3. Completed Works
TPSS 11 was delivered and assembled at Warden Ave – Nov 28, 2019
All Intersection guideway construction and track slab was completed from
Victoria Park Ave to Rosemount Dr – Dec 16, 2019
The west side crosswalk was reinstated at Eglinton Square – Jan 6, 2020
TPSS 10 was delivered and assembled at Victoria Park Ave – Feb 9, 2020
Maintenance holes were raised to street level south on Warden Ave – Feb 14,
2020
Extended hours and south side culvert connection was completed at Massey
Creek Culvert – Feb 18, 2020
Eastbound and westbound stops were completed at Pharmacy Ave – Feb 20,
2020
First shelter installed at the eastbound stop at Pharmacy Ave – Mar 3, 2020
3
4. Victoria Park Avenue to Rosemount Drive Look Ahead
4
ACTIVITY LOCATION APPROX. DATE AND DURATION
Stop Construction and Shelter Installation
Eglinton Ave E b/w Victoria Park
Ave and Pharmacy Ave
Underway through spring 2020
Stop Construction and Shelter Installation
Eglinton Ave E b/w Pharmacy Ave
and Hakimi Lebovic Ave
Underway through spring 2020
Stop Construction and Shelter Installation
Eglinton Ave E b/w Hakimi Lebovic
Ave and Warden Ave
Underway through spring 2020
Stop Construction and Shelter Installation
Eglinton Ave E b/w Warden Ave
and Birchmount Rd
Underway through spring 2020
Stop Construction and Shelter Installation Eglinton Ave E b/w Birchmount Rd
and Rosemount Dr
Underway through spring 2020
Stop Construction and Shelter Installation
Eglinton Ave E b/w Rosemount
and Ionview Rd
Underway through spring 2020
Midblock Guideway Eglinton Ave E b/w Rosemount Rd
and Kennedy Rd
Ongoing
5. What to Expect:
Guideway, Stop Construction, Track Installation, Permanent Signal Work
Eglinton Ave E from Victoria Park Ave to Rosemount Dr
Traffic and Pedestrian Impacts
• Daily temporary lane closures
• Periodic sidewalk and crosswalk closures
• Noise from construction equipment, generators and vehicles
• Nearby businesses and residents can expect noise from excavation, bobcats, trucks and other
construction equipment as well as site lighting
• A minimum of one lane of eastbound and westbound through traffic will be maintained during this
work
Hours of Work
• Construction will take place between the hours of 7:00 a.m. and 11:00 p.m.
• The contractor may not always work during the permitted hours but may do so at its discretion.
• Work may be rescheduled due to weather conditions or unforeseen circumstances.
• Emergency services access will be maintained.
5
7. Current work from Victoria Park Ave to Kennedy Road
7
ACTIVITY LOCATION
APPROX. DATE AND
DURATION
Closure North of Rosemount Dr for Massey Creek Culvert
Reconstruction
Rosemount Dr / Eglinton Ave E Extended to June 1, 2020
Westbound Stop Shelter Installation Pharmacy Ave / Eglinton Ave E April 7, 2020 – April 10, 2020
Tree Removal – TTC North Service Parking Lot Expansion North of Kennedy Station
March 30, 2020 – April
10,2020
*Proposed Work
Permanent Sidewalk and Curb Installation
Eglinton Ave E b/w Birchmount
Rd and Kennedy Rd
April 15, 2020 (TBC)
*Proposed Work
Driveway and Boulevard Restoration
Eglinton Ave E b/w Birchmount
Rd and Kennedy Rd
Late April, 2020 (TBC)
Stop Construction Hakimi Ave / Eglinton Ave E Ongoing
Permanent Signal Work
Eglinton Ave E b/w Victoria
Park Ave and Kennedy Rd
Ongoing
Eastbound Left Turn Lane Removal Birchmount Rd / Eglinton Ave E Summer / Fall 2020
Northbound and Southbound Left Turn Removals Pharmacy Ave / Eglinton Ave E Summer / Fall 2020
8. Current Traffic Configuration: Rosemount Dr and Eglinton Ave E
January 6, 2020 – June 1, 2020
8
• Extended road closure for Massey Creek Culvert reconstruction.
9. Upcoming Traffic Configuration: Pharmacy Ave and Eglinton Ave E
April 7, 2020 – April 10, 2020
9
• One westbound lane will be restricted east of Pharmacy Avenue for the shelter
installation of the future westbound LRT stop. No through traffic in the right curb
lane, right turns only.
10. Tree Removal – North of Kennedy Station March 30, 2020 – April 10, 2020
10
• The tree removal is in support of the TTC North Service Parking Lot Expansion.
Tree protection measures are in place, all removals have been approved by the
City of Toronto.
11. *Proposed Upcoming Traffic Configuration: Permanent Sidewalk and Curb
Installation Birchmount Rd to Kennedy Rd – April 15, 2020
11
• The work will be completed in sections moving eastward beginning at
Birchmount Rd and ending at Kennedy Rd.
12. 12
Summer / Fall 2020 – The eastbound
and westbound left turn will be
prohibited at Birchmount Road
permanently. Left turns are available
at nearby streets including Warden
Ave and Kennedy Rd.
November 13 – The westbound left
turn will be prohibited at Birchmount
Road permanently. Left turns are
available at nearby streets including
Warden Ave and Kennedy Rd.
Left Turn Removals: Birchmount Rd
17. Kennedy Station Look Ahead
ACTIVITY LOCATION
APPROX. DATE AND
DURATION
Portal Excavation, lagging and tie backs
The west portal was completed
East of GO excavation, lagging and tie backs
Underpinning of TTC infrastructure SRT
Second tower crane installation
Kennedy Station Completed
Traffic Configuration Change
Kennedy Rd and Eglinton
Ave E
Ongoing
• Decking Removal (Temporary Traffic Change)
Kennedy Rd and Eglinton
Ave E
May, 2020
• Platform Decking
GO West Platform July, 2020
• Dewatering activities
• Support of excavation
• Underground mechanical and electrical works
• Waterproofing
• Masonry
Kennedy Station - Main
Station Box
Ongoing through late 2020
Concrete, Electrical and Mechanical Works
Kennedy Station – East of
GO
Ongoing through late 2020
Backfilling and Installation of Structural Streel
Kennedy Station – West
Portal and GO platform
Ongoing through late 2020