3. SECTION ONE AT-GRADE UPDATE
3
Activity Location Approx. Date & Duration
Brentcliffe Retaining Wall
Construction
North side of Eglinton Ave, east of
Brentcliffe Rd
On hold
North curb concrete pour
Waterproofing
West Don River Bridge
Completed February
Ongoing through March
• Shelter finishing activities
• Platform ramps
• Platform walls
• Handrails
Sunnybrook Park Stop Ongoing through March
Track Works: Overnight OCS wiring
installation
Closures at Leslie Rd March 1 – April 2
Multi-use path construction: backfill
and compaction
Serena Gundy Park – West of Leslie St. Ongoing through Spring 2021
Pedestrian staircase installation
Backfill on Leslie Trail
Eglinton and Leslie St. – South side Ongoing through Spring 2021
Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
4. RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON
EAST OF BRENTCLIFFE ROAD
4
• This retaining wall is required to hold the
embankment created from the widened Eglinton
Ave.
• Retaining wall construction was put on hold while
temporary slope stabilization work took place
• Slope stabilization work is now complete and
retaining wall construction will resume in March
2021
• Slope restoration design is in review by CTS and
the City of Toronto
5. TRACK WORK: OCS WIRING INSTALLATION
5
Overnight, March 1 – April 2
6. RAMP CONSTRUCTION, WEST OF LESLIE STREET
MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK
6
• Construction activities for path construction include: Excavation, backfill and installation of topsoil
• Landscaping will take place this year as part of the final restoration plan
Mid-July 2020 through Spring 2021
7. PARKING LOT CLOSURE FOR NEW PEDESTRIAN STAIRCASE INSTALLATION
EGLINTON AVENUE EAST AT LESLIE STREET – SOUTH SIDE
7
• Crews will be installing structural steel to form the new pedestrian staircase. A crane is installed installed at the work zone
to lift materials into place.
• To accommodate these activities, a section of the E.T Seton Park north parking lot will be closed. Access for pedestrian,
cyclists and vehicles will be maintained.
• No changes to traffic on Eglinton Avenue East.
Ongoing until Spring 2021
10. SCIENCE CENTRE STATION UPDATE
10
Activity Location Approx. Date & Duration
Artwork tiling
Electrical equipment installation
Station box Completed February
Roofing installation Bus terminal Completed February
Wall tiling
Elevator installation
Main entrance Completed February
Ceiling grid & tile installation
Pedestrian tunnel
Bus terminal
Main entrance
Station box
Ongoing through Spring 2021
Wall & floor tiling
Second art wall installation
Mechanical and electrical installation
Station box Ongoing through Spring 2021
Drywall installation
Wall & floor tiling
Sliding door installation
Bus terminal Ongoing through Spring 2021
Electrical finishes
Floor tiling
Sliding door installation
Main entrance Ongoing through Spring 2021
15. SECTION TWO AT-GRADE UPDATE
15
Activity Location Approx. Date & Duration
• Shelter finishing activities
• Platform curbs
Aga Khan Park & Museum Stop Ongoing through March
Retaining walls Swift Drive & Eglinton Ave E Ongoing through March (North)
Road widening Swift Drive to Bermondsey Road Ongoing through mid-March
Barrier curbs East Don River Bridge Ongoing through March
• Shelter structure installation
• Platform curbs
• Handrails
• North sidewalk
Sloane Stop
Completed February
Ongoing through March
Track Works: Overnight OCS wiring
installation
Closures at Sloane Ave March 1 – April 2
• Shelter finishing activities
• Platform curbs
• Platform ramps
O’Connor Stop Ongoing through March
16. TRACK WORK: OCS WIRING INSTALLATION
16
Overnight, March 1 – April 2