SlideShare ist ein Scribd-Unternehmen logo
1 von 30
Outline: One Storey Building
Construction
• Part I: Pre-Construction Process
• Part II: Construction Process
• Break Ground
• Excavation
• Foundation
• Utilities
• Framing
• Roofing
• Weather Resistant Barrier
Outline: One Storey Building
Construction
• Part II: Construction Process
• Rough Plumbing
• Mechanical Systems
• Lighting and Electrical
• Air Sealing
• Insulation
• Drywall
• Sliding
• Flooring
Outline: One Storey Building
Construction
• Part II: Construction Process
• Tiling
• Painting
• Cabinets, Shelving
• Finish Plumbing
• Finish Electrical and Lighting
• Certificate of Occupancy
• Moving In
One Storey Building Construction:
Pre-Construction
Process
Residential
• It is designed for people to live in.
• Site Survey
• provides us with information on land levels,
land contours, trees/vegetation, water/power
service, and footpath locations for accurate
drafting of plans.
Preliminaries and Site
Management
One Storey BuildingConstruction: Pre-Construction Process
• After a contract is awarded, the contractor has to:
• Determine the key personnel to supervise work
• Make provisions for the equipment to be used
• Determine the location and methods of
erecting temporary structures
Preliminaries and Site
Management
One Storey BuildingConstruction: Pre-Construction Process
• The job should be adequate, but not excessively
staffed, to ensure efficient execution of work
• The construction site should be maintained in strict
tidiness and in an orderly routine because it has
psychological effect on the staff and the workers.
Preliminaries and Site
Management
One Storey BuildingConstruction: Pre-Construction Process
• In carrying out the construction work, idle time and
unnecessary cost should be avoided
• Sufficient copies of the plan and specification
should be procured to be distributed.
Preliminaries and Site
Management
One Storey BuildingConstruction: Pre-Construction Process
• Project undergoes series of stages which includes:
• Planning
• Execution of Minor Activities
• Project Phase Out
Preliminaries in Organizing a
Construction Job
One Storey BuildingConstruction: Pre-Construction Process
• Organization of the work consist of making proper
assignments and sequence of the works in a
systematic order aimed at making the best use of
labour, materials and time
Organization of Work
One Storey BuildingConstruction: Pre-Construction Process
• The contractor has to determine the material
requirement and scheduled the sequence of its
deliveries
Material Supply
One Storey BuildingConstruction: Pre-Construction Process
• A purchasing order form should contain all the
information such as:
1. Description of the materials
2. Quantities required
3. Time and place of delivery
4. Unit price
5. Amount
Material Supply
One Storey BuildingConstruction: Pre-Construction Process
• The business must have sufficient capital structure
to sustain it’s growth
Financial and Budgeting
One Storey BuildingConstruction: Pre-Construction Process
• A budget properly planned and operated, may
have a constructive influence on the personnel of
an organization
Financial and Budgeting
One Storey BuildingConstruction: Pre-Construction Process
• It must serve as a means of bringing understanding
of the common goals of all who belong the
organization
• The budget will serve as a coordinating and
unifying influence to all concerned
Financial and Budgeting
One Storey BuildingConstruction: Pre-Construction Process
• It is important to get the right materials delivered
from the supplier to the site on time
Procurement Processes
One Storey BuildingConstruction: Pre-Construction Process
• The following major procurement factors must be
maintained:
1. QUALITY of materials
2. QUANTITY of materials
3. TIME of delivery
4. PRICE of materials
Procurement Processes
One Storey BuildingConstruction: Pre-Construction Process
• Effective inventory control is aimed at providing an
adequate but not excessive supply of materials at
hand at all times to meet operating requirements.
Inventory Control
One Storey BuildingConstruction: Pre-Construction Process
• Safety in the project construction must be given
primary consideration.
• The working place must be properly arranged and
maintained wherein equipment and the like are all
in safe operating conditions
Site Management of the Work
One Storey BuildingConstruction: Pre-Construction Process
• A complete safety program has to do with
promotion of workers health, with prevention of
such occupancy diseases and fire prevention.
Site Management of the Work
One Storey BuildingConstruction: Pre-Construction Process
• Effective maintenance of the plant and
construction equipment is a prerequisite to
efficient operation and uninterrupted construction
activities
Planned Maintenance
One Storey BuildingConstruction: Pre-Construction Process
• Planned maintenance is an organized attempt to
prevent sudden breakdown in equipment and
periodic shutdown for repairs.
Planned Maintenance
One Storey BuildingConstruction: Pre-Construction Process
• Renting equipment offers the advantages of no
capital outlay, no maintenance or servicing worries
for the user.
Equipment Rental
One Storey BuildingConstruction: Pre-Construction Process
Summary: Pre-Construction
Process
• Preliminaries and Site Management
• Preliminaries in Organizing a
Construction Job
• Organization of the Work
• Material Supply
• Financial and Budgeting
• The financial Budget
One Storey Building
Construction
One Storey BuildingConstruction: Pre-Construction Process
Summary: Pre-Construction
Process
• Procurement Process
• Quantity • Time
• Quality • Price
• Inventory Control
• Site Management of the Work
• Planned Maintenance
• Equipment Rental
One Storey Building
Construction
One Storey BuildingConstruction: Pre-Construction Process
Mabbalo!
One Storey Building Construction (Pre-Construction Process)

Weitere ähnliche Inhalte

Was ist angesagt?

Construction difficulties
Construction difficultiesConstruction difficulties
Construction difficultiesNahid0521
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of buildingARUN KUMAR
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture) Muhammad Aljalali
 
9. introduction to site preparation
9. introduction to site preparation9. introduction to site preparation
9. introduction to site preparationNoshad Ahmed Wahocho
 
STRIPPING OF FORMWORK
STRIPPING OF FORMWORKSTRIPPING OF FORMWORK
STRIPPING OF FORMWORKK.K. PATHAK
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & SequenceDavid H Moloney
 
Top 10 quantity surveyors interview questions and answers
Top 10 quantity surveyors interview questions and answersTop 10 quantity surveyors interview questions and answers
Top 10 quantity surveyors interview questions and answersbutlerrhett166
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSKHUSHBU SHAH
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 

Was ist angesagt? (20)

MODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction ManagementMODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction Management
 
Construction difficulties
Construction difficultiesConstruction difficulties
Construction difficulties
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
Construction equipments and methods
Construction equipments and methodsConstruction equipments and methods
Construction equipments and methods
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
9. introduction to site preparation
9. introduction to site preparation9. introduction to site preparation
9. introduction to site preparation
 
STRIPPING OF FORMWORK
STRIPPING OF FORMWORKSTRIPPING OF FORMWORK
STRIPPING OF FORMWORK
 
Construction management
Construction managementConstruction management
Construction management
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
Top 10 quantity surveyors interview questions and answers
Top 10 quantity surveyors interview questions and answersTop 10 quantity surveyors interview questions and answers
Top 10 quantity surveyors interview questions and answers
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Setting out 12042018
Setting out 12042018Setting out 12042018
Setting out 12042018
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 

Ähnlich wie One Storey Building Construction (Pre-Construction Process)

Project life cycle.pptx
Project life cycle.pptxProject life cycle.pptx
Project life cycle.pptxSaranya260167
 
Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfShanthaNimalBandaraA
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfShanthaNimalBandaraA
 
How to Navigate the Commissioning Process From Planning to Post-Constructi...
How to Navigate the Commissioning Process    From Planning to Post-Constructi...How to Navigate the Commissioning Process    From Planning to Post-Constructi...
How to Navigate the Commissioning Process From Planning to Post-Constructi...Olivia Wilson
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTRiyaVerma238431
 
Mechanized construction
Mechanized constructionMechanized construction
Mechanized constructionsrinivas2036
 
iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdfXiMdhk
 
1.Project Management in construction Industry
1.Project Management in construction Industry1.Project Management in construction Industry
1.Project Management in construction IndustryRohitKulkarni528981
 
61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft
61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft
61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draftJames Zhang (Chi, Zhang)
 
Mouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxMouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxZakaria156221
 
Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Elsahen
 
Introduction to construction project.pptx
Introduction to construction project.pptxIntroduction to construction project.pptx
Introduction to construction project.pptxJignesh patel
 
WEC CV_2016 09 06
WEC CV_2016 09 06WEC CV_2016 09 06
WEC CV_2016 09 06Wauren Cruz
 

Ähnlich wie One Storey Building Construction (Pre-Construction Process) (20)

Project life cycle.pptx
Project life cycle.pptxProject life cycle.pptx
Project life cycle.pptx
 
Qaqc in civil construction
Qaqc in civil constructionQaqc in civil construction
Qaqc in civil construction
 
Greg Southorn CV 2017
Greg Southorn CV 2017Greg Southorn CV 2017
Greg Southorn CV 2017
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
 
How to Navigate the Commissioning Process From Planning to Post-Constructi...
How to Navigate the Commissioning Process    From Planning to Post-Constructi...How to Navigate the Commissioning Process    From Planning to Post-Constructi...
How to Navigate the Commissioning Process From Planning to Post-Constructi...
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
 
Mechanized construction
Mechanized constructionMechanized construction
Mechanized construction
 
cv17 uk
cv17 ukcv17 uk
cv17 uk
 
Project Review Presentation (2)
Project Review Presentation (2)Project Review Presentation (2)
Project Review Presentation (2)
 
iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdf
 
1.Project Management in construction Industry
1.Project Management in construction Industry1.Project Management in construction Industry
1.Project Management in construction Industry
 
W1.pdf
W1.pdfW1.pdf
W1.pdf
 
61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft
61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft
61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft
 
Mouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxMouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptx
 
Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016
 
shahul updated resume
shahul updated resumeshahul updated resume
shahul updated resume
 
Introduction to construction project.pptx
Introduction to construction project.pptxIntroduction to construction project.pptx
Introduction to construction project.pptx
 
Ateeq cv d
Ateeq cv dAteeq cv d
Ateeq cv d
 
WEC CV_2016 09 06
WEC CV_2016 09 06WEC CV_2016 09 06
WEC CV_2016 09 06
 

Kürzlich hochgeladen

Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 

Kürzlich hochgeladen (20)

Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 

One Storey Building Construction (Pre-Construction Process)

  • 1.
  • 2. Outline: One Storey Building Construction • Part I: Pre-Construction Process • Part II: Construction Process • Break Ground • Excavation • Foundation • Utilities • Framing • Roofing • Weather Resistant Barrier
  • 3. Outline: One Storey Building Construction • Part II: Construction Process • Rough Plumbing • Mechanical Systems • Lighting and Electrical • Air Sealing • Insulation • Drywall • Sliding • Flooring
  • 4. Outline: One Storey Building Construction • Part II: Construction Process • Tiling • Painting • Cabinets, Shelving • Finish Plumbing • Finish Electrical and Lighting • Certificate of Occupancy • Moving In
  • 5. One Storey Building Construction: Pre-Construction Process
  • 6. Residential • It is designed for people to live in.
  • 7. • Site Survey • provides us with information on land levels, land contours, trees/vegetation, water/power service, and footpath locations for accurate drafting of plans. Preliminaries and Site Management One Storey BuildingConstruction: Pre-Construction Process
  • 8. • After a contract is awarded, the contractor has to: • Determine the key personnel to supervise work • Make provisions for the equipment to be used • Determine the location and methods of erecting temporary structures Preliminaries and Site Management One Storey BuildingConstruction: Pre-Construction Process
  • 9. • The job should be adequate, but not excessively staffed, to ensure efficient execution of work • The construction site should be maintained in strict tidiness and in an orderly routine because it has psychological effect on the staff and the workers. Preliminaries and Site Management One Storey BuildingConstruction: Pre-Construction Process
  • 10. • In carrying out the construction work, idle time and unnecessary cost should be avoided • Sufficient copies of the plan and specification should be procured to be distributed. Preliminaries and Site Management One Storey BuildingConstruction: Pre-Construction Process
  • 11. • Project undergoes series of stages which includes: • Planning • Execution of Minor Activities • Project Phase Out Preliminaries in Organizing a Construction Job One Storey BuildingConstruction: Pre-Construction Process
  • 12. • Organization of the work consist of making proper assignments and sequence of the works in a systematic order aimed at making the best use of labour, materials and time Organization of Work One Storey BuildingConstruction: Pre-Construction Process
  • 13. • The contractor has to determine the material requirement and scheduled the sequence of its deliveries Material Supply One Storey BuildingConstruction: Pre-Construction Process
  • 14. • A purchasing order form should contain all the information such as: 1. Description of the materials 2. Quantities required 3. Time and place of delivery 4. Unit price 5. Amount Material Supply One Storey BuildingConstruction: Pre-Construction Process
  • 15. • The business must have sufficient capital structure to sustain it’s growth Financial and Budgeting One Storey BuildingConstruction: Pre-Construction Process
  • 16. • A budget properly planned and operated, may have a constructive influence on the personnel of an organization Financial and Budgeting One Storey BuildingConstruction: Pre-Construction Process
  • 17. • It must serve as a means of bringing understanding of the common goals of all who belong the organization • The budget will serve as a coordinating and unifying influence to all concerned Financial and Budgeting One Storey BuildingConstruction: Pre-Construction Process
  • 18. • It is important to get the right materials delivered from the supplier to the site on time Procurement Processes One Storey BuildingConstruction: Pre-Construction Process
  • 19. • The following major procurement factors must be maintained: 1. QUALITY of materials 2. QUANTITY of materials 3. TIME of delivery 4. PRICE of materials Procurement Processes One Storey BuildingConstruction: Pre-Construction Process
  • 20. • Effective inventory control is aimed at providing an adequate but not excessive supply of materials at hand at all times to meet operating requirements. Inventory Control One Storey BuildingConstruction: Pre-Construction Process
  • 21. • Safety in the project construction must be given primary consideration. • The working place must be properly arranged and maintained wherein equipment and the like are all in safe operating conditions Site Management of the Work One Storey BuildingConstruction: Pre-Construction Process
  • 22. • A complete safety program has to do with promotion of workers health, with prevention of such occupancy diseases and fire prevention. Site Management of the Work One Storey BuildingConstruction: Pre-Construction Process
  • 23. • Effective maintenance of the plant and construction equipment is a prerequisite to efficient operation and uninterrupted construction activities Planned Maintenance One Storey BuildingConstruction: Pre-Construction Process
  • 24. • Planned maintenance is an organized attempt to prevent sudden breakdown in equipment and periodic shutdown for repairs. Planned Maintenance One Storey BuildingConstruction: Pre-Construction Process
  • 25. • Renting equipment offers the advantages of no capital outlay, no maintenance or servicing worries for the user. Equipment Rental One Storey BuildingConstruction: Pre-Construction Process
  • 26. Summary: Pre-Construction Process • Preliminaries and Site Management • Preliminaries in Organizing a Construction Job • Organization of the Work • Material Supply • Financial and Budgeting • The financial Budget One Storey Building Construction One Storey BuildingConstruction: Pre-Construction Process
  • 27. Summary: Pre-Construction Process • Procurement Process • Quantity • Time • Quality • Price • Inventory Control • Site Management of the Work • Planned Maintenance • Equipment Rental One Storey Building Construction One Storey BuildingConstruction: Pre-Construction Process
  • 28.

Hinweis der Redaktion

  1. Without sufficient financing, a business cannot get started. Without adequate budgeting, a business once started cannot reach it’s full potential.