3. 3
East At-Grade (Pharmacy to Rosemount) Update
July 2017
• Preparatory works are underway or complete
• Geotechnical Investigations completed
• Subsurface Utility Investigations
– Ongoing (as required)
• Tree Protection and Removals
– Ongoing (mostly completed in the Kennedy area, advancing at At-Grade)
• Median Removals temporarily on hold pending technical discussions with City
Summer/Fall 2017
• Currently work being completed for design and expecting utility relocations to
start in the near future
– Utilities Relocation
– Road Work
4. 4
Kennedy Station Update
Upcoming works:
• Preparatory works in progress and the site trailer will be ready by end of July
• Enbridge Gas Main replacements
– The service connection for the buddy shop will start this week and continue for
the next 40 days
• Dry utility relocations (Telecommunications) - pending permits
• Toronto Hydro relocations
– Work started on Jun 26 for section 4, from Birchmount to Hydro corridor
• Wet utility relocations (Water, Sanitary Sewer, Storm Sewer)
– Wet Utility relocation work for all utilities located under Eglinton bridge are
completed
• Road works around TTC’s Kennedy Station
– Pending TTC approval
• Demolition of Existing TTC North Entrance
– Pending TTC approval and City permit
• Start of support of excavation activities expected to start Fall 2017
• Eglinton Ave road widening expected to start late 2017