SlideShare ist ein Scribd-Unternehmen logo
1 von 43
Chapter Six
Network Models and
Project Management
Introduction
• A project is a series of activities designed to
achieve a specific objective, and which has a
definite beginning and a definite end.
• Project life cycle:
• Concept
• Feasibility analysis
• Planning
• Execution
• Termination
PERT AND CPM
• Used techniques for planning and
coordinating large scale projects
 Using PERT and CPM, it is possible to:
• Graphically displays project activities
• Estimates how long the project will take
• Indicates most critical activities
• Show where delays will not affect project
PERT/CPM
• Project managers rely on PERT/CPM to help them answer
questions such as:
 What is the total time to complete the project?
 What are the scheduled start and finish dates for each specific
activity?
 Which activities are critical and must be completed exactly as
scheduled to keep the project on schedule?
 How long can noncritical activities be delayed before they
cause an increase in the project completion time?
 If activity times are uncertain (i.e., they are random variables),
what is the probability that the project will be finished in any
given time-frame?
 If there is a cost associated with “crashing” each activity, what
is the extra cost of completing the project at a time earlier than
the normal time?
5
Difference
 Critical Path Method (CPM)
• Deterministic task times
• Activity-on-node network construction
• Repetitive nature of jobs
 Project Evaluation and Review Technique
(PERT)
• Multiple task time estimates (probabilistic nature)
• Activity-on-arrow network construction
• Non-repetitive jobs (R & D work)
The Network Diagram
 Network diagram is diagram of project activities
that shows sequential relationships by use of
arrows and nodes.
Arrows: Indicate Activity, a time consuming
effort that is required to perform a part of
the work.
Nodes : are represented by a circle
- Indicate Event, a point in time where one or
more activities start and/or finish.
1
2
3
4
5 6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Hire and
train
Remodel
Move in
1
2
3
5
6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Remodel
Move in
4
Hire and
train
7
S
Terms
 Preceding activities: activities which must be
accomplished before a given event can occur
 Succeeding activities: activities which cannot
be accomplished until any event has occurred
 Concurrent activities: activities that can be
accomplished concurrently
 Dummy activities are neither consume time
nor resources
 Merge events
 Burst events
Example: Draw a network diagram
Activity Immediate
Expected time
Predecessor
A -
4
B -
6
C A
EXERCISE
Activity Predecessor Duration (Days)
A - 2
B - 6
C - 4
D A 3
E C 5
F A 4
G B,D,E 2
Determining project completion time
1. CPM
• The length of each path
• The critical path
• The expected length of the project
• Amount of slack time for each path
• Amount of slack time for each activity
13
CPM calculation
 Path
 A connected sequence of activities
leading from the starting event to the
ending event
 Critical Path
 The longest path (time); determines the
project duration
 Critical Activities
 All of the activities that make up the critical
path
14
CPM analysis
 Draw the CPM network
 Analyze the paths through the network
 Determine the float for each activity
 Float = LS - ES = LF – EF
 Float is the maximum amount of time that this activity can
be delay in its completion before it becomes a critical
activity, i.e., delays completion of the project
 Find the critical path is that the sequence of activities and
events where there is no “slack” i.e.. Zero slack
 Find the project duration / minimum project completion
time
 Longest path through a network
15
Forward Pass
 Earliest Start Time (ES)
 Earliest time an activity can start
 ES = maximum EF of immediate predecessors
 Earliest finish time (EF)
 Earliest time an activity can finish
 Earliest start time plus activity time
 EF= ES + t
 Latest Start Time (LS)
 Latest time an activity can start without delaying critical
path time
 LS= LF - t
 Latest finish time (LF)
 latest time an activity can be completed without delaying
critical path time
Backward Pass
Consider below table summarizing the details of a project involving 10
activities
Activity Immediate precedence duration
a - 6
b - 8
c - 5
d b 13
e c 9
f a 15
g a 17
h f 9
i g 6
j d, e 12
Construct the CPM network. Determine the critical path and project
completion time .Also compute total float and free floats for the non-
critical activities
16
17
CPM Example:
• CPM Network
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
18
CPM Example
• ES and EF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
0 6
0 8
0 5
19
CPM Example
• ES and EF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21
6 23
6 21
20
CPM Example
• ES and EF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21 21 33
6 23
21 30
23 29
6 21
Project’s EF = 33
21
CPM Example
• LS and LF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17
h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21
21 33
6 23
21 30
23 29
6 21
21 33
27 33
24 33
22
CPM Example
• LS and LF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17
h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21
21 33
6 23
21 30
23 29
6 21
4 10
0 8
7 12
12 21
21 33
27 33
8 21
10 27
24 33
18 24
23
CPM Example
• Float
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17
h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21 21 33
6 23
21 30
23 29
6 21
3 9
0 8
7 12
12 21
21 33
27 33
8 21
10 27
24 33
9 24
3 4
3
3
4
0
0
7
7
0
24
CPM Example
• Critical Path
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
darla/smbs/vit 25
PERT
• PERT is based on the assumption that an activity’s duration
follows a probability distribution instead of being a single value
• Three time estimates are required to compute the parameters
of an activity’s duration distribution:
– pessimistic time (tp ) - the time the activity would take if
things did not go well
– most likely time (tm ) - the consensus best estimate of the
activity’s duration
– optimistic time (to ) - the time the activity would take if
things did go well
Mean (expected time): te =
tp + 4 tm + to
6
Variance: Vt = 2 =
tp - to
6
2
26
PERT analysis
• Draw the network.
• Analyze the paths through the network and find the critical path.
• The length of the critical path is the mean of the project duration
probability distribution which is assumed to be normal
• The standard deviation of the project duration probability
distribution is computed by adding the variances of the critical
activities (all of the activities that make up the critical path) and
taking the square root of that sum
• Probability computations can now be made using the normal
distribution table.
27
Probability computation
Determine probability that project is completed within specified time
Z =
x - 

where  = tp = project mean time
 = project standard mean time
x = (proposed ) specified time
28
Normal Distribution of Project Time
 = tp Time
x
Z
Probability
29
PERT Example
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)
A -- 4 6 8
B -- 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B,C 3 4 5
G B,C 1 1.5 5
H E,F 5 6 7
I E,F 2 5 8
J D,H 2.5 2.75 4.5
K G,I 3 5 7
30
PERT Example
A
D
C
B
F
E
G
I
H
K
J
PERT Network
31
PERT Example
Activity Expected Time Variance
A 6 4/9
B 4 4/9
C 3 0
D 5 1/9
E 1 1/36
F 4 1/9
G 2 4/9
H 6 1/9
I 5 1
J 3 1/9
K 5 4/9
32
PERT Example
Activity ES EF LS LF Slack
A 0 6 0 6 0 *critical
B 0 4 5 9 5
C 6 9 6 9 0 *
D 6 11 15 20 9
E 6 7 12 13 6
F 9 13 9 13 0 *
G 9 11 16 18 7
H 13 19 14 20 1
I 13 18 13 18 0 *
J 19 22 20 23 1
K 18 23 18 23 0 *
33
PERT Example
Vpath = VA + VC + VF + VI + VK
= 4/9 + 0 + 1/9 + 1 + 4/9
= 2
path = 1.414
z = (24 - 23)/(24-23)/1.414 = .71
From the Standard Normal Distribution table:
P(z < .71) = .5 + .2612 = .7612
PROJECT COST
35
Cost consideration in project
• Project managers may have the option or requirement to crash
the project, or accelerate the completion of the project.
• This is accomplished by reducing the length of the critical path(s).
• The length of the critical path is reduced by reducing the
duration of the activities on the critical path.
• If each activity requires the expenditure of an amount of money
to reduce its duration by one unit of time, then the project
manager selects the least cost critical activity, reduces it by one
time unit, and traces that change through the remainder of the
network.
• As a result of a reduction in an activity’s time, a new critical path
may be created.
• When there is more than one critical path, each of the critical
paths must be reduced.
• If the length of the project needs to be reduced further, the
process is repeated.
36
Project Crashing
• Crashing
– reducing project time by expending additional resources
• Crash time
– an amount of time an activity is reduced
• Crash cost
– cost of reducing activity time
• Goal
– reduce project duration at minimum cost
37
Time-Cost Relationship
 Crashing costs increase as project duration decreases
 Indirect costs increase as project duration increases
 Reduce project length as long as crashing costs are less than indirect costs
Time-Cost Tradeoff
time
Direct cost
Indirect
cost
Total project cost
Min total cost =
optimal project
time
38
Benefits of CPM/PERT
• Useful at many stages of project management
• Mathematically simple
• Give critical path and slack time
• Provide project documentation
• Useful in monitoring costs
•How long will the entire project take to be completed? What are the risks involved?
•Which are the critical activities or tasks in the project which could delay the entire
project if they were not completed on time?
•Is the project on schedule, behind schedule or ahead of schedule?
•If the project has to be finished earlier than planned, what is the best way to do this
at the least cost?
CPM/PERT can answer the following important
questions:
39
Limitations to CPM/PERT
• Clearly defined, independent and stable activities
• Specified precedence relationships
• Over emphasis on critical paths
• Deterministic CPM model
• Activity time estimates are subjective and depend on judgment
• PERT assumes a beta distribution for these time estimates, but
the actual distribution may be different
• PERT consistently underestimates the expected project
completion time due to alternate paths becoming critical
To overcome the limitation, Monte Carlo simulations can be
performed on the network to eliminate the optimistic bias
40
CPM PERT
CPM uses activity oriented network. PERT uses event oriented Network.
Durations of activity may be estimated
with a fair degree of accuracy.
Estimate of time for activities are not so
accurate and definite.
It is used extensively in construction
projects.
It is used mostly in research and
development projects, particularly
projects of non-repetitive nature.
Deterministic concept is used. Probabilistic model concept is used.
CPM can control both time and cost
when planning.
PERT is basically a tool for planning.
In CPM, cost optimization is given prime
importance. The time for the completion
of the project depends upon cost
optimization. The cost is not directly
proportioned to time. Thus, cost is the
In PERT, it is assumed that cost varies
directly with time. Attention is therefore
given to minimize the time so that
minimum cost results. Thus in PERT, time
is the controlling factor.
PERT vs CPM
Time-Cost Trade Offs: Crashing
• It is possible to reduce the length of a project by
injecting additional resources
• A project manager may be able to shorten a
project: by realizing a savings on indirect project
costs by increasing direct expenses to speed up
the project.
• The objective of project crash cost analysis is to
reduce the total projected completion time
while minimizing the cost of crashing.
• A manager needs the following information:
• Regular time and crash time estimates
• Regular (normal) cost and crash cost estimates
• A list of activates that are on the critical path
Example:
• Using information below develop an optimum
time – cost solution. Assume that indirect
project costs are birr 1000 per day.
End of
Chapter Six

Weitere ähnliche Inhalte

Was ist angesagt?

L 1 Introduction to strategic mgmt
L 1 Introduction to strategic mgmtL 1 Introduction to strategic mgmt
L 1 Introduction to strategic mgmtSudhir Upadhyay
 
Management consulting process
Management consulting process Management consulting process
Management consulting process kazkuroda
 
Strategic management process
Strategic management processStrategic management process
Strategic management processSajjad Qadri
 
strategic tools
strategic toolsstrategic tools
strategic toolsPaul J. Walsh
 
Strategic Planning Introduction
Strategic Planning IntroductionStrategic Planning Introduction
Strategic Planning IntroductionJon R Wallace
 
Strategic Alignment Workshop Presentation
Strategic Alignment Workshop PresentationStrategic Alignment Workshop Presentation
Strategic Alignment Workshop PresentationMarcus Vannini
 
Sabaruddin de AB_S_Six Step ERP Project Management_FINAL
Sabaruddin de AB_S_Six Step ERP Project Management_FINALSabaruddin de AB_S_Six Step ERP Project Management_FINAL
Sabaruddin de AB_S_Six Step ERP Project Management_FINALsabaruddin de AB
 
Corporate strategy
Corporate strategyCorporate strategy
Corporate strategyTanvir Bhatti
 
FĂĄbrica de Software
FĂĄbrica de SoftwareFĂĄbrica de Software
FĂĄbrica de SoftwareVinicius Garcia
 
Advanced strategic management
Advanced strategic managementAdvanced strategic management
Advanced strategic managementShashankdiv
 
Business policy & Strategic Management for MBA
Business policy & Strategic Management for MBABusiness policy & Strategic Management for MBA
Business policy & Strategic Management for MBAUlhas Wadivkar
 
Strategic thinking
Strategic thinkingStrategic thinking
Strategic thinkingAmir NikKhah
 
Mrp MRPII Erp Implementation
Mrp MRPII Erp ImplementationMrp MRPII Erp Implementation
Mrp MRPII Erp ImplementationAnand Subramaniam
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectSharad Srivastava
 
ADVANCED STRATEGIC MANAGEMENT ASSIGNMENT 1
ADVANCED STRATEGIC MANAGEMENT ASSIGNMENT 1ADVANCED STRATEGIC MANAGEMENT ASSIGNMENT 1
ADVANCED STRATEGIC MANAGEMENT ASSIGNMENT 1Nikolas Giampelis, MBA
 
Mba strategic management 2
Mba strategic management 2Mba strategic management 2
Mba strategic management 2Ahmed Hamza
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dateskrunalplanning
 

Was ist angesagt? (20)

L 1 Introduction to strategic mgmt
L 1 Introduction to strategic mgmtL 1 Introduction to strategic mgmt
L 1 Introduction to strategic mgmt
 
Management consulting process
Management consulting process Management consulting process
Management consulting process
 
1 introduction to strategy
1   introduction to strategy1   introduction to strategy
1 introduction to strategy
 
Strategic management process
Strategic management processStrategic management process
Strategic management process
 
strategic tools
strategic toolsstrategic tools
strategic tools
 
Strategic Planning Introduction
Strategic Planning IntroductionStrategic Planning Introduction
Strategic Planning Introduction
 
Strategic Alignment Workshop Presentation
Strategic Alignment Workshop PresentationStrategic Alignment Workshop Presentation
Strategic Alignment Workshop Presentation
 
Sabaruddin de AB_S_Six Step ERP Project Management_FINAL
Sabaruddin de AB_S_Six Step ERP Project Management_FINALSabaruddin de AB_S_Six Step ERP Project Management_FINAL
Sabaruddin de AB_S_Six Step ERP Project Management_FINAL
 
Corporate strategy
Corporate strategyCorporate strategy
Corporate strategy
 
FĂĄbrica de Software
FĂĄbrica de SoftwareFĂĄbrica de Software
FĂĄbrica de Software
 
Advanced strategic management
Advanced strategic managementAdvanced strategic management
Advanced strategic management
 
Business policy & Strategic Management for MBA
Business policy & Strategic Management for MBABusiness policy & Strategic Management for MBA
Business policy & Strategic Management for MBA
 
Strategic thinking
Strategic thinkingStrategic thinking
Strategic thinking
 
Mrp MRPII Erp Implementation
Mrp MRPII Erp ImplementationMrp MRPII Erp Implementation
Mrp MRPII Erp Implementation
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics Project
 
ADVANCED STRATEGIC MANAGEMENT ASSIGNMENT 1
ADVANCED STRATEGIC MANAGEMENT ASSIGNMENT 1ADVANCED STRATEGIC MANAGEMENT ASSIGNMENT 1
ADVANCED STRATEGIC MANAGEMENT ASSIGNMENT 1
 
Togaf 9 template benefits diagram
Togaf 9 template   benefits diagramTogaf 9 template   benefits diagram
Togaf 9 template benefits diagram
 
Mba strategic management 2
Mba strategic management 2Mba strategic management 2
Mba strategic management 2
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
TOGAF em Ação
TOGAF em AçãoTOGAF em Ação
TOGAF em Ação
 

Ähnlich wie chapter 6.ppt

PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project managementAhmad Basim Hamza
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptxShwetaMahdole
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii referenceahsanrabbani
 
Project management
Project managementProject management
Project managementKwesi Kissiedu
 
Project management techniques
Project management techniquesProject management techniques
Project management techniquesRagjni Govindaraju
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pertSheetu Goel
 

Ähnlich wie chapter 6.ppt (20)

PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
Project management
Project managementProject management
Project management
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 

Mehr von DejeneDay

Fundamentals of marketing management.pptx
Fundamentals of marketing management.pptxFundamentals of marketing management.pptx
Fundamentals of marketing management.pptxDejeneDay
 
The-Five-Functions-of-Management overview.pptx
The-Five-Functions-of-Management overview.pptxThe-Five-Functions-of-Management overview.pptx
The-Five-Functions-of-Management overview.pptxDejeneDay
 
best for normal distribution.ppt
best for normal distribution.pptbest for normal distribution.ppt
best for normal distribution.pptDejeneDay
 
CHAPTER THREE QABD 2016.pptx
CHAPTER THREE QABD 2016.pptxCHAPTER THREE QABD 2016.pptx
CHAPTER THREE QABD 2016.pptxDejeneDay
 
Chapter 1 Presentation.ppt
Chapter 1 Presentation.pptChapter 1 Presentation.ppt
Chapter 1 Presentation.pptDejeneDay
 
psychometrics ch 2 -2016.ppt
psychometrics ch 2 -2016.pptpsychometrics ch 2 -2016.ppt
psychometrics ch 2 -2016.pptDejeneDay
 
OB chapter 2 modied.pptx
OB chapter 2 modied.pptxOB chapter 2 modied.pptx
OB chapter 2 modied.pptxDejeneDay
 
CHAPTER ONE pyschometrics new.pptx
CHAPTER ONE pyschometrics new.pptxCHAPTER ONE pyschometrics new.pptx
CHAPTER ONE pyschometrics new.pptxDejeneDay
 
Chapter one management theory.pptx
Chapter one management theory.pptxChapter one management theory.pptx
Chapter one management theory.pptxDejeneDay
 
best note.pptx
best note.pptxbest note.pptx
best note.pptxDejeneDay
 
facility location.ppt
facility location.pptfacility location.ppt
facility location.pptDejeneDay
 
project mgmt chapter 1.pptx
project mgmt chapter 1.pptxproject mgmt chapter 1.pptx
project mgmt chapter 1.pptxDejeneDay
 
chapter 1.pptx
chapter 1.pptxchapter 1.pptx
chapter 1.pptxDejeneDay
 
Chapter 2 ppt
Chapter 2 pptChapter 2 ppt
Chapter 2 pptDejeneDay
 
entrelreneurship chapter 2pt
entrelreneurship chapter 2ptentrelreneurship chapter 2pt
entrelreneurship chapter 2ptDejeneDay
 
enterpreneurship chapter 1.pptx
enterpreneurship  chapter 1.pptxenterpreneurship  chapter 1.pptx
enterpreneurship chapter 1.pptxDejeneDay
 
BS chapter 4.pptx
BS chapter 4.pptxBS chapter 4.pptx
BS chapter 4.pptxDejeneDay
 
managerial economics Introduction.pptx
managerial economics  Introduction.pptxmanagerial economics  Introduction.pptx
managerial economics Introduction.pptxDejeneDay
 
Production and Cost.pptx
Production and Cost.pptxProduction and Cost.pptx
Production and Cost.pptxDejeneDay
 
business ethics.ppt
business ethics.pptbusiness ethics.ppt
business ethics.pptDejeneDay
 

Mehr von DejeneDay (20)

Fundamentals of marketing management.pptx
Fundamentals of marketing management.pptxFundamentals of marketing management.pptx
Fundamentals of marketing management.pptx
 
The-Five-Functions-of-Management overview.pptx
The-Five-Functions-of-Management overview.pptxThe-Five-Functions-of-Management overview.pptx
The-Five-Functions-of-Management overview.pptx
 
best for normal distribution.ppt
best for normal distribution.pptbest for normal distribution.ppt
best for normal distribution.ppt
 
CHAPTER THREE QABD 2016.pptx
CHAPTER THREE QABD 2016.pptxCHAPTER THREE QABD 2016.pptx
CHAPTER THREE QABD 2016.pptx
 
Chapter 1 Presentation.ppt
Chapter 1 Presentation.pptChapter 1 Presentation.ppt
Chapter 1 Presentation.ppt
 
psychometrics ch 2 -2016.ppt
psychometrics ch 2 -2016.pptpsychometrics ch 2 -2016.ppt
psychometrics ch 2 -2016.ppt
 
OB chapter 2 modied.pptx
OB chapter 2 modied.pptxOB chapter 2 modied.pptx
OB chapter 2 modied.pptx
 
CHAPTER ONE pyschometrics new.pptx
CHAPTER ONE pyschometrics new.pptxCHAPTER ONE pyschometrics new.pptx
CHAPTER ONE pyschometrics new.pptx
 
Chapter one management theory.pptx
Chapter one management theory.pptxChapter one management theory.pptx
Chapter one management theory.pptx
 
best note.pptx
best note.pptxbest note.pptx
best note.pptx
 
facility location.ppt
facility location.pptfacility location.ppt
facility location.ppt
 
project mgmt chapter 1.pptx
project mgmt chapter 1.pptxproject mgmt chapter 1.pptx
project mgmt chapter 1.pptx
 
chapter 1.pptx
chapter 1.pptxchapter 1.pptx
chapter 1.pptx
 
Chapter 2 ppt
Chapter 2 pptChapter 2 ppt
Chapter 2 ppt
 
entrelreneurship chapter 2pt
entrelreneurship chapter 2ptentrelreneurship chapter 2pt
entrelreneurship chapter 2pt
 
enterpreneurship chapter 1.pptx
enterpreneurship  chapter 1.pptxenterpreneurship  chapter 1.pptx
enterpreneurship chapter 1.pptx
 
BS chapter 4.pptx
BS chapter 4.pptxBS chapter 4.pptx
BS chapter 4.pptx
 
managerial economics Introduction.pptx
managerial economics  Introduction.pptxmanagerial economics  Introduction.pptx
managerial economics Introduction.pptx
 
Production and Cost.pptx
Production and Cost.pptxProduction and Cost.pptx
Production and Cost.pptx
 
business ethics.ppt
business ethics.pptbusiness ethics.ppt
business ethics.ppt
 

KĂźrzlich hochgeladen

Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis GagnĂŠ
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 

KĂźrzlich hochgeladen (20)

Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 

chapter 6.ppt

  • 1. Chapter Six Network Models and Project Management
  • 2. Introduction • A project is a series of activities designed to achieve a specific objective, and which has a definite beginning and a definite end. • Project life cycle: • Concept • Feasibility analysis • Planning • Execution • Termination
  • 3. PERT AND CPM • Used techniques for planning and coordinating large scale projects  Using PERT and CPM, it is possible to: • Graphically displays project activities • Estimates how long the project will take • Indicates most critical activities • Show where delays will not affect project
  • 4. PERT/CPM • Project managers rely on PERT/CPM to help them answer questions such as:  What is the total time to complete the project?  What are the scheduled start and finish dates for each specific activity?  Which activities are critical and must be completed exactly as scheduled to keep the project on schedule?  How long can noncritical activities be delayed before they cause an increase in the project completion time?  If activity times are uncertain (i.e., they are random variables), what is the probability that the project will be finished in any given time-frame?  If there is a cost associated with “crashing” each activity, what is the extra cost of completing the project at a time earlier than the normal time?
  • 5. 5 Difference  Critical Path Method (CPM) • Deterministic task times • Activity-on-node network construction • Repetitive nature of jobs  Project Evaluation and Review Technique (PERT) • Multiple task time estimates (probabilistic nature) • Activity-on-arrow network construction • Non-repetitive jobs (R & D work)
  • 6. The Network Diagram  Network diagram is diagram of project activities that shows sequential relationships by use of arrows and nodes. Arrows: Indicate Activity, a time consuming effort that is required to perform a part of the work. Nodes : are represented by a circle - Indicate Event, a point in time where one or more activities start and/or finish.
  • 9. Terms  Preceding activities: activities which must be accomplished before a given event can occur  Succeeding activities: activities which cannot be accomplished until any event has occurred  Concurrent activities: activities that can be accomplished concurrently  Dummy activities are neither consume time nor resources  Merge events  Burst events
  • 10. Example: Draw a network diagram Activity Immediate Expected time Predecessor A - 4 B - 6 C A
  • 11. EXERCISE Activity Predecessor Duration (Days) A - 2 B - 6 C - 4 D A 3 E C 5 F A 4 G B,D,E 2
  • 12. Determining project completion time 1. CPM • The length of each path • The critical path • The expected length of the project • Amount of slack time for each path • Amount of slack time for each activity
  • 13. 13 CPM calculation  Path  A connected sequence of activities leading from the starting event to the ending event  Critical Path  The longest path (time); determines the project duration  Critical Activities  All of the activities that make up the critical path
  • 14. 14 CPM analysis  Draw the CPM network  Analyze the paths through the network  Determine the float for each activity  Float = LS - ES = LF – EF  Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project  Find the critical path is that the sequence of activities and events where there is no “slack” i.e.. Zero slack  Find the project duration / minimum project completion time  Longest path through a network
  • 15. 15 Forward Pass  Earliest Start Time (ES)  Earliest time an activity can start  ES = maximum EF of immediate predecessors  Earliest finish time (EF)  Earliest time an activity can finish  Earliest start time plus activity time  EF= ES + t  Latest Start Time (LS)  Latest time an activity can start without delaying critical path time  LS= LF - t  Latest finish time (LF)  latest time an activity can be completed without delaying critical path time Backward Pass
  • 16. Consider below table summarizing the details of a project involving 10 activities Activity Immediate precedence duration a - 6 b - 8 c - 5 d b 13 e c 9 f a 15 g a 17 h f 9 i g 6 j d, e 12 Construct the CPM network. Determine the critical path and project completion time .Also compute total float and free floats for the non- critical activities 16
  • 17. 17 CPM Example: • CPM Network a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12
  • 18. 18 CPM Example • ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5
  • 19. 19 CPM Example • ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 6 23 6 21
  • 20. 20 CPM Example • ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 Project’s EF = 33
  • 21. 21 CPM Example • LS and LF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 21 33 27 33 24 33
  • 22. 22 CPM Example • LS and LF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 4 10 0 8 7 12 12 21 21 33 27 33 8 21 10 27 24 33 18 24
  • 23. 23 CPM Example • Float a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 3 9 0 8 7 12 12 21 21 33 27 33 8 21 10 27 24 33 9 24 3 4 3 3 4 0 0 7 7 0
  • 24. 24 CPM Example • Critical Path a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12
  • 25. darla/smbs/vit 25 PERT • PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value • Three time estimates are required to compute the parameters of an activity’s duration distribution: – pessimistic time (tp ) - the time the activity would take if things did not go well – most likely time (tm ) - the consensus best estimate of the activity’s duration – optimistic time (to ) - the time the activity would take if things did go well Mean (expected time): te = tp + 4 tm + to 6 Variance: Vt = 2 = tp - to 6 2
  • 26. 26 PERT analysis • Draw the network. • Analyze the paths through the network and find the critical path. • The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal • The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum • Probability computations can now be made using the normal distribution table.
  • 27. 27 Probability computation Determine probability that project is completed within specified time Z = x -   where  = tp = project mean time  = project standard mean time x = (proposed ) specified time
  • 28. 28 Normal Distribution of Project Time  = tp Time x Z Probability
  • 29. 29 PERT Example Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 4 6 8 B -- 1 4.5 5 C A 3 3 3 D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 7
  • 31. 31 PERT Example Activity Expected Time Variance A 6 4/9 B 4 4/9 C 3 0 D 5 1/9 E 1 1/36 F 4 1/9 G 2 4/9 H 6 1/9 I 5 1 J 3 1/9 K 5 4/9
  • 32. 32 PERT Example Activity ES EF LS LF Slack A 0 6 0 6 0 *critical B 0 4 5 9 5 C 6 9 6 9 0 * D 6 11 15 20 9 E 6 7 12 13 6 F 9 13 9 13 0 * G 9 11 16 18 7 H 13 19 14 20 1 I 13 18 13 18 0 * J 19 22 20 23 1 K 18 23 18 23 0 *
  • 33. 33 PERT Example Vpath = VA + VC + VF + VI + VK = 4/9 + 0 + 1/9 + 1 + 4/9 = 2 path = 1.414 z = (24 - 23)/(24-23)/1.414 = .71 From the Standard Normal Distribution table: P(z < .71) = .5 + .2612 = .7612
  • 35. 35 Cost consideration in project • Project managers may have the option or requirement to crash the project, or accelerate the completion of the project. • This is accomplished by reducing the length of the critical path(s). • The length of the critical path is reduced by reducing the duration of the activities on the critical path. • If each activity requires the expenditure of an amount of money to reduce its duration by one unit of time, then the project manager selects the least cost critical activity, reduces it by one time unit, and traces that change through the remainder of the network. • As a result of a reduction in an activity’s time, a new critical path may be created. • When there is more than one critical path, each of the critical paths must be reduced. • If the length of the project needs to be reduced further, the process is repeated.
  • 36. 36 Project Crashing • Crashing – reducing project time by expending additional resources • Crash time – an amount of time an activity is reduced • Crash cost – cost of reducing activity time • Goal – reduce project duration at minimum cost
  • 37. 37 Time-Cost Relationship  Crashing costs increase as project duration decreases  Indirect costs increase as project duration increases  Reduce project length as long as crashing costs are less than indirect costs Time-Cost Tradeoff time Direct cost Indirect cost Total project cost Min total cost = optimal project time
  • 38. 38 Benefits of CPM/PERT • Useful at many stages of project management • Mathematically simple • Give critical path and slack time • Provide project documentation • Useful in monitoring costs •How long will the entire project take to be completed? What are the risks involved? •Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? •Is the project on schedule, behind schedule or ahead of schedule? •If the project has to be finished earlier than planned, what is the best way to do this at the least cost? CPM/PERT can answer the following important questions:
  • 39. 39 Limitations to CPM/PERT • Clearly defined, independent and stable activities • Specified precedence relationships • Over emphasis on critical paths • Deterministic CPM model • Activity time estimates are subjective and depend on judgment • PERT assumes a beta distribution for these time estimates, but the actual distribution may be different • PERT consistently underestimates the expected project completion time due to alternate paths becoming critical To overcome the limitation, Monte Carlo simulations can be performed on the network to eliminate the optimistic bias
  • 40. 40 CPM PERT CPM uses activity oriented network. PERT uses event oriented Network. Durations of activity may be estimated with a fair degree of accuracy. Estimate of time for activities are not so accurate and definite. It is used extensively in construction projects. It is used mostly in research and development projects, particularly projects of non-repetitive nature. Deterministic concept is used. Probabilistic model concept is used. CPM can control both time and cost when planning. PERT is basically a tool for planning. In CPM, cost optimization is given prime importance. The time for the completion of the project depends upon cost optimization. The cost is not directly proportioned to time. Thus, cost is the In PERT, it is assumed that cost varies directly with time. Attention is therefore given to minimize the time so that minimum cost results. Thus in PERT, time is the controlling factor. PERT vs CPM
  • 41. Time-Cost Trade Offs: Crashing • It is possible to reduce the length of a project by injecting additional resources • A project manager may be able to shorten a project: by realizing a savings on indirect project costs by increasing direct expenses to speed up the project. • The objective of project crash cost analysis is to reduce the total projected completion time while minimizing the cost of crashing. • A manager needs the following information: • Regular time and crash time estimates • Regular (normal) cost and crash cost estimates • A list of activates that are on the critical path
  • 42. Example: • Using information below develop an optimum time – cost solution. Assume that indirect project costs are birr 1000 per day.