1
RIVER MARKET TRANSIT HUB
ARCH 609 | SPRING 2016 | PADGET
MATT KENNEY | LUKE MCELWAIN | CULIN THOMPSON
2
3
Project Thesis
Context
Precedents
Pre-Design Phase
Schematic Design Phase
Design Development Phase
Wall Sections
Living Building + Well Building Challenge
Final Reflections
4
6
12
16
22
28
50
58
84
4
	 The River Market Transit Hub serves as a staple for the greater Kansas
City Metropolitan area. A beacon of the future of mass transit and sustainabil-
ity, this net-zero living building combines the benefits of transit-oriented com-
munities, offices, retail, luxury living and community assets. This combination
of combining live work and providing commuters with centralized amenities
they currently utilize generates a new model of efficiency within transit devel-
opment and office construction.
	 Focused around a modern, realistic and simple design, the River Mar-
ket Transit Hub utilizes centralized atria to allow daylighting, ventilation and
views throughout the complex. As the complex circulates the site edges, its
three buildings each carry this atria language - following a pattern of decen-
tralizing from the center atria of the eastern-most building.
	 The future of transit-oriented development requires creating an ex-
perience that is as user-friendly as is it accessible. The need for child care
facilities, dry cleaners, restaurants, fast food facilities, local business retail
opportunities, parking, commuter and light rail, bus connections, health facili-
ties, coffee shops, community facilities and convenience stores only increas-
es as sprawl and the average commute time to work continues to increase.
Through combining the daily trips of workers within the Kansas City down-
town district, the River Market Transit Hub is able to minimize the time individ-
uals spend commuting and running errands - granting additional family time
and community time. This time allows for the building of a diverse economy,
happy family networks and healthy communities; it is essential towards the
continued growth and development of our cities and the River Market Transit
Hub is proud to offer this to Kansas City.
PROJECT THESIS
5
6
	 When researching the historical significance of this site, one of the
greatest finds was that it initially was developed as a brewery in the late
1800s and early 1900s. The brewery changed hands multiple times and
went through various names but Pabst at one point was an owner. Having
been in an industry driven part of town, this site had constant traffice typical-
ly drawing from the crowds at the city trading center and market across the
street. Travelers would typically come from the river and offer goods that they
brought from various places.
	 Having such a great histrorical significance with a brewery, we decided
to make the design decision to bring a brewery back to the site. Using this
idea allowed us to create a specific anchor in our desitination which would
bring people in at all times of the day. This additionally provides jobs and al-
lows for a product unique to this location to be sold regionally and nationwide
if desired. The brewery includes a restaurant as well.
SITE HISTORY
7
8
9
COLD STORAGE LOFTS
CHINESE FOOD MARKET
HISTORIC CITY MARKET
10
	 The site currently serves as and will
continue to be focused as a center of trans-
portation. In the past, this lot had been fo-
cused on a street car and often serving
as outdoor market space which held large
crowds in addition to the city market across
the corner. Currently the site is a parking lot for
commuters who use the new light rail station,
the MegaBus, the local bus systems, or walk
to local businesses and attractions. The prop-
erty is owned by the Kansas City Area Trans-
portation Authority.
	 Part of redeveloping the site is to keep
the destination focused using transit oriented
design. In future planning, a commuter rail is
planned to arrive at this station to the north.
With this site continuing to serve many com-
muters, we used this as an opportunity to
drive our design decisions. Some of these in-
cluded a ground level transit hub, a bus pass
through in the site by repurposing Oak St.,
bicycle storage and showers, shaded seating
and waiting areas, underground parking, and
ground level retail and amenities.
TRANSPORTATION
11
STREETCARLINE
BUSLINE
COMMUTER RAIL
12
564 Beatty was particularly studied
for the south facing facade as well
as the structure in relation to the of-
fice layout. We studied how the cur-
tain wall system used metal paneling
as spandrels as well as overhanging
louvers to block particular angles of
sunlight. We further studied the idea
conditions for our region using Se-
faira. Additionally, we examined the
structural grid which was 30’ x 30’,
the same spacing we used, as to
how this informs the office arrange-
ment.
PRECEDENTS
564 BEATTY
Vancouver, BC, Canada
13
The ETFO Building had a few signif-
icant contributions to our research
and conceptual design. One of the
concepts that we found interesting
was the folded skin and overhang
that provided shade and thermal
mass to the structure. Additionally,
we focused on the cross and stack
ventilation techniques used to draw
air up the atrium and across the
office floor plates.
ETFO BUILDING
Toronto, Ontario, Canada
14
When examining the Center for
Interactive Research on Sustain-
ability, the element that stood out
to us most was the atrium space.
This design exposes the structure,
particularly beams, and provides a
quick reference to the vertical circu-
lation taking place. Additionally, the
space uses stack ventilation and
is well lit thus making the atrium a
celebrated feature which we used to
inform our design.
CENTER FOR INTERACTIVE
RESEARCH ON SUSTAINABILITY
Vancouver, BC, Canada
15
The Sage VIP Building was a driving
example of form for our west build-
ing on the site. We studied the way
that the shade structure and inset
balconies allowed for outdoor gath-
ering and used these concepts to
provide space and shade for people
gathering outside of the transporta-
tion hub or the local office spaces.
SAGE VIP BUILDING
Pretoria, South Africa
16
KENNEY SCHEME
17
18
THOMPSON SCHEME
	 Focused around a central
courtyard, this initial scheme de-
veloped upon providing a closed
facade along third street to maximize
upon the retail potential a transit-fo-
cused street.
	 The additional emphasis upon
having an occupiable rooftop to pro-
vide views to Kansas City drove the
rooftop occupancy availability and
voids to allow for natural daylighting
and ventilation.
19
20
McELWAIN SCHEME
	 Opening the corner to the Riv-
er Market provides access and an
open square for the visitors to create
a space for people to occupy and
explore. The buildings are optimized
for lighting and ventilation.
	
	 The addition of businesses
and ammeneties in this development
support the people that are already
in the area as well as the new-com-
ers from the light rail and the future
commuter rail.
21
22
STRUCTURE
SCHEMATIC DESIGN
23
PROGRAM
24
1STLEVEL FLOOR PLAN
5TH LEVEL FLOOR PLAN
	 Raised access floor provide
flexible open office floor plans and
allow for direct and personalized
ventilation systems and thermal
comfort. The integration of the bar
as a focal point highlights the devel-
opment as a unique landmark within
the Kansas City region and provides
a way to build and promote commu-
nity.
	 The preservation of Oak Street
on the site as a through-way for bus
circulation generates a closed pe-
destrian plaza level, while the intro-
duction of a secondary street for car
circulation between the development
and the Cold Storage building pro-
vides both circulation and a buffer
between the two developments.
25
OR PLAN
RETAIL RETAIL
ATRIUM
RETAIL
RETAIL
OFFICE
OR PLAN
BREWERY LOFTS LOFTS
26
STEEL STRUCTURE
BEAMS: W18 X 40 WIDE FLANGE
COLUMNS: W14X176 WIDE FLANGE
27
The structure of the building is steel I
beams. The heirarchy of structure car-
rys a 30 foot bay pattern and this allows
for optimum renting and layout space
for the clients renting the space. The
structure carrys all the way down to the
ground through the concrete parking
structure.
The floors of the building are built from
concrete decking over a metal deck.
The floor space is largely optimised to
allow for air flow and sunlight penetra-
tion for better work and living environ-
ments.
Walls of the buildings are R-40 for opti-
mum thermal breaking from the exte-
rior. The glass walls are double paned
argon filled allowing the sin exposure to
be reduced.
The HV/AC system is largely under-
floor for the office and the residences
and the atriums will be conditioned by
forced air.
Sloar arrays on the top of the north and
south buildings will power the whole
site.
28
DESIGN DEVELOPMENT
29
ROOF/SITE PLAN
SCALE: 1”=30’
1
2
3
4
5
PARKING RAMP
PLAZA
PV ARRAY
COLD STORAGE LOFTS
ASIAN MARKET
6
7
8
9
10
STREETCAR STOP
ONE-WAY BUS DRIVE
POWER PLANT
COMMUNITY GARDEN
POOL
KEY
1
2
3
4
5
6
7
8
9
10
11 ROOFTOP BAR
11
GRANDAVENUE
3RD STREET
12 CITY MARKET
12
13 COMMUTER RAIL STOP
13
30
31
32
33
34
JIHGFEDCB
1
2
3
5
4
19
A109
DN
REF.
REF.
JIHGFEDCB
1
2
3
5
A
2
A109
4
DN
REF.
UP
JIHGFEDCB
1
2
3
5
A
4
REF.
UP
WWH
REF.
WWH
REF.
WWH
REF.
WWH
REF.
WWH
REF.
WWH
REF.
WWH
REF.
WWH
REF.
WH
W W REF.
WH
WWREF.
WH
WW
W REF.WREF. WREF. W REF. WREF. W REF.
UP
DN
JIHGFEDCB
1
2
3
5
K L M NA
2
A109
4
19
A109
A109
12
A109
13
A109
14
FIRST FLOOR PLAN
SCALE: 1/16”=1’
THIRD FLOOR PLAN
SCALE: 1/16”=1’
FIFTH FLOOR PLAN
SCALE: 1/16”=1’
SIXTH FLOOR PLAN
SCALE: 1/16”=1’
14
15
16 17
18 19
20
21
2223
24 25
18000	
28800	
25200	
7000	
25500	
8100	
NORTH	BUILDING	
Retail	 Office	 Residen4al		 Mechanical	 Circula4on	 Transit	
8100	
41400	
4500	
3600	
14400	
10800	
EAST	BUILDING	
Retail	 Office	 Mechanical	 Circula4on	 Gym	 Transit	
	 The north building incorpo-
rates services and amenities for
the transit hub in addition to office
space. Offering a childcare facility,
dry cleaners, restaurants, bar and
office space the northern building
integrates the live-work mentality of
millennials and future mixed use city
design.
35
WH
WH
WH
WH
WHH
UNIT LAYOUT A
SCALE: 1/8”=1’
UNIT LAYOUT B
SCALE: 1/8”=1’
UNIT LAYOUT C
SCALE: 1/8”=1’
14
15
16
17
18
BICYCLE STORAGE / SHOWERS
LOCAL BUSINESS RETAIL
FREIGHT ELEVATOR
MECHANICAL ROOM
FOOD RETAIL
19
20
21
22
23
DRY CLEANERS
OFFICE SPACE
OFFICE SPACE
BREWERY RESTAURANT
BREW AREA / KITCHEN
KEY
24 ROOFTOP BAR
25 LUXURY LOFTS
36
37
38
EDCBA
Level 2
18' - 5"
Level 3
31' - 5"
Level 4
44' - 5"
Level 5
57' - 5"
Level 6
70' - 5"
Level 7
80' - 5"
Level 8
90' - 5"
Level 1
0' - 5"
Level 9
100' - 5"
1 2 3 5
Parking 1
-11' - 0"
Parking 2
-22' - 0"
Parking 3
-33' - 0"
Parking 4
-44' - 0"
Level 2
18' - 5"
Level 3
31' - 5"
Level 4
44' - 5"
Level 5
57' - 5"
Level 6
70' - 5"
Level 7
80' - 5"
Level 8
90' - 5"
4
Level 9
100' - 5"
BUILDING SECTION
SCALE: 1/16”=1’
39
JIHGF K L M N
Parking 1
-11' - 0"
Parking 2
-22' - 0"
Parking 3
-33' - 0"
Parking 4
-44' - 0"
Level 2
18' - 5"
Level 3
31' - 5"
Level 4
44' - 5"
Level 5
57' - 5"
Level 6
70' - 5"
Level 7
80' - 5"
Level 8
90' - 5"
Level 1
0' - 5"
Level 9
100' - 5"
BUILDING SECTION
SCALE: 1/16”=1’
40
41
8100	
41400	
4500	
3600	
14400	
10800	
EAST	BUILDING	
Retail	 Office	 Mechanical	 Circula4on	 Gym	 Transit
42
26
27
28
29
30
TRANSPORTATION TICKET COUNTER
BUS WAITING AREA
CAFE/ COMPUTER LOUNGE
MECHANICAL ROOM
BASKETBALL COURT
31
32
33
34
35
LOCKER ROOM
GYM
OPEN OFFICE
YOGA STUDIO
BANQUET/EVENT ROOM
KEY
36 ROOFTOP GARDEN PLOTS
37 ROOFTOP POOL
38 OUTDOOR TERRACE
UP
UP
UP
UP
11
22
33
55
K L M N
15
9
13
11
8
7
6
4 4
REF
REF.REF.
1
2
3
5
K
K
L
L
M
M
N
N
15
4
FIRST FLOOR PLAN
SCALE: 1/16”=1’
SECOND FLOOR PLAN
SCALE: 1/16”=1’
26
27
28
29 29
30
31
32
32
33
34
43
F.
1
2
3
5
N
N
15
9
13
11
8
7
6
4
11
22
33
55
K
K
L
L
M
M
N
N
1515
9
13
11
8
7
6
4 4
11
22
33
5
K L M N
15
9
11
8
7
6
4 4
THIRD FLOOR PLAN
SCALE: 1/16”=1’
FIFTH FLOOR PLAN
SCALE: 1/16”=1’
2929
33
35
36
37
38
44
1 2 3 5
Parking 1
-11' - 0"
Parking 2
-22' - 0"
Parking 3
-33' - 0"
Parking 4
-44' - 0"
9 11876
Level 2
18' - 5"
Level 3
31' - 5"
Level 4
44' - 5"
Level 5
57' - 5"
Level 6
70' - 5"
Level 7
80' - 5"
Level 8
90' - 5"
Level 1
0' - 5"
4
Level 9
100' - 5"
BUILDING SECTION
SCALE: 1/16”=1’
45
1513
K L M N
Parking 1
-11' - 0"
Parking 2
-22' - 0"
Parking 3
-33' - 0"
Parking 4
-44' - 0"
Level 2
18' - 5"
Level 3
31' - 5"
Level 4
44' - 5"
Level 5
57' - 5"
Level 6
70' - 5"
Level 1
0' - 5"
BUILDING SECTION
SCALE: 1/16”=1’
46
FIRST FLOOR PLAN
SECOND FLOOR
PLAN
47
PARKING LEVEL 1 PLAN
PARKING LEVEL 3 PLAN
48
BUILDING SECTION
49
50
Level 2
18' - 5"
Level 3
31' - 5"
Level 5
57' - 5"
Level 6
70' - 5"
Level 1
0' - 5"
A109
6
1
2
3
4
5
6
7
8
9
10
THOMPSON WALL SECTIONS
1 METAL PANELING
FURING STRIP
ROOF DRAIN
OPERABLE DOORS
GLASS RAILING
SPANDREL PANEL
RAISED ACCESS FLOOR
LIGHT SHELF
DOUBLE PANE GLASS
CONCRETE PANEL
KEY
PV PANELS
METAL PANELING
2
3
4
5
6
7
8
9
10
11
12
13 LOFT PARTITION
51
Level 2
18' - 5"
Level 5
57' - 5"
Level 6
70' - 5"
Level 7
80' - 5"
Level 8
90' - 5"
Level 1
0' - 5"
A109
3
A109
4
A109
5
11
12
13
52
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
22
53
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
ALUMINUM MULLION
SPANDREL PANEL
L-ANGLE BOLTED CONNECTION
FIRE STOP
RAISED CONCERE PANEL
RIGID INSULATION
ANCHOR BOLT
RAISED ACCESS FLOOR
MOISTURE BARRIER
UNISTRUT
L-ANGLE
C-CHANNEL
RIGID INSULATION
FURRING STRIP
LOUVERS
GREEN HANGING STRUCTURE
LIGHT GUAGE STEEL
KEY
54
KENNEY WALL SECTIONS
1 METAL PANELING
FURING STRIP
ROOF DRAIN
OPERABLE DOORS
GLASS RAILING
SPANDREL PANEL
RAISED ACCESS FLOOR
DOUBLE PANE GLASS
CONCRETE PANEL
KEY
METAL PANELING
2
3
4
5
6
7
8
9
10
11
12
13
14
15
ALUMINUM MULLION
BENT METAL FLASHING
16
17
18
19
L-ANGLE BOLTED CONNECTION
RAISED CONCERTE PANEL
RIGID INSULATION
ANCHOR BOLT
MOISTURE BARRIER
UNISTRUT
L-ANGLE
3
20 FIBER EXPANSION JOINT
K L
Level 2
18' - 5"
Level 3
31' - 5"
Level 4
44' - 5"
Level 5
57' - 5"
Level 1
0' - 5"
1
2
3
7
9
10
12
17
20
8
55
11
14
17
15
K L
Level 2
18' - 5"
Level 3
31' - 5"
Level 4
44' - 5"
Level 5
57' - 5"
Level 1
0' - 5"
---
-
---
-
5
6
10
17
20
56
McELWAIN WALL SECTIONS
57
58
LIVING BUILDING CHALLENGE
59
THIS STANDARD IS AN ACT OF OPTIMISM
AND BELIEF THAT WITH THE RIGHT TOOLS
IN THE HANDS OF PASSIONATE, LITERATE
AND SENSITIVE INDIVIDUALS. A REVOLU-
TIONARY TRANSFORMATION IS POSSI-
BLE. IT IS A PROGRAM THAT ASKS US TO
THINK HOLISTICALLY AND ENGAGE BOTH
OUR RIGHT AND LEFT BRAINS, HEAD AND
HEART.
60
LIVING BUILDING - ENERGY
ROOF/SITE PLAN
SCALE: 1”=30’
1
2
3
4
5
PARKING RAMP
PLAZA
PV ARRAY
COLD STORAGE LOFTS
ASIAN MARKET
6
7
8
9
10
STREETCAR STOP
ONE-WAY BUS DRIVE
POWER PLANT
COMMUNITY GARDEN
POOL
KEY
1
2
3
4
5
6
7
8
9
10
11 ROOFTOP BAR
11
GRANDAVENUE
3RD STREET
12 CITY MARKET
12
13 COMMUTER RAIL STOP
13
61
PV PANELS
Photovoltaic panels allow us to offset the
amount of energy used within the building
to become net positive
WEST SECTION
NATURAL VENTILATION
The use of large open atria throughout the
site maximizes the natural ventilation of
fresh and stale air
OVERHANGS
The integration of large overhangs allows
us to shield the building from a majority of
direct sunlight
Level 5
57' - 5"
Level 6
70' - 5"
SUN SHELVES
Placing sun shelves over glass curtain
walls and integration mullions provides ad-
ditional blockage from direct sun
62
LIVING BUILDING - WATER
ROOF/SITE PLAN
SCALE: 1”=30’
1
2
3
4
5
PARKING RAMP
PLAZA
PV ARRAY
COLD STORAGE LOFTS
ASIAN MARKET
6
7
8
9
10
STREETCAR STOP
ONE-WAY BUS DRIVE
POWER PLANT
COMMUNITY GARDEN
POOL
KEY
1
2
3
4
5
6
7
8
9
10
11 ROOFTOP BAR
11
GRANDAVENUE
3RD STREET
12 CITY MARKET
12
13 COMMUTER RAIL STOP
13
63
PHOTOLUMINESCENT ALGAE
Algae is a critical component of filtering
and conserving water from the brewery -
allowing a more sustainable process
RETENTION PONDS
Integration of retention ponds allows us
to utilize roof-collected water over potable
water
A109
6
STORMWATER COLLECTION
Plugging stormwater into graywater sys-
tems allows for conservation of potable
water within plumbing systems
RAIN GARDENS
Placing biowales and rain gardens on-site
allows the site to begin to filter out toxins
before hitting the streetscape
64
LIVING BUILDING - PLACE
ROOF/SITE PLAN
SCALE: 1”=30’
1
2
3
4
5
PARKING RAMP
PLAZA
PV ARRAY
COLD STORAGE LOFTS
ASIAN MARKET
6
7
8
9
10
STREETCAR STOP
ONE-WAY BUS DRIVE
POWER PLANT
COMMUNITY GARDEN
POOL
KEY
1
2
3
4
5
6
7
8
9
10
11 ROOFTOP BAR
11
GRANDAVENUE
3RD STREET
12 CITY MARKET
12
13 COMMUTER RAIL STOP
13
65
URBAN GARDENING
Encouraging urban agriculture and gar-
dening through community building
BROWNFIELD CONSTRUCTION
Construction on the site of a current park-
ing lot does not damage any wetlands or
natural habitats
HABITAT EXCHANGE
Designating preservations offsite along the
Kansas River help to mitigate the environ-
mental damage from construction
BICYCLE STORAGE
Indoor bicycle storage and showers offer
incentives to bike to work over driving
66
LIVING BUILDING - MATERIALS
RED LIST
Compliance with the red list of banned
materials
LOCAL MATERIALS
Maximization of materials coming from
500 km or less from the site
EPA Chemical of Concern Ban
Ban of any integration of materials made
from chemicals on the US EPA Chemical
of Concern list
RECYCLING MATERIALS
Recycling of waste materials from the site
67
LIVING BUILDING - EQUITY
UNIVERSAL ACCESSIBILITY
Universal access to all public features of
the site including daylight, ventilation and
outdoor amenities
TRANSPORTATION
Incorporation of multi-modal transportation
including private and public mass-transit
AFFORDABLE HOUSING
Integration of affordable housing units and
4% low income housing tax credits to hel-
op finance the project
COMMUNITY BUILDING
Community building features such as a
brewery, urban garden, public plaza and
local business incubation
68
LIVING BUILDING - BEAUTY
ROOF/SITE PLAN
SCALE: 1”=30’
1
2
3
4
5
PARKING RAMP
PLAZA
PV ARRAY
COLD STORAGE LOFTS
ASIAN MARKET
6
7
8
9
10
STREETCAR STOP
ONE-WAY BUS DRIVE
POWER PLANT
COMMUNITY GARDEN
POOL
KEY
1
2
3
4
5
6
7
8
9
10
11 ROOFTOP BAR
11
GRANDAVENUE
3RD STREET
12 CITY MARKET
12
13 COMMUTER RAIL STOP
13
69
PUBLIC GATHERING & ART
Integration of public plazas and integration
of local business and art
BIOPHILIC ENVIRONMENT
Placement of greenery and water features
throughout the project site
EDUCATION
Educational boards and programs about
the sustainable features of the project
RAIN GARDENS
Placing biowales and rain gardens on-site
allows the site to begin to filter out toxins
before hitting the streetscape
70
LIVING BUILDING - HEALTH
ROOF/SITE PLAN
SCALE: 1”=30’
1
2
3
4
5
PARKING RAMP
PLAZA
PV ARRAY
COLD STORAGE LOFTS
ASIAN MARKET
6
7
8
9
10
STREETCAR STOP
ONE-WAY BUS DRIVE
POWER PLANT
COMMUNITY GARDEN
POOL
KEY
1
2
3
4
5
6
7
8
9
10
11 ROOFTOP BAR
11
GRANDAVENUE
3RD STREET
12 CITY MARKET
12
13 COMMUTER RAIL STOP
13
71
OPERABLE WINDOWS
Operable windows provide natural daylight
and ventilation to occupants
TOBACCO BAN
Banning tobacco products on the site
boundary promote healthy living and life-
styles
GREEN WALLS
Green walls help to provide air filtration
and promote the use of atrium stairs
OUTDOOR CONNECTIONS
Direct connections to the exterior balco-
nies of the site provide natural air and en-
vironemntal benefits
72
WELL BUILDING STANDARD
73
We believe that the time has come to
elevate human health and comfort to
the forefront of building practices and
reinvent buildings that are not only
better for the planet—but also for
people.
74
WELL BUILDING - AIR
ROOF/SITE PLAN
SCALE: 1”=30’
1
2
3
4
5
PARKING RAMP
PLAZA
PV ARRAY
COLD STORAGE LOFTS
ASIAN MARKET
6
7
8
9
10
STREETCAR STOP
ONE-WAY BUS DRIVE
POWER PLANT
COMMUNITY GARDEN
POOL
KEY
1
2
3
4
5
6
7
8
9
10
11 ROOFTOP BAR
11
GRANDAVENUE
3RD STREET
12 CITY MARKET
12
13 COMMUTER RAIL STOP
13
75
OPERABLE WINDOWS
Operable windows provide natural daylight
and ventilation to occupants
ADVANCED AIR PURIFICATION
Advanced mechanical and natural air puri-
fication produces cleaner air
INCREASED VENTILATION
Increased and direct sourced ventilation
provides fresher air to the project
CLEANABLE ENVIRONMENT
The use of aluminum paneling for the
walls of the building allows for easy
cleaning methods
76
WELL BUILDING - WATER
ROOF/SITE PLAN
SCALE: 1”=30’
1
2
3
4
5
PARKING RAMP
PLAZA
PV ARRAY
COLD STORAGE LOFTS
ASIAN MARKET
6
7
8
9
10
STREETCAR STOP
ONE-WAY BUS DRIVE
POWER PLANT
COMMUNITY GARDEN
POOL
KEY
1
2
3
4
5
6
7
8
9
10
11 ROOFTOP BAR
11
GRANDAVENUE
3RD STREET
12 CITY MARKET
12
13 COMMUTER RAIL STOP
13
77
PHOTOLUMINESCENT ALGAE
Algae is a critical component of filtering
and conserving water from the brewery -
allowing a more sustainable process
STEAM TAPPING
Tapping into the steam plant adjacent to
the site reduces on-side energy and water
consumption
PUBLIC WATER ADDITIVES
Addition of disinfectants and fluoride into
the water systems
DRINKING WATER PROMOTION
Additional water fountain placement and
promotion of renewable water bottles
78
WELL BUILDING - NOURISHMENT
ROOF/SITE PLAN
SCALE: 1”=30’
1
2
3
4
5
PARKING RAMP
PLAZA
PV ARRAY
COLD STORAGE LOFTS
ASIAN MARKET
6
7
8
9
10
STREETCAR STOP
ONE-WAY BUS DRIVE
POWER PLANT
COMMUNITY GARDEN
POOL
KEY
1
2
3
4
5
6
7
8
9
10
11 ROOFTOP BAR
11
GRANDAVENUE
3RD STREET
12 CITY MARKET
12
13 COMMUTER RAIL STOP
13
79
URBAN GARDENING
Encouraging urban agriculture and gar-
dening through community building
HAND WASHING
Separated hand washing stations to en-
courage sanitary procedures
NUTRITIONAL INFORMATION
Graphic and visual design standards for
food nutritional values in restaurants
RESPONSIBLE FOOD PRODUCTION
Sanitary and responsible separated food pro-
duction zones for all restaurants
80
WELL BUILDING - LIGHT
SOLAR GLARE CONTROL
Solar glare shelves and glazings to pre-
vent glare in workspaces
RIGHT TO LIGHT
Natural daylighting within all spaces max-
imized by a narrow footprint and light
shelves
DAYLIGHT MODELING
Daylight maximization and modeling within
Sefaira
DAYLIGHT FENESTRATION
Windows, shelves and screens incorpo-
rated within the fenestration of individual
wall systems
81
WELL BUILDING - FITNESS
PHYSICAL ACTIVITY SPACES
Integration of a gym within the project to
encourage exercise and a balanced life-
style
STRUCTURED FITNESS
Daily fitness classes to encourage healthy
activity and movement
INTERIOR FITNESS CIRCULATION
Visual stairs integrated within atria to en-
courage healthy daily habits and stair use
FITNESS EQUIPMENT
Mixed integration of high and low intensity
fitness equipemnent as well as exercise
amentities such as a basketball court
82
WELL BUILDING - COMFORT
ADA DESIGN STANDARDS
Acceptance and integration of ADA de-
sign standards for all areas of the project
THERMAL COMFORT
Meeting ASHRAE design standard 55
INDIVIDUAL THERMAL COMFORT
Individual thermal comfort techniques
through floor air distribution, operable win-
dows, screens, etc.
83
WELL BUILDING - MIND
MATERIAL TRANSPARENCY
Labels and health label declaration for
50% of materials utilized in the project
WORKPLACE FAMLIY SUPPORT
Child care facilities and mandatory office
family support policies
POST-OCCUPANCY SURVEYS
Post-occupancy surveys to determine the
performance of equipment and programs
84
THOMPSON REFLECTION
Changing the uninamous aluminum
metal paneling around and offering
materials facade differences over
physical building cuts could have
provided a more comprehensive
and complete image for how the
buildings came together. The in-
troduction of brick into the project
could have additionally related it
more to the surrounding context.
I would have liked to introduced the
concept of blue algae more into the
scheme. The ability to purify air and
treat water offers a staple of sus-
tainability which can be visual and
appealing. Intorducing more of these
tubes into the plaza, etc. would have
been a nice way to highlight this
feature further.
Introducing more of a stepped con-
cept to our buildings would have
allowed for additional outdoor occu-
piable space within the project. The
current adoption of these outdoor
spaces in the lofts and the bar help
to relate the building to the plaza,
and I believe more introduction of
this concept would benefit the proj-
ect.
Additional site diagrams and context
would have been beneficial to relate
the size of the development with
the surrounding scale and building
context. The lack of these diagrams
on our board prevented the jury from
understanding how the development
fit into the surrounding context.
85
KENNEY REFLECTION
One of the largest changes I would
make is increasing the use of natu-
ral materials. Underneath our folded
plates and overhangs, I would incor-
porate wood paneling to provide a
warmth in such a shaded and dark
space.
To connect the south building to the
north and west elements, I would
explore the opportunity to provide
a covered walk which spans the
interior facades and would allow for
circulation year round with shielding
from the elements.
I felt that while our underground retail
was a nice element, that it did not fit
into the surrounding context to in-
form the site. I feel that bringing the
retail into covered stalls much like
the city market would allow for more
pedestrian activity to occur in the
courtyard and provide movement.
An idea that we had at one point
explored was exposing our water
treatment from the brewery. I think
that if we were to follow through, it
could be a unique element of the
facade which would also allow for an
educational element on the site. This
could feed into the central purifying
system and show the process.
86
McELWAIN REFLECTION
One of the largest changes I would
make is to the bus terminals and the
transit hub. There needs to be a
connection to the new commuter rail
and a better integration to the new
light rail.
I would explore the underground
retail in more depth in order to cre-
ate a connection to the north and
south buildings. This would provide
another connection to the site and a
path for people to explore while still
making it financially feasible.
I would explore more surrounding
buildings and the connection to the
site in terms of materials. The en-
tire building is completely different
than the surrounding buildings and
it seems to stick out too much from
the surrounding buildings.
The south building needs more
development in terms of the pro-
gramming of the building to make
it more viable for the developers
to make the proforma work for the
building. This is an area that will be
highly trafficked and it needs a better
connection to the site and the east
building.

Weitere ähnliche Inhalte

Was ist angesagt?

appendix A1 -Pedestrian Plan_201402051129059977
appendix A1 -Pedestrian Plan_201402051129059977appendix A1 -Pedestrian Plan_201402051129059977
appendix A1 -Pedestrian Plan_201402051129059977
Carson Quam
 
Group 10 Development Presentation
Group 10 Development PresentationGroup 10 Development Presentation
Group 10 Development Presentation
GP Design PS
 
FinalRedevelopmentOpportunitiesMasterplan
FinalRedevelopmentOpportunitiesMasterplanFinalRedevelopmentOpportunitiesMasterplan
FinalRedevelopmentOpportunitiesMasterplan
David West, LEED AP
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
Crosstown TO
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
Crosstown TO
 
Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder Portfolio
Dominic Holder
 
EIA Project - Presentation
EIA Project - PresentationEIA Project - Presentation
EIA Project - Presentation
Emma Syrat
 
Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder Portfolio
Dominic Holder
 
Jersey City Real Estate 2060 Redevelopment Plan for Journal Square
Jersey City Real Estate 2060 Redevelopment Plan for Journal SquareJersey City Real Estate 2060 Redevelopment Plan for Journal Square
Jersey City Real Estate 2060 Redevelopment Plan for Journal Square
Hudson Realty Group
 
buttress masterplanning lr
buttress masterplanning lrbuttress masterplanning lr
buttress masterplanning lr
Gavin Sorby
 

Was ist angesagt? (20)

appendix A1 -Pedestrian Plan_201402051129059977
appendix A1 -Pedestrian Plan_201402051129059977appendix A1 -Pedestrian Plan_201402051129059977
appendix A1 -Pedestrian Plan_201402051129059977
 
Sorell community administration centre a4 doc
Sorell community administration centre a4 docSorell community administration centre a4 doc
Sorell community administration centre a4 doc
 
Urban design ppt - 21 09-16
Urban design ppt - 21 09-16Urban design ppt - 21 09-16
Urban design ppt - 21 09-16
 
Ulx April09
Ulx April09Ulx April09
Ulx April09
 
Group 10 Development Presentation
Group 10 Development PresentationGroup 10 Development Presentation
Group 10 Development Presentation
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015
 
FinalRedevelopmentOpportunitiesMasterplan
FinalRedevelopmentOpportunitiesMasterplanFinalRedevelopmentOpportunitiesMasterplan
FinalRedevelopmentOpportunitiesMasterplan
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Achieving Separated Cycling Facilities in a Constrained Town Centre Environme...
Achieving Separated Cycling Facilities in a Constrained Town Centre Environme...Achieving Separated Cycling Facilities in a Constrained Town Centre Environme...
Achieving Separated Cycling Facilities in a Constrained Town Centre Environme...
 
"Autohoods", an introduction
"Autohoods", an introduction"Autohoods", an introduction
"Autohoods", an introduction
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
 
Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder Portfolio
 
EIA Project - Presentation
EIA Project - PresentationEIA Project - Presentation
EIA Project - Presentation
 
Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder Portfolio
 
Jersey City Real Estate 2060 Redevelopment Plan for Journal Square
Jersey City Real Estate 2060 Redevelopment Plan for Journal SquareJersey City Real Estate 2060 Redevelopment Plan for Journal Square
Jersey City Real Estate 2060 Redevelopment Plan for Journal Square
 
Marquette Plaza, Minneapolis, Minnesota, United States.
Marquette Plaza, Minneapolis, Minnesota, United States.Marquette Plaza, Minneapolis, Minnesota, United States.
Marquette Plaza, Minneapolis, Minnesota, United States.
 
041916-HBP-Media Packet-Complete
041916-HBP-Media Packet-Complete041916-HBP-Media Packet-Complete
041916-HBP-Media Packet-Complete
 
buttress masterplanning lr
buttress masterplanning lrbuttress masterplanning lr
buttress masterplanning lr
 
HS2.3 RK First Ten Years
HS2.3 RK First Ten YearsHS2.3 RK First Ten Years
HS2.3 RK First Ten Years
 

Ähnlich wie Documentation

Strategic plan poster final
Strategic plan poster finalStrategic plan poster final
Strategic plan poster final
Vanessa Baratta
 
DESIGN FOLIO snapshot
DESIGN FOLIO snapshotDESIGN FOLIO snapshot
DESIGN FOLIO snapshot
Sandra Huang
 
Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder Portfolio
Dominic Holder
 
Greening govt center symposium program
Greening govt center symposium programGreening govt center symposium program
Greening govt center symposium program
bostonredevelopment
 

Ähnlich wie Documentation (20)

Portfolio spreads
Portfolio spreadsPortfolio spreads
Portfolio spreads
 
W Palmer Portfolio
W Palmer  PortfolioW Palmer  Portfolio
W Palmer Portfolio
 
Strategic plan poster final
Strategic plan poster finalStrategic plan poster final
Strategic plan poster final
 
تحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحومي
تحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحوميتحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحومي
تحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحومي
 
%100
%100%100
%100
 
Final Boards
Final BoardsFinal Boards
Final Boards
 
Portfolio
PortfolioPortfolio
Portfolio
 
Portfolio
PortfolioPortfolio
Portfolio
 
Current Works
Current WorksCurrent Works
Current Works
 
DESIGN FOLIO snapshot
DESIGN FOLIO snapshotDESIGN FOLIO snapshot
DESIGN FOLIO snapshot
 
Urban Design Portfolio Tim Hays
Urban Design Portfolio Tim HaysUrban Design Portfolio Tim Hays
Urban Design Portfolio Tim Hays
 
Marquette plaza agresh & snehansu
Marquette plaza agresh & snehansuMarquette plaza agresh & snehansu
Marquette plaza agresh & snehansu
 
Luis sotelo architectural portfolio
Luis sotelo   architectural portfolioLuis sotelo   architectural portfolio
Luis sotelo architectural portfolio
 
What if 280 came down
What if 280 came downWhat if 280 came down
What if 280 came down
 
Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder Portfolio
 
Fidi tour handout 2.pdf
Fidi tour handout 2.pdfFidi tour handout 2.pdf
Fidi tour handout 2.pdf
 
Ryan Davis - Selected Work
Ryan Davis - Selected WorkRyan Davis - Selected Work
Ryan Davis - Selected Work
 
Greening govt center symposium program
Greening govt center symposium programGreening govt center symposium program
Greening govt center symposium program
 
River-Front Revitalisation
River-Front RevitalisationRiver-Front Revitalisation
River-Front Revitalisation
 
Downtown Redding Transportation Plan Workshop 2 combined boards
Downtown Redding Transportation Plan Workshop 2 combined boardsDowntown Redding Transportation Plan Workshop 2 combined boards
Downtown Redding Transportation Plan Workshop 2 combined boards
 

Documentation

  • 1. 1 RIVER MARKET TRANSIT HUB ARCH 609 | SPRING 2016 | PADGET MATT KENNEY | LUKE MCELWAIN | CULIN THOMPSON
  • 2. 2
  • 3. 3 Project Thesis Context Precedents Pre-Design Phase Schematic Design Phase Design Development Phase Wall Sections Living Building + Well Building Challenge Final Reflections 4 6 12 16 22 28 50 58 84
  • 4. 4 The River Market Transit Hub serves as a staple for the greater Kansas City Metropolitan area. A beacon of the future of mass transit and sustainabil- ity, this net-zero living building combines the benefits of transit-oriented com- munities, offices, retail, luxury living and community assets. This combination of combining live work and providing commuters with centralized amenities they currently utilize generates a new model of efficiency within transit devel- opment and office construction. Focused around a modern, realistic and simple design, the River Mar- ket Transit Hub utilizes centralized atria to allow daylighting, ventilation and views throughout the complex. As the complex circulates the site edges, its three buildings each carry this atria language - following a pattern of decen- tralizing from the center atria of the eastern-most building. The future of transit-oriented development requires creating an ex- perience that is as user-friendly as is it accessible. The need for child care facilities, dry cleaners, restaurants, fast food facilities, local business retail opportunities, parking, commuter and light rail, bus connections, health facili- ties, coffee shops, community facilities and convenience stores only increas- es as sprawl and the average commute time to work continues to increase. Through combining the daily trips of workers within the Kansas City down- town district, the River Market Transit Hub is able to minimize the time individ- uals spend commuting and running errands - granting additional family time and community time. This time allows for the building of a diverse economy, happy family networks and healthy communities; it is essential towards the continued growth and development of our cities and the River Market Transit Hub is proud to offer this to Kansas City. PROJECT THESIS
  • 5. 5
  • 6. 6 When researching the historical significance of this site, one of the greatest finds was that it initially was developed as a brewery in the late 1800s and early 1900s. The brewery changed hands multiple times and went through various names but Pabst at one point was an owner. Having been in an industry driven part of town, this site had constant traffice typical- ly drawing from the crowds at the city trading center and market across the street. Travelers would typically come from the river and offer goods that they brought from various places. Having such a great histrorical significance with a brewery, we decided to make the design decision to bring a brewery back to the site. Using this idea allowed us to create a specific anchor in our desitination which would bring people in at all times of the day. This additionally provides jobs and al- lows for a product unique to this location to be sold regionally and nationwide if desired. The brewery includes a restaurant as well. SITE HISTORY
  • 7. 7
  • 8. 8
  • 9. 9 COLD STORAGE LOFTS CHINESE FOOD MARKET HISTORIC CITY MARKET
  • 10. 10 The site currently serves as and will continue to be focused as a center of trans- portation. In the past, this lot had been fo- cused on a street car and often serving as outdoor market space which held large crowds in addition to the city market across the corner. Currently the site is a parking lot for commuters who use the new light rail station, the MegaBus, the local bus systems, or walk to local businesses and attractions. The prop- erty is owned by the Kansas City Area Trans- portation Authority. Part of redeveloping the site is to keep the destination focused using transit oriented design. In future planning, a commuter rail is planned to arrive at this station to the north. With this site continuing to serve many com- muters, we used this as an opportunity to drive our design decisions. Some of these in- cluded a ground level transit hub, a bus pass through in the site by repurposing Oak St., bicycle storage and showers, shaded seating and waiting areas, underground parking, and ground level retail and amenities. TRANSPORTATION
  • 12. 12 564 Beatty was particularly studied for the south facing facade as well as the structure in relation to the of- fice layout. We studied how the cur- tain wall system used metal paneling as spandrels as well as overhanging louvers to block particular angles of sunlight. We further studied the idea conditions for our region using Se- faira. Additionally, we examined the structural grid which was 30’ x 30’, the same spacing we used, as to how this informs the office arrange- ment. PRECEDENTS 564 BEATTY Vancouver, BC, Canada
  • 13. 13 The ETFO Building had a few signif- icant contributions to our research and conceptual design. One of the concepts that we found interesting was the folded skin and overhang that provided shade and thermal mass to the structure. Additionally, we focused on the cross and stack ventilation techniques used to draw air up the atrium and across the office floor plates. ETFO BUILDING Toronto, Ontario, Canada
  • 14. 14 When examining the Center for Interactive Research on Sustain- ability, the element that stood out to us most was the atrium space. This design exposes the structure, particularly beams, and provides a quick reference to the vertical circu- lation taking place. Additionally, the space uses stack ventilation and is well lit thus making the atrium a celebrated feature which we used to inform our design. CENTER FOR INTERACTIVE RESEARCH ON SUSTAINABILITY Vancouver, BC, Canada
  • 15. 15 The Sage VIP Building was a driving example of form for our west build- ing on the site. We studied the way that the shade structure and inset balconies allowed for outdoor gath- ering and used these concepts to provide space and shade for people gathering outside of the transporta- tion hub or the local office spaces. SAGE VIP BUILDING Pretoria, South Africa
  • 17. 17
  • 18. 18 THOMPSON SCHEME Focused around a central courtyard, this initial scheme de- veloped upon providing a closed facade along third street to maximize upon the retail potential a transit-fo- cused street. The additional emphasis upon having an occupiable rooftop to pro- vide views to Kansas City drove the rooftop occupancy availability and voids to allow for natural daylighting and ventilation.
  • 19. 19
  • 20. 20 McELWAIN SCHEME Opening the corner to the Riv- er Market provides access and an open square for the visitors to create a space for people to occupy and explore. The buildings are optimized for lighting and ventilation. The addition of businesses and ammeneties in this development support the people that are already in the area as well as the new-com- ers from the light rail and the future commuter rail.
  • 21. 21
  • 24. 24 1STLEVEL FLOOR PLAN 5TH LEVEL FLOOR PLAN Raised access floor provide flexible open office floor plans and allow for direct and personalized ventilation systems and thermal comfort. The integration of the bar as a focal point highlights the devel- opment as a unique landmark within the Kansas City region and provides a way to build and promote commu- nity. The preservation of Oak Street on the site as a through-way for bus circulation generates a closed pe- destrian plaza level, while the intro- duction of a secondary street for car circulation between the development and the Cold Storage building pro- vides both circulation and a buffer between the two developments.
  • 26. 26 STEEL STRUCTURE BEAMS: W18 X 40 WIDE FLANGE COLUMNS: W14X176 WIDE FLANGE
  • 27. 27 The structure of the building is steel I beams. The heirarchy of structure car- rys a 30 foot bay pattern and this allows for optimum renting and layout space for the clients renting the space. The structure carrys all the way down to the ground through the concrete parking structure. The floors of the building are built from concrete decking over a metal deck. The floor space is largely optimised to allow for air flow and sunlight penetra- tion for better work and living environ- ments. Walls of the buildings are R-40 for opti- mum thermal breaking from the exte- rior. The glass walls are double paned argon filled allowing the sin exposure to be reduced. The HV/AC system is largely under- floor for the office and the residences and the atriums will be conditioned by forced air. Sloar arrays on the top of the north and south buildings will power the whole site.
  • 29. 29 ROOF/SITE PLAN SCALE: 1”=30’ 1 2 3 4 5 PARKING RAMP PLAZA PV ARRAY COLD STORAGE LOFTS ASIAN MARKET 6 7 8 9 10 STREETCAR STOP ONE-WAY BUS DRIVE POWER PLANT COMMUNITY GARDEN POOL KEY 1 2 3 4 5 6 7 8 9 10 11 ROOFTOP BAR 11 GRANDAVENUE 3RD STREET 12 CITY MARKET 12 13 COMMUTER RAIL STOP 13
  • 30. 30
  • 31. 31
  • 32. 32
  • 33. 33
  • 34. 34 JIHGFEDCB 1 2 3 5 4 19 A109 DN REF. REF. JIHGFEDCB 1 2 3 5 A 2 A109 4 DN REF. UP JIHGFEDCB 1 2 3 5 A 4 REF. UP WWH REF. WWH REF. WWH REF. WWH REF. WWH REF. WWH REF. WWH REF. WWH REF. WH W W REF. WH WWREF. WH WW W REF.WREF. WREF. W REF. WREF. W REF. UP DN JIHGFEDCB 1 2 3 5 K L M NA 2 A109 4 19 A109 A109 12 A109 13 A109 14 FIRST FLOOR PLAN SCALE: 1/16”=1’ THIRD FLOOR PLAN SCALE: 1/16”=1’ FIFTH FLOOR PLAN SCALE: 1/16”=1’ SIXTH FLOOR PLAN SCALE: 1/16”=1’ 14 15 16 17 18 19 20 21 2223 24 25 18000 28800 25200 7000 25500 8100 NORTH BUILDING Retail Office Residen4al Mechanical Circula4on Transit 8100 41400 4500 3600 14400 10800 EAST BUILDING Retail Office Mechanical Circula4on Gym Transit The north building incorpo- rates services and amenities for the transit hub in addition to office space. Offering a childcare facility, dry cleaners, restaurants, bar and office space the northern building integrates the live-work mentality of millennials and future mixed use city design.
  • 35. 35 WH WH WH WH WHH UNIT LAYOUT A SCALE: 1/8”=1’ UNIT LAYOUT B SCALE: 1/8”=1’ UNIT LAYOUT C SCALE: 1/8”=1’ 14 15 16 17 18 BICYCLE STORAGE / SHOWERS LOCAL BUSINESS RETAIL FREIGHT ELEVATOR MECHANICAL ROOM FOOD RETAIL 19 20 21 22 23 DRY CLEANERS OFFICE SPACE OFFICE SPACE BREWERY RESTAURANT BREW AREA / KITCHEN KEY 24 ROOFTOP BAR 25 LUXURY LOFTS
  • 36. 36
  • 37. 37
  • 38. 38 EDCBA Level 2 18' - 5" Level 3 31' - 5" Level 4 44' - 5" Level 5 57' - 5" Level 6 70' - 5" Level 7 80' - 5" Level 8 90' - 5" Level 1 0' - 5" Level 9 100' - 5" 1 2 3 5 Parking 1 -11' - 0" Parking 2 -22' - 0" Parking 3 -33' - 0" Parking 4 -44' - 0" Level 2 18' - 5" Level 3 31' - 5" Level 4 44' - 5" Level 5 57' - 5" Level 6 70' - 5" Level 7 80' - 5" Level 8 90' - 5" 4 Level 9 100' - 5" BUILDING SECTION SCALE: 1/16”=1’
  • 39. 39 JIHGF K L M N Parking 1 -11' - 0" Parking 2 -22' - 0" Parking 3 -33' - 0" Parking 4 -44' - 0" Level 2 18' - 5" Level 3 31' - 5" Level 4 44' - 5" Level 5 57' - 5" Level 6 70' - 5" Level 7 80' - 5" Level 8 90' - 5" Level 1 0' - 5" Level 9 100' - 5" BUILDING SECTION SCALE: 1/16”=1’
  • 40. 40
  • 42. 42 26 27 28 29 30 TRANSPORTATION TICKET COUNTER BUS WAITING AREA CAFE/ COMPUTER LOUNGE MECHANICAL ROOM BASKETBALL COURT 31 32 33 34 35 LOCKER ROOM GYM OPEN OFFICE YOGA STUDIO BANQUET/EVENT ROOM KEY 36 ROOFTOP GARDEN PLOTS 37 ROOFTOP POOL 38 OUTDOOR TERRACE UP UP UP UP 11 22 33 55 K L M N 15 9 13 11 8 7 6 4 4 REF REF.REF. 1 2 3 5 K K L L M M N N 15 4 FIRST FLOOR PLAN SCALE: 1/16”=1’ SECOND FLOOR PLAN SCALE: 1/16”=1’ 26 27 28 29 29 30 31 32 32 33 34
  • 43. 43 F. 1 2 3 5 N N 15 9 13 11 8 7 6 4 11 22 33 55 K K L L M M N N 1515 9 13 11 8 7 6 4 4 11 22 33 5 K L M N 15 9 11 8 7 6 4 4 THIRD FLOOR PLAN SCALE: 1/16”=1’ FIFTH FLOOR PLAN SCALE: 1/16”=1’ 2929 33 35 36 37 38
  • 44. 44 1 2 3 5 Parking 1 -11' - 0" Parking 2 -22' - 0" Parking 3 -33' - 0" Parking 4 -44' - 0" 9 11876 Level 2 18' - 5" Level 3 31' - 5" Level 4 44' - 5" Level 5 57' - 5" Level 6 70' - 5" Level 7 80' - 5" Level 8 90' - 5" Level 1 0' - 5" 4 Level 9 100' - 5" BUILDING SECTION SCALE: 1/16”=1’
  • 45. 45 1513 K L M N Parking 1 -11' - 0" Parking 2 -22' - 0" Parking 3 -33' - 0" Parking 4 -44' - 0" Level 2 18' - 5" Level 3 31' - 5" Level 4 44' - 5" Level 5 57' - 5" Level 6 70' - 5" Level 1 0' - 5" BUILDING SECTION SCALE: 1/16”=1’
  • 47. 47 PARKING LEVEL 1 PLAN PARKING LEVEL 3 PLAN
  • 49. 49
  • 50. 50 Level 2 18' - 5" Level 3 31' - 5" Level 5 57' - 5" Level 6 70' - 5" Level 1 0' - 5" A109 6 1 2 3 4 5 6 7 8 9 10 THOMPSON WALL SECTIONS 1 METAL PANELING FURING STRIP ROOF DRAIN OPERABLE DOORS GLASS RAILING SPANDREL PANEL RAISED ACCESS FLOOR LIGHT SHELF DOUBLE PANE GLASS CONCRETE PANEL KEY PV PANELS METAL PANELING 2 3 4 5 6 7 8 9 10 11 12 13 LOFT PARTITION
  • 51. 51 Level 2 18' - 5" Level 5 57' - 5" Level 6 70' - 5" Level 7 80' - 5" Level 8 90' - 5" Level 1 0' - 5" A109 3 A109 4 A109 5 11 12 13
  • 53. 53 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 ALUMINUM MULLION SPANDREL PANEL L-ANGLE BOLTED CONNECTION FIRE STOP RAISED CONCERE PANEL RIGID INSULATION ANCHOR BOLT RAISED ACCESS FLOOR MOISTURE BARRIER UNISTRUT L-ANGLE C-CHANNEL RIGID INSULATION FURRING STRIP LOUVERS GREEN HANGING STRUCTURE LIGHT GUAGE STEEL KEY
  • 54. 54 KENNEY WALL SECTIONS 1 METAL PANELING FURING STRIP ROOF DRAIN OPERABLE DOORS GLASS RAILING SPANDREL PANEL RAISED ACCESS FLOOR DOUBLE PANE GLASS CONCRETE PANEL KEY METAL PANELING 2 3 4 5 6 7 8 9 10 11 12 13 14 15 ALUMINUM MULLION BENT METAL FLASHING 16 17 18 19 L-ANGLE BOLTED CONNECTION RAISED CONCERTE PANEL RIGID INSULATION ANCHOR BOLT MOISTURE BARRIER UNISTRUT L-ANGLE 3 20 FIBER EXPANSION JOINT K L Level 2 18' - 5" Level 3 31' - 5" Level 4 44' - 5" Level 5 57' - 5" Level 1 0' - 5" 1 2 3 7 9 10 12 17 20 8
  • 55. 55 11 14 17 15 K L Level 2 18' - 5" Level 3 31' - 5" Level 4 44' - 5" Level 5 57' - 5" Level 1 0' - 5" --- - --- - 5 6 10 17 20
  • 57. 57
  • 59. 59 THIS STANDARD IS AN ACT OF OPTIMISM AND BELIEF THAT WITH THE RIGHT TOOLS IN THE HANDS OF PASSIONATE, LITERATE AND SENSITIVE INDIVIDUALS. A REVOLU- TIONARY TRANSFORMATION IS POSSI- BLE. IT IS A PROGRAM THAT ASKS US TO THINK HOLISTICALLY AND ENGAGE BOTH OUR RIGHT AND LEFT BRAINS, HEAD AND HEART.
  • 60. 60 LIVING BUILDING - ENERGY ROOF/SITE PLAN SCALE: 1”=30’ 1 2 3 4 5 PARKING RAMP PLAZA PV ARRAY COLD STORAGE LOFTS ASIAN MARKET 6 7 8 9 10 STREETCAR STOP ONE-WAY BUS DRIVE POWER PLANT COMMUNITY GARDEN POOL KEY 1 2 3 4 5 6 7 8 9 10 11 ROOFTOP BAR 11 GRANDAVENUE 3RD STREET 12 CITY MARKET 12 13 COMMUTER RAIL STOP 13
  • 61. 61 PV PANELS Photovoltaic panels allow us to offset the amount of energy used within the building to become net positive WEST SECTION NATURAL VENTILATION The use of large open atria throughout the site maximizes the natural ventilation of fresh and stale air OVERHANGS The integration of large overhangs allows us to shield the building from a majority of direct sunlight Level 5 57' - 5" Level 6 70' - 5" SUN SHELVES Placing sun shelves over glass curtain walls and integration mullions provides ad- ditional blockage from direct sun
  • 62. 62 LIVING BUILDING - WATER ROOF/SITE PLAN SCALE: 1”=30’ 1 2 3 4 5 PARKING RAMP PLAZA PV ARRAY COLD STORAGE LOFTS ASIAN MARKET 6 7 8 9 10 STREETCAR STOP ONE-WAY BUS DRIVE POWER PLANT COMMUNITY GARDEN POOL KEY 1 2 3 4 5 6 7 8 9 10 11 ROOFTOP BAR 11 GRANDAVENUE 3RD STREET 12 CITY MARKET 12 13 COMMUTER RAIL STOP 13
  • 63. 63 PHOTOLUMINESCENT ALGAE Algae is a critical component of filtering and conserving water from the brewery - allowing a more sustainable process RETENTION PONDS Integration of retention ponds allows us to utilize roof-collected water over potable water A109 6 STORMWATER COLLECTION Plugging stormwater into graywater sys- tems allows for conservation of potable water within plumbing systems RAIN GARDENS Placing biowales and rain gardens on-site allows the site to begin to filter out toxins before hitting the streetscape
  • 64. 64 LIVING BUILDING - PLACE ROOF/SITE PLAN SCALE: 1”=30’ 1 2 3 4 5 PARKING RAMP PLAZA PV ARRAY COLD STORAGE LOFTS ASIAN MARKET 6 7 8 9 10 STREETCAR STOP ONE-WAY BUS DRIVE POWER PLANT COMMUNITY GARDEN POOL KEY 1 2 3 4 5 6 7 8 9 10 11 ROOFTOP BAR 11 GRANDAVENUE 3RD STREET 12 CITY MARKET 12 13 COMMUTER RAIL STOP 13
  • 65. 65 URBAN GARDENING Encouraging urban agriculture and gar- dening through community building BROWNFIELD CONSTRUCTION Construction on the site of a current park- ing lot does not damage any wetlands or natural habitats HABITAT EXCHANGE Designating preservations offsite along the Kansas River help to mitigate the environ- mental damage from construction BICYCLE STORAGE Indoor bicycle storage and showers offer incentives to bike to work over driving
  • 66. 66 LIVING BUILDING - MATERIALS RED LIST Compliance with the red list of banned materials LOCAL MATERIALS Maximization of materials coming from 500 km or less from the site EPA Chemical of Concern Ban Ban of any integration of materials made from chemicals on the US EPA Chemical of Concern list RECYCLING MATERIALS Recycling of waste materials from the site
  • 67. 67 LIVING BUILDING - EQUITY UNIVERSAL ACCESSIBILITY Universal access to all public features of the site including daylight, ventilation and outdoor amenities TRANSPORTATION Incorporation of multi-modal transportation including private and public mass-transit AFFORDABLE HOUSING Integration of affordable housing units and 4% low income housing tax credits to hel- op finance the project COMMUNITY BUILDING Community building features such as a brewery, urban garden, public plaza and local business incubation
  • 68. 68 LIVING BUILDING - BEAUTY ROOF/SITE PLAN SCALE: 1”=30’ 1 2 3 4 5 PARKING RAMP PLAZA PV ARRAY COLD STORAGE LOFTS ASIAN MARKET 6 7 8 9 10 STREETCAR STOP ONE-WAY BUS DRIVE POWER PLANT COMMUNITY GARDEN POOL KEY 1 2 3 4 5 6 7 8 9 10 11 ROOFTOP BAR 11 GRANDAVENUE 3RD STREET 12 CITY MARKET 12 13 COMMUTER RAIL STOP 13
  • 69. 69 PUBLIC GATHERING & ART Integration of public plazas and integration of local business and art BIOPHILIC ENVIRONMENT Placement of greenery and water features throughout the project site EDUCATION Educational boards and programs about the sustainable features of the project RAIN GARDENS Placing biowales and rain gardens on-site allows the site to begin to filter out toxins before hitting the streetscape
  • 70. 70 LIVING BUILDING - HEALTH ROOF/SITE PLAN SCALE: 1”=30’ 1 2 3 4 5 PARKING RAMP PLAZA PV ARRAY COLD STORAGE LOFTS ASIAN MARKET 6 7 8 9 10 STREETCAR STOP ONE-WAY BUS DRIVE POWER PLANT COMMUNITY GARDEN POOL KEY 1 2 3 4 5 6 7 8 9 10 11 ROOFTOP BAR 11 GRANDAVENUE 3RD STREET 12 CITY MARKET 12 13 COMMUTER RAIL STOP 13
  • 71. 71 OPERABLE WINDOWS Operable windows provide natural daylight and ventilation to occupants TOBACCO BAN Banning tobacco products on the site boundary promote healthy living and life- styles GREEN WALLS Green walls help to provide air filtration and promote the use of atrium stairs OUTDOOR CONNECTIONS Direct connections to the exterior balco- nies of the site provide natural air and en- vironemntal benefits
  • 73. 73 We believe that the time has come to elevate human health and comfort to the forefront of building practices and reinvent buildings that are not only better for the planet—but also for people.
  • 74. 74 WELL BUILDING - AIR ROOF/SITE PLAN SCALE: 1”=30’ 1 2 3 4 5 PARKING RAMP PLAZA PV ARRAY COLD STORAGE LOFTS ASIAN MARKET 6 7 8 9 10 STREETCAR STOP ONE-WAY BUS DRIVE POWER PLANT COMMUNITY GARDEN POOL KEY 1 2 3 4 5 6 7 8 9 10 11 ROOFTOP BAR 11 GRANDAVENUE 3RD STREET 12 CITY MARKET 12 13 COMMUTER RAIL STOP 13
  • 75. 75 OPERABLE WINDOWS Operable windows provide natural daylight and ventilation to occupants ADVANCED AIR PURIFICATION Advanced mechanical and natural air puri- fication produces cleaner air INCREASED VENTILATION Increased and direct sourced ventilation provides fresher air to the project CLEANABLE ENVIRONMENT The use of aluminum paneling for the walls of the building allows for easy cleaning methods
  • 76. 76 WELL BUILDING - WATER ROOF/SITE PLAN SCALE: 1”=30’ 1 2 3 4 5 PARKING RAMP PLAZA PV ARRAY COLD STORAGE LOFTS ASIAN MARKET 6 7 8 9 10 STREETCAR STOP ONE-WAY BUS DRIVE POWER PLANT COMMUNITY GARDEN POOL KEY 1 2 3 4 5 6 7 8 9 10 11 ROOFTOP BAR 11 GRANDAVENUE 3RD STREET 12 CITY MARKET 12 13 COMMUTER RAIL STOP 13
  • 77. 77 PHOTOLUMINESCENT ALGAE Algae is a critical component of filtering and conserving water from the brewery - allowing a more sustainable process STEAM TAPPING Tapping into the steam plant adjacent to the site reduces on-side energy and water consumption PUBLIC WATER ADDITIVES Addition of disinfectants and fluoride into the water systems DRINKING WATER PROMOTION Additional water fountain placement and promotion of renewable water bottles
  • 78. 78 WELL BUILDING - NOURISHMENT ROOF/SITE PLAN SCALE: 1”=30’ 1 2 3 4 5 PARKING RAMP PLAZA PV ARRAY COLD STORAGE LOFTS ASIAN MARKET 6 7 8 9 10 STREETCAR STOP ONE-WAY BUS DRIVE POWER PLANT COMMUNITY GARDEN POOL KEY 1 2 3 4 5 6 7 8 9 10 11 ROOFTOP BAR 11 GRANDAVENUE 3RD STREET 12 CITY MARKET 12 13 COMMUTER RAIL STOP 13
  • 79. 79 URBAN GARDENING Encouraging urban agriculture and gar- dening through community building HAND WASHING Separated hand washing stations to en- courage sanitary procedures NUTRITIONAL INFORMATION Graphic and visual design standards for food nutritional values in restaurants RESPONSIBLE FOOD PRODUCTION Sanitary and responsible separated food pro- duction zones for all restaurants
  • 80. 80 WELL BUILDING - LIGHT SOLAR GLARE CONTROL Solar glare shelves and glazings to pre- vent glare in workspaces RIGHT TO LIGHT Natural daylighting within all spaces max- imized by a narrow footprint and light shelves DAYLIGHT MODELING Daylight maximization and modeling within Sefaira DAYLIGHT FENESTRATION Windows, shelves and screens incorpo- rated within the fenestration of individual wall systems
  • 81. 81 WELL BUILDING - FITNESS PHYSICAL ACTIVITY SPACES Integration of a gym within the project to encourage exercise and a balanced life- style STRUCTURED FITNESS Daily fitness classes to encourage healthy activity and movement INTERIOR FITNESS CIRCULATION Visual stairs integrated within atria to en- courage healthy daily habits and stair use FITNESS EQUIPMENT Mixed integration of high and low intensity fitness equipemnent as well as exercise amentities such as a basketball court
  • 82. 82 WELL BUILDING - COMFORT ADA DESIGN STANDARDS Acceptance and integration of ADA de- sign standards for all areas of the project THERMAL COMFORT Meeting ASHRAE design standard 55 INDIVIDUAL THERMAL COMFORT Individual thermal comfort techniques through floor air distribution, operable win- dows, screens, etc.
  • 83. 83 WELL BUILDING - MIND MATERIAL TRANSPARENCY Labels and health label declaration for 50% of materials utilized in the project WORKPLACE FAMLIY SUPPORT Child care facilities and mandatory office family support policies POST-OCCUPANCY SURVEYS Post-occupancy surveys to determine the performance of equipment and programs
  • 84. 84 THOMPSON REFLECTION Changing the uninamous aluminum metal paneling around and offering materials facade differences over physical building cuts could have provided a more comprehensive and complete image for how the buildings came together. The in- troduction of brick into the project could have additionally related it more to the surrounding context. I would have liked to introduced the concept of blue algae more into the scheme. The ability to purify air and treat water offers a staple of sus- tainability which can be visual and appealing. Intorducing more of these tubes into the plaza, etc. would have been a nice way to highlight this feature further. Introducing more of a stepped con- cept to our buildings would have allowed for additional outdoor occu- piable space within the project. The current adoption of these outdoor spaces in the lofts and the bar help to relate the building to the plaza, and I believe more introduction of this concept would benefit the proj- ect. Additional site diagrams and context would have been beneficial to relate the size of the development with the surrounding scale and building context. The lack of these diagrams on our board prevented the jury from understanding how the development fit into the surrounding context.
  • 85. 85 KENNEY REFLECTION One of the largest changes I would make is increasing the use of natu- ral materials. Underneath our folded plates and overhangs, I would incor- porate wood paneling to provide a warmth in such a shaded and dark space. To connect the south building to the north and west elements, I would explore the opportunity to provide a covered walk which spans the interior facades and would allow for circulation year round with shielding from the elements. I felt that while our underground retail was a nice element, that it did not fit into the surrounding context to in- form the site. I feel that bringing the retail into covered stalls much like the city market would allow for more pedestrian activity to occur in the courtyard and provide movement. An idea that we had at one point explored was exposing our water treatment from the brewery. I think that if we were to follow through, it could be a unique element of the facade which would also allow for an educational element on the site. This could feed into the central purifying system and show the process.
  • 86. 86 McELWAIN REFLECTION One of the largest changes I would make is to the bus terminals and the transit hub. There needs to be a connection to the new commuter rail and a better integration to the new light rail. I would explore the underground retail in more depth in order to cre- ate a connection to the north and south buildings. This would provide another connection to the site and a path for people to explore while still making it financially feasible. I would explore more surrounding buildings and the connection to the site in terms of materials. The en- tire building is completely different than the surrounding buildings and it seems to stick out too much from the surrounding buildings. The south building needs more development in terms of the pro- gramming of the building to make it more viable for the developers to make the proforma work for the building. This is an area that will be highly trafficked and it needs a better connection to the site and the east building.