Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

Clause No. 4

The Contractor

Sub-Clause No. 4.2

Performance Security






Summary
Performance Security is in the amount as stated in particular conditions of the contract as a guarantee towards
performance of the contractor.
Performance Security is valid and enforceable until the contractor has executed and completed the works, remedied
any defects and has become entitled to receive performance certificate after issue of performance certificate by the
employer.
Performance Security is also linked with failure by the contractor to pay the employer an amount due, as either agreed
by the contractor or determined under employer’s claim, claims, disputes and arbitration and termination by employer.

Content of the FIDIC Clause in Brief
The Contractor shall obtain (at his cost) a Performance Security for proper performance, in the amount and currencies
stated in the Particular Conditions. If an amount is not stated in the Particular Conditions, this Sub-Clause shall not apply.
The Contractor shall deliver the Performance Security to the Employer within 28 days after both Parties have signed the
Contract Agreement. The Performance Security shall be issued by an entity and from within a country (or other
jurisdiction) approved by the Employer, and shall be in the form annexed to the Particular Conditions or in another form
approved by the Employer.
The Contractor shall ensure that the Performance Security is valid and enforceable until the Contractor has executed and
completed the Works and remedied any defects. If the terms of the Performance Security specify its expiry date, and the
Contractor has not become entitled to receive the Performance Certificate by the date 28 days prior to the expiry date, the
Contractor shall extend the validity of the Performance Security until the Works have been completed and any defects
have been remedied.
The Employer shall not make a claim under the Performance Security, except for amounts to which the Employer is
entitled under the Contract in the event of:
(a) failure by the Contractor to extend the validity of the Performance Security as described in the preceding paragraph, in
which event the Employer may claim the full amount of the Performance Security,
(b) failure by the Contractor to pay the Employer an amount due, as either agreed by the Contractor or determined under
Sub-Clause 2.5 [Employer's Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement
or determination,
(c) failure by the Contractor to remedy a default within 42 days after receiving the Employer's notice requiring the default
to be remedied, or
(d) circumstances which entitle the Employer to termination under Sub-Clause 15.2 [Termination by Employer],
irrespective of whether notice of termination has been given.
The Employer shall return the Performance Security to the Contractor within 21 days after the Contractor has become
entitled to receive the Performance Certificate.

Increasing the Amount of Performance Security during the Execution of the Contract
Clause 11 ‘Defect Liability’, Sub-Clause ‘Removal of Defective Work’ (To understand the provision in FIDIC related to
increase amount of Performance Security)
If the defect or damage cannot be remedied expeditiously on the Site and the Employer gives consent, the Contractor may
remove from the Site for the purposes of repair such items of Plant as are defective or damaged. This consent may require
the Contractor to increase the amount of the Performance Security by the full replacement cost of these items, or to
provide other appropriate security.
Pg. 1/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

Guidance for Performance Security
The amount of the performance security shall be ten percent 10% of the contract price stated in the contract agreement.
If the performance security is in the form of a bank guarantee, it shall be issued either (a) by a bank located in the country,
or (b) directly by a foreign bank acceptable to the employer. If the performance security is not in the form of a bank
guarantee, it shall be furnished by a financial entity registered, or licensed to do business, in the country.
Forms of Performance Security
Demand Guarantee: Performance bond or other type of guarantee payable to the employer on demand, often without
the presentation of other documents and without the need to show the demand is in compliance with the terms of the
underlying contract. In effect, it is a substitute for a cash deposit. Under UK law, a demand guarantee is independent of the
underlying contract and is separate from the counter-guarantee (if any) given by the employer’s bank to
the contractor’s bank. Under US law also a demand guarantee enjoys similar protection and is called a standby letter of
credit.
Surety Bond: Formal, legally enforceable contract between the contractor and the employer and a third party (the surety,
such as a bank, bonding company, or insurance company) whereby the surety guarantees payment of a specified
maximum sum, or to otherwise compensate (indemnify), the employer against damage or loss caused by the actions (or
a failure to perform.
Notes:
 It is quite common for the employer to require an ‘on demand’ guarantee. It is however recommended that a ‘surety
bond’ as should be used. ‘On demand’ guarantees are quite a dangerous instrument due to the fact that in principle the
beneficiary becomes entitled to call for payment despite lack of any reason or justification to do so, whereas a ‘surety
bond’ can only be drawn if and when a substantial claim exists which remains unsatisfied.
 The intention behind this security is to have the financial responsibility of the surety standing behind the contractor’s
completion obligations. Thus it is critical to pay as much attention to the language of the performance bond as to the
language of any significant contract. The FIDIC model forms of securities require that the surety indemnify the
employer for the consequences of default or breach of contract.
It is critical to carefully scrutinize the extent of liability under the performance security, in particular because Subclause
4.2 includes an indemnity to the contractor if the employer was not entitled to make the claim.
Applied Clauses of the Performance Security/ Bond for EPC Contracts (FIDIC or Mixed)
(References to the clauses are removed)
Performance Security means the bonds and the parent company guarantee.
Performance Bond means the bond in the form set out in annexure (Performance Bond), issued by a bank or financial
institution reasonably acceptable to the employer with a credit rating of no worse than [A+] (Standard and Poor’s) or [A1]
(Moody’s).
The performance bond shall be the equivalent of 10% of the contract price (or any replacement thereof pursuant to
clause).
In the event of a variation under (Variations and Adjustments), which results in an increase or decrease in the contract
price by an amount equal to or greater than 5% (either by itself or when aggregated with all variations since any previous
adjustment to the amount of the bonds), the maximum amounts available under the bonds pursuant shall be increased or
decreased accordingly, and the contractor shall deliver a replacement bond to cover such increased or decreased maximum
amount issued by an entity meeting the requirements as previously approved by the employer, such approval not to be
unreasonably withheld or delayed and otherwise on the same terms as the replaced bond. Such replacement bond shall be
delivered duly executed to the employer no later than 30 days following the variation. All fees, taxes and expenses
Pg. 2/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

associated with procuring, preparing, completing and stamping (if applicable) each of the bonds and the parent company
guarantee shall be paid by the contractor.
If the contractor fails to provide an extension to a bond or replacement bond, the employer shall have the right to call the
outstanding balance of the bond and use and apply the same as security for compliance by the contractor with its
obligations and liabilities under the contract. The employer shall be entitled to make deductions against any amounts so
held in respect of any claim for which it would have been entitled to call against an extended or replacement bond (had the
contractor provided the same), but shall otherwise return to the contractor the remaining balance of such amounts (without
any interest).
Event of Performance Security in Sequence of Contract Activities as Per FIDIC
Schematic (only symbol
to be considered as time-line)
Signing of
the Contract
Agreement

< 28
Days

Issue of
Performance
Security by
the
Contractor
< 42 Days

Time for
Completion

Tests on
Completion

Issue of
Taking
Over
Certificate

Remedying
of Defects

Commencement
Date



Pg. 3/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC

Defect
Notification
Period

Issue of the
Performance
Certificate

Within
21
Days

Return of
the
Performance
Security by
the
Employer

Weitere ähnliche Inhalte

Was ist angesagt?

Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
Muneesh Methwani
 

Was ist angesagt? (20)

Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdf
 
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Why EPC
Why EPCWhy EPC
Why EPC
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 

Ähnlich wie Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999.

Avn 99 aircraft finance lease contract continuing liability endorsement
Avn 99 aircraft finance lease contract   continuing liability endorsement Avn 99 aircraft finance lease contract   continuing liability endorsement
Avn 99 aircraft finance lease contract continuing liability endorsement
Ridwan Ichsan
 
Avn 67 c airline finance lease contract endorsement hull war
Avn 67 c airline finance lease contract endorsement hull warAvn 67 c airline finance lease contract endorsement hull war
Avn 67 c airline finance lease contract endorsement hull war
Ridwan Ichsan
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
Ryan Hatton
 
JPMorgan Chase Guaranty Amended 3-24-08
JPMorgan Chase Guaranty Amended 3-24-08JPMorgan Chase Guaranty Amended 3-24-08
JPMorgan Chase Guaranty Amended 3-24-08
finance2
 
Avn 67 c airline finance lease contract endorsement
Avn 67 c airline finance lease contract endorsementAvn 67 c airline finance lease contract endorsement
Avn 67 c airline finance lease contract endorsement
Ridwan Ichsan
 
Letter of Gurantee
Letter of GuranteeLetter of Gurantee
Letter of Gurantee
Raxid Aqeel
 
Title Insurance Commitment
Title Insurance CommitmentTitle Insurance Commitment
Title Insurance Commitment
legal1
 

Ähnlich wie Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999. (20)

Clause 14.docx
Clause 14.docxClause 14.docx
Clause 14.docx
 
Vietnam Accounting Standards - VAS 19 Insurance Contract
Vietnam Accounting Standards - VAS 19 Insurance ContractVietnam Accounting Standards - VAS 19 Insurance Contract
Vietnam Accounting Standards - VAS 19 Insurance Contract
 
Mechanics Lien Coverage
Mechanics Lien CoverageMechanics Lien Coverage
Mechanics Lien Coverage
 
Calling of a demand guarantee
Calling of a demand guaranteeCalling of a demand guarantee
Calling of a demand guarantee
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract Drafting
 
Avn 99 aircraft finance lease contract continuing liability endorsement
Avn 99 aircraft finance lease contract   continuing liability endorsement Avn 99 aircraft finance lease contract   continuing liability endorsement
Avn 99 aircraft finance lease contract continuing liability endorsement
 
Avn 67 c airline finance lease contract endorsement hull war
Avn 67 c airline finance lease contract endorsement hull warAvn 67 c airline finance lease contract endorsement hull war
Avn 67 c airline finance lease contract endorsement hull war
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
 
JPMorgan Chase Guaranty Amended 3-24-08
JPMorgan Chase Guaranty Amended 3-24-08JPMorgan Chase Guaranty Amended 3-24-08
JPMorgan Chase Guaranty Amended 3-24-08
 
Avn 67 c airline finance lease contract endorsement
Avn 67 c airline finance lease contract endorsementAvn 67 c airline finance lease contract endorsement
Avn 67 c airline finance lease contract endorsement
 
Guarantee-Backed Lines of Credit
Guarantee-Backed Lines of CreditGuarantee-Backed Lines of Credit
Guarantee-Backed Lines of Credit
 
IFRS 4
IFRS 4IFRS 4
IFRS 4
 
Surety Bonds
Surety BondsSurety Bonds
Surety Bonds
 
Letter of Gurantee
Letter of GuranteeLetter of Gurantee
Letter of Gurantee
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Business laws
Business lawsBusiness laws
Business laws
 
Risk Management For Contractors
Risk Management For ContractorsRisk Management For Contractors
Risk Management For Contractors
 
Title Insurance Commitment
Title Insurance CommitmentTitle Insurance Commitment
Title Insurance Commitment
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Bonds
BondsBonds
Bonds
 

Mehr von Divyanshu Dayal

4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax
Divyanshu Dayal
 
3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)
Divyanshu Dayal
 

Mehr von Divyanshu Dayal (20)

incoterms-2010
incoterms-2010incoterms-2010
incoterms-2010
 
RESUME WITH A SOUL
RESUME WITH A SOULRESUME WITH A SOUL
RESUME WITH A SOUL
 
The Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and TrucksThe Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and Trucks
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
 
Development of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and ContractsDevelopment of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and Contracts
 
Purchasing Management
Purchasing ManagementPurchasing Management
Purchasing Management
 
International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...
 
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
 
Coal Facts 2013 Demand Supply
Coal Facts 2013 Demand SupplyCoal Facts 2013 Demand Supply
Coal Facts 2013 Demand Supply
 
Mining Law in Asia
Mining Law in AsiaMining Law in Asia
Mining Law in Asia
 
Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)
 
How to Export From India- An Introduction
How to Export From India- An IntroductionHow to Export From India- An Introduction
How to Export From India- An Introduction
 
Type of Contracts.
Type of Contracts.Type of Contracts.
Type of Contracts.
 
Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.
 
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
 
Resume
ResumeResume
Resume
 
4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax
 
3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)
 
2. Indian Taxation. Customs Duty.
2. Indian Taxation. Customs Duty.2. Indian Taxation. Customs Duty.
2. Indian Taxation. Customs Duty.
 

Kürzlich hochgeladen

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 

Kürzlich hochgeladen (20)

Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
Introduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMIntroduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDM
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 

Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999.

  • 1. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 Clause No. 4 The Contractor Sub-Clause No. 4.2 Performance Security    Summary Performance Security is in the amount as stated in particular conditions of the contract as a guarantee towards performance of the contractor. Performance Security is valid and enforceable until the contractor has executed and completed the works, remedied any defects and has become entitled to receive performance certificate after issue of performance certificate by the employer. Performance Security is also linked with failure by the contractor to pay the employer an amount due, as either agreed by the contractor or determined under employer’s claim, claims, disputes and arbitration and termination by employer. Content of the FIDIC Clause in Brief The Contractor shall obtain (at his cost) a Performance Security for proper performance, in the amount and currencies stated in the Particular Conditions. If an amount is not stated in the Particular Conditions, this Sub-Clause shall not apply. The Contractor shall deliver the Performance Security to the Employer within 28 days after both Parties have signed the Contract Agreement. The Performance Security shall be issued by an entity and from within a country (or other jurisdiction) approved by the Employer, and shall be in the form annexed to the Particular Conditions or in another form approved by the Employer. The Contractor shall ensure that the Performance Security is valid and enforceable until the Contractor has executed and completed the Works and remedied any defects. If the terms of the Performance Security specify its expiry date, and the Contractor has not become entitled to receive the Performance Certificate by the date 28 days prior to the expiry date, the Contractor shall extend the validity of the Performance Security until the Works have been completed and any defects have been remedied. The Employer shall not make a claim under the Performance Security, except for amounts to which the Employer is entitled under the Contract in the event of: (a) failure by the Contractor to extend the validity of the Performance Security as described in the preceding paragraph, in which event the Employer may claim the full amount of the Performance Security, (b) failure by the Contractor to pay the Employer an amount due, as either agreed by the Contractor or determined under Sub-Clause 2.5 [Employer's Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement or determination, (c) failure by the Contractor to remedy a default within 42 days after receiving the Employer's notice requiring the default to be remedied, or (d) circumstances which entitle the Employer to termination under Sub-Clause 15.2 [Termination by Employer], irrespective of whether notice of termination has been given. The Employer shall return the Performance Security to the Contractor within 21 days after the Contractor has become entitled to receive the Performance Certificate. Increasing the Amount of Performance Security during the Execution of the Contract Clause 11 ‘Defect Liability’, Sub-Clause ‘Removal of Defective Work’ (To understand the provision in FIDIC related to increase amount of Performance Security) If the defect or damage cannot be remedied expeditiously on the Site and the Employer gives consent, the Contractor may remove from the Site for the purposes of repair such items of Plant as are defective or damaged. This consent may require the Contractor to increase the amount of the Performance Security by the full replacement cost of these items, or to provide other appropriate security. Pg. 1/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
  • 2. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 Guidance for Performance Security The amount of the performance security shall be ten percent 10% of the contract price stated in the contract agreement. If the performance security is in the form of a bank guarantee, it shall be issued either (a) by a bank located in the country, or (b) directly by a foreign bank acceptable to the employer. If the performance security is not in the form of a bank guarantee, it shall be furnished by a financial entity registered, or licensed to do business, in the country. Forms of Performance Security Demand Guarantee: Performance bond or other type of guarantee payable to the employer on demand, often without the presentation of other documents and without the need to show the demand is in compliance with the terms of the underlying contract. In effect, it is a substitute for a cash deposit. Under UK law, a demand guarantee is independent of the underlying contract and is separate from the counter-guarantee (if any) given by the employer’s bank to the contractor’s bank. Under US law also a demand guarantee enjoys similar protection and is called a standby letter of credit. Surety Bond: Formal, legally enforceable contract between the contractor and the employer and a third party (the surety, such as a bank, bonding company, or insurance company) whereby the surety guarantees payment of a specified maximum sum, or to otherwise compensate (indemnify), the employer against damage or loss caused by the actions (or a failure to perform. Notes:  It is quite common for the employer to require an ‘on demand’ guarantee. It is however recommended that a ‘surety bond’ as should be used. ‘On demand’ guarantees are quite a dangerous instrument due to the fact that in principle the beneficiary becomes entitled to call for payment despite lack of any reason or justification to do so, whereas a ‘surety bond’ can only be drawn if and when a substantial claim exists which remains unsatisfied.  The intention behind this security is to have the financial responsibility of the surety standing behind the contractor’s completion obligations. Thus it is critical to pay as much attention to the language of the performance bond as to the language of any significant contract. The FIDIC model forms of securities require that the surety indemnify the employer for the consequences of default or breach of contract. It is critical to carefully scrutinize the extent of liability under the performance security, in particular because Subclause 4.2 includes an indemnity to the contractor if the employer was not entitled to make the claim. Applied Clauses of the Performance Security/ Bond for EPC Contracts (FIDIC or Mixed) (References to the clauses are removed) Performance Security means the bonds and the parent company guarantee. Performance Bond means the bond in the form set out in annexure (Performance Bond), issued by a bank or financial institution reasonably acceptable to the employer with a credit rating of no worse than [A+] (Standard and Poor’s) or [A1] (Moody’s). The performance bond shall be the equivalent of 10% of the contract price (or any replacement thereof pursuant to clause). In the event of a variation under (Variations and Adjustments), which results in an increase or decrease in the contract price by an amount equal to or greater than 5% (either by itself or when aggregated with all variations since any previous adjustment to the amount of the bonds), the maximum amounts available under the bonds pursuant shall be increased or decreased accordingly, and the contractor shall deliver a replacement bond to cover such increased or decreased maximum amount issued by an entity meeting the requirements as previously approved by the employer, such approval not to be unreasonably withheld or delayed and otherwise on the same terms as the replaced bond. Such replacement bond shall be delivered duly executed to the employer no later than 30 days following the variation. All fees, taxes and expenses Pg. 2/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
  • 3. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 associated with procuring, preparing, completing and stamping (if applicable) each of the bonds and the parent company guarantee shall be paid by the contractor. If the contractor fails to provide an extension to a bond or replacement bond, the employer shall have the right to call the outstanding balance of the bond and use and apply the same as security for compliance by the contractor with its obligations and liabilities under the contract. The employer shall be entitled to make deductions against any amounts so held in respect of any claim for which it would have been entitled to call against an extended or replacement bond (had the contractor provided the same), but shall otherwise return to the contractor the remaining balance of such amounts (without any interest). Event of Performance Security in Sequence of Contract Activities as Per FIDIC Schematic (only symbol to be considered as time-line) Signing of the Contract Agreement < 28 Days Issue of Performance Security by the Contractor < 42 Days Time for Completion Tests on Completion Issue of Taking Over Certificate Remedying of Defects Commencement Date  Pg. 3/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC Defect Notification Period Issue of the Performance Certificate Within 21 Days Return of the Performance Security by the Employer