SlideShare ist ein Scribd-Unternehmen logo
1 von 15
Downloaden Sie, um offline zu lesen
January 13, 2022
Eglinton Crosstown LRT
Construction Liaison Committee Meeting
Brentcliffe Road to Victoria Park Avenue
METROLINX LAND ACKNOWLEDGMENT
2
Let us take a moment to acknowledge that we are on the traditional territory of Indigenous
Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples.
We are all Treaty people. Many of us have come here as settlers and immigrants … in this
generation or generations past.
Metrolinx declares its commitment to building meaningful relationships with Indigenous Peoples.
We acknowledge the historic and continued impacts of colonization and the need to work towards
meaningful reconciliation with the original caretakers of this land.
We acknowledge that Metrolinx operates on lands covered by 20 Treaties, and that we have a
responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct
business in a matter that is built on the foundation of trust, respect and collaboration.
Section One At-Grade:
Brentcliffe Portal to Sunnybrook Park Stop
SECTION ONE AT-GRADE UPDATE
4
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Road Restoration Brentcliffe – Don Mills Spring 2022
Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Spring 2022
Landscaping along Eglinton Brentcliffe – Kennedy Resuming Spring 2022
• Brentcliffe Retaining Wall -
Landscape Restoration Works
• East Brentcliffe Retaining Wall
North side of Eglinton Ave, east of
Brentcliffe Rd
Ongoing through Spring 2022
• Platform ramps & curbs
• Electrical finishes
Sunnybrook Park Stop Ongoing through Spring 2022
• Multi-use path construction -
Landscaping works
Serena Gundy Park – West of Leslie St. Ongoing through Spring 2022
EAST TESTING & COMMISSIONING
5
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through Spring 2022.
• Dynamic Testing began August 24, 2021, and
will last through Spring 2022.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
WATERMAIN CONNECTION WORK – EGLINTON AVENUE EAST AND BRENTCLIFFE ROAD
6
• Phase One: Eastbound traffic on Eglinton Ave E
reduced to one lane. South sidewalk closed east
of Brentcliffe Rd. Approx. three weeks.
• Phases Two and Three: Traffic on Eglinton Ave E
reduced to one lane in each direction. Phase
Two: approx. one week ; Phase Three: approx.
three weeks
• Phase Four: Brentcliffe Rd closed at Eglinton Ave
E. Westbound traffic on Eglinton Ave E reduced
to one through-lane and one left-turn lane.
Eastbound traffic on Eglinton Ave E reduced to a
single lane. East crosswalk closed. Approx. three
weeks.
Monday, January 17, 2022 for approx. 10 weeks
• Watermain connection works on Eglinton
Avenue East between Brentcliffe Road and
Glassworks Drive.
• Will include the installation of a new watermain
line and four fire hydrants
• Work between 6:00 a.m. and 11:00 p.m.
CONSTRUCTION PROGRESS PHOTOS
7
GREEN TRACK – CLEAR STONE INSTALLATION
SUNNYBROOK – DON MILLS
INSTALLATION
EAST BRENTCLIFFE RETAINING WALL
Science Centre Station
SCIENCE CENTRE STATION UPDATE
9
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Road Restoration Brentcliffe – Don Mills Spring 2022
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, mechanical and electrical
finishes, handrail installation
Station Box
Ongoing through Spring 2022
Finishing Activities:
• Wall & floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes, canopy Installation
• Bike storage
Bus Terminal
Ongoing through Spring 2022
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes
Main Entrance
Ongoing through Spring 2022
SCIENCE CENTRE TRAFFIC CONFIGURATION
10
August 2021
CONSTRUCTION PROGRESS PHOTOS
11
SIGN BAND INSTALLATION
PLATFORM LEVEL
CLADDING
BUS TERMINAL
Section Two At-Grade
Aga Khan Park & Museum Stop to O’Connor Stop
SECTION TWO AT-GRADE UPDATE
13
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Road Restoration Brentcliffe – Don Mills Spring 2022
Landscaping along Eglinton Brentcliffe – Kennedy Resuming Spring 2022
• Platform ramps & curbs
• Electrical finishes
Aga Khan Park & Museum Stop
• Ongoing through Spring 2022
•
• Platform ramps & curbs
• Electrical finishes
Sloane Stop
• Ongoing through Spring 2022
•
• Platform ramps & curbs
• Electrical finishes
O’Connor Stop
• Ongoing through Spring 2022
•
CONSTRUCTION PROGRESS PHOTOS
14
SIDEWALK WORK
SWIFT DR
LANDSCAPING
GERVAIS DR
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022

Weitere ähnliche Inhalte

Was ist angesagt?

CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Crosstown TO
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
Crosstown TO
 

Was ist angesagt? (20)

CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Cedarvale & Forest Hill Construction Update (November 24, 2021)
Cedarvale & Forest Hill Construction Update (November 24, 2021)Cedarvale & Forest Hill Construction Update (November 24, 2021)
Cedarvale & Forest Hill Construction Update (November 24, 2021)
 
Fairbank-Oakwood Construction Update - January 2022
Fairbank-Oakwood Construction Update - January 2022Fairbank-Oakwood Construction Update - January 2022
Fairbank-Oakwood Construction Update - January 2022
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
 
Eglinton & Mt Pleasant CLC - march 9 2022
Eglinton & Mt Pleasant CLC - march 9 2022Eglinton & Mt Pleasant CLC - march 9 2022
Eglinton & Mt Pleasant CLC - march 9 2022
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 

Ähnlich wie Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022

CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 

Ähnlich wie Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022 (20)

CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
 
CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptxChaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 

Mehr von Crosstown TO

Mehr von Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
 
Test
TestTest
Test
 
Leaside-Laird CLC - March 14 2022 - v2.pdf
Leaside-Laird CLC - March 14 2022 - v2.pdfLeaside-Laird CLC - March 14 2022 - v2.pdf
Leaside-Laird CLC - March 14 2022 - v2.pdf
 

Kürzlich hochgeladen

Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
ScottMeyers35
 
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
ScottMeyers35
 

Kürzlich hochgeladen (20)

Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
 
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...
Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
Honasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdfHonasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdf
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
Vasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In MumbaiVasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
 
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
 
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
 
Private Call Girls Bidar 9332606886Call Girls Advance Cash On Delivery Service
Private Call Girls Bidar  9332606886Call Girls Advance Cash On Delivery ServicePrivate Call Girls Bidar  9332606886Call Girls Advance Cash On Delivery Service
Private Call Girls Bidar 9332606886Call Girls Advance Cash On Delivery Service
 
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
tOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTRtOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTR
 
Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218
 
2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.
 
NGO working for orphan children’s education
NGO working for orphan children’s educationNGO working for orphan children’s education
NGO working for orphan children’s education
 

Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022

  • 1. January 13, 2022 Eglinton Crosstown LRT Construction Liaison Committee Meeting Brentcliffe Road to Victoria Park Avenue
  • 2. METROLINX LAND ACKNOWLEDGMENT 2 Let us take a moment to acknowledge that we are on the traditional territory of Indigenous Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples. We are all Treaty people. Many of us have come here as settlers and immigrants … in this generation or generations past. Metrolinx declares its commitment to building meaningful relationships with Indigenous Peoples. We acknowledge the historic and continued impacts of colonization and the need to work towards meaningful reconciliation with the original caretakers of this land. We acknowledge that Metrolinx operates on lands covered by 20 Treaties, and that we have a responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct business in a matter that is built on the foundation of trust, respect and collaboration.
  • 3. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  • 4. SECTION ONE AT-GRADE UPDATE 4 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing Road Restoration Brentcliffe – Don Mills Spring 2022 Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Spring 2022 Landscaping along Eglinton Brentcliffe – Kennedy Resuming Spring 2022 • Brentcliffe Retaining Wall - Landscape Restoration Works • East Brentcliffe Retaining Wall North side of Eglinton Ave, east of Brentcliffe Rd Ongoing through Spring 2022 • Platform ramps & curbs • Electrical finishes Sunnybrook Park Stop Ongoing through Spring 2022 • Multi-use path construction - Landscaping works Serena Gundy Park – West of Leslie St. Ongoing through Spring 2022
  • 5. EAST TESTING & COMMISSIONING 5 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through Spring 2022. • Dynamic Testing began August 24, 2021, and will last through Spring 2022. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 6. WATERMAIN CONNECTION WORK – EGLINTON AVENUE EAST AND BRENTCLIFFE ROAD 6 • Phase One: Eastbound traffic on Eglinton Ave E reduced to one lane. South sidewalk closed east of Brentcliffe Rd. Approx. three weeks. • Phases Two and Three: Traffic on Eglinton Ave E reduced to one lane in each direction. Phase Two: approx. one week ; Phase Three: approx. three weeks • Phase Four: Brentcliffe Rd closed at Eglinton Ave E. Westbound traffic on Eglinton Ave E reduced to one through-lane and one left-turn lane. Eastbound traffic on Eglinton Ave E reduced to a single lane. East crosswalk closed. Approx. three weeks. Monday, January 17, 2022 for approx. 10 weeks • Watermain connection works on Eglinton Avenue East between Brentcliffe Road and Glassworks Drive. • Will include the installation of a new watermain line and four fire hydrants • Work between 6:00 a.m. and 11:00 p.m.
  • 7. CONSTRUCTION PROGRESS PHOTOS 7 GREEN TRACK – CLEAR STONE INSTALLATION SUNNYBROOK – DON MILLS INSTALLATION EAST BRENTCLIFFE RETAINING WALL
  • 9. SCIENCE CENTRE STATION UPDATE 9 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing Road Restoration Brentcliffe – Don Mills Spring 2022 Finishing Activities: • Floor tiling, ceiling grid & tile installation, mechanical and electrical finishes, handrail installation Station Box Ongoing through Spring 2022 Finishing Activities: • Wall & floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes, canopy Installation • Bike storage Bus Terminal Ongoing through Spring 2022 Finishing Activities: • Floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes Main Entrance Ongoing through Spring 2022
  • 10. SCIENCE CENTRE TRAFFIC CONFIGURATION 10 August 2021
  • 11. CONSTRUCTION PROGRESS PHOTOS 11 SIGN BAND INSTALLATION PLATFORM LEVEL CLADDING BUS TERMINAL
  • 12. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  • 13. SECTION TWO AT-GRADE UPDATE 13 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing Road Restoration Brentcliffe – Don Mills Spring 2022 Landscaping along Eglinton Brentcliffe – Kennedy Resuming Spring 2022 • Platform ramps & curbs • Electrical finishes Aga Khan Park & Museum Stop • Ongoing through Spring 2022 • • Platform ramps & curbs • Electrical finishes Sloane Stop • Ongoing through Spring 2022 • • Platform ramps & curbs • Electrical finishes O’Connor Stop • Ongoing through Spring 2022 •
  • 14. CONSTRUCTION PROGRESS PHOTOS 14 SIDEWALK WORK SWIFT DR LANDSCAPING GERVAIS DR