SlideShare ist ein Scribd-Unternehmen logo
1 von 28
Practical Construction
Law for Practitioners
- Payments
Chan Kheng Hoe
Topics Covered
● Must retention sum be in separate account?
● Can sub-contract provide for back-to-back
payments?
● Can contractor suspend, go slow or
terminate due to non-payment?
● Difference between interim, penultimate and
final certs?
● Can certificates be revised?
Retention Monies- must it be
in a separate account? (1)
For discussion
Why is this question important?
Retention Monies- must it be
in a separate account? (2)
Why is this question important?
● Most contracts provide for retention
sum (usually 5%)
● Usually released in 2 moiety
○ 1st moiety upon CPC
○ 2nd moiety upon CMGD
● If not set aside in separate account:
○ Employer may utilise monies for its
own purposes
○ Monies at risk if employer enters into
liquidation before full release
○ Employer may be indebted to other
creditors whose claim may affect the
monies held
Retention Monies- must it be
in a separate account? (3)
Contractually:
● PAM
○ Employer has fiduciary duty as trustee of
money to Contractor
○ Contractor’s beneficial interest subject to
deductions certified by Architect
○ Contractor can demand for monies to be
held in trust account at its cost
● CIDB
● JKR
○ No retention sum - use of performance bond
instead
For discussion:
● Even though PAM provides for contractors
to demand for monies to be held in trust
account, it is extremely rare for contractors
to do so. Why do you think that is so?
Retention Monies- must it be
in a separate account? (4)
Case Law: Qimonda Malaysia Sdn Bhd (in
liquidation) v Sediabena Sdn Bhd & Anor
[2012] 3 MLJ 422, CA
Facts:
● Employer voluntarily wound up
● Did not release in excess of RM6m of
retention sum to contractor & sub-con
● Contractor sought declaration retention
monies were held in trust
Employer’s Arguments:
● Contract does not provide for a trust
● Retention sum not set aside in separate
account (no request by Contractor either)
● Contractor filed proof of debt as creditor-
claim as trust money would be preferential
treatment of Contractor as a creditor
● So, how would you argue against the
Employer in this case?
Retention Monies- must it be
in a separate account? (5)
Case Law: Qimonda Malaysia Sdn Bhd (in
liquidation) v Sediabena Sdn Bhd & Anor
[2012] 3 MLJ 422, CA
Contractor’s Arguments:
● Retention monies, by nature, are trust
monies
● Express clause not a precondition of trust-
can be by operation of law
● Employer is fiduciary to the trust
● No issue of preferential treatment because
retention monies do not belong to Employer
in the first place
● Filing of proof of debt as an estoppel is an
afterthought and non-issue, and is without
prejudice to Contractor’s claim for retention
sum as trust money
So, how would you decide if you were the
panel?
Retention Monies- must it be
in a separate account? (6)
Case Law: Qimonda Malaysia Sdn Bhd (in
liquidation) v Sediabena Sdn Bhd & Anor
[2012] 3 MLJ 422, CA
Held by the Court:
● Property in retention sum resides with
Contractor and is held by Employer in trust
● Retention Sum already earned by
Contractor for works already done- mere
provision for making good defects. Even if
mixed in common fund, is traceable
● No requirement to be held in separate
account or Contractor must make such
request. Contractor may not want to
jeopardise relationship/applied its mind
● Failure to separate monies cannot defeat
the trust. Release or preservation of monies
after liquidation is not preferential treatment
because monies do not belong to Employer
● Allowing retention to be part of general
funds would unjustly enrich other creditors
Back to Back Payments (1)
Commonly known as:
● Back-to-back
● Pay when paid
● Pay if paid
Back to Back Payments (2)
Not so much an issue any longer.
Section 35(1) CIPAA
● Renders conditional payment
provisions void
For discussion:
● Are conditional payment clauses in
construction contracts entered into
prior to CIPAA void?
● Wouldn’t a retrospective application of
CIPAA be an interference with vested
interests/rights?
Back to Back Payments (3)
Case Law: UDA Holdings Bhd v Bisraya
Construction Sdn Bhd & Anor and
another case [2015] 11 MLJ 499, HC
Central Issue: Whether CIPAA applies to
payment disputes and their underlying
contracts which arose before the coming
into force of CIPAA
Important Consideration:
● CIPAA not only introduces
adjudication but also affects
substantive rights, including:
○ Right of Contractor to suspend works
○ Right of Contractor to demand direct
payment from principal
○ Prohibition of conditional payments
Back to Back Payments (4)
Case Law: UDA Holdings Bhd v Bisraya
Construction Sdn Bhd & Anor and
another case [2015] 11 MLJ 499, HC
Held by Court:
● “Substantive rights” are not vested by
written law but merely in contracts
● Rights not accrued, vested or acquired
save for pending liti/ arb preserved
under s41
● CIPAA as new procedural legislation
introduces new forum, and no vested
rights under law affected, so can apply
retrospectively
● Section 35 CIPAA is merely
declaratory in nature
● In any case, if conditional payment
defence is allowed, it would defeat
CIPAA
Right of Contractor to
Suspend, Go Slow and
Terminate (1)
For Discussion
Based on general principles of law, do you
think that a contractor has the right to
suspend works, go slow on works, or even
terminate the contract for failure of the
Employer to make timely progress
payments?
Right of Contractor to
Suspend, Go Slow and
Terminate (2)
100% Safe Approach
Section 29 CIPAA
● Contractor may suspend works or
reduce rate of progress after 14 days’
notice if adjudicated sum is not paid
● When he does so, the Contractor:
○ Is not in breach of contract
○ Is entitled to reasonable EOT
○ Is entitled to recover loss and
expenses
○ Must resume work within 10 working
days after being paid
Right of Contractor to
Suspend, Go Slow and
Terminate (3)
Outside the scope of CIPAA, the Contractor
would have to rely on contractual provisions
or common law principles
For example, PAM:
● Failure to pay certified sums allows
Contractor to suspend works after 14
days’ notice
● Contractor may also terminate the
contract for failure to pay certified
sums or obstruction from issuance of
certificates by Employer
● Note: Going slow is not provided in all
contracts. If not provided, it would
seem a riskier approach because time
continues to run leading to potential
issues with delay/LAD
Right of Contractor to
Suspend, Go Slow and
Terminate (4)
Case Law: Kah Seng Construction Sdn
Bhd v Selsin Development Sdn Bhd
[1997] 1 CLJ Supp 448, HC
Facts:
● There was no formal contract
● Contractor made claims progressively
and certificates were issued
● On basis of estimated costs for
defective works and LAD, Employer
withheld payment of later certificates
● Contractor suspended works and sued
for payment. Employer counterclaimed
for damages.
So how would you decide if you were the
judge in this case?
Right of Contractor to
Suspend, Go Slow and
Terminate (5)
Case Law: Kah Seng Construction Sdn
Bhd v Selsin Development Sdn Bhd
[1997] 1 CLJ Supp 448, HC
Held:
● Contractor can elect to terminate if
there is repudiatory breach by
Employer or to affirm the contract and
proceed with works
● There is no intermediate right to
suspend works
● Any suspension becomes a
repudiatory breach by the Contractor
In Conclusion, how would you advise a
Contractor client who wants to suspend
works for non-payment?
Interim, Penultimate and Final
Certs (1)
Interim certificates:
● Issued progressively to estimate
amount and value of work carried out
and payment due to Contractor
Penultimate certificate:
● Issued after completion and before
final certificate- usually after CPC to
facilitate release of retention sums
Final certificate:
● Issued at end of contract period to
verify final amount due (after CMGD)
The effect and conclusiveness of the
certificate largely depends on the
contractual terms, but even a “conclusive”
certificate may be reviewed by an arbitrator
or challenged before a judge.
Interim, Penultimate and Final
Certs (2)
Example of Contractual Term in PAM:
● Final Certificates are conclusive with
regard to the final value of the works
carried out
● But not conclusive that any work,
materials, goods and designs are in
accordance with the Contract
Interim, Penultimate and Final
Certs (3)
Case Law: Shen Yuen Pai v Dato Wee
Hood Teck & Ors [1976] 1 MLJ 16
● This case discussed, inter alia, the
position of the Architect’s Final
Certificate
Held by Court:
● Architect is owner’s agent to give
instructions for works
● But for issuing certificates, Architect is
independent authority
● Architect owes duty of care not to
issue final certificate unless satisfied
with work. Once issued, final cert is
conclusive
● Form of cert depends on contract
terms. If no form is prescribed,
Architect can determine the form.
Interim, Penultimate and Final
Certs (4)
c.f. Thamesa Designs Sdn Bhd & Ors v
Kuching Hotels Sdn Bhd [1993] 3 MLJ
25, SC
Held:
Employer handed over site late to
contractor
Employer therefore not entitled to LAD
Certificate of final payment issued by
consultant authorizing deduction of
LAD is invalid and not binding on
parties
LAD which was deducted from retention
fund must be restored
Note: Article by Vinayak Pradhan questions
case- Shen Yuen Pai not brought to
Court’s attention
Revision of certificates (1)
PAM:
● Architect cannot revise payment
certificates except for clerical,
computational and typographical
errors
● But Architect can by a subsequent
certificate correct or modify any
valuation errors in earlier certificates
CIDB:
● Superintending Officer can by any
Interim Certificate correct any error in
previous Interim Certificate and adjust
amount due to account for any under
or over valuation
Revision of certificates (2)
Case Law: Fairweather Ltd v Asden
Securities Ltd (1979) 12 BLR 40
Facts:
● After issuing Final Certificate,
Architect subsequently issued CNC
Held by Court:
● After issuing Final Certificate,
Architect was functus officio and
precluded from issuing further CNC
cf. Bukit Cerakah Development Sdn Bhd v
L’Grande Development Sdn Bhd [2008] 3
MLJ 547, CA held:
● It is a question of construction and not
a question of general law as to
whether an Architect is functus
Claims for Direct Payment (1)
For discussion:
Can a sub-contractor make a claim for
direct payment from the Employer?
Would your answer be different if it was a
nominated sub-contractor?
Claims for direct payment (2)
General Principle: Privity of Contract
There is no privity of contract between a
subcontractor and an Employer to allow a
direct claim
Exceptions:
● Contractual exceptions (eg JKR
contracts)
● Statutory exceptions (CIPAA)
Claims for direct payment (3)
Contractual Exceptions
● JKR contracts provide for direct
payment to nominated sub-contractors
● Even in non-JKR contracts, some
NSCs require direct payment when
nominated- usually by a side letter or
supplemental agreement
● Must be agreed to by the Main
Contractor
Statutory Exception
● Section 30 CIPAA allows for requests
to be made to principal for direct
payment of adjudicated sum
● But there is no provision for
consequences to principal who fails to
comply
● So what can be done if principal fails
to comply?
Claims for direct payment (4)
Practical Problems with Direct Payment
● Potentially creates a collateral contract
between sub-contractor and Employer
(would it subject Employer to potential
adjudication claims?)
● Potentially an undue preference of the
sub-contractor as an unsecured
creditor in the event of insolvency of
Main Contractor
● This issue arose in:
○ Joo Yee Construction Pte Ltd v
Diethelm Industries Pte Ltd & Ors
[1990] 2 MLJ 66, HC (S’pore)
● Direct payment to sub-contractor may
not have taken into account defects or
delays, leaving main contractor
saddled with all defects and LAD
claims by Employer
That’s all Folks!
Thank You
Chan Kheng Hoe
khenghoe@khenghoe.com

Weitere ähnliche Inhalte

Was ist angesagt?

A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Sow Wei Henn
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct paymentsKheng Hoe Advocates
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement methodhiewliming
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sumEst
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Arissa Loh
 
PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation Jaey Chai
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017DarrenTofu
 

Was ist angesagt? (20)

A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
SMM2 Explained
SMM2 ExplainedSMM2 Explained
SMM2 Explained
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct payments
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 

Andere mochten auch

Personal Data Protection in Malaysia
Personal Data Protection in MalaysiaPersonal Data Protection in Malaysia
Personal Data Protection in Malaysiakhenghoe
 
Overtime in Quantity Surveying Firms in Malaysia
Overtime in Quantity Surveying Firms in MalaysiaOvertime in Quantity Surveying Firms in Malaysia
Overtime in Quantity Surveying Firms in MalaysiaIshka Rogbeer
 
ICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxmkyong1996
 
Company profile 2012 (rev.7)
Company profile 2012 (rev.7)Company profile 2012 (rev.7)
Company profile 2012 (rev.7)PK146
 
Measurement 4 Presentation (QS)
Measurement 4 Presentation (QS)Measurement 4 Presentation (QS)
Measurement 4 Presentation (QS)Hasif Alias
 
Universiti Teknologi Malaysia
Universiti Teknologi MalaysiaUniversiti Teknologi Malaysia
Universiti Teknologi Malaysialeversole
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor温 庄壁
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)Js Cheok
 
Quantity Surveyor CV
Quantity  Surveyor CVQuantity  Surveyor CV
Quantity Surveyor CVvasant koli
 
RWY CIPAA 2012 - Scope and Applicability
RWY CIPAA 2012 - Scope and ApplicabilityRWY CIPAA 2012 - Scope and Applicability
RWY CIPAA 2012 - Scope and Applicabilityjyhling
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorSyafiq Deen
 
50639312 roll-of-quantity-surveyor
50639312 roll-of-quantity-surveyor50639312 roll-of-quantity-surveyor
50639312 roll-of-quantity-surveyorhlksd
 

Andere mochten auch (20)

MSc Construction Law & Practice
MSc Construction Law & PracticeMSc Construction Law & Practice
MSc Construction Law & Practice
 
Personal Data Protection in Malaysia
Personal Data Protection in MalaysiaPersonal Data Protection in Malaysia
Personal Data Protection in Malaysia
 
Accounts project
Accounts projectAccounts project
Accounts project
 
Ici qs
Ici qsIci qs
Ici qs
 
Overtime in Quantity Surveying Firms in Malaysia
Overtime in Quantity Surveying Firms in MalaysiaOvertime in Quantity Surveying Firms in Malaysia
Overtime in Quantity Surveying Firms in Malaysia
 
ICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptx
 
Company profile 2012 (rev.7)
Company profile 2012 (rev.7)Company profile 2012 (rev.7)
Company profile 2012 (rev.7)
 
Measurement 4 Presentation (QS)
Measurement 4 Presentation (QS)Measurement 4 Presentation (QS)
Measurement 4 Presentation (QS)
 
Universiti Teknologi Malaysia
Universiti Teknologi MalaysiaUniversiti Teknologi Malaysia
Universiti Teknologi Malaysia
 
Qs booklet
Qs bookletQs booklet
Qs booklet
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
 
Meas 4-presentation
Meas 4-presentationMeas 4-presentation
Meas 4-presentation
 
Introduction
IntroductionIntroduction
Introduction
 
Quantity Surveyor CV
Quantity  Surveyor CVQuantity  Surveyor CV
Quantity Surveyor CV
 
RWY CIPAA 2012 - Scope and Applicability
RWY CIPAA 2012 - Scope and ApplicabilityRWY CIPAA 2012 - Scope and Applicability
RWY CIPAA 2012 - Scope and Applicability
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
50639312 roll-of-quantity-surveyor
50639312 roll-of-quantity-surveyor50639312 roll-of-quantity-surveyor
50639312 roll-of-quantity-surveyor
 

Ähnlich wie Payments in the construction industry

Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-paymentArthur Wilson
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
CIPAA Update June 2019 - a case of creeping complexities?
CIPAA Update June 2019 - a case of creeping complexities?CIPAA Update June 2019 - a case of creeping complexities?
CIPAA Update June 2019 - a case of creeping complexities?Kheng Hoe Advocates
 
Contract - Construction Contracts and Specification
Contract - Construction Contracts and SpecificationContract - Construction Contracts and Specification
Contract - Construction Contracts and SpecificationMANNU KUMAR
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...SHKLaw
 
CL Seminar
CL SeminarCL Seminar
CL Seminarkohwenqi
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - QuestionKai Yun Pang
 
FM Forum - Termination & TUPE
FM Forum - Termination & TUPEFM Forum - Termination & TUPE
FM Forum - Termination & TUPELewis Silkin
 
Controversies in taxation of real estate projects & ICDs for real estate deve...
Controversies in taxation of real estate projects & ICDs for real estate deve...Controversies in taxation of real estate projects & ICDs for real estate deve...
Controversies in taxation of real estate projects & ICDs for real estate deve...Kunal Gandhi
 
APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...Association for Project Management
 
20091118 Construction Life cycle completion
20091118 Construction Life cycle completion20091118 Construction Life cycle completion
20091118 Construction Life cycle completionraymond_wan2005
 
COVID-19 (Coronavirus): Your Business Questions Answered
COVID-19 (Coronavirus): Your Business Questions AnsweredCOVID-19 (Coronavirus): Your Business Questions Answered
COVID-19 (Coronavirus): Your Business Questions AnsweredTom Willis
 

Ähnlich wie Payments in the construction industry (20)

Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
 
Seminar
SeminarSeminar
Seminar
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
CIPAA Update June 2019 - a case of creeping complexities?
CIPAA Update June 2019 - a case of creeping complexities?CIPAA Update June 2019 - a case of creeping complexities?
CIPAA Update June 2019 - a case of creeping complexities?
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
Contract - Construction Contracts and Specification
Contract - Construction Contracts and SpecificationContract - Construction Contracts and Specification
Contract - Construction Contracts and Specification
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
 
CL Seminar
CL SeminarCL Seminar
CL Seminar
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
FM Forum - Termination & TUPE
FM Forum - Termination & TUPEFM Forum - Termination & TUPE
FM Forum - Termination & TUPE
 
Controversies in taxation of real estate projects & ICDs for real estate deve...
Controversies in taxation of real estate projects & ICDs for real estate deve...Controversies in taxation of real estate projects & ICDs for real estate deve...
Controversies in taxation of real estate projects & ICDs for real estate deve...
 
The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..
 
Pp2 p7
Pp2   p7Pp2   p7
Pp2 p7
 
APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...
 
20091118 Construction Life cycle completion
20091118 Construction Life cycle completion20091118 Construction Life cycle completion
20091118 Construction Life cycle completion
 
COVID-19 (Coronavirus): Your Business Questions Answered
COVID-19 (Coronavirus): Your Business Questions AnsweredCOVID-19 (Coronavirus): Your Business Questions Answered
COVID-19 (Coronavirus): Your Business Questions Answered
 

Kürzlich hochgeladen

一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理ss
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxfilippoluciani9
 
Clarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo forClarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo forRoger Valdez
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理Airst S
 
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdfNavigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdfMilind Agarwal
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理Airst S
 
$ Love Spells^ 💎 (310) 882-6330 in Utah, UT | Psychic Reading Best Black Magi...
$ Love Spells^ 💎 (310) 882-6330 in Utah, UT | Psychic Reading Best Black Magi...$ Love Spells^ 💎 (310) 882-6330 in Utah, UT | Psychic Reading Best Black Magi...
$ Love Spells^ 💎 (310) 882-6330 in Utah, UT | Psychic Reading Best Black Magi...PsychicRuben LoveSpells
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理Airst S
 
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxKEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxRRR Chambers
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Dr. Oliver Massmann
 
3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.pptseri bangash
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxRRR Chambers
 
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptxAnalysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptxadvabhayjha2627
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理Airst S
 
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...SUHANI PANDEY
 
CAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction FailsCAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction FailsAurora Consulting
 
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)Delhi Call girls
 
PowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptxPowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptxca2or2tx
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYJulian Scutts
 
Relationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfRelationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfKelechi48
 

Kürzlich hochgeladen (20)

一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptx
 
Clarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo forClarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo for
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
 
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdfNavigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理
 
$ Love Spells^ 💎 (310) 882-6330 in Utah, UT | Psychic Reading Best Black Magi...
$ Love Spells^ 💎 (310) 882-6330 in Utah, UT | Psychic Reading Best Black Magi...$ Love Spells^ 💎 (310) 882-6330 in Utah, UT | Psychic Reading Best Black Magi...
$ Love Spells^ 💎 (310) 882-6330 in Utah, UT | Psychic Reading Best Black Magi...
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理
 
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxKEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
 
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptxAnalysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
 
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
 
CAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction FailsCAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction Fails
 
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
 
PowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptxPowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptx
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
Relationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfRelationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdf
 

Payments in the construction industry

  • 1. Practical Construction Law for Practitioners - Payments Chan Kheng Hoe
  • 2. Topics Covered ● Must retention sum be in separate account? ● Can sub-contract provide for back-to-back payments? ● Can contractor suspend, go slow or terminate due to non-payment? ● Difference between interim, penultimate and final certs? ● Can certificates be revised?
  • 3. Retention Monies- must it be in a separate account? (1) For discussion Why is this question important?
  • 4. Retention Monies- must it be in a separate account? (2) Why is this question important? ● Most contracts provide for retention sum (usually 5%) ● Usually released in 2 moiety ○ 1st moiety upon CPC ○ 2nd moiety upon CMGD ● If not set aside in separate account: ○ Employer may utilise monies for its own purposes ○ Monies at risk if employer enters into liquidation before full release ○ Employer may be indebted to other creditors whose claim may affect the monies held
  • 5. Retention Monies- must it be in a separate account? (3) Contractually: ● PAM ○ Employer has fiduciary duty as trustee of money to Contractor ○ Contractor’s beneficial interest subject to deductions certified by Architect ○ Contractor can demand for monies to be held in trust account at its cost ● CIDB ● JKR ○ No retention sum - use of performance bond instead For discussion: ● Even though PAM provides for contractors to demand for monies to be held in trust account, it is extremely rare for contractors to do so. Why do you think that is so?
  • 6. Retention Monies- must it be in a separate account? (4) Case Law: Qimonda Malaysia Sdn Bhd (in liquidation) v Sediabena Sdn Bhd & Anor [2012] 3 MLJ 422, CA Facts: ● Employer voluntarily wound up ● Did not release in excess of RM6m of retention sum to contractor & sub-con ● Contractor sought declaration retention monies were held in trust Employer’s Arguments: ● Contract does not provide for a trust ● Retention sum not set aside in separate account (no request by Contractor either) ● Contractor filed proof of debt as creditor- claim as trust money would be preferential treatment of Contractor as a creditor ● So, how would you argue against the Employer in this case?
  • 7. Retention Monies- must it be in a separate account? (5) Case Law: Qimonda Malaysia Sdn Bhd (in liquidation) v Sediabena Sdn Bhd & Anor [2012] 3 MLJ 422, CA Contractor’s Arguments: ● Retention monies, by nature, are trust monies ● Express clause not a precondition of trust- can be by operation of law ● Employer is fiduciary to the trust ● No issue of preferential treatment because retention monies do not belong to Employer in the first place ● Filing of proof of debt as an estoppel is an afterthought and non-issue, and is without prejudice to Contractor’s claim for retention sum as trust money So, how would you decide if you were the panel?
  • 8. Retention Monies- must it be in a separate account? (6) Case Law: Qimonda Malaysia Sdn Bhd (in liquidation) v Sediabena Sdn Bhd & Anor [2012] 3 MLJ 422, CA Held by the Court: ● Property in retention sum resides with Contractor and is held by Employer in trust ● Retention Sum already earned by Contractor for works already done- mere provision for making good defects. Even if mixed in common fund, is traceable ● No requirement to be held in separate account or Contractor must make such request. Contractor may not want to jeopardise relationship/applied its mind ● Failure to separate monies cannot defeat the trust. Release or preservation of monies after liquidation is not preferential treatment because monies do not belong to Employer ● Allowing retention to be part of general funds would unjustly enrich other creditors
  • 9. Back to Back Payments (1) Commonly known as: ● Back-to-back ● Pay when paid ● Pay if paid
  • 10. Back to Back Payments (2) Not so much an issue any longer. Section 35(1) CIPAA ● Renders conditional payment provisions void For discussion: ● Are conditional payment clauses in construction contracts entered into prior to CIPAA void? ● Wouldn’t a retrospective application of CIPAA be an interference with vested interests/rights?
  • 11. Back to Back Payments (3) Case Law: UDA Holdings Bhd v Bisraya Construction Sdn Bhd & Anor and another case [2015] 11 MLJ 499, HC Central Issue: Whether CIPAA applies to payment disputes and their underlying contracts which arose before the coming into force of CIPAA Important Consideration: ● CIPAA not only introduces adjudication but also affects substantive rights, including: ○ Right of Contractor to suspend works ○ Right of Contractor to demand direct payment from principal ○ Prohibition of conditional payments
  • 12. Back to Back Payments (4) Case Law: UDA Holdings Bhd v Bisraya Construction Sdn Bhd & Anor and another case [2015] 11 MLJ 499, HC Held by Court: ● “Substantive rights” are not vested by written law but merely in contracts ● Rights not accrued, vested or acquired save for pending liti/ arb preserved under s41 ● CIPAA as new procedural legislation introduces new forum, and no vested rights under law affected, so can apply retrospectively ● Section 35 CIPAA is merely declaratory in nature ● In any case, if conditional payment defence is allowed, it would defeat CIPAA
  • 13. Right of Contractor to Suspend, Go Slow and Terminate (1) For Discussion Based on general principles of law, do you think that a contractor has the right to suspend works, go slow on works, or even terminate the contract for failure of the Employer to make timely progress payments?
  • 14. Right of Contractor to Suspend, Go Slow and Terminate (2) 100% Safe Approach Section 29 CIPAA ● Contractor may suspend works or reduce rate of progress after 14 days’ notice if adjudicated sum is not paid ● When he does so, the Contractor: ○ Is not in breach of contract ○ Is entitled to reasonable EOT ○ Is entitled to recover loss and expenses ○ Must resume work within 10 working days after being paid
  • 15. Right of Contractor to Suspend, Go Slow and Terminate (3) Outside the scope of CIPAA, the Contractor would have to rely on contractual provisions or common law principles For example, PAM: ● Failure to pay certified sums allows Contractor to suspend works after 14 days’ notice ● Contractor may also terminate the contract for failure to pay certified sums or obstruction from issuance of certificates by Employer ● Note: Going slow is not provided in all contracts. If not provided, it would seem a riskier approach because time continues to run leading to potential issues with delay/LAD
  • 16. Right of Contractor to Suspend, Go Slow and Terminate (4) Case Law: Kah Seng Construction Sdn Bhd v Selsin Development Sdn Bhd [1997] 1 CLJ Supp 448, HC Facts: ● There was no formal contract ● Contractor made claims progressively and certificates were issued ● On basis of estimated costs for defective works and LAD, Employer withheld payment of later certificates ● Contractor suspended works and sued for payment. Employer counterclaimed for damages. So how would you decide if you were the judge in this case?
  • 17. Right of Contractor to Suspend, Go Slow and Terminate (5) Case Law: Kah Seng Construction Sdn Bhd v Selsin Development Sdn Bhd [1997] 1 CLJ Supp 448, HC Held: ● Contractor can elect to terminate if there is repudiatory breach by Employer or to affirm the contract and proceed with works ● There is no intermediate right to suspend works ● Any suspension becomes a repudiatory breach by the Contractor In Conclusion, how would you advise a Contractor client who wants to suspend works for non-payment?
  • 18. Interim, Penultimate and Final Certs (1) Interim certificates: ● Issued progressively to estimate amount and value of work carried out and payment due to Contractor Penultimate certificate: ● Issued after completion and before final certificate- usually after CPC to facilitate release of retention sums Final certificate: ● Issued at end of contract period to verify final amount due (after CMGD) The effect and conclusiveness of the certificate largely depends on the contractual terms, but even a “conclusive” certificate may be reviewed by an arbitrator or challenged before a judge.
  • 19. Interim, Penultimate and Final Certs (2) Example of Contractual Term in PAM: ● Final Certificates are conclusive with regard to the final value of the works carried out ● But not conclusive that any work, materials, goods and designs are in accordance with the Contract
  • 20. Interim, Penultimate and Final Certs (3) Case Law: Shen Yuen Pai v Dato Wee Hood Teck & Ors [1976] 1 MLJ 16 ● This case discussed, inter alia, the position of the Architect’s Final Certificate Held by Court: ● Architect is owner’s agent to give instructions for works ● But for issuing certificates, Architect is independent authority ● Architect owes duty of care not to issue final certificate unless satisfied with work. Once issued, final cert is conclusive ● Form of cert depends on contract terms. If no form is prescribed, Architect can determine the form.
  • 21. Interim, Penultimate and Final Certs (4) c.f. Thamesa Designs Sdn Bhd & Ors v Kuching Hotels Sdn Bhd [1993] 3 MLJ 25, SC Held: Employer handed over site late to contractor Employer therefore not entitled to LAD Certificate of final payment issued by consultant authorizing deduction of LAD is invalid and not binding on parties LAD which was deducted from retention fund must be restored Note: Article by Vinayak Pradhan questions case- Shen Yuen Pai not brought to Court’s attention
  • 22. Revision of certificates (1) PAM: ● Architect cannot revise payment certificates except for clerical, computational and typographical errors ● But Architect can by a subsequent certificate correct or modify any valuation errors in earlier certificates CIDB: ● Superintending Officer can by any Interim Certificate correct any error in previous Interim Certificate and adjust amount due to account for any under or over valuation
  • 23. Revision of certificates (2) Case Law: Fairweather Ltd v Asden Securities Ltd (1979) 12 BLR 40 Facts: ● After issuing Final Certificate, Architect subsequently issued CNC Held by Court: ● After issuing Final Certificate, Architect was functus officio and precluded from issuing further CNC cf. Bukit Cerakah Development Sdn Bhd v L’Grande Development Sdn Bhd [2008] 3 MLJ 547, CA held: ● It is a question of construction and not a question of general law as to whether an Architect is functus
  • 24. Claims for Direct Payment (1) For discussion: Can a sub-contractor make a claim for direct payment from the Employer? Would your answer be different if it was a nominated sub-contractor?
  • 25. Claims for direct payment (2) General Principle: Privity of Contract There is no privity of contract between a subcontractor and an Employer to allow a direct claim Exceptions: ● Contractual exceptions (eg JKR contracts) ● Statutory exceptions (CIPAA)
  • 26. Claims for direct payment (3) Contractual Exceptions ● JKR contracts provide for direct payment to nominated sub-contractors ● Even in non-JKR contracts, some NSCs require direct payment when nominated- usually by a side letter or supplemental agreement ● Must be agreed to by the Main Contractor Statutory Exception ● Section 30 CIPAA allows for requests to be made to principal for direct payment of adjudicated sum ● But there is no provision for consequences to principal who fails to comply ● So what can be done if principal fails to comply?
  • 27. Claims for direct payment (4) Practical Problems with Direct Payment ● Potentially creates a collateral contract between sub-contractor and Employer (would it subject Employer to potential adjudication claims?) ● Potentially an undue preference of the sub-contractor as an unsecured creditor in the event of insolvency of Main Contractor ● This issue arose in: ○ Joo Yee Construction Pte Ltd v Diethelm Industries Pte Ltd & Ors [1990] 2 MLJ 66, HC (S’pore) ● Direct payment to sub-contractor may not have taken into account defects or delays, leaving main contractor saddled with all defects and LAD claims by Employer
  • 28. That’s all Folks! Thank You Chan Kheng Hoe khenghoe@khenghoe.com