July 14, 2017 Version 1.0
David D. Bustin
Risk Management Plan
Human Resource Software Implementation
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 II
REVISIONS AND DISTRIBUTION
Revision Release date
Distributed to*
Client
Consultant
DBMainoffice(s)
Allprojectmgmt.dept.
Sub-contractors
Suppliers
Rev. 0 (draft) 14/07/2017
*) Detailed distribution lists will beprepared for each distribution event. Further details as per the project
communication plan
Amendments
Changes to this plan may periodically occur. Any amendment(s) to this plan shall be
communicated to the change control board. When submitting changes to the change control
board, a change request form must be used. Once approved by the change control board, only
the update will be distributed and the complete revised document will be located internally.
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 III
PROJECT SPONSOR APPROVAL
Prepared by: Reviewed by: Approved by Proj. Sponsor:
14/07/2017 Place, dd/mm/yyyy Place, dd/mm/yyyy
David D. Bustin
Designation
Name
Designation
Name
Designation
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 IV
TABLE OF CONTENTS
Revisions and Distribution……………………….………………..…………………………………………………..II
Amendments……………………..…………………..………………………………………………………....II
Project Sponsor Approval……………………………..…………………….…………………………………..……III
Table of Contents………………………………………………………………….……………………………………..IV
1. Introduction
1.1 Purpose................................................................................................................1
1.2 Intended Audience..............................................................................................1
1.3 Risk Management Approach...............................................................................2
1.3.1 Risk Identification........................................................................................2
1.3.2 Risk Analysis ................................................................................................2
1.3.3 Response Planning ......................................................................................2
1.3.4 Risk Monitoring and Control .......................................................................2
2. Roles and Responsibilities
2.1 Project Manager..................................................................................................3
2.2 Project Team .......................................................................................................3
2.3 Software Quality Assurance Lead…...……………………………………………………………...3
2.4 Project Sponsors..................................................................................................3
2.5 Project Stakeholders……………………………………………………………………………………….3
3. Risk Identification
3.1 Background…………………………………………………………………………………………………….4
3.2 Risk Categories…………………….…………………………………………………………………………4
3.2.1 People………………………………………………………………………………………….......……4
3.2.2 Security………………………………………………………………………………………......……..4
3.2.3 Technical..……………………………………………………………….…………………….………..4
3.3 Sources…………………………………………………………………………………..…………….………..4
3.4 Documentation…………………………………………………………………………………......………4
3.5 Risk Categories Table………………………………………………………………………………………5
4. Risk Analysis
4.1 Background…………………………………………………………………………………………………….6
4.1.1 Qualitative Analysis…………………………………………………………………………………6
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 V
4.2 Documentation……..............................................................................................6
4.3 Probability and Impact Matrix………………………...………………………………………………7
5. Response Planning
5.1 Background.……………………………….…………………………………………………………………...8
5.2 Risk Strategies......................................................................................................8
5.2.1 Risk Avoidance.............................................................................................8
5.2.2 Risk Transference........................................................................................8
5.2.3 Risk Mitigation.............................................................................................8
5.2.4 Risk Acceptance...........................................................................................8
5.3 Documentation...………………………………………………………….………………………………….8
6. Risk Monitoring and Control
6.1 Background..........................................................................................................9
6.2 Timing..................................................................................................................9
6.3 Documentation……………………………………………………………………………………………….9
List of Tables and Figures
Figure 1 - Risk Management Model……………………………….………………………………………...….…2
Table 1 - Risk Categories……………………………………………….…………………………………………….….5
Table 2 - Risk Probability Definitions….…………………....….………………………………………….….….6
Table 3 - Risk Impact Definitions…....……….......…………….………………………………………….….….6
Table 4 - Probability and Impact Matrix..............................................................................7
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 P a g e | 1
INTRODUCTION
The risk management plan is an element of the project management plan that provides a view of
the risks and the organizations structured approach to handling them.
Purpose
The purpose of this plan is to prioritize and document risk through identification, categorization,
analysis, response planning, and risk definitions for integrating new human resources software.
Introducing new software brings challenges not only for the IT staff but also end users in the
human resources department. Identifying all potential risks is impossible. The risk management
plan will provide a guidance for handling known risks before they occur and unknown risks as they
occur.
Intended Audience
This risk management plan is intended to provide guidance for the IT staff, project and functional
managers, executives, project team members, contractors and subcontractors, and other project
sponsors or stakeholders.
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 P a g e | 2
RISK MANAGEMENT APPROACH
Risk Identification
All known risks and their associated strategies should be communicated in the beginning of the
project or as soon as possible. Continuous attention must be given to potential risks and once
identified, that risks will be categorized. Risk owners and appropriate strategies will be assigned.
Risk identification will include the source of risk, risk events, and risk indicators. Strategies to
handle individual risks will be incorporated into the response planning and monitoring procedures.
Risk Analysis
In risk analysis, a qualitative risk analysis will be conducted to determine the probability of
occurrence and impact to the project if the risk materialized.
Response Planning
During response planning, risk management and contingency plans will be developed. Strategies
for handling each risk will be developed by the assigned risk owner. The approaches used in risk
response are avoidance, transference, mitigation, and acceptance.
Risk Monitoring and Control
Action plans will be created, integrated, and monitored during the response planning phase.
During risk monitoring and control, corrective action plans are developed, implemented, and
monitored.
Figure 1 RiskManagement Model
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 P a g e | 3
ROLES AND RESPONSIBILITIES
CEO
The CEO approves or disapproves investments and funding for projects. Also, he/she decides the
project organization structure.
Steering Committee
The steering committee ensures the quality and timeliness of the project. They provide advice and
often decisions on project alterations. Specifically, they will align the IT strategy with
organizational goals.
Project Manager
The project manager is responsible for approval of the risk management plan (this document),
leads and participates in the risk management process, and takes ownership of risk
mitigation/contingency planning and execution. The project manager is ultimately responsible for
the final decision on risk actions, in coordination with the project sponsors.
Project Team
Project team members (analysts/product managers, developers, testers, and deployment team
members) participate in the risk identification process and discuss risk monitoring and mitigation
activities at team meetings. Carries out the activities for project completion
Software Quality Assurance Lead
The software quality assurance (SQA) lead is responsible for ensuring identified risks are being
managed per the risk management plan. The SQA lead also assist in identifying new risks and/or
proposing mitigation strategies and contingency plans, along with proposing improvements to the
risk management plan and processes.
Project Sponsors
Project sponsors participate in risk identification and risk activities, as necessary. Project sponsors
also receive escalated risks and assist with mitigation and contingency actions for escalated risks.
Project Stakeholders
Stakeholders assist in monitoring risk action effectiveness and participate in risk escalation, as
necessary.
Audit Team
The audit team determines the level of compliance with the defined processes, regulatory
mandates, and industry standards.
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 P a g e | 4
RISK IDENTIFICATION
Background
Sources of risks and risk events are developed in the risk identification process. Some risks are
known and pre-defined in order to form an orderly process in risk identification throughout the
project. Categories of risks may evolve and new risks are developed over the course of the
project. After identifying and categorizing the risk event, it is entered into the risk register.
Risk Categories
The following categories will identify risks.
ď‚· People: Inadequate skilled end users, Senior management support, IT staff capability of
maintenance and operations
ď‚· Security: Confidentiality, Integrity, Availability
ď‚· Technical: Compatibility with existing systems, Vendor support and customer service,
Configuration tailored to specific organizational policy and procedures
Sources
The following tools and techniques will be employed for risk identification:
ď‚· Team meetings
ď‚· Expert interviews
ď‚· Analogy comparisons
ď‚· Assumptions analysis
ď‚· SWOT analysis
ď‚· Checklists
Documentation
All identified risks should be documented and entered into the risk register. During risk
identification, the following information is required for documentation:
ď‚· Risk category
ď‚· Risk trigger
ď‚· Potential outcome
ď‚· Source
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 P a g e | 5
Table 1 – Risk Categories
Reference
Number Risk
Risk
Category Risk Trigger
Potential
Outcome Source
1
non-compliance
in reporting Technical
System failed in
compliance
reporting to
regulatory
agencies
Sarbanes-Oxley
Compliance Audit
ExpertInterviews,
Analogy
Comparisons
2
No application
security
Security Network Breach
Employee’s
personal data
stolen
Expert Interviews
Team Meetings
SWOT Analysis
3
Performance
reviews not
submitted
Technical
Notification
failures
Employees
receive late
performance
evaluations
Team Meetings
4
Inadequately
skilled staff
People
Unable to
complete task
accurately and
on time
Employee morale
Team Meetings,
Analogy
Comparisons,
Assumptions
Analysis
5
Financial abuse
People
Improper
separation of
duties
Fraud
Analogy
Comparisons
6
Discriminatory
practices,
unsuitable
candidates
selected
People Unethical hiring
Potential lawsuits,
negative public
relations, loss of
business, fines.
Checklists
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 P a g e | 6
RISK ANALYSIS
Background
The risk score can be calculated after the risk impact and probability are identified. The
risk probability and impact matrix is shown below on page 7 of this risk management plan. The
matrix illustrates a combination of impact and probability that produce a risk priority.
Qualitative Analysis consists of the probability of a risk occurring and that risk’s impact on
the project. The potential likelihood that a given risk will occur is assessed, and an appropriate risk
probability is selected from the chart below.
Probability Category Probability Description
Very High 0.90 Risk event expected to occur
High 0.70 Risk event more likely than not to occur
Probable 0.50 Risk event may or may not occur
Low 0.30 Risk event less likely than not to occur
Very Low 0.10 Risk event not expected to occur
Table 2 – Risk Probability Definitions
The below chart displays risk impact definitions for each project area.
Project Objective Very Low
0.05
Low
0.10
Moderate
0.20
High
0.40
Very High
0.80
Cost Insignificant cost
impact
< 10% costimpact 10-20% cost
impact
20-40% cost
impact
> 40% costimpact
Schedule Insignificant
schedule impact
< 5% schedule
impact
5-10% schedule
impact
10-20% schedule
impact
> 20% schedule
impact
Scope Barely noticeable Minor areas
impacted
Major areas
impacted
Changes
unacceptableto
sponsor
Product becomes
effectively useless
Quality Barely noticeable Only very
demanding
applications
impacted
Sponsor must
approve quality
reduction
Quality reduction
unacceptableto
sponsor
Product becomes
effectively useless
Table 3 – Risk Impact Definitions
Documentation
Risk analysis results are documented in the risk register. Information shall be entered in the
register:
ď‚· Risk impact
ď‚· Risk probability
ď‚· Risk matrix score
 Risk priority – computed by the risk register spreadsheet after impact and probability are
entered
 Qualitative impact – descriptive comments about the potential risk impact
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 P a g e | 7
PROBABILITY AND IMPACT MATRIX
Different levels of risk probability and impact should be specific to the individual project. The risk
probability and impact matrix illustrate a combination of risk impact and probability. The result of
the matrix enables risks prioritization. Red cells in the matrix are the highest priority which should
receive the most of the risk management resources during response planning and risk
monitoring/control. Risks located in the yellow cells are the next highest priority, followed by
lowest priority risks in the green cells.
Probability
Very High
.90
High
.70
Probable
.50
Low
.30
Very Low
.10
.05
Very Low
.10
Low
.20
Moderate
.40
High
.80
Very High
Impact
Table 4 – Probability and Impact Matrix
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 P a g e | 8
RESPONSE PLANNING
Background
Response planning includes strategies and plans to manage risks to an acceptable level.
Risk Strategies
Risk Avoidance - Parts of the overall project management plan may need to be eliminated
to alleviate the threat, segregate objectives from the risk’s impact, or
alter the schedule. By early identification of risks, they can be avoided
much more easily.
Risk Transference – Directing the negative risks toward a third party would relieve the
organization from the burden brought about by risks. Alternatives
include insurance, vendors, or contractors.
Risk Mitigation - Reducing risks to acceptable levels when possible. Consulting subject
matter experts and the project manager is required.
Risk Acceptance – Reserves for time and costs should be set aside for unforeseen risks that
are encountered.
Documentation
Response planning results will be documented in the risk register. The following information will
be included in the register:
ď‚· Response strategy (avoid, transfer, mitigate, or accept)
ď‚· Response notes (description of plan)
ď‚· Risk owner
Risk
Human Resource Software Implementation
Dav id D. Bustin Version 1.0 P a g e | 9
RISK MONITORING AND CONTROL
Background
Monitoring for identified risks, identify new risks, and ensuring execution of planned risk
responses and evaluating overall effectiveness of the risk management plan in order to reduce risk
to the lowest possible level is the ongoing process for the entire project. Risks should be assigned
an owner which will report on the status during weekly meetings until resolved. All risks will be
entered into the risk register. Re-prioritization of risks may be necessary upon discovery and
evaluation of the particular risks. The new risk will be categorized, assigned a risk score, and
entered into a probability-impact matrix. Monitoring and control tasks will include the following:
ď‚· Maintain a record of identified risks and monitor trigger conditions
ď‚· Examine project performance
ď‚· Re-evaluate predefined risks to determine if the probability, impact, or
proper response plan has changed
ď‚· Assess the execution of risk responses and analyze their effectiveness
ď‚· Ensure organizational risk management policies are applied
ď‚· Identify, analyze, and plan for undiscovered risks
Timing
The risk monitoring and control process will continue throughout the lifetime of the project.
Specifically, the schedule of risk reporting, re-evaluation, and review will occur no less than at the
end of each implementation phase for the human resource information systems. In the event
major risk, cost, or schedule delays occur, a project re-evaluation will be conducted immediately.
Documentation
The results of risk monitoring and control should be documented in the risk register. The
following information shall be entered in the register:
 Status – valid statuses are:
 Identified – Risk documented, but analysis not performed
 Analysis Complete – Risk analysis done, but response planning not
performed
 Planning Complete – Response planning complete
 Triggered – Risk trigger has occurred and threat has been realized
 Resolved – Realized risk has been contained
 Retired – Identified risk no longer requires active monitoring

Weitere ähnliche Inhalte

Was ist angesagt?

Organizational influences and project life cycle
Organizational influences and project life cycleOrganizational influences and project life cycle
Organizational influences and project life cycleAli Adil
 
Project Risk Management PMBOK
Project Risk Management PMBOKProject Risk Management PMBOK
Project Risk Management PMBOKGeoDiga
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Agus Suhanto
 
12.0 Project Procurement Management Overview
12.0 Project Procurement Management Overview12.0 Project Procurement Management Overview
12.0 Project Procurement Management OverviewDavidMcLachlan1
 
9.1 Plan Resource Management
9.1 Plan Resource Management9.1 Plan Resource Management
9.1 Plan Resource ManagementDavidMcLachlan1
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Agus Suhanto
 
Develop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow DiagramDevelop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow Diagramriosabel
 
Risk Assessment Step PowerPoint Presentation Slides
Risk Assessment Step PowerPoint Presentation SlidesRisk Assessment Step PowerPoint Presentation Slides
Risk Assessment Step PowerPoint Presentation SlidesSlideTeam
 
How to set up initiatives portfolio management
How to set up initiatives portfolio managementHow to set up initiatives portfolio management
How to set up initiatives portfolio managementJuha-Matti Saario
 
Project Estimating Process
Project Estimating Process Project Estimating Process
Project Estimating Process Crystal Guliford
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Risk-management
 Risk-management Risk-management
Risk-managementUmesh Gupta
 
Risk Management Outline PowerPoint Presentation Slides
Risk Management Outline PowerPoint Presentation SlidesRisk Management Outline PowerPoint Presentation Slides
Risk Management Outline PowerPoint Presentation SlidesSlideTeam
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementAbdullah Ahmed, PMP, RMP
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Agus Suhanto
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisBPUG Congress
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio ManagementAnand Subramaniam
 

Was ist angesagt? (20)

Project Charter
Project CharterProject Charter
Project Charter
 
Organizational influences and project life cycle
Organizational influences and project life cycleOrganizational influences and project life cycle
Organizational influences and project life cycle
 
Project Risk Management PMBOK
Project Risk Management PMBOKProject Risk Management PMBOK
Project Risk Management PMBOK
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6
 
12.0 Project Procurement Management Overview
12.0 Project Procurement Management Overview12.0 Project Procurement Management Overview
12.0 Project Procurement Management Overview
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
9.1 Plan Resource Management
9.1 Plan Resource Management9.1 Plan Resource Management
9.1 Plan Resource Management
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
Develop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow DiagramDevelop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow Diagram
 
Risk Assessment Step PowerPoint Presentation Slides
Risk Assessment Step PowerPoint Presentation SlidesRisk Assessment Step PowerPoint Presentation Slides
Risk Assessment Step PowerPoint Presentation Slides
 
How to set up initiatives portfolio management
How to set up initiatives portfolio managementHow to set up initiatives portfolio management
How to set up initiatives portfolio management
 
Project Estimating Process
Project Estimating Process Project Estimating Process
Project Estimating Process
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Risk-management
 Risk-management Risk-management
Risk-management
 
Risk Management Outline PowerPoint Presentation Slides
Risk Management Outline PowerPoint Presentation SlidesRisk Management Outline PowerPoint Presentation Slides
Risk Management Outline PowerPoint Presentation Slides
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon Lewis
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio Management
 

Ă„hnlich wie Risk management plan for Human Resource Software

Risk management plan tyre recycling plant
Risk management plan  tyre recycling plantRisk management plan  tyre recycling plant
Risk management plan tyre recycling plantabhishekthakur309
 
HC Data Pro Risk Management Plan
HC Data Pro Risk Management PlanHC Data Pro Risk Management Plan
HC Data Pro Risk Management PlanLaura Aviles
 
Risk management-plan template
Risk management-plan templateRisk management-plan template
Risk management-plan templateVivek Srivastava
 
Project management course for MSC students Chapter 4 and 5
Project management course for MSC students Chapter 4 and 5Project management course for MSC students Chapter 4 and 5
Project management course for MSC students Chapter 4 and 5Abebaw31
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfmohamed Ismail
 
Risk based thinking
Risk based thinkingRisk based thinking
Risk based thinkingRanjeet Singh
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentationRaven Morgan
 
Intex Company, IT infrastructure construction project State of M
Intex Company, IT infrastructure construction project State of MIntex Company, IT infrastructure construction project State of M
Intex Company, IT infrastructure construction project State of MTatianaMajor22
 
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docx
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docxProject Name Risk Management PlanVersion 1.0 Error! Unkno.docx
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docxwkyra78
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxMehediHasan636262
 
Chap007
Chap007Chap007
Chap007maisuradi
 
Project risk management
Project risk managementProject risk management
Project risk managementBarnatuCoffee
 
· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docxalinainglis
 
Risk management
Risk managementRisk management
Risk managementbipulpwc
 
Pmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk ManagementPmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk ManagementHossam Maghrabi
 
1Contents1 Introduction21.1 Project Description21.2
1Contents1 Introduction21.1 Project Description21.2 1Contents1 Introduction21.1 Project Description21.2
1Contents1 Introduction21.1 Project Description21.2 EttaBenton28
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enVyacheslav Guzovsky
 

Ă„hnlich wie Risk management plan for Human Resource Software (20)

Risk management plan tyre recycling plant
Risk management plan  tyre recycling plantRisk management plan  tyre recycling plant
Risk management plan tyre recycling plant
 
HC Data Pro Risk Management Plan
HC Data Pro Risk Management PlanHC Data Pro Risk Management Plan
HC Data Pro Risk Management Plan
 
Risk management-plan template
Risk management-plan templateRisk management-plan template
Risk management-plan template
 
Project management course for MSC students Chapter 4 and 5
Project management course for MSC students Chapter 4 and 5Project management course for MSC students Chapter 4 and 5
Project management course for MSC students Chapter 4 and 5
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdf
 
Risk based thinking
Risk based thinkingRisk based thinking
Risk based thinking
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
Intex Company, IT infrastructure construction project State of M
Intex Company, IT infrastructure construction project State of MIntex Company, IT infrastructure construction project State of M
Intex Company, IT infrastructure construction project State of M
 
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docx
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docxProject Name Risk Management PlanVersion 1.0 Error! Unkno.docx
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docx
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Chap007
Chap007Chap007
Chap007
 
Project risk management
Project risk managementProject risk management
Project risk management
 
· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx
 
Risk management
Risk managementRisk management
Risk management
 
Pmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk ManagementPmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk Management
 
1Contents1 Introduction21.1 Project Description21.2
1Contents1 Introduction21.1 Project Description21.2 1Contents1 Introduction21.1 Project Description21.2
1Contents1 Introduction21.1 Project Description21.2
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_en
 
PMP_Project Risk Management
PMP_Project Risk ManagementPMP_Project Risk Management
PMP_Project Risk Management
 

Mehr von David Bustin

Security Analysis Findings and Recommendations for the Department of Veterans...
Security Analysis Findings and Recommendations for the Department of Veterans...Security Analysis Findings and Recommendations for the Department of Veterans...
Security Analysis Findings and Recommendations for the Department of Veterans...David Bustin
 
Risk Breakdown Structure by David Bustin
Risk Breakdown Structure by David BustinRisk Breakdown Structure by David Bustin
Risk Breakdown Structure by David BustinDavid Bustin
 
Risk governance by David Bustin
Risk governance by David BustinRisk governance by David Bustin
Risk governance by David BustinDavid Bustin
 
Project Management: Integrating a PMO Case Study by David Bustin
Project Management: Integrating a PMO Case Study by David BustinProject Management: Integrating a PMO Case Study by David Bustin
Project Management: Integrating a PMO Case Study by David BustinDavid Bustin
 
Managing IT projects by David Bustin
Managing IT projects by David BustinManaging IT projects by David Bustin
Managing IT projects by David BustinDavid Bustin
 
Business it and labor strategy infrastructure enhancements to achieve corpora...
Business it and labor strategy infrastructure enhancements to achieve corpora...Business it and labor strategy infrastructure enhancements to achieve corpora...
Business it and labor strategy infrastructure enhancements to achieve corpora...David Bustin
 
Case Problem for Global Finance, Inc.
Case Problem for Global Finance, Inc.Case Problem for Global Finance, Inc.
Case Problem for Global Finance, Inc.David Bustin
 
My Risk Assessment and Mitigation Strategy by David Bustin
My Risk Assessment and Mitigation Strategy by David BustinMy Risk Assessment and Mitigation Strategy by David Bustin
My Risk Assessment and Mitigation Strategy by David BustinDavid Bustin
 

Mehr von David Bustin (8)

Security Analysis Findings and Recommendations for the Department of Veterans...
Security Analysis Findings and Recommendations for the Department of Veterans...Security Analysis Findings and Recommendations for the Department of Veterans...
Security Analysis Findings and Recommendations for the Department of Veterans...
 
Risk Breakdown Structure by David Bustin
Risk Breakdown Structure by David BustinRisk Breakdown Structure by David Bustin
Risk Breakdown Structure by David Bustin
 
Risk governance by David Bustin
Risk governance by David BustinRisk governance by David Bustin
Risk governance by David Bustin
 
Project Management: Integrating a PMO Case Study by David Bustin
Project Management: Integrating a PMO Case Study by David BustinProject Management: Integrating a PMO Case Study by David Bustin
Project Management: Integrating a PMO Case Study by David Bustin
 
Managing IT projects by David Bustin
Managing IT projects by David BustinManaging IT projects by David Bustin
Managing IT projects by David Bustin
 
Business it and labor strategy infrastructure enhancements to achieve corpora...
Business it and labor strategy infrastructure enhancements to achieve corpora...Business it and labor strategy infrastructure enhancements to achieve corpora...
Business it and labor strategy infrastructure enhancements to achieve corpora...
 
Case Problem for Global Finance, Inc.
Case Problem for Global Finance, Inc.Case Problem for Global Finance, Inc.
Case Problem for Global Finance, Inc.
 
My Risk Assessment and Mitigation Strategy by David Bustin
My Risk Assessment and Mitigation Strategy by David BustinMy Risk Assessment and Mitigation Strategy by David Bustin
My Risk Assessment and Mitigation Strategy by David Bustin
 

KĂĽrzlich hochgeladen

A Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docxA Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docxComplianceQuest1
 
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...MyIntelliSource, Inc.
 
Optimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTVOptimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTVshikhaohhpro
 
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...kellynguyen01
 
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICECHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
W01_panagenda_Navigating-the-Future-with-The-Hitchhikers-Guide-to-Notes-and-D...
W01_panagenda_Navigating-the-Future-with-The-Hitchhikers-Guide-to-Notes-and-D...W01_panagenda_Navigating-the-Future-with-The-Hitchhikers-Guide-to-Notes-and-D...
W01_panagenda_Navigating-the-Future-with-The-Hitchhikers-Guide-to-Notes-and-D...panagenda
 
HR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.comHR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.comFatema Valibhai
 
Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...OnePlan Solutions
 
How To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.jsHow To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.jsAndolasoft Inc
 
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfThe Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfkalichargn70th171
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software DevelopersVinodh Ram
 
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...MyIntelliSource, Inc.
 
Salesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantSalesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantAxelRicardoTrocheRiq
 
Unlocking the Future of AI Agents with Large Language Models
Unlocking the Future of AI Agents with Large Language ModelsUnlocking the Future of AI Agents with Large Language Models
Unlocking the Future of AI Agents with Large Language Modelsaagamshah0812
 
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️Delhi Call girls
 
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...harshavardhanraghave
 
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...OnePlan Solutions
 
Software Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsSoftware Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsArshad QA
 
why an Opensea Clone Script might be your perfect match.pdf
why an Opensea Clone Script might be your perfect match.pdfwhy an Opensea Clone Script might be your perfect match.pdf
why an Opensea Clone Script might be your perfect match.pdfjoe51371421
 

KĂĽrzlich hochgeladen (20)

A Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docxA Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docx
 
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
 
Optimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTVOptimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTV
 
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
 
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICECHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
 
W01_panagenda_Navigating-the-Future-with-The-Hitchhikers-Guide-to-Notes-and-D...
W01_panagenda_Navigating-the-Future-with-The-Hitchhikers-Guide-to-Notes-and-D...W01_panagenda_Navigating-the-Future-with-The-Hitchhikers-Guide-to-Notes-and-D...
W01_panagenda_Navigating-the-Future-with-The-Hitchhikers-Guide-to-Notes-and-D...
 
HR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.comHR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.com
 
Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...
 
How To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.jsHow To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.js
 
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfThe Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software Developers
 
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
 
Salesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantSalesforce Certified Field Service Consultant
Salesforce Certified Field Service Consultant
 
Unlocking the Future of AI Agents with Large Language Models
Unlocking the Future of AI Agents with Large Language ModelsUnlocking the Future of AI Agents with Large Language Models
Unlocking the Future of AI Agents with Large Language Models
 
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
 
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
 
Vip Call Girls Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS Live
Vip Call Girls Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS LiveVip Call Girls Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS Live
Vip Call Girls Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS Live
 
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
 
Software Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsSoftware Quality Assurance Interview Questions
Software Quality Assurance Interview Questions
 
why an Opensea Clone Script might be your perfect match.pdf
why an Opensea Clone Script might be your perfect match.pdfwhy an Opensea Clone Script might be your perfect match.pdf
why an Opensea Clone Script might be your perfect match.pdf
 

Risk management plan for Human Resource Software

  • 1. David Bustin [Company Address] Tel: Fax: 706 555 - 0100 706 555 - 0199 [Company E-mail] July 14, 2017 Version 1.0 David D. Bustin Risk Management Plan Human Resource Software Implementation
  • 2. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 II REVISIONS AND DISTRIBUTION Revision Release date Distributed to* Client Consultant DBMainoffice(s) Allprojectmgmt.dept. Sub-contractors Suppliers Rev. 0 (draft) 14/07/2017 *) Detailed distribution lists will beprepared for each distribution event. Further details as per the project communication plan Amendments Changes to this plan may periodically occur. Any amendment(s) to this plan shall be communicated to the change control board. When submitting changes to the change control board, a change request form must be used. Once approved by the change control board, only the update will be distributed and the complete revised document will be located internally.
  • 3. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 III PROJECT SPONSOR APPROVAL Prepared by: Reviewed by: Approved by Proj. Sponsor: 14/07/2017 Place, dd/mm/yyyy Place, dd/mm/yyyy David D. Bustin Designation Name Designation Name Designation
  • 4. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 IV TABLE OF CONTENTS Revisions and Distribution……………………….………………..…………………………………………………..II Amendments……………………..…………………..………………………………………………………....II Project Sponsor Approval……………………………..…………………….…………………………………..……III Table of Contents………………………………………………………………….……………………………………..IV 1. Introduction 1.1 Purpose................................................................................................................1 1.2 Intended Audience..............................................................................................1 1.3 Risk Management Approach...............................................................................2 1.3.1 Risk Identification........................................................................................2 1.3.2 Risk Analysis ................................................................................................2 1.3.3 Response Planning ......................................................................................2 1.3.4 Risk Monitoring and Control .......................................................................2 2. Roles and Responsibilities 2.1 Project Manager..................................................................................................3 2.2 Project Team .......................................................................................................3 2.3 Software Quality Assurance Lead…...……………………………………………………………...3 2.4 Project Sponsors..................................................................................................3 2.5 Project Stakeholders……………………………………………………………………………………….3 3. Risk Identification 3.1 Background…………………………………………………………………………………………………….4 3.2 Risk Categories…………………….…………………………………………………………………………4 3.2.1 People………………………………………………………………………………………….......……4 3.2.2 Security………………………………………………………………………………………......……..4 3.2.3 Technical..……………………………………………………………….…………………….………..4 3.3 Sources…………………………………………………………………………………..…………….………..4 3.4 Documentation…………………………………………………………………………………......………4 3.5 Risk Categories Table………………………………………………………………………………………5 4. Risk Analysis 4.1 Background…………………………………………………………………………………………………….6 4.1.1 Qualitative Analysis…………………………………………………………………………………6
  • 5. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 V 4.2 Documentation……..............................................................................................6 4.3 Probability and Impact Matrix………………………...………………………………………………7 5. Response Planning 5.1 Background.……………………………….…………………………………………………………………...8 5.2 Risk Strategies......................................................................................................8 5.2.1 Risk Avoidance.............................................................................................8 5.2.2 Risk Transference........................................................................................8 5.2.3 Risk Mitigation.............................................................................................8 5.2.4 Risk Acceptance...........................................................................................8 5.3 Documentation...………………………………………………………….………………………………….8 6. Risk Monitoring and Control 6.1 Background..........................................................................................................9 6.2 Timing..................................................................................................................9 6.3 Documentation……………………………………………………………………………………………….9 List of Tables and Figures Figure 1 - Risk Management Model……………………………….………………………………………...….…2 Table 1 - Risk Categories……………………………………………….…………………………………………….….5 Table 2 - Risk Probability Definitions….…………………....….………………………………………….….….6 Table 3 - Risk Impact Definitions…....……….......…………….………………………………………….….….6 Table 4 - Probability and Impact Matrix..............................................................................7
  • 6. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 P a g e | 1 INTRODUCTION The risk management plan is an element of the project management plan that provides a view of the risks and the organizations structured approach to handling them. Purpose The purpose of this plan is to prioritize and document risk through identification, categorization, analysis, response planning, and risk definitions for integrating new human resources software. Introducing new software brings challenges not only for the IT staff but also end users in the human resources department. Identifying all potential risks is impossible. The risk management plan will provide a guidance for handling known risks before they occur and unknown risks as they occur. Intended Audience This risk management plan is intended to provide guidance for the IT staff, project and functional managers, executives, project team members, contractors and subcontractors, and other project sponsors or stakeholders.
  • 7. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 P a g e | 2 RISK MANAGEMENT APPROACH Risk Identification All known risks and their associated strategies should be communicated in the beginning of the project or as soon as possible. Continuous attention must be given to potential risks and once identified, that risks will be categorized. Risk owners and appropriate strategies will be assigned. Risk identification will include the source of risk, risk events, and risk indicators. Strategies to handle individual risks will be incorporated into the response planning and monitoring procedures. Risk Analysis In risk analysis, a qualitative risk analysis will be conducted to determine the probability of occurrence and impact to the project if the risk materialized. Response Planning During response planning, risk management and contingency plans will be developed. Strategies for handling each risk will be developed by the assigned risk owner. The approaches used in risk response are avoidance, transference, mitigation, and acceptance. Risk Monitoring and Control Action plans will be created, integrated, and monitored during the response planning phase. During risk monitoring and control, corrective action plans are developed, implemented, and monitored. Figure 1 RiskManagement Model
  • 8. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 P a g e | 3 ROLES AND RESPONSIBILITIES CEO The CEO approves or disapproves investments and funding for projects. Also, he/she decides the project organization structure. Steering Committee The steering committee ensures the quality and timeliness of the project. They provide advice and often decisions on project alterations. Specifically, they will align the IT strategy with organizational goals. Project Manager The project manager is responsible for approval of the risk management plan (this document), leads and participates in the risk management process, and takes ownership of risk mitigation/contingency planning and execution. The project manager is ultimately responsible for the final decision on risk actions, in coordination with the project sponsors. Project Team Project team members (analysts/product managers, developers, testers, and deployment team members) participate in the risk identification process and discuss risk monitoring and mitigation activities at team meetings. Carries out the activities for project completion Software Quality Assurance Lead The software quality assurance (SQA) lead is responsible for ensuring identified risks are being managed per the risk management plan. The SQA lead also assist in identifying new risks and/or proposing mitigation strategies and contingency plans, along with proposing improvements to the risk management plan and processes. Project Sponsors Project sponsors participate in risk identification and risk activities, as necessary. Project sponsors also receive escalated risks and assist with mitigation and contingency actions for escalated risks. Project Stakeholders Stakeholders assist in monitoring risk action effectiveness and participate in risk escalation, as necessary. Audit Team The audit team determines the level of compliance with the defined processes, regulatory mandates, and industry standards.
  • 9. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 P a g e | 4 RISK IDENTIFICATION Background Sources of risks and risk events are developed in the risk identification process. Some risks are known and pre-defined in order to form an orderly process in risk identification throughout the project. Categories of risks may evolve and new risks are developed over the course of the project. After identifying and categorizing the risk event, it is entered into the risk register. Risk Categories The following categories will identify risks. ď‚· People: Inadequate skilled end users, Senior management support, IT staff capability of maintenance and operations ď‚· Security: Confidentiality, Integrity, Availability ď‚· Technical: Compatibility with existing systems, Vendor support and customer service, Configuration tailored to specific organizational policy and procedures Sources The following tools and techniques will be employed for risk identification: ď‚· Team meetings ď‚· Expert interviews ď‚· Analogy comparisons ď‚· Assumptions analysis ď‚· SWOT analysis ď‚· Checklists Documentation All identified risks should be documented and entered into the risk register. During risk identification, the following information is required for documentation: ď‚· Risk category ď‚· Risk trigger ď‚· Potential outcome ď‚· Source
  • 10. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 P a g e | 5 Table 1 – Risk Categories Reference Number Risk Risk Category Risk Trigger Potential Outcome Source 1 non-compliance in reporting Technical System failed in compliance reporting to regulatory agencies Sarbanes-Oxley Compliance Audit ExpertInterviews, Analogy Comparisons 2 No application security Security Network Breach Employee’s personal data stolen Expert Interviews Team Meetings SWOT Analysis 3 Performance reviews not submitted Technical Notification failures Employees receive late performance evaluations Team Meetings 4 Inadequately skilled staff People Unable to complete task accurately and on time Employee morale Team Meetings, Analogy Comparisons, Assumptions Analysis 5 Financial abuse People Improper separation of duties Fraud Analogy Comparisons 6 Discriminatory practices, unsuitable candidates selected People Unethical hiring Potential lawsuits, negative public relations, loss of business, fines. Checklists
  • 11. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 P a g e | 6 RISK ANALYSIS Background The risk score can be calculated after the risk impact and probability are identified. The risk probability and impact matrix is shown below on page 7 of this risk management plan. The matrix illustrates a combination of impact and probability that produce a risk priority. Qualitative Analysis consists of the probability of a risk occurring and that risk’s impact on the project. The potential likelihood that a given risk will occur is assessed, and an appropriate risk probability is selected from the chart below. Probability Category Probability Description Very High 0.90 Risk event expected to occur High 0.70 Risk event more likely than not to occur Probable 0.50 Risk event may or may not occur Low 0.30 Risk event less likely than not to occur Very Low 0.10 Risk event not expected to occur Table 2 – Risk Probability Definitions The below chart displays risk impact definitions for each project area. Project Objective Very Low 0.05 Low 0.10 Moderate 0.20 High 0.40 Very High 0.80 Cost Insignificant cost impact < 10% costimpact 10-20% cost impact 20-40% cost impact > 40% costimpact Schedule Insignificant schedule impact < 5% schedule impact 5-10% schedule impact 10-20% schedule impact > 20% schedule impact Scope Barely noticeable Minor areas impacted Major areas impacted Changes unacceptableto sponsor Product becomes effectively useless Quality Barely noticeable Only very demanding applications impacted Sponsor must approve quality reduction Quality reduction unacceptableto sponsor Product becomes effectively useless Table 3 – Risk Impact Definitions Documentation Risk analysis results are documented in the risk register. Information shall be entered in the register: ď‚· Risk impact ď‚· Risk probability ď‚· Risk matrix score ď‚· Risk priority – computed by the risk register spreadsheet after impact and probability are entered ď‚· Qualitative impact – descriptive comments about the potential risk impact
  • 12. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 P a g e | 7 PROBABILITY AND IMPACT MATRIX Different levels of risk probability and impact should be specific to the individual project. The risk probability and impact matrix illustrate a combination of risk impact and probability. The result of the matrix enables risks prioritization. Red cells in the matrix are the highest priority which should receive the most of the risk management resources during response planning and risk monitoring/control. Risks located in the yellow cells are the next highest priority, followed by lowest priority risks in the green cells. Probability Very High .90 High .70 Probable .50 Low .30 Very Low .10 .05 Very Low .10 Low .20 Moderate .40 High .80 Very High Impact Table 4 – Probability and Impact Matrix
  • 13. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 P a g e | 8 RESPONSE PLANNING Background Response planning includes strategies and plans to manage risks to an acceptable level. Risk Strategies Risk Avoidance - Parts of the overall project management plan may need to be eliminated to alleviate the threat, segregate objectives from the risk’s impact, or alter the schedule. By early identification of risks, they can be avoided much more easily. Risk Transference – Directing the negative risks toward a third party would relieve the organization from the burden brought about by risks. Alternatives include insurance, vendors, or contractors. Risk Mitigation - Reducing risks to acceptable levels when possible. Consulting subject matter experts and the project manager is required. Risk Acceptance – Reserves for time and costs should be set aside for unforeseen risks that are encountered. Documentation Response planning results will be documented in the risk register. The following information will be included in the register: ď‚· Response strategy (avoid, transfer, mitigate, or accept) ď‚· Response notes (description of plan) ď‚· Risk owner
  • 14. Risk Human Resource Software Implementation Dav id D. Bustin Version 1.0 P a g e | 9 RISK MONITORING AND CONTROL Background Monitoring for identified risks, identify new risks, and ensuring execution of planned risk responses and evaluating overall effectiveness of the risk management plan in order to reduce risk to the lowest possible level is the ongoing process for the entire project. Risks should be assigned an owner which will report on the status during weekly meetings until resolved. All risks will be entered into the risk register. Re-prioritization of risks may be necessary upon discovery and evaluation of the particular risks. The new risk will be categorized, assigned a risk score, and entered into a probability-impact matrix. Monitoring and control tasks will include the following: ď‚· Maintain a record of identified risks and monitor trigger conditions ď‚· Examine project performance ď‚· Re-evaluate predefined risks to determine if the probability, impact, or proper response plan has changed ď‚· Assess the execution of risk responses and analyze their effectiveness ď‚· Ensure organizational risk management policies are applied ď‚· Identify, analyze, and plan for undiscovered risks Timing The risk monitoring and control process will continue throughout the lifetime of the project. Specifically, the schedule of risk reporting, re-evaluation, and review will occur no less than at the end of each implementation phase for the human resource information systems. In the event major risk, cost, or schedule delays occur, a project re-evaluation will be conducted immediately. Documentation The results of risk monitoring and control should be documented in the risk register. The following information shall be entered in the register: ď‚· Status – valid statuses are: ď‚· Identified – Risk documented, but analysis not performed ď‚· Analysis Complete – Risk analysis done, but response planning not performed ď‚· Planning Complete – Response planning complete ď‚· Triggered – Risk trigger has occurred and threat has been realized ď‚· Resolved – Realized risk has been contained ď‚· Retired – Identified risk no longer requires active monitoring