SlideShare ist ein Scribd-Unternehmen logo
1 von 36
Downloaden Sie, um offline zu lesen
BASELINE SCHEDULING BASICS
                                               Part 2: May 3, 2007

                                                             Mark Boe, P.E., PSP
                                                                   Vice President
                                                          Capital Project Management, Inc.
                                                               mboe@cpmiteam.com

                                                               Chris Carson, PSP
                                                              Project Controls Manager
                                                                 Alpha Corporation
                                                        chris.carson@alphacorporation.com




The information in this presentation or publication was developed and prepared by the authors for the purpose of education about the subject. This presentation or
publication does not necessarily reflect the views of the Construction Management Association of America or constitute a position or policy of the Construction
Management Association of America (CMAA). This material was presented with the permission of the authors and is subject to copyright under applicable law. The
information contained herein is presented as descriptive of issues related to the subject at the time it was presented, but it has not been peer reviewed or approved by
CMAA. No part of this presentation or publication is to be reproduced or used without written permission from the author and CMAA.
Baseline Scheduling
How should you benefit from this
session?
  Understanding of complex concepts
  Understanding of legal risks
  Overview of review standards
  Understanding of complex terminology
  QC – Program & checklists
  Recognition of gamesmanship

                                         2
Introduction – Complex Concepts
 Schedule Approvals
   Traits necessary to approve
   Time frame recommendations for approval
 Failure to approve schedule
   What happens then?
   Best way to minimize risk
 Early Completion schedules
 Ownership of float

                                             3
Review Definitions
Critical Path Method (CPM) – representation of a project
plan by a network that depicts the duration, sequence
and interrelation of the work activities.
Critical Path – longest path (or sequence) of activities,
driven by their relationships, lags, leads, calendars, and
constraints, through the project.
Total Float – the amount of time an activity can slip
without impacting project completion (contingency time).
Logic/Relationship Types – description of the
interrelation between the individual work activities



                                                             4
Schedule Approvals
Schedule traits & features to win approval
  Meets specifications
  Matches Owner dictated sequencing
  Starts and finishes on time
  Provides a ‘reasonable’ plan of work
  Critical path (LP) includes proportional share of
  activities
  Includes Owner mandated milestones
  Includes contractual scope of work
  Provides ‘reasonable’ use of resources
  Does not include hidden tricks such as unknown lags,
  float sequestering, positioning for claims



                                                         5
Schedule Approvals
Time frame recommendations
  No industry standards
  Important to get an approved schedule in place
  Two-Tiered schedules
    • Consider a pre-construction or outline schedule
       submitted early, covering early work
    • More detailed schedule with more time to develop
  Cost and resource loading require more time
    • Consider submitted schedule for preliminary
       schedule as soon as logic worked out prior to loading
  Data needs to be captured periodically while schedule
  is in review (can do informal updates)
  Actual data will help minimize confusion and claims
  positioning by either side

                                                               6
Failure to Approve Schedule
 What happens if schedule is not approved?
   Examine the legal situation if not resolved
     • In a claim situation, any schedules used for
       management of the project will be used for analysis,
       regardless of formal approval
   Examine the management situation
     • Schedules are necessary for planning and
       monitoring
     • If the schedule is used to manage the project, it
       becomes the “schedule”
   Schedules used for billing, if not approved, could hold
   up invoices



                                                              7
Failure to Approve Schedule
 How to minimize risk?
   Require review deficiencies in writing
   Make corrections for reasonable review comments
   Formally submit all revised submittals
   Show re-submittal cycle in schedule
   Keep a copy of official submittal schedule (baseline)
   without progress
   Capture update information even while developing
   schedule
   If stalemate, correct all reasonable, document
   unreasonable requests carefully when submitting last
   schedule
   Use last submitted (the best meeting of the minds for
   the plan) schedule for updates

                                                           8
Early Completion Schedules
 Unintentional Early Completion
   Review durations and other components carefully
   Do not leave float in baseline schedule
   Constrain Substantial Completion for contractual date
   Re-sequence or provide contingency time so schedule
   does not complete early
 Intentional Early Completion
   Check specification requirements for early completion
   Document or require documentation that project was
   bid with general conditions to match project duration
   If Contractor, notify Owner that intention is to finish
   early
   If Owner, suggest formal change order to move the
   completion date to the scheduled completion
   Negotiate the completion during baseline review
                                                             9
Review (or QC) Standards
Develop Standardized Schedule Review Checklist for schedule
review and internal Contractor quality control




                                                              10
Review Standards
Compliance with specifications
Owner milestones or constraints
Start and End dates
Schedule Architecture
  Software settings and rules
  Verify calculations & no progress
  Statistics
  Critical Path settings

                                      11
Review Standards
Schedule Architecture (continued)
  Dictionaries (activity, resource code)
  Calendars
  Evaluate activities
    Descriptions & scope coverage
    Ratio work/non-work activities
    Ratio trade work
    Types (owner, utilities, management, etc.)
    Relationship types

                                                 12
Work Calendars
Purpose
  Tailor the schedule to specific work or non-work
  periods
Examples
  Holiday periods
  Non-work periods (e.g., winter months for sitework
  activities)
  Adverse weather planning (based on NWS average
  records)
  7 day activities vs. 5 day activities (curing or
  submittals)
  Fixed time periods (e.g., available work areas)

                                                       13
Different Calendars = Different Float
                                                             11 12 13 14
  1     2   3   4       5           6    7    8   9   10

One Calendar –                                0 days Float
5 day/week calendar

                                                             Strip Forms
      Form & Pour                   Cure 1 week
                                                                           3
                                                      5
                    5



                                                             11 12 13 14
  1     2   3   4       5           6    7    8   9   10

Multiple Calendars –
5 day/week calendar
      Form & Pour                                            Strip Forms
                    5                                                      3
                                        2 days Float, but
                                        still critical
7 day/week calendar
                                Cure 1 week
                                                      7
                                              10 11 12 13 14 15 16 17 18
  1     2   3       4   5   6   7   8    9
Different Calendars = Different Float
                                                                     11 12 13 14
  1     2   3   4       5           6    7    8   9   10

One Calendar -                                0 days Float
5 day/week calendar

                                                                    Strip Forms
      Form & Pour                   Cure 1 week
                                                                                  3
                                                      5
                    5
                                                                 What’s important
                                                                         11 12 13 14
  1     2   3   4       5           6    7    8   9   10
                                                             The “Cure” activity will
                                                             appear on the 2 day
Multiple Calendars –
                                                             float path even though
5 day/week calendar
                                                             it is critical. The Zero
      Form & Pour                                            Float path willFormsa 5
                                                                         Strip have
                                                             day gap.
                    5                                                               3

                                        2 days Float, but
                                        still critical
7 day/week calendar
                                Cure 1 week
                                                      7
                                              10 11 12 13 14 15 16 17 18
  1     2   3       4   5   6   7   8    9
Work Calendar Best Practices

 Use the least number of calendars that you
 can, while reasonably modeling the project
 Multiple calendars make analysis more
 difficult
 Multiple use of calendars will amplify or
 reduce the effects of delay



                                              16
Review Standards
Schedule Architecture (continued)
  Logic
    Statistics (lags, leads, relationship types)
    Evaluate Critical Path
    Develop rules of thumb for ratio of CP
    activities
         Based on type of project, facilities/infrastructure
     •

         Also review near-critical activities
     •




                                                               17
Review Standards
Data retrieval from schedule
  Develop data crunching methodologies
    Master layouts with filters
    Export filters to export to Excel or Lotus
    Standard Pivot tables
    Input/output worksheet spreadsheets
    Graphical depictions for reasonableness
         Histogram distributions
     •

         Tables
     •

         Charts
     •

                                                 18
Review Standards
Use Pivot Tables or other data
collecting & collating methodologies




                                       19
No. Activities
                       H
                        am
                          m
                           oc
                             ks
                                      an
                                          d
                                A
                                  sp Mile
                             C        ha            st
                              le




                                                                     0
                                                                         50
                                                                              100
                                                                                    150
                                                                                          200
                                                                                                250
                                                                                                      300
                                                       on
                                 ar lt P                    es
                                   in          la
                                      g           c
                                         an em
                                             d            en
                                                G
                                                    ru t
                                                       bb
                                                            i
                                            D
                                      D        em ng
                       E
                        ro               em o
                          si                 ob litio
                            on
                                                  ili n
                                &                    za
                                   S
                                     ed E tion
                                         im lec
                                             en tri
                                                 t C ca
                                                      on l
                                                           tro
                                                                 l
                                                 G
                                         La ra
                                                       d
                                    M nd ing
                                                 sc
                                       at
                                                     a
                                          er
                                            ia pin
                                                              g
                                                lD
                             M                       e
                        S
                         to aint Mo live
                                                              ry
                           rm en b
                               D an iliza
                                 ra         ce          tio
                                    in
                                        / S of n
                                            to Tra
                                                                                                            Distribution of Activities




                                               rm ffi




     Feature of Work
                                                     Se c
                                                          w
                                  S                           er
                                    tri So
                                       pi        un
                               S                      dw
                                 ub ng
                                     m / P al
                                                               l
                                       itt
                                                                                                                                                 proportion detail in trade activities)




                                          al aint
                                 S
                                   id         / A ing
                                                                                                                                                                                            Review Standards




                              U ewa ppr
                                nd                      ov
                                    er lk /                   al
                                                  M
                                       gr
                                          ou ed
                                              nd ia
                                                              n
                                                    U
                                                      til
                                                         iti
                                                                                                                                         Histogram of Activity Work Scope (showing out of




                                                             es
20
Review Standards
Require or provide Written Narrative
  Check specifications
  Develop checklist for narrative
  Develop sequencing plan
  Good narrative explains the plan




                                       21
Review Standards
Develop a good narrative checklist




                                     22
Review Standards
Develop & provide Sequencing Plan




                                    23
Gamesmanship
Approaches used to control outcome, or is it
just bad scheduling?
  No schedule or very late submittal
  Incomplete product submittals (statused as
  done)
  Missing management activities (fab, etc.)
  Overview schedule (minimal detail) or highly
  convoluted schedule (too much logic)
  Constraint driven schedule
  Calendar schedule (especially MSP)


                                                 24
Gamesmanship
Software calendar/date failure or just bad scheduling?
    MS Project
        Status date? Adjustable? Good feature? How does it calculate?
        Who understands it?
        Calendar schedule ability (just type in dates), where’s the logic?
    Primavera P3eC, Version 5.0
        How many ways can you say “date”?
        Remaining & Remaining Late Start/Finish; calculated or manual,
        leveled or not (but not a resource calendar)
        Plain old “Start” or “Finish” – what do they mean; who’s in charge?
          • Start - “Remaining Start date until activity is started, then set to
             the Actual Start date”
          • Finish - “Activity Planned Finish date when…not started, the
             Remaining Finish date when … in progress, and the Actual
             Finish date once … completed.”
    Be sure to understand how the software you are using works with
    progress
    Need industry standardization

                                                                                   25
Update Process
Microsoft Project
Foundations
                  Structural Steel
              4
                                         Roof
                                     4
                                          1
                           Curtainwall
                                                                          Punch
                                                    Interior Finishes
                                                4
                                                                           List
                                                                        4
                                                                             1

Months
                                                10 11 12 13 14 15 16 17 18
1    2   3    4   5    6    7    8       9




                                                                                  26
Update Process
Microsoft Project                        Does not automatically
Foundations                              reschedule uncompleted work
                  Structural Steel
              4
                                         Roof
                                     4
                                          1
                           Curtainwall
                                                                          Punch
                                                    Interior Finishes
                                                4
                                                                           List
                                                                        4
                                                                             1

Months
                                                10 11 12 13 14 15 16 17 18
1    2   3    4   5    6    7    8       9




                                                                                  27
Update Process
Microsoft Project                        Does not automatically
Foundations                              reschedule uncompleted work
                  Structural Steel
              4
                                         Roof
                                     4
                                          1
                           Curtainwall
                                                                           Punch
                                                     Interior Finishes
                                                 4
                                                                            List
                                                                         4
                                                                              1

Months
                                                 10 11 12 13 14 15 16 17 18
1    2   3    4   5    6    7    8       9
Primavera                                Properly rescheduled                      2 months
Foundations
                  Structural Steel
              4
                                         Roof
                                     4
                                             1
                                         Curtainwall
                                                                                      Punch
                                                                Interior Finishes
                                                            4
                                                                                       List
                                                                                    4
                                                                                          1
                                                                                              28
Microsoft Project
Reschedule Uncompleted Work to Start on
Current Date




                                          29
Gamesmanship
Tricks used to benefit schedule creator
    Contrived Critical Path
       Runs primarily through Owner items
       Runs primarily through A&E review
       Inappropriate successor relationships
       Constraints & calendars corrupt path
    Sequestered float (everything is critical)
    Hidden float (lags, durations, calendars)
    Out of proportion detail in trade work
    Inappropriate length of Critical Path
Definition of Critical Path (LP, TF<?)
Any risk shifting behavior

                                                 30
Gamesmanship - Defense
Approaches
  Minimize risk shifting contract language and behavior
  Partnering
     Develop process for updates and revisions early in project
     Follow the process
  Get involved in Dispute Resolution/Claims Avoidance
  Reconcile schedule gain/loss with each update
     Identify causes and responsibility for delay
     Require and provide recovery when schedule slips
     Timely legitimate time extensions
     Do not allow issues to fester


                                                                  31
Gamesmanship - Defense
                  Collect Admin                         Verify All
Request for
                  Progress Data                          Data
Update Data                                                                                                                       No
                                                                                           Compare to            Critical Path
                                                                                            Baseline               Delay?
                                              Status                     Update
                  Collect Field
                                             Schedule                   Schedule
                  Progress Data
                                                                                                                         Yes

                                   Identify Contract
                                                                                                              Identify Previous
                                      Changes
                                                                                                                                                  Publish
                                                                                                                   Period
                                                                                                                                                  Updated
                                                                                                                Critical Path
                                                                                                                                                  Schedule
        Research
                                  Quantify             Identify Causal             Identify Changes
      Documents For
                                   Delays              Delay Activities             To Critical Path
      Driving Delays


                                                                                                 Is the
         Assess                         Any                         Perform                     Owner
                                                       Yes                                                       Yes
                                                                                                                                       Prepare
       Responsibility                Concurrent                 Concurrent Delay              Responsible
                                                                                                                                       Recovery
        For Delays                    Delays?                      Analysis                    For Delay?
                                                                                                                                       Schedule

                                              No
                                                                                                       No
                                                                                                                                   Resolve
                                                                                                                                 Subcontractor
                                    Verify Single                                                 Is a
                                                                        Is the
                                                                                                                                 Contributions
                                    Source Delay                                      No                         No
                                                                                              Subcontractor
                                                                       Owner
                                    Responsibility                                            Responsible
                                                                     Responsible
Develop a                                                                                      For Delay?
                                                                      For Delay?
                                                                                                                       Discuss Delay &
                                                                                                                        Mitigation with
process for updates                                                                                     Yes
                                                                                                                        Subcontractor
                                                                            Yes


and revisions early                                                                                         Discuss Delay                Prepare Delay

& follow it                                                                                                  & Mitigation                  Analysis
                                                                                                             With Owner                 & Change Order
Gamesmanship - Defense
Defense against schedule tricks
  Careful and detailed schedule review
  Analysis of Critical & Near Critical Path
  Keep good records
  Insist on accurate dates
  Promote or insist on maintaining schedule so it is current,
  providing a good model
  Good specifications
  Experienced schedulers and reviewers
  Field buy-in of schedule
  Management use of schedule

                                                                33
Gamesmanship - Defense
Track path to each milestone or constraint separately – multiple
critical paths should be isolated and reported individually




                                                                   34
Gamesmanship - Defense

Suggested Reading
  Jim Zack, Ex.: “Construction Scheduling
  Games & Ways to Win”
  Donald F. McDonald, Ex.: “Tripping Hazards
  in Schedules”
Documents are available at AACE website


                                           35
BASELINE SCHEDULING BASICS
        Part 2: May 3, 2007
   See You in the Next Webinar!

            Mark Boe, P.E., PSP
                    Vice President
           Capital Project Management, Inc.
                mboe@cpmiteam.com

              Chris Carson, PSP
                Project Controls Manager
                   Alpha Corporation
          chris.carson@alphacorporation.com

Weitere ähnliche Inhalte

Was ist angesagt?

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةM Maged Hegazy, LLM, MBA, CCP, P3O
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 

Was ist angesagt? (20)

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافية
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Pmp Final Review - M Maged
Pmp Final Review - M MagedPmp Final Review - M Maged
Pmp Final Review - M Maged
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Schedule Review
Schedule ReviewSchedule Review
Schedule Review
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Delay - EOT claims
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 

Andere mochten auch

Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008jmpflaum
 
Railwayto greenwayfinalpresentation
Railwayto greenwayfinalpresentationRailwayto greenwayfinalpresentation
Railwayto greenwayfinalpresentationcander014
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse WeatherChris Carson
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and trackingyenohhoney
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 

Andere mochten auch (13)

Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008
 
Railwayto greenwayfinalpresentation
Railwayto greenwayfinalpresentationRailwayto greenwayfinalpresentation
Railwayto greenwayfinalpresentation
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and tracking
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 

Ähnlich wie Baseline Scheduling Basics Part 2

Price.rick
Price.rickPrice.rick
Price.rickNASAPMC
 
Price.rick
Price.rickPrice.rick
Price.rickNASAPMC
 
Glen Ballard Last Planner Lean Construction Institute
Glen Ballard Last Planner Lean Construction InstituteGlen Ballard Last Planner Lean Construction Institute
Glen Ballard Last Planner Lean Construction InstituteYefersonCcoyllulle1
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentAcumen
 
Project Planning - Key Concepts for project scheduling
Project Planning - Key Concepts for project schedulingProject Planning - Key Concepts for project scheduling
Project Planning - Key Concepts for project schedulingJaiveer Singh
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
 
20220621 Project Management Innovation Conference Harrisburg PA Seatbelts and...
20220621 Project Management Innovation Conference Harrisburg PA Seatbelts and...20220621 Project Management Innovation Conference Harrisburg PA Seatbelts and...
20220621 Project Management Innovation Conference Harrisburg PA Seatbelts and...Craeg Strong
 
Relationship Business-Projects-Operations
Relationship Business-Projects-OperationsRelationship Business-Projects-Operations
Relationship Business-Projects-OperationsHari Thapliyal
 
Project Managment Good Practices
Project Managment Good PracticesProject Managment Good Practices
Project Managment Good PracticesHari Thapliyal
 
2012 Training Offerings One Sheet Final
2012 Training Offerings One Sheet   Final2012 Training Offerings One Sheet   Final
2012 Training Offerings One Sheet FinalRicky Smith CMRP, CMRT
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.kNASAPMC
 
Process of Project Planning
Process of Project PlanningProcess of Project Planning
Process of Project PlanningAshish Mittal
 
Project Management-scope creep.pptx
Project Management-scope creep.pptxProject Management-scope creep.pptx
Project Management-scope creep.pptxhassan507210
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual ConferenceThe 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual ConferenceJames Kovacevic, MMP CMRP CAMA
 
The Process of Communication, A Practical Guide for Project Managers
The Process of Communication, A Practical Guide for Project ManagersThe Process of Communication, A Practical Guide for Project Managers
The Process of Communication, A Practical Guide for Project ManagersHarvard Web Working Group
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 

Ähnlich wie Baseline Scheduling Basics Part 2 (20)

Price.rick
Price.rickPrice.rick
Price.rick
 
Price.rick
Price.rickPrice.rick
Price.rick
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
Glen Ballard Last Planner Lean Construction Institute
Glen Ballard Last Planner Lean Construction InstituteGlen Ballard Last Planner Lean Construction Institute
Glen Ballard Last Planner Lean Construction Institute
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule Assessment
 
Project Planning - Key Concepts for project scheduling
Project Planning - Key Concepts for project schedulingProject Planning - Key Concepts for project scheduling
Project Planning - Key Concepts for project scheduling
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
20220621 Project Management Innovation Conference Harrisburg PA Seatbelts and...
20220621 Project Management Innovation Conference Harrisburg PA Seatbelts and...20220621 Project Management Innovation Conference Harrisburg PA Seatbelts and...
20220621 Project Management Innovation Conference Harrisburg PA Seatbelts and...
 
Microsot project basics
Microsot project basicsMicrosot project basics
Microsot project basics
 
Relationship Business-Projects-Operations
Relationship Business-Projects-OperationsRelationship Business-Projects-Operations
Relationship Business-Projects-Operations
 
Project Managment Good Practices
Project Managment Good PracticesProject Managment Good Practices
Project Managment Good Practices
 
2012 Training Offerings One Sheet Final
2012 Training Offerings One Sheet   Final2012 Training Offerings One Sheet   Final
2012 Training Offerings One Sheet Final
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
 
Process of Project Planning
Process of Project PlanningProcess of Project Planning
Process of Project Planning
 
Project Management-scope creep.pptx
Project Management-scope creep.pptxProject Management-scope creep.pptx
Project Management-scope creep.pptx
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual ConferenceThe 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
 
The Process of Communication, A Practical Guide for Project Managers
The Process of Communication, A Practical Guide for Project ManagersThe Process of Communication, A Practical Guide for Project Managers
The Process of Communication, A Practical Guide for Project Managers
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 

Mehr von Chris Carson

Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Design &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan PresentationDesign &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan PresentationChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 

Mehr von Chris Carson (20)

Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Design &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan PresentationDesign &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan Presentation
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 

Baseline Scheduling Basics Part 2

  • 1. BASELINE SCHEDULING BASICS Part 2: May 3, 2007 Mark Boe, P.E., PSP Vice President Capital Project Management, Inc. mboe@cpmiteam.com Chris Carson, PSP Project Controls Manager Alpha Corporation chris.carson@alphacorporation.com The information in this presentation or publication was developed and prepared by the authors for the purpose of education about the subject. This presentation or publication does not necessarily reflect the views of the Construction Management Association of America or constitute a position or policy of the Construction Management Association of America (CMAA). This material was presented with the permission of the authors and is subject to copyright under applicable law. The information contained herein is presented as descriptive of issues related to the subject at the time it was presented, but it has not been peer reviewed or approved by CMAA. No part of this presentation or publication is to be reproduced or used without written permission from the author and CMAA.
  • 2. Baseline Scheduling How should you benefit from this session? Understanding of complex concepts Understanding of legal risks Overview of review standards Understanding of complex terminology QC – Program & checklists Recognition of gamesmanship 2
  • 3. Introduction – Complex Concepts Schedule Approvals Traits necessary to approve Time frame recommendations for approval Failure to approve schedule What happens then? Best way to minimize risk Early Completion schedules Ownership of float 3
  • 4. Review Definitions Critical Path Method (CPM) – representation of a project plan by a network that depicts the duration, sequence and interrelation of the work activities. Critical Path – longest path (or sequence) of activities, driven by their relationships, lags, leads, calendars, and constraints, through the project. Total Float – the amount of time an activity can slip without impacting project completion (contingency time). Logic/Relationship Types – description of the interrelation between the individual work activities 4
  • 5. Schedule Approvals Schedule traits & features to win approval Meets specifications Matches Owner dictated sequencing Starts and finishes on time Provides a ‘reasonable’ plan of work Critical path (LP) includes proportional share of activities Includes Owner mandated milestones Includes contractual scope of work Provides ‘reasonable’ use of resources Does not include hidden tricks such as unknown lags, float sequestering, positioning for claims 5
  • 6. Schedule Approvals Time frame recommendations No industry standards Important to get an approved schedule in place Two-Tiered schedules • Consider a pre-construction or outline schedule submitted early, covering early work • More detailed schedule with more time to develop Cost and resource loading require more time • Consider submitted schedule for preliminary schedule as soon as logic worked out prior to loading Data needs to be captured periodically while schedule is in review (can do informal updates) Actual data will help minimize confusion and claims positioning by either side 6
  • 7. Failure to Approve Schedule What happens if schedule is not approved? Examine the legal situation if not resolved • In a claim situation, any schedules used for management of the project will be used for analysis, regardless of formal approval Examine the management situation • Schedules are necessary for planning and monitoring • If the schedule is used to manage the project, it becomes the “schedule” Schedules used for billing, if not approved, could hold up invoices 7
  • 8. Failure to Approve Schedule How to minimize risk? Require review deficiencies in writing Make corrections for reasonable review comments Formally submit all revised submittals Show re-submittal cycle in schedule Keep a copy of official submittal schedule (baseline) without progress Capture update information even while developing schedule If stalemate, correct all reasonable, document unreasonable requests carefully when submitting last schedule Use last submitted (the best meeting of the minds for the plan) schedule for updates 8
  • 9. Early Completion Schedules Unintentional Early Completion Review durations and other components carefully Do not leave float in baseline schedule Constrain Substantial Completion for contractual date Re-sequence or provide contingency time so schedule does not complete early Intentional Early Completion Check specification requirements for early completion Document or require documentation that project was bid with general conditions to match project duration If Contractor, notify Owner that intention is to finish early If Owner, suggest formal change order to move the completion date to the scheduled completion Negotiate the completion during baseline review 9
  • 10. Review (or QC) Standards Develop Standardized Schedule Review Checklist for schedule review and internal Contractor quality control 10
  • 11. Review Standards Compliance with specifications Owner milestones or constraints Start and End dates Schedule Architecture Software settings and rules Verify calculations & no progress Statistics Critical Path settings 11
  • 12. Review Standards Schedule Architecture (continued) Dictionaries (activity, resource code) Calendars Evaluate activities Descriptions & scope coverage Ratio work/non-work activities Ratio trade work Types (owner, utilities, management, etc.) Relationship types 12
  • 13. Work Calendars Purpose Tailor the schedule to specific work or non-work periods Examples Holiday periods Non-work periods (e.g., winter months for sitework activities) Adverse weather planning (based on NWS average records) 7 day activities vs. 5 day activities (curing or submittals) Fixed time periods (e.g., available work areas) 13
  • 14. Different Calendars = Different Float 11 12 13 14 1 2 3 4 5 6 7 8 9 10 One Calendar – 0 days Float 5 day/week calendar Strip Forms Form & Pour Cure 1 week 3 5 5 11 12 13 14 1 2 3 4 5 6 7 8 9 10 Multiple Calendars – 5 day/week calendar Form & Pour Strip Forms 5 3 2 days Float, but still critical 7 day/week calendar Cure 1 week 7 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9
  • 15. Different Calendars = Different Float 11 12 13 14 1 2 3 4 5 6 7 8 9 10 One Calendar - 0 days Float 5 day/week calendar Strip Forms Form & Pour Cure 1 week 3 5 5 What’s important 11 12 13 14 1 2 3 4 5 6 7 8 9 10 The “Cure” activity will appear on the 2 day Multiple Calendars – float path even though 5 day/week calendar it is critical. The Zero Form & Pour Float path willFormsa 5 Strip have day gap. 5 3 2 days Float, but still critical 7 day/week calendar Cure 1 week 7 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9
  • 16. Work Calendar Best Practices Use the least number of calendars that you can, while reasonably modeling the project Multiple calendars make analysis more difficult Multiple use of calendars will amplify or reduce the effects of delay 16
  • 17. Review Standards Schedule Architecture (continued) Logic Statistics (lags, leads, relationship types) Evaluate Critical Path Develop rules of thumb for ratio of CP activities Based on type of project, facilities/infrastructure • Also review near-critical activities • 17
  • 18. Review Standards Data retrieval from schedule Develop data crunching methodologies Master layouts with filters Export filters to export to Excel or Lotus Standard Pivot tables Input/output worksheet spreadsheets Graphical depictions for reasonableness Histogram distributions • Tables • Charts • 18
  • 19. Review Standards Use Pivot Tables or other data collecting & collating methodologies 19
  • 20. No. Activities H am m oc ks an d A sp Mile C ha st le 0 50 100 150 200 250 300 on ar lt P es in la g c an em d en G ru t bb i D D em ng E ro em o si ob litio on ili n & za S ed E tion im lec en tri t C ca on l tro l G La ra d M nd ing sc at a er ia pin g lD M e S to aint Mo live ry rm en b D an iliza ra ce tio in / S of n to Tra Distribution of Activities rm ffi Feature of Work Se c w S er tri So pi un S dw ub ng m / P al l itt proportion detail in trade activities) al aint S id / A ing Review Standards U ewa ppr nd ov er lk / al M gr ou ed nd ia n U til iti Histogram of Activity Work Scope (showing out of es 20
  • 21. Review Standards Require or provide Written Narrative Check specifications Develop checklist for narrative Develop sequencing plan Good narrative explains the plan 21
  • 22. Review Standards Develop a good narrative checklist 22
  • 23. Review Standards Develop & provide Sequencing Plan 23
  • 24. Gamesmanship Approaches used to control outcome, or is it just bad scheduling? No schedule or very late submittal Incomplete product submittals (statused as done) Missing management activities (fab, etc.) Overview schedule (minimal detail) or highly convoluted schedule (too much logic) Constraint driven schedule Calendar schedule (especially MSP) 24
  • 25. Gamesmanship Software calendar/date failure or just bad scheduling? MS Project Status date? Adjustable? Good feature? How does it calculate? Who understands it? Calendar schedule ability (just type in dates), where’s the logic? Primavera P3eC, Version 5.0 How many ways can you say “date”? Remaining & Remaining Late Start/Finish; calculated or manual, leveled or not (but not a resource calendar) Plain old “Start” or “Finish” – what do they mean; who’s in charge? • Start - “Remaining Start date until activity is started, then set to the Actual Start date” • Finish - “Activity Planned Finish date when…not started, the Remaining Finish date when … in progress, and the Actual Finish date once … completed.” Be sure to understand how the software you are using works with progress Need industry standardization 25
  • 26. Update Process Microsoft Project Foundations Structural Steel 4 Roof 4 1 Curtainwall Punch Interior Finishes 4 List 4 1 Months 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9 26
  • 27. Update Process Microsoft Project Does not automatically Foundations reschedule uncompleted work Structural Steel 4 Roof 4 1 Curtainwall Punch Interior Finishes 4 List 4 1 Months 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9 27
  • 28. Update Process Microsoft Project Does not automatically Foundations reschedule uncompleted work Structural Steel 4 Roof 4 1 Curtainwall Punch Interior Finishes 4 List 4 1 Months 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9 Primavera Properly rescheduled 2 months Foundations Structural Steel 4 Roof 4 1 Curtainwall Punch Interior Finishes 4 List 4 1 28
  • 29. Microsoft Project Reschedule Uncompleted Work to Start on Current Date 29
  • 30. Gamesmanship Tricks used to benefit schedule creator Contrived Critical Path Runs primarily through Owner items Runs primarily through A&E review Inappropriate successor relationships Constraints & calendars corrupt path Sequestered float (everything is critical) Hidden float (lags, durations, calendars) Out of proportion detail in trade work Inappropriate length of Critical Path Definition of Critical Path (LP, TF<?) Any risk shifting behavior 30
  • 31. Gamesmanship - Defense Approaches Minimize risk shifting contract language and behavior Partnering Develop process for updates and revisions early in project Follow the process Get involved in Dispute Resolution/Claims Avoidance Reconcile schedule gain/loss with each update Identify causes and responsibility for delay Require and provide recovery when schedule slips Timely legitimate time extensions Do not allow issues to fester 31
  • 32. Gamesmanship - Defense Collect Admin Verify All Request for Progress Data Data Update Data No Compare to Critical Path Baseline Delay? Status Update Collect Field Schedule Schedule Progress Data Yes Identify Contract Identify Previous Changes Publish Period Updated Critical Path Schedule Research Quantify Identify Causal Identify Changes Documents For Delays Delay Activities To Critical Path Driving Delays Is the Assess Any Perform Owner Yes Yes Prepare Responsibility Concurrent Concurrent Delay Responsible Recovery For Delays Delays? Analysis For Delay? Schedule No No Resolve Subcontractor Verify Single Is a Is the Contributions Source Delay No No Subcontractor Owner Responsibility Responsible Responsible Develop a For Delay? For Delay? Discuss Delay & Mitigation with process for updates Yes Subcontractor Yes and revisions early Discuss Delay Prepare Delay & follow it & Mitigation Analysis With Owner & Change Order
  • 33. Gamesmanship - Defense Defense against schedule tricks Careful and detailed schedule review Analysis of Critical & Near Critical Path Keep good records Insist on accurate dates Promote or insist on maintaining schedule so it is current, providing a good model Good specifications Experienced schedulers and reviewers Field buy-in of schedule Management use of schedule 33
  • 34. Gamesmanship - Defense Track path to each milestone or constraint separately – multiple critical paths should be isolated and reported individually 34
  • 35. Gamesmanship - Defense Suggested Reading Jim Zack, Ex.: “Construction Scheduling Games & Ways to Win” Donald F. McDonald, Ex.: “Tripping Hazards in Schedules” Documents are available at AACE website 35
  • 36. BASELINE SCHEDULING BASICS Part 2: May 3, 2007 See You in the Next Webinar! Mark Boe, P.E., PSP Vice President Capital Project Management, Inc. mboe@cpmiteam.com Chris Carson, PSP Project Controls Manager Alpha Corporation chris.carson@alphacorporation.com