A PM SQUARED PRESENTATION
ProjectAudit – A Guideline
A PM SQUARED PRESENTATION
A PM SQUARED PRESENTATION
Introduction
There comes a time as a project manager that you will need to conduct a
project audit when the project is not achieving the planned goals and
objectives.
Even the best planned projects will encounter problems along the way.
These hurdles however, do not mean that your project is doomed to
failure. The key is to identify these challenges early and take the
appropriate steps to get your project back on track.
A project audit can be conducted when you have just taken over a project
from a project manager or during a project that is underway and you need
to have an understanding of why the project is running into trouble.
A PM SQUARED PRESENTATION
Introduction
Objective
The objective of the project audit is to evaluate:
• The way your projects are managed
• How your project governance and
methodology meet the business requirements.
Outcome
The project audit will provide :
• A view of what goes well and what needs to be
improved.
• An action plan to bring the project back on
track
A PM SQUARED PRESENTATION
Indicators of a Troubled Project
Category Indication
Documentation
and process
• There is a lack of trust in the project process
• Processes are informal and improvised
• No formal documentation is in place
Cost and
Schedule
• The initial cost does not manage the agreed scope baseline
• The schedule for the project is being pushed out from the original
baseline
Stakeholders • Stakeholders management is not in place
Project Resources • The project teams are not aligned with the required project
deliverables
• There is not enough skills to perform the assigned roles and
responsibilities
Risks • There is significant exposure to risks with large impact
• Mitigation strategies are not working
Quality • There is no proper process in place to ensure quality is managed
throughout the project process
A PM SQUARED PRESENTATION
Action Plan
Step 1
• Define the audit charter
Step 2
• Outline the assessment plan
Step 3
• Conduct the audit
Step 4
• Present the report
Step 5
• Implement the approved plan
A PM SQUARED PRESENTATION
Once it has been agreed that a project audit should go ahead - a project
charter should be setup to provide the project manager with the authority
to move ahead with the audit and to ensure that there is enough budget to
cover the audit.
Identify
stakeholders
State
objectives
State audit
milestones
Identify
Risks
Define the
scope
Approve the
budget
• The inputs for the project charter should be agreed with the
stakeholders
• The project charter should be kept as a project record
Define the Audit Charter
A PM SQUARED PRESENTATION
Outline the Audit Plan
Finalise the
tasks
Finalise the
timeline
Assign the
team
Confirm
the costs
Review
the plan
Finalise the
plan
• During the course of the audit there will be updates to the project
plan.
• Each plan should be re-baselined against the first baseline to manage
and track all of the changes
The plan should very clearly outline what tasks/activities will need to be
carried out to perform the audit. Once the tasks have been agreed the
allocation of the teams and costs can be aligned to allow the project plan
to be approved by the stakeholders
A PM SQUARED PRESENTATION
Conduct the audit
Identify
assessment
areas
Develop
the audit
matrix
Define the
questionnaire
Submit the
questionnaire
Setup
review
meetings
Update the
audit
matrix
• One on one meetings with the team can help with completing the
questionnaires
• Each team member could present to the forum their feedback on why
projects are going wrong and how this could be improved this helps to
build team morale during the audit
The audit will provide an understanding of what needs to be focussed on
to bring the projects back to a successful state. To gather the correct
information for the audit a questionnaire should be sent out to the team.
A PM SQUARED PRESENTATION
Present the report
The report for the audit must be presented in a concise and clear manner
that allows for easy readying by both the stakeholders as well as the team.
The report should clearly show the findings from the audit and provide the
solutions to allow for successful project delivery
Finalise the
Table of
Contents
Send out
first draft
of report
Update report
with feedback
Hold a
walkthrough
meeting
Finalise
the
report
Obtain
stakeholder
approval
• The walkthrough meeting is the right time to finalise any changes to
your document to ensure approval and the ability to move forward to
the implementation of the agreed project process..
A PM SQUARED PRESENTATION
Implement the approved plan
The implementation of the approved plan must be conducted as a normal
project following the agreed process and governance. Training will be
required to introduce the amended process and governance
Confirm
projects to
be rolled
out
Finalise
the
project
roadmap
Provide
training for the
project rollout
Monitor the
progress of
the projects
Final
review on
projects
Finalise process
and move into
project office
• It is important to get buy-in from both the stakeholders and team
during the implementation of the new process. As you rollout the
process allow the team to feedback on what they are happy with and
what needs to be changed.
A PM SQUARED PRESENTATION
Project Audit
Reference and support information
A PM SQUARED PRESENTATION
A PM SQUARED PRESENTATION
Identifythe areasor groups for Assessment
The assessment could cover the following areas:
• Projects in progress
• Governance and methodology
• Project and SDLC processes
• Project Vendor Management
• Project Resource Management
• Project Metrics and Reports
• Project Communication Management
• Project Change Management
• Project Quality Management
A PM SQUARED PRESENTATION
Conducting the Audit – Projects in Progress
Objective:
To measure what project plans are in place to manage the projects
Proposed Questions (these can be amended as required)
• How do you manage and track your projects?
• Are milestones (gates) easily identified?
• Does each task have an approved deliverable?
• Is each project task assigned the correct resources at the agreed allocation?
• Has the project plan been approved and baselined?
• How do you track your resources and time allocations?
• How do you sign off on deliverables?
A PM SQUARED PRESENTATION
Conducting the Audit – Governanceand Methodology
Objective
To measure the governance and methodologies used to manage and deploy your
projects
Proposed Questions (these can be amended as required)
• How do you ensure that governance is applied to your projects?
• What documentation do you use for your projects and where are they kept?
• What project folders are setup to store documentation?
• Do you have a shared site for all project documentation?
• Has the project methodology been approved by the key stakeholders?
• What audits are performed on the projects in progress?
A PM SQUARED PRESENTATION
Conducting the Audit– Project Best Practice
Objective:
To measure if your company uses best practices for the project management
Proposed Questions (these can be amended as required)
• Do you apply the principles of PMBOK for your project management process?
• Do you use Prince2 in any of your processes?
• How do you align your software deliverables and what process are they based on e.g.
Waterfall, Agile, Scrum, Iterative, etc.?
• Are the processes integrated to work within your organisation?
A PM SQUARED PRESENTATION
Conducting the Audit– Vendor Management
Objective:
To measure how the contracts and service level agreements are managed for the
suppliers and vendors
Proposed Questions (these can be amended as required)
• How do you manage your relationships with your vendors?
• What process do you use for Request for Proposal?
• How do you notify vendors that they have been successful?
• What contracts are in place to manage the deliverables?
• How do you measure the deliverables from the vendors?
• What Service Level Agreements do you have in place to maintain operations within
your live environment?
• What outsourcing are you currently performing?
• How do you manage your contracted staff?
• What audits are in place to measure the performance of your suppliers and
contractors?
A PM SQUARED PRESENTATION
Conducting the Audit– Resource Management
Objective:
To measure the project teams and how they are aligned to project deliverables
Proposed Questions (these can be amended as required)
• Does each resource have a defined job description?
• Does the project team understand their specific role and responsibility within the
project?
• Are there the correct skills for the projects to be delivered?
• Are there enough resources on board to deliver the projects?
• Is there an organogram showing how the company structure works?
A PM SQUARED PRESENTATION
Conducting the Audit– Metrics and Reports
Objective:
To measure what reports and metrics are used to track projects within the life cycles and
how these are presented to the stakeholders
Proposed Questions (these can be amended as required)
What metrics are used to measure success or failure within the projects
• Tasks completed
• Slippage ratios (SPI Index)
• Cost slippage (CPI)
• Web Analytics
• MIS reports
• Financial reports
• Supplier review reports
Where are the reports stored?
Do you have a cloud management system to distribute reports to your suppliers and
contractors?
A PM SQUARED PRESENTATION
Perform the Audit – Communication Management
Objective
To measure if reports are timeously distributed using the correct information to the
agreed team members
Proposed Questions (these can be amended as required)
• How is the weekly status presented to the forums?
• How do you manage issues and risks and reporting back on this?
• Do you use dashboard reports on projects and enhancements to show progress?
• What regularly scheduled meetings do you have to report back on projects ?
• How does the project team track and manage problems and issues?
• Who takes the minutes and where are they stored?
A PM SQUARED PRESENTATION
Conducting the Audit – Change Management
Objective:
To measure how all changes within project management are tracked and managed to
ensure that there is a minimum impact to the agreed cost, scope and schedule baselines.
Proposed Questions (these can be amended as required)
• What process is currently in place to manage and control any requested change?
• Is there an understanding of what the impact is?
• Who is responsible for raising the changes and authorising the outcome of the
required changes?
• How are these changes tracked back into the roadmap delivery plan?
A PM SQUARED PRESENTATION
Conducting the Audit – ProjectImplementation
Objective
To ensure that the quality of the product is managed controlled and meets the correct
standards before being deployed
Proposed Questions (these can be amended as required)
• What quality standards are in place for the deployment of projects into the live
environment?
• Are there project-specific instructions regarding the procedures, naming conventions,
supporting tools, equipment, standards and metrics to be applied by the project team
to achieve quality objectives at each phase of the Project
• How is the testing controlled and tracked before deploying the product?
• Is there a roll back process in place?
A PM SQUARED PRESENTATION
Closing Summary
• When there is a common, simple approach for Project Management and the correct tools
are available, your project team will be empowered to reach their goals, together and
individually.
• A easy to use Project Management Methodology gives your business a framework that
makes it achievable for your product to move from vision to action.
• It will also provide you with a competitive advantage to get your product into the market
on time within budget and meeting the quality requirements each and every time.

Weitere ähnliche Inhalte

Was ist angesagt?

OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2Idris Animasaun, PMP
 
2. traditional project management -ch2
2. traditional project management -ch22. traditional project management -ch2
2. traditional project management -ch2Mazhar Poohlah
 
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...Ricardo Viana Vargas
 
Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elementsharoldtaylor1113
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleImran Jamil
 
Neil Varma - Stages of Project Management
Neil Varma - Stages of Project ManagementNeil Varma - Stages of Project Management
Neil Varma - Stages of Project ManagementNeil Varma
 
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process GroupsVanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groupsvanessahartsfield
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guiderobsonnasc
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1reddvise
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesMohamed Loey
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaEdureka!
 
Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsGlobalSkillup
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management UploadBhuWan Khadka
 

Was ist angesagt? (20)

OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
 
2. traditional project management -ch2
2. traditional project management -ch22. traditional project management -ch2
2. traditional project management -ch2
 
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
 
Project management
Project managementProject management
Project management
 
Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elements
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Building a Milestone Plan
Building a Milestone PlanBuilding a Milestone Plan
Building a Milestone Plan
 
Neil Varma - Stages of Project Management
Neil Varma - Stages of Project ManagementNeil Varma - Stages of Project Management
Neil Varma - Stages of Project Management
 
Project Health Checks
Project Health ChecksProject Health Checks
Project Health Checks
 
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process GroupsVanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guide
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
 
Integrating project life cycle with process groups
Integrating project life cycle with process groupsIntegrating project life cycle with process groups
Integrating project life cycle with process groups
 
Different project management methodologies
Different project management methodologiesDifferent project management methodologies
Different project management methodologies
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 
Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groups
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
Project Closure Checklist
Project Closure ChecklistProject Closure Checklist
Project Closure Checklist
 
Portfolio mostafa saad_jan_2020
Portfolio mostafa saad_jan_2020Portfolio mostafa saad_jan_2020
Portfolio mostafa saad_jan_2020
 

Andere mochten auch (6)

Strategy planning for small digital companies
Strategy planning for small digital companiesStrategy planning for small digital companies
Strategy planning for small digital companies
 
Managing your suppliers makes perfect sense
Managing your suppliers makes perfect senseManaging your suppliers makes perfect sense
Managing your suppliers makes perfect sense
 
Pm audit and assessment approach final
Pm audit and assessment approach   finalPm audit and assessment approach   final
Pm audit and assessment approach final
 
Cliona O Hanrahan Introduction 2011
Cliona O Hanrahan Introduction 2011Cliona O Hanrahan Introduction 2011
Cliona O Hanrahan Introduction 2011
 
Jeanie Liu Portfolio
Jeanie Liu PortfolioJeanie Liu Portfolio
Jeanie Liu Portfolio
 
Lets get digital
Lets get digitalLets get digital
Lets get digital
 

Ähnlich wie Pm audit and assessment approach final

122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docxRAJU852744
 
E success client-software-development
E success client-software-developmentE success client-software-development
E success client-software-developmentRiyaan Sharma
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsJacobs Engineering
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1Toe Myint Naing
 
Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdfGourhariBiswas1
 
Project Management
Project ManagementProject Management
Project ManagementAtif Rehmat
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
Your project selected_for_audit_sip18_project_auditors
Your project selected_for_audit_sip18_project_auditorsYour project selected_for_audit_sip18_project_auditors
Your project selected_for_audit_sip18_project_auditorsJoy Gumz
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptxGagan331641
 

Ähnlich wie Pm audit and assessment approach final (20)

Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162
 
Making of Stakeholders Delight
Making of Stakeholders DelightMaking of Stakeholders Delight
Making of Stakeholders Delight
 
Project health check updated and improved
Project health check updated and improvedProject health check updated and improved
Project health check updated and improved
 
pmppgoav14.ppt
pmppgoav14.pptpmppgoav14.ppt
pmppgoav14.ppt
 
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
 
E success client-software-development
E success client-software-developmentE success client-software-development
E success client-software-development
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdf
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
Project Cost.pptx
Project Cost.pptxProject Cost.pptx
Project Cost.pptx
 
The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
 
Your project selected_for_audit_sip18_project_auditors
Your project selected_for_audit_sip18_project_auditorsYour project selected_for_audit_sip18_project_auditors
Your project selected_for_audit_sip18_project_auditors
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 

Mehr von Project Management Solutions (12)

A project quick start guide
A project quick start guideA project quick start guide
A project quick start guide
 
Taking a web site from concept to launch
Taking a web site from concept to launchTaking a web site from concept to launch
Taking a web site from concept to launch
 
Managing multiple projects
Managing multiple projectsManaging multiple projects
Managing multiple projects
 
Turning your project around
Turning your project aroundTurning your project around
Turning your project around
 
A guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery projectA guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery project
 
The agile pmo v2
The agile pmo v2The agile pmo v2
The agile pmo v2
 
Business and project changing the paradigm
Business and project changing the paradigmBusiness and project changing the paradigm
Business and project changing the paradigm
 
Why not - Words to make you think
Why not - Words to make you thinkWhy not - Words to make you think
Why not - Words to make you think
 
Project management today a step ahead
Project management today   a step aheadProject management today   a step ahead
Project management today a step ahead
 
Ready get set go your project is approved
Ready get set go your project is approvedReady get set go your project is approved
Ready get set go your project is approved
 
The digital project manager
The digital project managerThe digital project manager
The digital project manager
 
Getting Ready for UAT
Getting Ready for UATGetting Ready for UAT
Getting Ready for UAT
 

Kürzlich hochgeladen

Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 

Kürzlich hochgeladen (20)

Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 

Pm audit and assessment approach final

  • 1. A PM SQUARED PRESENTATION ProjectAudit – A Guideline A PM SQUARED PRESENTATION
  • 2. A PM SQUARED PRESENTATION Introduction There comes a time as a project manager that you will need to conduct a project audit when the project is not achieving the planned goals and objectives. Even the best planned projects will encounter problems along the way. These hurdles however, do not mean that your project is doomed to failure. The key is to identify these challenges early and take the appropriate steps to get your project back on track. A project audit can be conducted when you have just taken over a project from a project manager or during a project that is underway and you need to have an understanding of why the project is running into trouble.
  • 3. A PM SQUARED PRESENTATION Introduction Objective The objective of the project audit is to evaluate: • The way your projects are managed • How your project governance and methodology meet the business requirements. Outcome The project audit will provide : • A view of what goes well and what needs to be improved. • An action plan to bring the project back on track
  • 4. A PM SQUARED PRESENTATION Indicators of a Troubled Project Category Indication Documentation and process • There is a lack of trust in the project process • Processes are informal and improvised • No formal documentation is in place Cost and Schedule • The initial cost does not manage the agreed scope baseline • The schedule for the project is being pushed out from the original baseline Stakeholders • Stakeholders management is not in place Project Resources • The project teams are not aligned with the required project deliverables • There is not enough skills to perform the assigned roles and responsibilities Risks • There is significant exposure to risks with large impact • Mitigation strategies are not working Quality • There is no proper process in place to ensure quality is managed throughout the project process
  • 5. A PM SQUARED PRESENTATION Action Plan Step 1 • Define the audit charter Step 2 • Outline the assessment plan Step 3 • Conduct the audit Step 4 • Present the report Step 5 • Implement the approved plan
  • 6. A PM SQUARED PRESENTATION Once it has been agreed that a project audit should go ahead - a project charter should be setup to provide the project manager with the authority to move ahead with the audit and to ensure that there is enough budget to cover the audit. Identify stakeholders State objectives State audit milestones Identify Risks Define the scope Approve the budget • The inputs for the project charter should be agreed with the stakeholders • The project charter should be kept as a project record Define the Audit Charter
  • 7. A PM SQUARED PRESENTATION Outline the Audit Plan Finalise the tasks Finalise the timeline Assign the team Confirm the costs Review the plan Finalise the plan • During the course of the audit there will be updates to the project plan. • Each plan should be re-baselined against the first baseline to manage and track all of the changes The plan should very clearly outline what tasks/activities will need to be carried out to perform the audit. Once the tasks have been agreed the allocation of the teams and costs can be aligned to allow the project plan to be approved by the stakeholders
  • 8. A PM SQUARED PRESENTATION Conduct the audit Identify assessment areas Develop the audit matrix Define the questionnaire Submit the questionnaire Setup review meetings Update the audit matrix • One on one meetings with the team can help with completing the questionnaires • Each team member could present to the forum their feedback on why projects are going wrong and how this could be improved this helps to build team morale during the audit The audit will provide an understanding of what needs to be focussed on to bring the projects back to a successful state. To gather the correct information for the audit a questionnaire should be sent out to the team.
  • 9. A PM SQUARED PRESENTATION Present the report The report for the audit must be presented in a concise and clear manner that allows for easy readying by both the stakeholders as well as the team. The report should clearly show the findings from the audit and provide the solutions to allow for successful project delivery Finalise the Table of Contents Send out first draft of report Update report with feedback Hold a walkthrough meeting Finalise the report Obtain stakeholder approval • The walkthrough meeting is the right time to finalise any changes to your document to ensure approval and the ability to move forward to the implementation of the agreed project process..
  • 10. A PM SQUARED PRESENTATION Implement the approved plan The implementation of the approved plan must be conducted as a normal project following the agreed process and governance. Training will be required to introduce the amended process and governance Confirm projects to be rolled out Finalise the project roadmap Provide training for the project rollout Monitor the progress of the projects Final review on projects Finalise process and move into project office • It is important to get buy-in from both the stakeholders and team during the implementation of the new process. As you rollout the process allow the team to feedback on what they are happy with and what needs to be changed.
  • 11. A PM SQUARED PRESENTATION Project Audit Reference and support information A PM SQUARED PRESENTATION
  • 12. A PM SQUARED PRESENTATION Identifythe areasor groups for Assessment The assessment could cover the following areas: • Projects in progress • Governance and methodology • Project and SDLC processes • Project Vendor Management • Project Resource Management • Project Metrics and Reports • Project Communication Management • Project Change Management • Project Quality Management
  • 13. A PM SQUARED PRESENTATION Conducting the Audit – Projects in Progress Objective: To measure what project plans are in place to manage the projects Proposed Questions (these can be amended as required) • How do you manage and track your projects? • Are milestones (gates) easily identified? • Does each task have an approved deliverable? • Is each project task assigned the correct resources at the agreed allocation? • Has the project plan been approved and baselined? • How do you track your resources and time allocations? • How do you sign off on deliverables?
  • 14. A PM SQUARED PRESENTATION Conducting the Audit – Governanceand Methodology Objective To measure the governance and methodologies used to manage and deploy your projects Proposed Questions (these can be amended as required) • How do you ensure that governance is applied to your projects? • What documentation do you use for your projects and where are they kept? • What project folders are setup to store documentation? • Do you have a shared site for all project documentation? • Has the project methodology been approved by the key stakeholders? • What audits are performed on the projects in progress?
  • 15. A PM SQUARED PRESENTATION Conducting the Audit– Project Best Practice Objective: To measure if your company uses best practices for the project management Proposed Questions (these can be amended as required) • Do you apply the principles of PMBOK for your project management process? • Do you use Prince2 in any of your processes? • How do you align your software deliverables and what process are they based on e.g. Waterfall, Agile, Scrum, Iterative, etc.? • Are the processes integrated to work within your organisation?
  • 16. A PM SQUARED PRESENTATION Conducting the Audit– Vendor Management Objective: To measure how the contracts and service level agreements are managed for the suppliers and vendors Proposed Questions (these can be amended as required) • How do you manage your relationships with your vendors? • What process do you use for Request for Proposal? • How do you notify vendors that they have been successful? • What contracts are in place to manage the deliverables? • How do you measure the deliverables from the vendors? • What Service Level Agreements do you have in place to maintain operations within your live environment? • What outsourcing are you currently performing? • How do you manage your contracted staff? • What audits are in place to measure the performance of your suppliers and contractors?
  • 17. A PM SQUARED PRESENTATION Conducting the Audit– Resource Management Objective: To measure the project teams and how they are aligned to project deliverables Proposed Questions (these can be amended as required) • Does each resource have a defined job description? • Does the project team understand their specific role and responsibility within the project? • Are there the correct skills for the projects to be delivered? • Are there enough resources on board to deliver the projects? • Is there an organogram showing how the company structure works?
  • 18. A PM SQUARED PRESENTATION Conducting the Audit– Metrics and Reports Objective: To measure what reports and metrics are used to track projects within the life cycles and how these are presented to the stakeholders Proposed Questions (these can be amended as required) What metrics are used to measure success or failure within the projects • Tasks completed • Slippage ratios (SPI Index) • Cost slippage (CPI) • Web Analytics • MIS reports • Financial reports • Supplier review reports Where are the reports stored? Do you have a cloud management system to distribute reports to your suppliers and contractors?
  • 19. A PM SQUARED PRESENTATION Perform the Audit – Communication Management Objective To measure if reports are timeously distributed using the correct information to the agreed team members Proposed Questions (these can be amended as required) • How is the weekly status presented to the forums? • How do you manage issues and risks and reporting back on this? • Do you use dashboard reports on projects and enhancements to show progress? • What regularly scheduled meetings do you have to report back on projects ? • How does the project team track and manage problems and issues? • Who takes the minutes and where are they stored?
  • 20. A PM SQUARED PRESENTATION Conducting the Audit – Change Management Objective: To measure how all changes within project management are tracked and managed to ensure that there is a minimum impact to the agreed cost, scope and schedule baselines. Proposed Questions (these can be amended as required) • What process is currently in place to manage and control any requested change? • Is there an understanding of what the impact is? • Who is responsible for raising the changes and authorising the outcome of the required changes? • How are these changes tracked back into the roadmap delivery plan?
  • 21. A PM SQUARED PRESENTATION Conducting the Audit – ProjectImplementation Objective To ensure that the quality of the product is managed controlled and meets the correct standards before being deployed Proposed Questions (these can be amended as required) • What quality standards are in place for the deployment of projects into the live environment? • Are there project-specific instructions regarding the procedures, naming conventions, supporting tools, equipment, standards and metrics to be applied by the project team to achieve quality objectives at each phase of the Project • How is the testing controlled and tracked before deploying the product? • Is there a roll back process in place?
  • 22. A PM SQUARED PRESENTATION Closing Summary • When there is a common, simple approach for Project Management and the correct tools are available, your project team will be empowered to reach their goals, together and individually. • A easy to use Project Management Methodology gives your business a framework that makes it achievable for your product to move from vision to action. • It will also provide you with a competitive advantage to get your product into the market on time within budget and meeting the quality requirements each and every time.