SlideShare ist ein Scribd-Unternehmen logo
1 von 14
November 24, 2020
Eglinton Crosstown LRT
Construction Liaison Committee
Victoria Park Avenue to Kennedy Station
Section Three and Four At-Grade:
O’Connor Stop to Ionview Stop
CONSTRUCTION ACTIVITIES
3
Location Activity Approx. Date & Duration
O’Connor Stop
• Concrete work and formwork
installation for ramps and curbs
• Sidewalk construction at 4 corners of
Eglinton Square intersection
Ongoing through to late November 2020
November 23, 2020 for two weeks
Pharmacy Stop
• Sidewalk construction at four corners
of the intersection
Complete
Hakimi Lebovic Stop
• Roadworks and sidewalk construction
at east side of intersection
November 23 for one week
Golden Mile Stop • Concrete works for stop ramps November – Mid December 2020
Birchmount Stop • Track works November – Mid December 2020
Rosemount Drive
• Massey Creek Culvert: Fill old culvert
and build west wing wall.
• Concrete works, west of Rosemount
Drive, sidewalk construction (north side)
November – Mid December 2020
Ionview Stop
• Formwork and concrete for stop ramps
and curbs
• Stop shelter installation
Ongoing through to early December 2020
Early December 2020 for one week
SIDEWALK CONSTRUCTION – EGLINTON SQUARE
4
November 23, 2020 November 30, 2020
• Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Eglinton Square intersection
• Closure of one eastbound and westbound lane at the intersection.
• Closure of the northbound lane at the intersection for construction activities on the east side.
• Closure of one southbound lane at the intersection for construction activities on the west side.
• The east crosswalk will be closed while crews are working on the east side.
• All crosswalks will be open while crews work on the west side.
SIDEWALK CONSTRUCTION – HAKIMI AND LEBOVIC AVE AT EGLINTON AVE E
EAST SIDE
5
November 18 – November 27, 2020
• Crews will be constructing final sidewalks at the four corners
of the Eglinton Ave E and Hakimi Lebovic Ave intersection.
Work on the east side will take place November 18 –
November 27, 2020
• The Eglinton Ave driveways for 1910 and 1920 Eglinton Ave
E will be closed for one week. Alternate driveways will
remain accessible on Hakimi Ave and Eglinton Ave E for the
duration of the works.
• Closure of one eastbound and westbound lane at the
intersection.
• Closure of one northbound lane at the intersection for
construction activities on the east side of the intersection.
ROSEMOUNT DRIVE AND EGLINTON AVE E
6
Early January – Late December 2020
• North side closure for Massey Creek Construction
• Crews will fill the old culvert and then construct the west wing wall
MASSEY CREEK ROOF SLAB
CONSTRUCTION IS NOW COMPLETE
CONSTRUCTION PROGRESS PHOTOS
7
SIDEWALK CONSTRUCTION AT
HAKIMI LEBOVIC INTERSECTION
TRACK WORK WEST OF
BIRCHMOUNT
GUARDRAIL INSTALLATION
COMPLETE AT BIRCHMOUTN STOP
Kennedy Station
KENNEDY STATION UPDATE
9
Location Activity Approx. Date & Duration
Kennedy Station Main Entrance
• Concrete and masonry works
• Conduit installation, plumbing and sheet
metal works, tiling, masonry works
• Structural steel and decking
• Elevator installation and painting
Ongoing through to late 2020
Kennedy Station – East of GO
• Concrete works
• Electrical and mechanical works
Ongoing through to late 2020
Kennedy Station Concourse Level
• Excavation and waterproofing
• Concrete works, rebar and shoring
Ongoing through to late 2020
Kennedy Portal (west of Kennedy Road)
• Railing installation
• Installation of light fixtures
• Track works
Ongoing through to late 2020
Kennedy Station Go Platform
• Curtain wall and glazing
• Excavation for new east platform
• Installation of metal railing
• Roofing at GO shelters, painting of shelter
and railing
• Mechanical and electrical works
Ongoing through to late 2020
CURRENT TRAFFIC CONFIGURATION
EGLINTON AVENUE EAST AND KENNEDY ROAD INTERSECTION
10
• Crews will be performing road works within the four
corners of the Eglinton Ave East and Kennedy
Road intersection.
• A shared through and right turn lane will be
implemented for northbound and southbound traffic
at the intersection.
• Periodic crosswalk closures will be required to
complete the work. A minimum of three crosswalks
will be maintained all times. Signage will be
installed directing pedestrians to available
crosswalks.
Mid July – Early December 2020
TRAFFIC CHANGE AT KENNEDY STATION, EAST OF KENNEDY ROAD
EARLY DECEMBER 2020 FOR 9 MONTHS
11
Traffic Details:
 Vehicles entering Transway Crescent will not be
permitted beyond the Kennedy Station Passenger Pick-
Up and south parking lot access points.
 Signal timing will be changed at Kennedy Road as well
as the North and South Service Road to accommodate
these changes.
 Right turn from eastbound lane on Eglinton and left turn
from westbound lane on Eglinton onto South Service Rd
will be prohibited.
 Left turn from eastbound lane on Eglinton onto North
Service Rd will be prohibited.
 Traffic entering South Service Road will be restricted to
TTC vehicles only.
GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR
KENNEDY STATION
AUGUST 17, 2020
12
• As part of GO Transit improvements at
Kennedy GO Station, crews at Kennedy
Station will be temporarily relocating the
west GO Transit platform as early as
August 17, 2020.
• Pedestrians will be rerouted through the
Kennedy TTC Station
• This configuration will remain in place for
approximately one year.
CONSTRUCTION PROGRESS PHOTOS
13
MAIN ENTRANCE ESCALATOR AND
ELEVATOR INSTALLATION AND BUILD
PAINTING STRUCTURAL
STEEL AT MAIN
ENTRANCE
CLC pharmacy to Kennedy (Nov24)

Weitere ähnliche Inhalte

Was ist angesagt?

Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Crosstown TO
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Crosstown TO
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Crosstown TO
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Crosstown TO
 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Crosstown TO
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020Crosstown TO
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Crosstown TO
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019Crosstown TO
 
CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 Crosstown TO
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsCrosstown TO
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Crosstown TO
 

Was ist angesagt? (20)

Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021
 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019
 
CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
 

Ähnlich wie CLC pharmacy to Kennedy (Nov24)

CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November Crosstown TO
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022Crosstown TO
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Crosstown TO
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCrosstown TO
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meetingCrosstown TO
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Crosstown TO
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCrosstown TO
 
Western works final
Western works final Western works final
Western works final Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 

Ähnlich wie CLC pharmacy to Kennedy (Nov24) (20)

CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
 
Western works final
Western works final Western works final
Western works final
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 

Mehr von Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

Mehr von Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Kürzlich hochgeladen

2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29JSchaus & Associates
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...aartirawatdelhi
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Building the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageBuilding the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageTechSoup
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Roomishabajaj13
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...Suhani Kapoor
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...tanu pandey
 
Fair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CTFair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CTaccounts329278
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 

Kürzlich hochgeladen (20)

2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
Building the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageBuilding the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized Storage
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
Fair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CTFair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CT
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
 

CLC pharmacy to Kennedy (Nov24)

  • 1. November 24, 2020 Eglinton Crosstown LRT Construction Liaison Committee Victoria Park Avenue to Kennedy Station
  • 2. Section Three and Four At-Grade: O’Connor Stop to Ionview Stop
  • 3. CONSTRUCTION ACTIVITIES 3 Location Activity Approx. Date & Duration O’Connor Stop • Concrete work and formwork installation for ramps and curbs • Sidewalk construction at 4 corners of Eglinton Square intersection Ongoing through to late November 2020 November 23, 2020 for two weeks Pharmacy Stop • Sidewalk construction at four corners of the intersection Complete Hakimi Lebovic Stop • Roadworks and sidewalk construction at east side of intersection November 23 for one week Golden Mile Stop • Concrete works for stop ramps November – Mid December 2020 Birchmount Stop • Track works November – Mid December 2020 Rosemount Drive • Massey Creek Culvert: Fill old culvert and build west wing wall. • Concrete works, west of Rosemount Drive, sidewalk construction (north side) November – Mid December 2020 Ionview Stop • Formwork and concrete for stop ramps and curbs • Stop shelter installation Ongoing through to early December 2020 Early December 2020 for one week
  • 4. SIDEWALK CONSTRUCTION – EGLINTON SQUARE 4 November 23, 2020 November 30, 2020 • Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Eglinton Square intersection • Closure of one eastbound and westbound lane at the intersection. • Closure of the northbound lane at the intersection for construction activities on the east side. • Closure of one southbound lane at the intersection for construction activities on the west side. • The east crosswalk will be closed while crews are working on the east side. • All crosswalks will be open while crews work on the west side.
  • 5. SIDEWALK CONSTRUCTION – HAKIMI AND LEBOVIC AVE AT EGLINTON AVE E EAST SIDE 5 November 18 – November 27, 2020 • Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Hakimi Lebovic Ave intersection. Work on the east side will take place November 18 – November 27, 2020 • The Eglinton Ave driveways for 1910 and 1920 Eglinton Ave E will be closed for one week. Alternate driveways will remain accessible on Hakimi Ave and Eglinton Ave E for the duration of the works. • Closure of one eastbound and westbound lane at the intersection. • Closure of one northbound lane at the intersection for construction activities on the east side of the intersection.
  • 6. ROSEMOUNT DRIVE AND EGLINTON AVE E 6 Early January – Late December 2020 • North side closure for Massey Creek Construction • Crews will fill the old culvert and then construct the west wing wall MASSEY CREEK ROOF SLAB CONSTRUCTION IS NOW COMPLETE
  • 7. CONSTRUCTION PROGRESS PHOTOS 7 SIDEWALK CONSTRUCTION AT HAKIMI LEBOVIC INTERSECTION TRACK WORK WEST OF BIRCHMOUNT GUARDRAIL INSTALLATION COMPLETE AT BIRCHMOUTN STOP
  • 9. KENNEDY STATION UPDATE 9 Location Activity Approx. Date & Duration Kennedy Station Main Entrance • Concrete and masonry works • Conduit installation, plumbing and sheet metal works, tiling, masonry works • Structural steel and decking • Elevator installation and painting Ongoing through to late 2020 Kennedy Station – East of GO • Concrete works • Electrical and mechanical works Ongoing through to late 2020 Kennedy Station Concourse Level • Excavation and waterproofing • Concrete works, rebar and shoring Ongoing through to late 2020 Kennedy Portal (west of Kennedy Road) • Railing installation • Installation of light fixtures • Track works Ongoing through to late 2020 Kennedy Station Go Platform • Curtain wall and glazing • Excavation for new east platform • Installation of metal railing • Roofing at GO shelters, painting of shelter and railing • Mechanical and electrical works Ongoing through to late 2020
  • 10. CURRENT TRAFFIC CONFIGURATION EGLINTON AVENUE EAST AND KENNEDY ROAD INTERSECTION 10 • Crews will be performing road works within the four corners of the Eglinton Ave East and Kennedy Road intersection. • A shared through and right turn lane will be implemented for northbound and southbound traffic at the intersection. • Periodic crosswalk closures will be required to complete the work. A minimum of three crosswalks will be maintained all times. Signage will be installed directing pedestrians to available crosswalks. Mid July – Early December 2020
  • 11. TRAFFIC CHANGE AT KENNEDY STATION, EAST OF KENNEDY ROAD EARLY DECEMBER 2020 FOR 9 MONTHS 11 Traffic Details:  Vehicles entering Transway Crescent will not be permitted beyond the Kennedy Station Passenger Pick- Up and south parking lot access points.  Signal timing will be changed at Kennedy Road as well as the North and South Service Road to accommodate these changes.  Right turn from eastbound lane on Eglinton and left turn from westbound lane on Eglinton onto South Service Rd will be prohibited.  Left turn from eastbound lane on Eglinton onto North Service Rd will be prohibited.  Traffic entering South Service Road will be restricted to TTC vehicles only.
  • 12. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR KENNEDY STATION AUGUST 17, 2020 12 • As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station will be temporarily relocating the west GO Transit platform as early as August 17, 2020. • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year.
  • 13. CONSTRUCTION PROGRESS PHOTOS 13 MAIN ENTRANCE ESCALATOR AND ELEVATOR INSTALLATION AND BUILD PAINTING STRUCTURAL STEEL AT MAIN ENTRANCE