SlideShare ist ein Scribd-Unternehmen logo
1 von 14
March 30, 2021
Eglinton Crosstown LRT
Construction Update
Victoria Park Avenue to Kennedy Station
Section Three and Four At-Grade:
O’Connor Stop to Ionview Stop
CONSTRUCTION ACTIVITIES
3
Location Activity Approx. Date & Duration
O’Connor Stop to
Ionview Stop
• Light poles installation (stops) • Completed March
O’Connor Stop
(Victoria Park Ave)
• Shelter finishing activities; platform ramps, walls • Ongoing through April
Pharmacy Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April
Hakimi Lebovic Stop
• Concrete for both east & west planter curbs
• Shelter finishing activities; platform ramps, walls
• Completed March
• Ongoing through April
Golden Mile Stop
(Warden Ave)
• Shelter finishing activities; platform ramps, walls • Ongoing through April
Birchmount Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April
Massey Creek Culvert
• West wing wall construction
• Backfill
• Completed March
• Ongoing through April
Ionview Stop • Shelter finishing activities; platform ramps, walls • Ongoing until April
ROSEMOUNT DRIVE AND EGLINTON AVE E
4
Until as early as April 2021
• North side closure for Massey Creek
Construction
• Crews have completed filling old culvert
• Crews have completed the wingwall
construction
• Crews continue with backfilling and minor
paving activities
CONSTRUCTION PROGRESS PHOTOS
5
CURB COMPLETE
O’CONNOR STOP
PLANTERS COMPLETED
PHARMACY STOP
CONSTRUCTION PROGRESS PHOTOS
6
PLANTERS COMPLETED
PHARMACY STOP
CURBS COMPLETE
BIRCHMOUNT STOP
Kennedy Station
KENNEDY STATION UPDATE
8
Location Activity Approx. Date & Duration
Kennedy Rd and Eglinton Ave E • Pedestrian Change • Ongoing for approx. six months
Kennedy Portal
(west of Kennedy Road)
• Track works • Ongoing through Spring
Kennedy Station Main Entrance
• Conduit installation, plumbing and sheet metal
works, tiling, masonry works
• Elevator & escalator installation
• TPSS & TVS electrical fit up
• Ongoing through 2021
• Ongoing through 2021
• Ongoing until May
Kennedy Station Box
• Concrete works, rebar, and shoring
• Floor tiling
• Ongoing through Spring
• Ongoing through 2021
Kennedy Station GO Entrance and
Platform
• GO entrance precast installation
• Excavation & concrete works
• Retaining wall construction
• Weekend utility work
• Completed March
• Ongoing through June
• Ongoing through Spring
• April 2 - 4
Kennedy Station – East of GO
• Final invert pour; waterproofing
• Concrete & masonry works
• Platform construction, track & drainage
alignment
• Electrical and mechanical works
• Completed March
• Ongoing through Spring
• Ongoing through 2021
• Ongoing through 2021
KENNEDY CURRENT TRAFFIC CONFIGURATION
9
March 2021 for approx. six months
UTILITY CASING CROSSING
10
• Installation of utility casing includes the use
of excavators, front end loaders, rollers,
and tampers
• Crews will be excavating to install the
casing, and then refilling and levelling the
demolition site with fresh granular material
and compaction of the material into the
ground
• Noise and vibration can be expected
April 2-4, 2021
GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR
11
• As part of GO Transit improvements at
Kennedy GO Station, crews at Kennedy
Station have temporarily relocated the west
GO Transit platform
• Pedestrians will be rerouted through the
Kennedy TTC Station
• This configuration will remain in place for
approximately one year.
August 17, 2020 for approx. one year
CONSTRUCTION PROGRESS PHOTOS
12
CONCRETE WORKS
GO EAST PLATFORM
CEILING GRID
INSTALLATION
PLATFORM LEVEL
CONSTRUCTION PROGRESS PHOTOS
13
REBAR AND CONCRETE WORK
STATION BOX
PRECAST INSTALLATION
GO ENTRANCE
CLC Pharmacy to Kennedy 2021

Weitere ähnliche Inhalte

Was ist angesagt?

Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Crosstown TO
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Crosstown TO
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Crosstown TO
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Crosstown TO
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Crosstown TO
 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Crosstown TO
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020Crosstown TO
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019Crosstown TO
 

Was ist angesagt? (20)

Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019
 

Ähnlich wie CLC Pharmacy to Kennedy 2021

Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...Crosstown TO
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Crosstown TO
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meetingCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Crosstown TO
 
Eastern Segment 5 works monthly meeting January 2021
Eastern Segment 5 works monthly meeting January 2021Eastern Segment 5 works monthly meeting January 2021
Eastern Segment 5 works monthly meeting January 2021Crosstown TO
 
Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Crosstown TO
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Crosstown TO
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Crosstown TO
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 Crosstown TO
 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Crosstown TO
 

Ähnlich wie CLC Pharmacy to Kennedy 2021 (20)

Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Eastern Segment 5 works monthly meeting January 2021
Eastern Segment 5 works monthly meeting January 2021Eastern Segment 5 works monthly meeting January 2021
Eastern Segment 5 works monthly meeting January 2021
 
Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022
 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)
 

Mehr von Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

Mehr von Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Kürzlich hochgeladen

The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learningNAP Global Network
 
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSgovindsharma81649
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCNAP Global Network
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processNAP Global Network
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCongressional Budget Office
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...tanu pandey
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.Christina Parmionova
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Call Girls in Nagpur High Profile
 

Kürzlich hochgeladen (20)

The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 

CLC Pharmacy to Kennedy 2021

  • 1. March 30, 2021 Eglinton Crosstown LRT Construction Update Victoria Park Avenue to Kennedy Station
  • 2. Section Three and Four At-Grade: O’Connor Stop to Ionview Stop
  • 3. CONSTRUCTION ACTIVITIES 3 Location Activity Approx. Date & Duration O’Connor Stop to Ionview Stop • Light poles installation (stops) • Completed March O’Connor Stop (Victoria Park Ave) • Shelter finishing activities; platform ramps, walls • Ongoing through April Pharmacy Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April Hakimi Lebovic Stop • Concrete for both east & west planter curbs • Shelter finishing activities; platform ramps, walls • Completed March • Ongoing through April Golden Mile Stop (Warden Ave) • Shelter finishing activities; platform ramps, walls • Ongoing through April Birchmount Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April Massey Creek Culvert • West wing wall construction • Backfill • Completed March • Ongoing through April Ionview Stop • Shelter finishing activities; platform ramps, walls • Ongoing until April
  • 4. ROSEMOUNT DRIVE AND EGLINTON AVE E 4 Until as early as April 2021 • North side closure for Massey Creek Construction • Crews have completed filling old culvert • Crews have completed the wingwall construction • Crews continue with backfilling and minor paving activities
  • 5. CONSTRUCTION PROGRESS PHOTOS 5 CURB COMPLETE O’CONNOR STOP PLANTERS COMPLETED PHARMACY STOP
  • 6. CONSTRUCTION PROGRESS PHOTOS 6 PLANTERS COMPLETED PHARMACY STOP CURBS COMPLETE BIRCHMOUNT STOP
  • 8. KENNEDY STATION UPDATE 8 Location Activity Approx. Date & Duration Kennedy Rd and Eglinton Ave E • Pedestrian Change • Ongoing for approx. six months Kennedy Portal (west of Kennedy Road) • Track works • Ongoing through Spring Kennedy Station Main Entrance • Conduit installation, plumbing and sheet metal works, tiling, masonry works • Elevator & escalator installation • TPSS & TVS electrical fit up • Ongoing through 2021 • Ongoing through 2021 • Ongoing until May Kennedy Station Box • Concrete works, rebar, and shoring • Floor tiling • Ongoing through Spring • Ongoing through 2021 Kennedy Station GO Entrance and Platform • GO entrance precast installation • Excavation & concrete works • Retaining wall construction • Weekend utility work • Completed March • Ongoing through June • Ongoing through Spring • April 2 - 4 Kennedy Station – East of GO • Final invert pour; waterproofing • Concrete & masonry works • Platform construction, track & drainage alignment • Electrical and mechanical works • Completed March • Ongoing through Spring • Ongoing through 2021 • Ongoing through 2021
  • 9. KENNEDY CURRENT TRAFFIC CONFIGURATION 9 March 2021 for approx. six months
  • 10. UTILITY CASING CROSSING 10 • Installation of utility casing includes the use of excavators, front end loaders, rollers, and tampers • Crews will be excavating to install the casing, and then refilling and levelling the demolition site with fresh granular material and compaction of the material into the ground • Noise and vibration can be expected April 2-4, 2021
  • 11. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR 11 • As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station have temporarily relocated the west GO Transit platform • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year. August 17, 2020 for approx. one year
  • 12. CONSTRUCTION PROGRESS PHOTOS 12 CONCRETE WORKS GO EAST PLATFORM CEILING GRID INSTALLATION PLATFORM LEVEL
  • 13. CONSTRUCTION PROGRESS PHOTOS 13 REBAR AND CONCRETE WORK STATION BOX PRECAST INSTALLATION GO ENTRANCE