project Management Certification – A Professional Commitment – A Responsibility
  • 85. Develop Schedule - Inputs 1 2 3 4 5 6 7 8 9 1) Activity List 2) Activity Attributes 3) Project Schedule Network Diagrams 4) Activity Resource Requirements 5) Resource Calendars 6) Activity Duration Estimates 7) Project Scope Statement 8) Enterprise Environmental Factors 9) Organizational Process Assets Project Management Certification – A Professional Commitment – A Responsibility
  • 86. Develop Schedule - Tools and Techniques 1 2 3 4 5 6 7 8 1) Schedule Network Analysis o Employs various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource leveling 2) Critical Path Method (CPM) o A Schedule Network Analysis technique used to determine the schedule flexibility and determine the minimum project duration o Calculates the theoretical start and finish dates by using a forward pass and backward pass analysis; o No consideration of resource limitations 3) Critical Chain Method o Critical Path Method + Resource constraints + Schedule Buffers Project Management Certification – A Professional Commitment – A Responsibility
  • 87. Develop Schedule - Tools and Techniques 1 2 3 4 5 6 7 8 4) Resource Leveling o A schedule network analysis technique applied to a schedule after critical path method o Necessary when required resources are over-allocated; often lets the schedule slip to smooth out resources o Can cause original Critical Path to change 5) What-if Scenario Analysis o Change conditions to simulate different possible scenarios o A schedule network analysis is performed o Monte Carlo Analysis: Random and iterative computer model showing probability distributions Project Management Certification – A Professional Commitment – A Responsibility
  • 88. Develop Schedule - Tools and Techniques 1 2 3 4 5 6 7 8 6) Apply Leads and Lags o Leads – head start o Lags – delay, time elapses 7) Schedule Compression o Shortens schedule with no change to project scope o Crashing: exchange higher costs for shorter schedule duration (eg. Add resources) o Fast tracking: converts sequential activities to parallel 8) Scheduling Tool o Example: MS Project, Primavera P6 Project Management Certification – A Professional Commitment – A Responsibility
  • 89. Develop Schedule - Critical Path Method (ES, EF, LF, LS) 1 2 3 4 5 6 7 8 Forward Pass Forward Pass 1. EF = ES + Duration 2. ES of successor tasks = latest EF of predecessor tasks ES = 0 EF = 3 Backward Pass Task A 1. LS = LF – Duration Duration = 3 days 2. LF of predecessor tasks = earliest LS of successor tasks LS = 2 LF = 5 ES = 5 EF = 20 Task D ES = 0 EF = 5 Duration = 15 days Task B LS = 5 LF = 20 ES = 20 EF = 26 Duration = 5 days Task F LS = 0 LF = 5 Duration = 6 days EF = 10 LS = 20 LF = 26 ES = 0 ES = 10 EF = 15 Task C Task E Backward Pass Duration = 10 days Duration = 5 days LS = 5 LF = 15 LS = 15 LF = 20 Note: Critical Path represents the path of the activities with the longest duration throughout the network diagram. Project Management Certification – A Professional Commitment – A Responsibility
  • 90. Develop Schedule - Critical Path Method (ES, EF, LF, LS) 1 2 3 4 5 6 7 8 • ES / EF (Forward-Pass) o Estimated Start / Estimated Finish • EF = ES + Activity Duration • ES of Successor tasks = latest EF of Predecessor tasks • LF / LS (Backward-Pass) o Latest Finish / Latest Start • LS = LF - Activity Duration • LF of Predecessor tasks = earliest LS of Successor tasks Project Management Certification – A Professional Commitment – A Responsibility
  • 91. Develop Schedule - Critical Path Method (Float) 1 2 3 4 5 6 7 8 1. Float (AKA free float, slack) = LF – EF. The amount of Forward Pass time a task can be delayed without affecting successor’s earliest start. 2. Total Float = The total amount of time that a schedule ES = 0 EF = 3 activity may be delayed from its early start date without the project finish date or violating a schedule Task A Float = 2 constraint Duration = 3 days 3. The critical path is the path that has Total Float = 0 4. Any delays along the critical path will delay the entire LS = 2 LF = 5 ES = 5 EF = 20 project 5. The tasks that have float > 0 can be delayed maximum Task D Float = 0 by the amount of the float without delaying the project ES = 0 EF = 5 Duration = 15 days Task B LS = 5 LF = 20 ES = 20 EF = 26 Duration = 5 days Float = 0 Task F LS = 0 LF = 5 Float = 0 Duration = 6 days EF = 10 LS = 20 LF = 26 ES = 0 ES = 10 EF = 15 Task C Float = 5 Task E Float = 5 Backward Pass Duration = 10 days Duration = 5 days LS = 5 LF = 15 LS = 15 LF = 20 What’s the total float of C-E-F? Project Management Certification – A Professional Commitment – A Responsibility
  • 92. Develop Schedule - Critical Path Method (Float) 1 2 3 4 5 6 7 8 • Float (AKA free float, slack) = LF – EF. Amount of time a task can be delayed without affecting successor’s earliest start. • Total Float = Total amount of time that a schedule activity may be delayed from its early start date without the project finish date or violating a schedule constraint • The critical path is the path that has Total Float = 0 • Any delays along the critical path will delay the entire project • The tasks that have float > 0 can, at the most, be delayed by the amount of the float without delaying the project Project Management Certification – A Professional Commitment – A Responsibility
  • 93. Develop Schedule - Class Activity 1 – CPM 1 2 3 4 5 6 7 8 Forward Pass ES = 0 EF = 5 Task A Float = 8 Duration = 5 days LS = 8 LF = 13 ES = 10 EF = 13 Task D Float = 3 ES = 0 EF = 10 Duration = 3 days Task B LS = 13 LF = 16 ES = 16 EF = 31 Duration = 10 days Float = 3 Task F LS = 3 LF = 13 Float = 0 Duration = 15 days EF = 8 LS = 16 LF = 31 ES = 0 ES = 8 EF = 16 Task C Float = 0 Task E Float = 0 Backward Pass Duration = 8 days Duration = 8 days LS = 0 LF = 8 LS = 8 LF = 16 - Calculate the ES, EF, LS, and LF - Calculate Floats - Identify the Critical Path Project Management Certification – A Professional Commitment – A Responsibility

Hinweis der Redaktion

  1. Project LifecycleInitiation – Starting the projectPlanning – Organizing and PreparingExecution – Carrying out the workClosure – Deliverables accepted and project is archivedCharacteristics: As time passes… stakeholder influence, risk and uncertainly goes down; cost of changes goes upOrg StructureFunctional, Weak Matrix, Balanced Matrix, Strong Matrix, Project-ized
  2. Emphasize the order of the 5 processes within “Time”
  3. When you are on a good project team, a word you will hear a lot is “Scope”. I have also see a lot of projects being executed with no clear scope definition. There are a lot of undocumented assumptions, leaving a lot of things up for individual’s interpretations. Example: you are being asked to deliver a website for a product. Do we know what the end-result should look like?Is it just a website for information display? Need to have a shopping cart? Any reports needed to track how many people visited the site but did not order?Open-ended “projects”: it never ends! And people don’t even know what we are supposed to do, and why we are working on it any more.
  4. You are bring a new cell phone to the market:Product scope: example, a cell phone needs to have the case, the buttons, the electronic system, the antena, the ability to make and receive phone calls.Project scope: the cell phone, marketing campaigns, initial setup of distribution channel, etc.
  5. Lateral Thinking: Thinking outside the boxPuzzle 1: A man marries twenty women in his neighborhoodbut isn't charged with polygamy.Puzzle 2: A man is alone on an island with no food and no water, yet he does not fear for his life.Puzzle 3: A horse jumps over a tower and lands on a man, who disappears.Pairwise comparison generally refers to any process of comparing entities in pairs to judge which of each entity is preferred based on pre-determind criteria.Making decisions requires comparing alternatives using a set of criteria. If there are more than two criteria, you need to rank the criteria by importanceExample:Planning a Vacation: to determine your vacation destination (vegas or Hawaii?). Your criteria might be cost, family-friendliness, quality of the locations, travel time. Which one of these is most important? How can you plan your vacation to optimize your enjoyment?
  6. scope statement - Progressive elaboration process. Still early in the planning process. Scope will be refined later on.Exclusion: same Website example, “this website will not provide email subscription functionality”Constraints: Time, Budget, Scope, Quality, Schedule, Resource, Technology, Directive Need to differentiate whether it’s real time constraint. *Example of Time Constraint: deadline of 1/28/2013 for new USPS barcode system; not a time constraint “we need to launch the product on 9/9 because we are planning to advertise on that day” *Example of Technology Constraint: want to store 10 years of transaction history, but don’t have enough storage space; wanted to target 25 year old who have a pet, but not having the data;Deliverables and Requirements that must be completed are referred to as Critical Success Factors
  7. What is scope creep? Uncontrolled expansion of project scope outside of the planned objectives, in other words, adding features and functionality (project scope) without addressing the effects on time, costs, and resources, or without customer approval.Example of scope creep: planned scope: build a website that takes customer orders and forward the order to fulfillment center for processing; expand scope to also build a login page where customers can log in to their account.But be flexible when the request is small and doesn’t have impact to schedule and cost.what can we do to address scope creep - Will discuss during “Control Scope” process
  8. Now we know what we talked about, lets see how it flows, and how the ITTO data is grouped.
  9. Purposes of creating WBS:To help more accurately and specifically define and organize the scope of the total project. to help theproject team to know exactly what has to be accomplished within each deliverable. This also allows for better estimating of cost, risk, and time because you can work from the smaller tasks back up to the level of the entire project. allows you double check all the deliverables' specifics with the stakeholders and make sure there is nothing missing or overlapping.
  10. Ask class: Project Management summary task – why is it on WBS?Time-consuming; team participating
  11. In practice, Define Activity and Sequence Activity are often done at the same time.
  12. Real life example. PMBOK milestone list doesn’t include timeline but we eventually need to have timeline to make milestones more meaningful (this can be done after the “develop schedule” process)
  13. Putting the puzzles together
  14. Arrow Diagramming Method (ADM) With the use of computer-supported scheduling, the Arrow Diagramming Method (ADM) and its Activity on Arrow (AOA) is rarely used.1) an activity can't be represented by more than one arrow in the network diagram. Suppose activity A precedes two activities in a network. To avoid duplicating activity A on the diagram, you would need to follow one arrow representing activity A by an end node. Then follow this end node for A by the two successor activities, B and C.2) no two activities can have the same begin and end nodes. Instead, if two activities are related or dependent, you can use a "dummy" activity to show the relationship. A dummy uses no resources and is represented by a dashed arrow.3) ADM shows the early and late schedules for the project. Both the early time (TE) and the late time (TL) for an event appear on the event node.
  15. Start-to-Finish:Example: the night shift must start before day shift can end. We will be better off using Finish-to-Start and build in Leads if needed (line 2 = line1 FS-1 for example)Just in case: PMBOK definition: the completion of the successor activity depends upon the initiation of the predecessor activity.
  16. "discretionary dependencies" - aka. preferred logic, preferential logic, or soft logic. good candidates for fast tracking. external dependency: EX: hardware must arrive before the upgrade can be completed.
  17. PMBOK Page 140Leads and Lags: if on MS Project, it is reflected in the “Predecessor” field as minus or plus from the predecessor.
  18. PMBOK Page 140Leads and Lags: if on MS Project, it is reflected in the “Predecessor” field as minus or plus from the predecessor.
  19. Only the Type and Quantity of resources. Resource assignment actually occurs during Executing processes “Acquire Project Team” and “Conduct Procurement”, when Resource Calendars for the project are generated.Resource CalendarsYou may find it confusing that Resource Calendars are used as an input to “Estimate Activity Resources” process. Look at it this way, there may be some preliminary information available on existing resources before you assemble the actual project team. It will help you identify the gaps, and may need to acquire additional resources externally or negotiate resources from another team. In real world, the team may be assembled toward the later stages of the Planning process, sometimes it could even be determined by upper management upfront before any detailed planning activities take place (still requiring the high-level assessment of which resource type / qty is required)
  20. In real life, an activity duration by using a junior staff may be longer. The project schedule should reflect this. The level of the resource may also play a role in estimating the cost in the next chapter.
  21. In real life, an activity duration by using a junior staff may be longer. The project schedule should reflect this. The level of the resource may also play a role in estimating the cost in the next chapter.
  22. In real life, an activity duration by using a junior staff may be longer. The project schedule should reflect this. The level of the resource may also play a role in estimating the cost in the next chapter.
  23. [Aimee’s Note] research why bottom-up estimating is not a technique for “Estimate Activity Duration” process
  24. Organizational Process Assets: Duration of past similar projects, lessons learned, etc.
  25. Organizational Process Assets: Duration of past similar projects, lessons learned, etc.
  26. Analogous EstimatingSimilar project – “Analogy”Example: If it took 4 weeks to remodel a 4-bedroom house, you estimate that it will take 4 weeks to remodel another similar 4-bedroom house, plus 1 more day because the owner of the 2nd house also ask for interior painting.Parametric Estimating“of parameter”Example: Duration - it took 2 hours to print 500 marketing flyers last month. This time, you need to print 1000 flyers, so you estimate that it will take 4 hours to print them. Cost – it costs $0.20/flyer last month, so you estimate that it will cost you $200 to print the 1000 flyers.
  27. Reserve AnalysisExample: Perform system testing is estimated to take 10 days. Due to the uncertainty of how many issues you may run into, you can build in 15% buffer in the schedule (total of 11.5 days)
  28. Bell Curve: For example, if you flip a coin 100 times and count how many times it comes up heads, the average result will be 50. But if you do this test 100 times, most of the results will be close to 50, but not exactly. You’ll get almost as many cases with 49, or 51. You’ll get quite a few 45s or 55s, but almost no 20s or 80s.Optional:Activity Variance = Standard Deviation2
  29. Optional:Activity Variance =Standard Deviation2 = 11.09
  30. Why is it important? Heart of planning process determines project start date and end date give team member target dates to hit (small wins along the way). A roadmapTime-related processes that have been completed are: define activities, sequence activities, estimate activity resources, estimate activity duration
  31. Tools and TechniquesNoticebottom-up is not a technique for develop schedule, because sum of activity duration <> project duration due to (1) not all activities are done in sequence (2) resource leveling(3) applying leads and lags etc. In real life, can be used to get a sense of project duration.
  32. Why is scope statement necessary as an input? Scope baseline was already used as an input to create the activity list; however, the project scope statement contains assumptions and constraints that can impact the development of the project schedule.Enterprise environmental factors can include the scheduling software (such as MS Project)Organizational process assets can include project calendar and scheduling methodology. Example: release schedule - company A does weekly releases on Wednesdays only.
  33. MS Project has “Resource Leveling” functionality (“Tools” -> “Level Resources”)[Aimee’s Notes] ask Bill’s opinion… example of schedule buffers – to account for non-work activities like waiting for legal approval for paperwork, waiting for decisions from executive, etc.
  34. MS Project has “Resource Leveling” functionality. menu “Resource” tab  “Level Resource” Top 5 Scheduling software programs: http://www.brighthubpm.com/software-reviews-tips/2492-the-top-five-project-scheduling-software-programs/
  35. Crashing – may not always effective to shorten the scheduleFast trackingask class if it's a good idea to fast track mandatory or external dependencies. No. for "discretionary dependencies“ are good candidates for fast tracking EX: coding for an application, user testing is usually after coding is done, but some user testing can be done when some functionalities have been developed, and while developers continue to code for other functionalities-------------------------Top 5 Scheduling software programs: http://www.brighthubpm.com/software-reviews-tips/2492-the-top-five-project-scheduling-software-programs/
  36. Note that total float for the C-E-F path = 5 not 10
  37. Note that total float for the C-E-F path = 5 not 10
  38. If Project Managers are not responsible for budget, the project performance evaluation should not include budget or cost measurement.
  39. Build vs. Buy – e.g., product lifecycle management tool; Cost estimating = cost to complete the projectPricing = the price to sell the product or service. Vendor’s price becomes part of our project cost.
  40. Expert Judgment, (2) Analogous estimating, (3) Parametric estimating, (5) Three-Point estimating, and (6) Reserve Analysis are also techniques for “Estimate Activity Durations”(4) Bottom-up estimating is also a technique for “Estimate Resources”
  41. Question for class: How does Scope Baseline help to estimate Cost?Triple Constraints: Time, Cost, Scope. One side of the triangle cannot be changed without affecting the others. A further refinement of the constraints separates product "quality" or "performance" from scope, and turns quality into a fourth constraint.“Fast, Cheap, Good” (or “pick any two”)
  42. Question for class: How does Scope Baseline help to estimate costs?
  43. Example of Analogous estimating – launching a new product – the costs involved could be similar
  44. (4) Bottom-up estimating is also a technique for “Estimate Resources” (5) Three-Point estimating, and (6) Reserve Analysis are also techniques for “Estimate Activity Durations”Bottom-up estimating is not a tools and technique for duration estimating in PMBOK but it is used to get general sense in real lifeContingency Reserve may be a percentage of the estimated cost, a fixed number, or may be developed by using quantitative analysis methods.
  45. * Contingency reserves are allowances for unplanned but potentially required changes that can result from realized risks identified in the risk register. * Management reserves are budgets reserved for unplanned changes to project scope and cost. * Contingency reserve is a part of the project cost baseline* Management reserve is NOT part of the cost baseline, but may be included in the total budget for the project. * Reserves are not a part of the earned value measurement (EVM) calculations
  46. Does cost baseline include contingency reserves? PMBOK page 174 and 177 have conflicting information. 174 – 7.2 (This baseline includes all authorized budgets, but excludes management reserves.); page 177, 7.2.2.2 Reserves Analysis, “Reserves are not a part of the project cost baseline, but may be included in the total budget for the project.”Based on my research, Cost Baseline does include contingency reserve.
  47. Costs shown on the cost baseline are cumulative costs.
  48. In-class activity: Discuss and calculate funding requirement for a certain period on the S-curve on previous slideReserves are released as project progresses & risk goes down, unless it’s a fixed fee contract. Reserves are released by adjusting total budget amount.
  49. Ask class: What are other components of Performance Measurement Baseline? Cost baselinePMBOK p.174 - cost baseline includes all authorized budgets, but excludes management reserves. p.177 under reserve analysis - "reserves are not a part of the project cost baseline, but may be included in the total budget of the project”