SlideShare ist ein Scribd-Unternehmen logo
1 von 10
MATERIAL AND CAPACITY REQUIREMENTS
PLANNING (MRP AND CRP)
Part -1
Dr. Mahmoud Abbas Mahmoud Al-Naimi
Assistant Professor
Industrial Engineering Branch
Department of Production Engineering and Metallurgy
University of Technology
Baghdad - Iraq
dr.mahmoudalnaimi@uotechnology.edu.iq
dr.mahmoudalnaimi@yahoo.com
2015 - 2016
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
1
6- MATERIAL AND CAPACITY REQUIREMENTS PLANNING (MRP AND
CRP)
6.1 MRP AND CRP OBJECTIVES
The demand for a finished good tends to be independent and relatively stable.
However, firms typically make more than one product on the same facilities, so
production is generally done in lots, e.g., of different end items or models. The
quantities and delivery times for the materials needed to make those end items are
determined by the production schedule.
Material Requirements Planning (MRP) is a computer-based technique for
determining the quantity and timing for the acquisition of dependent demand items
needed to satisfy the master schedule requirements. By identifying precisely what,
how many, and when components are needed, MRP systems are able to reduce
inventory costs improve scheduling effectiveness, and respond quickly to market
changes.
Capacity Requirements Planning (CRP) is the process of determining what
personnel and equipment capacities (times) are needed to meet the production
objectives embodied in the master schedule and the material requirements plan. MRP
focuses upon the priorities of materials, whereas CRP focuses primarily upon time.
Although both MRP and CRP can be done manually and in isolation, they are
typically integrated within a computerized system, and CRP (as well as production
activity control) functions are often assumed to be included within the concept of “an
MRP system.” Computerized MRP systems can effectively manage the flow of
thousands of components throughout a manufacturing facility. Following are some of
the terminology used to describe the functioning of MRP systems.
• MRP: A technique for determining the quantity and timing dependent demand
items.
• Dependent demand: Demand for a component that is derived from the demand for
other items.
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
2
• Parent and component items: A parent is an assembly made up of basic parts, or
components. The parent of one subgroup may be a component of a higher-level parent.
• Bill of materials: A listing of all components (subassemblies and materials) that go
into an assembled item. It frequently includes the part numbers and quantity required
per assembly.
• Level code: The level on which an item occurs in the structure, or bill-of-materials
format.
• Requirements explosion: The breaking down (exploding) of parent items into
component parts that can be individually planned and scheduled.
• Time phasing: Scheduling to produce or receive an appropriate amount (lot) of
material so that it will be available in the time periods when needed-not before or
after.
• Time bucket: The time period used for planning purposes in MRP-usually a week.
• Lot size: The quantity of items required for an order. The order may be either
purchased from a vendor or produced in-house. Lot sizing is the process of specifying
the order size.
• Lead-time offset: The supply time, or number of time buckets between releasing an
order and receiving the materials.
Figure 6.1 describes MRP and CRP activities in schematic form. Forecasts and orders
are combined in the production plan, which is formalized in the master production
schedule (MPS). The MPS, along with a bill-of-material (BOM) file and inventory
status information, is used to formulate the material-requirements plan. The MRP
determines what components are needed and when they should be ordered from an
outside vendor or produced in-house. The CRP function translates the MRP decisions
into hours of capacity (time) needed. If materials, equipment, and personnel are
adequate, orders are released and the workload is assigned to the various work centers.
End items, such as TV sets, have an independent demand that is closely linked to the
ongoing needs of consumers. It is random but relatively constant. Dependent demand
is linked more closely to the production process itself. Many firms use the same
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
3
facilities to produce different end items because it is economical to produce large lots
once the set-up cost is incurred. The components that go into a TV set, such as 24-inch
picture tubes, have a dependent demand that is governed by the lot size. Dependent
demand is predictable. MRP systems compute material requirements and specify when
orders should be released so that materials arrive exactly when needed. The process of
scheduling the receipt of inventory as needed over time is time phasing.
Fig. 6.1 Material and capacity planning flowchart
6.2 MRP INPUTS AND OUTPUTS
The essential inputs and outputs in an MRP system are listed in table 6.1:
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
4
Table 6.1
6.2.1 Bill of Materials
A bill of materials (BOM) is a listing of all the materials, components, and
subassemblies needed to assemble one unit of an end item. Major function of the bill
of materials is to provide the product structure hierarchy that guides the explosion
process. Different methods of describing a BOM are in use. Figure 6.2 shows (a) a
product structure tree, and (b) an indented BOM. Both are common ways of depicting
the parent-component relationships on a hierarchical basis. Knowledge of this
dependency structure reveals clearly and immediately what components are needed for
each higher-level assembly. A third method (c) is to use single-level bills of material.
6.2.2 Low-level Coding
Figure 6.2 also includes level coding information. Level 0 is the highest (e.g., the end-
item code) and level 3 the lowest for this particular BOM. Note that the four clamps
(C 20) constitute a subassembly that is combined with base (A 10) and two springs (B
11) to complete the end-item bracket (Z 100). However, the same clamp (C 20) is also
a component of the base (A 10). To facilitate the calculation of net requirements, the
product tree has been restructured from where the clamp components might have been
(shown dashed) to the lower level consistent with the other (identical) clamp. This
low-level coding enables the computer to scan the product structure level-by-level,
starting at the top, and obtain an accurate and complete count of all components
needed at one level before moving on to the next.
Bill of materials for Z 100 bracket is shown below:
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
5
Fig. 6.2 Product structure tree
Table 6.1(a) Indented bill of materials
SINGLE-LEVEL BOM
Table 9.1 (a) depicts a single-level bill of materials for Z 100 bracket. It is a less
intuitive but more efficient means of storing the information on computer. In the
single-level bill each entry (on the left) contains only an item or part number followed
by a list of the part numbers and quantities of components needed to make up the
parent item only. This type of listing avoids the searches for duplicate items down
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
6
through several levels of a tree. On the other hand, it necessitates that the computer
search through many single-level bills to find all the components that are included in a
product that has several levels of code. Single-level bills frequently contain “pointers”
to link the records of components with their parents and accommodate the retrieval of
a complete bill of materials for an item.
Table 6.1 (b) Single-level BOM
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
7
ILLUSTRATION 1: Determine the quantities of A10, B11, C20, D2l, E30, F3l, and
G32 needed to complete 50 of the Z100 brackets depicted in Fig. 6.2.
SOLUTION
Table 6.2 Determining BOM requirements
First determine the requirements for one bracket as shown in Table 6.2, and then
multiply by 50. Note that parts C and E are used in two different subassemblies, so
their separate amounts must be summed. For 50 brackets, each of the requirements
column amounts must be multiplied by 50 to obtain the gross requirements.
ILLUSTRATION 2: Given the product structure tree shown in Figure 6.3 for
wheelbarrow W099, develop an indented bill of materials.
Fig. 6.3
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
8
Table 6.3
ILLUSTRATION 3: (a) A flashlight is assembled from three major subassemblies: a
head assembly, two batteries, and a body assembly. The head assembly consists of a
plastic head, a lens, a bulb subassembly (comprising a bulb and bulb holder), and a
reflector. The body assembly consists of a coil spring and a shell assembly, which in
turn is made up of an on-off switch, two connector bars, and a plastic shell. The on-off
switch is assembled from a knob and two small metal slides. The plastic head is made
from one unit of orange plastic powder, and the plastic shell is made from three units
of orange plastic powder. Develop a product structure tree of the flashlight, and
include the level coding for each component.
Plastic head Lens Bulb assembly SpringShell assemblyReflector
Head assembly Body assemblyBatteries
Flashlight
Plastic powder
Bulb holder Plastic shellON-off switchBulb
Knob Metal slides (2) Plastic powder
(3)
Connector bars
(2)
Level 0
Level 1
Level 2
Level 3
Level 4
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
9
(b) Design an indented bill of materials for the flashlight in (a). (Note: Assign
appropriate four-digit part numbers to the components.)
Table 6.4

Weitere ähnliche Inhalte

Was ist angesagt?

AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING Aqib ali
 
5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptxvirshit
 
Material Requirement Planning (mrp)
Material Requirement Planning (mrp)Material Requirement Planning (mrp)
Material Requirement Planning (mrp)Snehav Sharma
 
Manufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) systemManufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) systemYash Dave
 
Capacity planning
Capacity planningCapacity planning
Capacity planningAkhil Lal
 
Materials requirements planning
Materials requirements planningMaterials requirements planning
Materials requirements planningjetromarquez
 
Presentation on operation scheduling
Presentation on operation schedulingPresentation on operation scheduling
Presentation on operation schedulingKamal Subedi
 
material requirement planning
material requirement planningmaterial requirement planning
material requirement planningNaushii Khan
 
Material Requirement Planning
Material Requirement PlanningMaterial Requirement Planning
Material Requirement PlanningPritesh Mogane
 
4. materials requirement planning
4. materials requirement planning4. materials requirement planning
4. materials requirement planningkunal.kakkad
 
Process Planning
Process PlanningProcess Planning
Process PlanningGuhan M
 

Was ist angesagt? (20)

AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING
 
5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx
 
MRP I and MRP II
MRP I and MRP IIMRP I and MRP II
MRP I and MRP II
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Material Requirement Planning (mrp)
Material Requirement Planning (mrp)Material Requirement Planning (mrp)
Material Requirement Planning (mrp)
 
Manufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) systemManufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) system
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Mrp
MrpMrp
Mrp
 
Mrp 1
Mrp 1Mrp 1
Mrp 1
 
Materials requirements planning
Materials requirements planningMaterials requirements planning
Materials requirements planning
 
Mrp ii
Mrp iiMrp ii
Mrp ii
 
Presentation on operation scheduling
Presentation on operation schedulingPresentation on operation scheduling
Presentation on operation scheduling
 
material requirement planning
material requirement planningmaterial requirement planning
material requirement planning
 
MRP-II
MRP-IIMRP-II
MRP-II
 
Material Requirement Planning
Material Requirement PlanningMaterial Requirement Planning
Material Requirement Planning
 
Mrp ii
Mrp iiMrp ii
Mrp ii
 
4. materials requirement planning
4. materials requirement planning4. materials requirement planning
4. materials requirement planning
 
Mrp & crp
Mrp & crp Mrp & crp
Mrp & crp
 
Process Planning
Process PlanningProcess Planning
Process Planning
 
Line balancing
Line balancingLine balancing
Line balancing
 

Andere mochten auch

Process Strategies and Capacity Planning
Process Strategies and Capacity PlanningProcess Strategies and Capacity Planning
Process Strategies and Capacity PlanningJaisa Gapuz
 
아토큐브 그림책
아토큐브 그림책아토큐브 그림책
아토큐브 그림책attocube
 
Multi tone am | Communication Systems
Multi tone am | Communication SystemsMulti tone am | Communication Systems
Multi tone am | Communication SystemsLearn By Watch
 
ACCIDENTE DE TRANSITO
ACCIDENTE DE TRANSITOACCIDENTE DE TRANSITO
ACCIDENTE DE TRANSITOUNEFA
 
Проблеми відновлення українського мовлення в Донецькій області
Проблеми відновлення українського мовлення в Донецькій областіПроблеми відновлення українського мовлення в Донецькій області
Проблеми відновлення українського мовлення в Донецькій областіDonetsk Institute of Information
 
Kriteria penilaian sni award 2016 organisasi kecil barang dan jasa
Kriteria penilaian sni award 2016 organisasi kecil barang dan jasaKriteria penilaian sni award 2016 organisasi kecil barang dan jasa
Kriteria penilaian sni award 2016 organisasi kecil barang dan jasaroellys
 
2016 Product Design Report from InVision
2016 Product Design Report from InVision2016 Product Design Report from InVision
2016 Product Design Report from InVisionInVision App
 
Capacity requirement planning sure 12mt07ind019
Capacity requirement planning sure 12mt07ind019Capacity requirement planning sure 12mt07ind019
Capacity requirement planning sure 12mt07ind019samjune
 
Objective of MRP and MRP II in computer study
Objective of MRP and MRP II in computer studyObjective of MRP and MRP II in computer study
Objective of MRP and MRP II in computer studyHaider Alkaisy
 
What Is Rough Cut Capacity Planning?
What Is Rough Cut Capacity Planning? What Is Rough Cut Capacity Planning?
What Is Rough Cut Capacity Planning? AvercastMarketing
 

Andere mochten auch (16)

Process Strategies and Capacity Planning
Process Strategies and Capacity PlanningProcess Strategies and Capacity Planning
Process Strategies and Capacity Planning
 
아토큐브 그림책
아토큐브 그림책아토큐브 그림책
아토큐브 그림책
 
Multi tone am | Communication Systems
Multi tone am | Communication SystemsMulti tone am | Communication Systems
Multi tone am | Communication Systems
 
Consultor Independiente
Consultor IndependienteConsultor Independiente
Consultor Independiente
 
ACCIDENTE DE TRANSITO
ACCIDENTE DE TRANSITOACCIDENTE DE TRANSITO
ACCIDENTE DE TRANSITO
 
Проблеми відновлення українського мовлення в Донецькій області
Проблеми відновлення українського мовлення в Донецькій областіПроблеми відновлення українського мовлення в Донецькій області
Проблеми відновлення українського мовлення в Донецькій області
 
Ejercicio 1 access 2016
Ejercicio 1 access 2016Ejercicio 1 access 2016
Ejercicio 1 access 2016
 
Taller electricidad grado noveno junio 2016
Taller electricidad grado noveno junio 2016Taller electricidad grado noveno junio 2016
Taller electricidad grado noveno junio 2016
 
Kriteria penilaian sni award 2016 organisasi kecil barang dan jasa
Kriteria penilaian sni award 2016 organisasi kecil barang dan jasaKriteria penilaian sni award 2016 organisasi kecil barang dan jasa
Kriteria penilaian sni award 2016 organisasi kecil barang dan jasa
 
2016 Product Design Report from InVision
2016 Product Design Report from InVision2016 Product Design Report from InVision
2016 Product Design Report from InVision
 
Capacity requirement planning sure 12mt07ind019
Capacity requirement planning sure 12mt07ind019Capacity requirement planning sure 12mt07ind019
Capacity requirement planning sure 12mt07ind019
 
Objective of MRP and MRP II in computer study
Objective of MRP and MRP II in computer studyObjective of MRP and MRP II in computer study
Objective of MRP and MRP II in computer study
 
Rccp report
Rccp reportRccp report
Rccp report
 
Capacity management
Capacity managementCapacity management
Capacity management
 
What Is Rough Cut Capacity Planning?
What Is Rough Cut Capacity Planning? What Is Rough Cut Capacity Planning?
What Is Rough Cut Capacity Planning?
 
Production Planning Control Overview
Production Planning Control OverviewProduction Planning Control Overview
Production Planning Control Overview
 

Ähnlich wie Material and capacity requirements planning (mrp and crp) part 1

Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant MustafaElAkkad
 
Global supply chains and distribution new competitive strategies project peropt
Global supply chains and distribution new competitive strategies project peroptGlobal supply chains and distribution new competitive strategies project peropt
Global supply chains and distribution new competitive strategies project peroptyvwang
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGjntuhcej
 
Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)jntuhcej
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...IRJET Journal
 
Production process
Production processProduction process
Production processBoss Hsiang
 
Manufacturing and materials management
Manufacturing and materials managementManufacturing and materials management
Manufacturing and materials managementAkbar Setiadi
 
Material Requisite Planning
Material Requisite PlanningMaterial Requisite Planning
Material Requisite Planningajithsrc
 
MRP Theory: Master Schedule, Bill of Material and Lead Times
MRP Theory: Master Schedule, Bill of Material and Lead TimesMRP Theory: Master Schedule, Bill of Material and Lead Times
MRP Theory: Master Schedule, Bill of Material and Lead Timesejalgfer
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Timesejalgfer
 
Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3Julien Lecadou,MSc.
 
Lecture 24 conversion cycle -the traditional manufacturing environment accou...
Lecture 24  conversion cycle -the traditional manufacturing environment accou...Lecture 24  conversion cycle -the traditional manufacturing environment accou...
Lecture 24 conversion cycle -the traditional manufacturing environment accou...Habib Ullah Qamar
 
Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniquesMohamad Sahiedan
 

Ähnlich wie Material and capacity requirements planning (mrp and crp) part 1 (20)

Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant
 
UNIT VI-3.pptx
UNIT VI-3.pptxUNIT VI-3.pptx
UNIT VI-3.pptx
 
Global supply chains and distribution new competitive strategies project peropt
Global supply chains and distribution new competitive strategies project peroptGlobal supply chains and distribution new competitive strategies project peropt
Global supply chains and distribution new competitive strategies project peropt
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
 
Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
 
Production process
Production processProduction process
Production process
 
Manufacturing and materials management
Manufacturing and materials managementManufacturing and materials management
Manufacturing and materials management
 
Ask93
Ask93Ask93
Ask93
 
CIM MODULE 2.pptx
CIM MODULE 2.pptxCIM MODULE 2.pptx
CIM MODULE 2.pptx
 
Resource Requirement Planning
Resource Requirement PlanningResource Requirement Planning
Resource Requirement Planning
 
Material Requisite Planning
Material Requisite PlanningMaterial Requisite Planning
Material Requisite Planning
 
Heizer 14
Heizer 14Heizer 14
Heizer 14
 
MRP Theory: Master Schedule, Bill of Material and Lead Times
MRP Theory: Master Schedule, Bill of Material and Lead TimesMRP Theory: Master Schedule, Bill of Material and Lead Times
MRP Theory: Master Schedule, Bill of Material and Lead Times
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
 
Article final ivan f
Article final ivan fArticle final ivan f
Article final ivan f
 
Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3
 
Lect 6.ppt
Lect 6.pptLect 6.ppt
Lect 6.ppt
 
Lecture 24 conversion cycle -the traditional manufacturing environment accou...
Lecture 24  conversion cycle -the traditional manufacturing environment accou...Lecture 24  conversion cycle -the traditional manufacturing environment accou...
Lecture 24 conversion cycle -the traditional manufacturing environment accou...
 
Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniques
 

Mehr von Dr. Mahmoud Al-Naimi

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfDr. Mahmoud Al-Naimi
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-NaimiDr. Mahmoud Al-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعDr. Mahmoud Al-Naimi
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةDr. Mahmoud Al-Naimi
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...Dr. Mahmoud Al-Naimi
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)Dr. Mahmoud Al-Naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1Dr. Mahmoud Al-Naimi
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsDr. Mahmoud Al-Naimi
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Dr. Mahmoud Al-Naimi
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationDr. Mahmoud Al-Naimi
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق Dr. Mahmoud Al-Naimi
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Dr. Mahmoud Al-Naimi
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing Dr. Mahmoud Al-Naimi
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةDr. Mahmoud Al-Naimi
 

Mehr von Dr. Mahmoud Al-Naimi (20)

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
Applications dr. mahmoud al-naimi
Applications   dr. mahmoud al-naimiApplications   dr. mahmoud al-naimi
Applications dr. mahmoud al-naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projects
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determination
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق
 
Control charts for variables
Control charts for variables Control charts for variables
Control charts for variables
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)
 
Evolution of mrp type systems
Evolution of mrp type systemsEvolution of mrp type systems
Evolution of mrp type systems
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكية
 
Network construction
Network construction  Network construction
Network construction
 

Kürzlich hochgeladen

MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 

Kürzlich hochgeladen (20)

MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 

Material and capacity requirements planning (mrp and crp) part 1

  • 1. MATERIAL AND CAPACITY REQUIREMENTS PLANNING (MRP AND CRP) Part -1 Dr. Mahmoud Abbas Mahmoud Al-Naimi Assistant Professor Industrial Engineering Branch Department of Production Engineering and Metallurgy University of Technology Baghdad - Iraq dr.mahmoudalnaimi@uotechnology.edu.iq dr.mahmoudalnaimi@yahoo.com 2015 - 2016
  • 2. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 1 6- MATERIAL AND CAPACITY REQUIREMENTS PLANNING (MRP AND CRP) 6.1 MRP AND CRP OBJECTIVES The demand for a finished good tends to be independent and relatively stable. However, firms typically make more than one product on the same facilities, so production is generally done in lots, e.g., of different end items or models. The quantities and delivery times for the materials needed to make those end items are determined by the production schedule. Material Requirements Planning (MRP) is a computer-based technique for determining the quantity and timing for the acquisition of dependent demand items needed to satisfy the master schedule requirements. By identifying precisely what, how many, and when components are needed, MRP systems are able to reduce inventory costs improve scheduling effectiveness, and respond quickly to market changes. Capacity Requirements Planning (CRP) is the process of determining what personnel and equipment capacities (times) are needed to meet the production objectives embodied in the master schedule and the material requirements plan. MRP focuses upon the priorities of materials, whereas CRP focuses primarily upon time. Although both MRP and CRP can be done manually and in isolation, they are typically integrated within a computerized system, and CRP (as well as production activity control) functions are often assumed to be included within the concept of “an MRP system.” Computerized MRP systems can effectively manage the flow of thousands of components throughout a manufacturing facility. Following are some of the terminology used to describe the functioning of MRP systems. • MRP: A technique for determining the quantity and timing dependent demand items. • Dependent demand: Demand for a component that is derived from the demand for other items.
  • 3. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 2 • Parent and component items: A parent is an assembly made up of basic parts, or components. The parent of one subgroup may be a component of a higher-level parent. • Bill of materials: A listing of all components (subassemblies and materials) that go into an assembled item. It frequently includes the part numbers and quantity required per assembly. • Level code: The level on which an item occurs in the structure, or bill-of-materials format. • Requirements explosion: The breaking down (exploding) of parent items into component parts that can be individually planned and scheduled. • Time phasing: Scheduling to produce or receive an appropriate amount (lot) of material so that it will be available in the time periods when needed-not before or after. • Time bucket: The time period used for planning purposes in MRP-usually a week. • Lot size: The quantity of items required for an order. The order may be either purchased from a vendor or produced in-house. Lot sizing is the process of specifying the order size. • Lead-time offset: The supply time, or number of time buckets between releasing an order and receiving the materials. Figure 6.1 describes MRP and CRP activities in schematic form. Forecasts and orders are combined in the production plan, which is formalized in the master production schedule (MPS). The MPS, along with a bill-of-material (BOM) file and inventory status information, is used to formulate the material-requirements plan. The MRP determines what components are needed and when they should be ordered from an outside vendor or produced in-house. The CRP function translates the MRP decisions into hours of capacity (time) needed. If materials, equipment, and personnel are adequate, orders are released and the workload is assigned to the various work centers. End items, such as TV sets, have an independent demand that is closely linked to the ongoing needs of consumers. It is random but relatively constant. Dependent demand is linked more closely to the production process itself. Many firms use the same
  • 4. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 3 facilities to produce different end items because it is economical to produce large lots once the set-up cost is incurred. The components that go into a TV set, such as 24-inch picture tubes, have a dependent demand that is governed by the lot size. Dependent demand is predictable. MRP systems compute material requirements and specify when orders should be released so that materials arrive exactly when needed. The process of scheduling the receipt of inventory as needed over time is time phasing. Fig. 6.1 Material and capacity planning flowchart 6.2 MRP INPUTS AND OUTPUTS The essential inputs and outputs in an MRP system are listed in table 6.1:
  • 5. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 4 Table 6.1 6.2.1 Bill of Materials A bill of materials (BOM) is a listing of all the materials, components, and subassemblies needed to assemble one unit of an end item. Major function of the bill of materials is to provide the product structure hierarchy that guides the explosion process. Different methods of describing a BOM are in use. Figure 6.2 shows (a) a product structure tree, and (b) an indented BOM. Both are common ways of depicting the parent-component relationships on a hierarchical basis. Knowledge of this dependency structure reveals clearly and immediately what components are needed for each higher-level assembly. A third method (c) is to use single-level bills of material. 6.2.2 Low-level Coding Figure 6.2 also includes level coding information. Level 0 is the highest (e.g., the end- item code) and level 3 the lowest for this particular BOM. Note that the four clamps (C 20) constitute a subassembly that is combined with base (A 10) and two springs (B 11) to complete the end-item bracket (Z 100). However, the same clamp (C 20) is also a component of the base (A 10). To facilitate the calculation of net requirements, the product tree has been restructured from where the clamp components might have been (shown dashed) to the lower level consistent with the other (identical) clamp. This low-level coding enables the computer to scan the product structure level-by-level, starting at the top, and obtain an accurate and complete count of all components needed at one level before moving on to the next. Bill of materials for Z 100 bracket is shown below:
  • 6. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 5 Fig. 6.2 Product structure tree Table 6.1(a) Indented bill of materials SINGLE-LEVEL BOM Table 9.1 (a) depicts a single-level bill of materials for Z 100 bracket. It is a less intuitive but more efficient means of storing the information on computer. In the single-level bill each entry (on the left) contains only an item or part number followed by a list of the part numbers and quantities of components needed to make up the parent item only. This type of listing avoids the searches for duplicate items down
  • 7. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 6 through several levels of a tree. On the other hand, it necessitates that the computer search through many single-level bills to find all the components that are included in a product that has several levels of code. Single-level bills frequently contain “pointers” to link the records of components with their parents and accommodate the retrieval of a complete bill of materials for an item. Table 6.1 (b) Single-level BOM
  • 8. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 7 ILLUSTRATION 1: Determine the quantities of A10, B11, C20, D2l, E30, F3l, and G32 needed to complete 50 of the Z100 brackets depicted in Fig. 6.2. SOLUTION Table 6.2 Determining BOM requirements First determine the requirements for one bracket as shown in Table 6.2, and then multiply by 50. Note that parts C and E are used in two different subassemblies, so their separate amounts must be summed. For 50 brackets, each of the requirements column amounts must be multiplied by 50 to obtain the gross requirements. ILLUSTRATION 2: Given the product structure tree shown in Figure 6.3 for wheelbarrow W099, develop an indented bill of materials. Fig. 6.3
  • 9. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 8 Table 6.3 ILLUSTRATION 3: (a) A flashlight is assembled from three major subassemblies: a head assembly, two batteries, and a body assembly. The head assembly consists of a plastic head, a lens, a bulb subassembly (comprising a bulb and bulb holder), and a reflector. The body assembly consists of a coil spring and a shell assembly, which in turn is made up of an on-off switch, two connector bars, and a plastic shell. The on-off switch is assembled from a knob and two small metal slides. The plastic head is made from one unit of orange plastic powder, and the plastic shell is made from three units of orange plastic powder. Develop a product structure tree of the flashlight, and include the level coding for each component. Plastic head Lens Bulb assembly SpringShell assemblyReflector Head assembly Body assemblyBatteries Flashlight Plastic powder Bulb holder Plastic shellON-off switchBulb Knob Metal slides (2) Plastic powder (3) Connector bars (2) Level 0 Level 1 Level 2 Level 3 Level 4
  • 10. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 9 (b) Design an indented bill of materials for the flashlight in (a). (Note: Assign appropriate four-digit part numbers to the components.) Table 6.4