The document provides updates on construction activities for the Eglinton Crosstown LRT project in sections 3 and 4 from O'Connor Station to Kennedy Station in November and December 2020. It outlines concrete works, sidewalk construction, track works, and other activities taking place at stops along the route. It also discusses traffic changes and pedestrian detours planned at Kennedy Station in early December 2020 and August 2020 respectively to accommodate GO Transit platform relocation works. Construction is ongoing at stations and is expected to continue through late 2020.
3. CONSTRUCTION ACTIVITIES
3
Location Activity Approx. Date & Duration
O’Connor Stop
• Concrete work and formwork
installation for ramps and curbs
• Sidewalk construction at 4 corners of
Eglinton Square intersection
Ongoing through to late November 2020
November 23, 2020 for two weeks
Pharmacy Stop
• Sidewalk construction at four corners
of the intersection
Complete
Hakimi Lebovic Stop
• Roadworks and sidewalk construction
at east side of intersection
November 23 for one week
Golden Mile Stop • Concrete works for stop ramps November – Mid December 2020
Birchmount Stop • Track works November – Mid December 2020
Rosemount Drive
• Massey Creek Culvert: Fill old culvert
and build west wing wall.
• Concrete works, west of Rosemount
Drive, sidewalk construction (north side)
November – Mid December 2020
Ionview Stop
• Formwork and concrete for stop ramps
and curbs
• Stop shelter installation
Ongoing through to early December 2020
Early December 2020 for one week
4. SIDEWALK CONSTRUCTION – EGLINTON SQUARE
4
November 23, 2020 November 30, 2020
• Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Eglinton Square intersection
• Closure of one eastbound and westbound lane at the intersection.
• Closure of the northbound lane at the intersection for construction activities on the east side.
• Closure of one southbound lane at the intersection for construction activities on the west side.
• The east crosswalk will be closed while crews are working on the east side.
• All crosswalks will be open while crews work on the west side.
5. SIDEWALK CONSTRUCTION – HAKIMI AND LEBOVIC AVE AT EGLINTON AVE E
EAST SIDE
5
November 18 – November 27, 2020
• Crews will be constructing final sidewalks at the four corners
of the Eglinton Ave E and Hakimi Lebovic Ave intersection.
Work on the east side will take place November 18 –
November 27, 2020
• The Eglinton Ave driveways for 1910 and 1920 Eglinton Ave
E will be closed for one week. Alternate driveways will
remain accessible on Hakimi Ave and Eglinton Ave E for the
duration of the works.
• Closure of one eastbound and westbound lane at the
intersection.
• Closure of one northbound lane at the intersection for
construction activities on the east side of the intersection.
6. ROSEMOUNT DRIVE AND EGLINTON AVE E
6
Early January – Late December 2020
• North side closure for Massey Creek Construction
• Crews will fill the old culvert and then construct the west wing wall
MASSEY CREEK ROOF SLAB
CONSTRUCTION IS NOW COMPLETE
7. CONSTRUCTION PROGRESS PHOTOS
7
SIDEWALK CONSTRUCTION AT
HAKIMI LEBOVIC INTERSECTION
TRACK WORK WEST OF
BIRCHMOUNT
GUARDRAIL INSTALLATION
COMPLETE AT BIRCHMOUTN STOP
9. KENNEDY STATION UPDATE
9
Location Activity Approx. Date & Duration
Kennedy Station Main Entrance
• Concrete and masonry works
• Conduit installation, plumbing and sheet
metal works, tiling, masonry works
• Structural steel and decking
• Elevator installation and painting
Ongoing through to late 2020
Kennedy Station – East of GO
• Concrete works
• Electrical and mechanical works
Ongoing through to late 2020
Kennedy Station Concourse Level
• Excavation and waterproofing
• Concrete works, rebar and shoring
Ongoing through to late 2020
Kennedy Portal (west of Kennedy Road)
• Railing installation
• Installation of light fixtures
• Track works
Ongoing through to late 2020
Kennedy Station Go Platform
• Curtain wall and glazing
• Excavation for new east platform
• Installation of metal railing
• Roofing at GO shelters, painting of shelter
and railing
• Mechanical and electrical works
Ongoing through to late 2020
10. CURRENT TRAFFIC CONFIGURATION
EGLINTON AVENUE EAST AND KENNEDY ROAD INTERSECTION
10
• Crews will be performing road works within the four
corners of the Eglinton Ave East and Kennedy
Road intersection.
• A shared through and right turn lane will be
implemented for northbound and southbound traffic
at the intersection.
• Periodic crosswalk closures will be required to
complete the work. A minimum of three crosswalks
will be maintained all times. Signage will be
installed directing pedestrians to available
crosswalks.
Mid July – Early December 2020
11. TRAFFIC CHANGE AT KENNEDY STATION, EAST OF KENNEDY ROAD
EARLY DECEMBER 2020 FOR 9 MONTHS
11
Traffic Details:
Vehicles entering Transway Crescent will not be
permitted beyond the Kennedy Station Passenger Pick-
Up and south parking lot access points.
Signal timing will be changed at Kennedy Road as well
as the North and South Service Road to accommodate
these changes.
Right turn from eastbound lane on Eglinton and left turn
from westbound lane on Eglinton onto South Service Rd
will be prohibited.
Left turn from eastbound lane on Eglinton onto North
Service Rd will be prohibited.
Traffic entering South Service Road will be restricted to
TTC vehicles only.
12. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR
KENNEDY STATION
AUGUST 17, 2020
12
• As part of GO Transit improvements at
Kennedy GO Station, crews at Kennedy
Station will be temporarily relocating the
west GO Transit platform as early as
August 17, 2020.
• Pedestrians will be rerouted through the
Kennedy TTC Station
• This configuration will remain in place for
approximately one year.