3. #BSL2014
29-37 Davies St
Richard Baglow
London Regional Director
IBSECAD
Rebecca Hodgson-Jones
Head of BIM
SIR ROBERT McALPINE
Your Speakers today
4. #BSL2014
29-37 Davies St
i. Project Background
ii. Cocktail for Success
iii. The Process
iv. The Objectives
v. The Benefits
vi. FM Handover
vii. BIM Journey continues
viii. Questions & Answers
Agenda
5. #BSL2014
29-37 Davies St
⢠UK building and civil
engineering contractor
⢠Design Division
⢠Family-owned and founded
in 1869
⢠Collaborative approach to
business
Sir Robert McAlpine
7. #BSL2014
29-37 Davies St
⢠Established in 1996
⢠Over 17 years experience in
the Construction Industry at
all levels
⢠We provide BIM Solutions to
our clients in the UK, AUS &
US markets.
⢠Our Focus is bringing design
and people together
Ibsecad
10. #BSL2014
29-37 Davies St
2009 â 2012 I Olympic Stadium
2006 â 2008 I New Street
2004 â 2005 I Emirates
2001 â 2003 I No.1, London Wall
Ingredient 1
PROJECTMANAGERâS
INTEREST
SUCCESS OF IMPLEMENTATION
Project Managers Interest
âI didnât see any
other way the
project could be
runâ
13. #BSL2014
29-37 Davies St
Ingredient 4
Contractual position
TRADITIONAL PROCESS
Stage
Design C
Design
Development
Stage
Design E
S/C Tender
Period
Detailed Coordination
Construction
Issue
Installation
Begins
âSTART EARLYâ PROCESS
TIME SAVED
Fabrication
Drawings
S/C
Tender
Period
Accelerated Construction
Model Production /
Coordination
Stage
Design C
Stage
Design E
Installation
Begins
Construction
Issue
Fabrication
Drawings
22. #BSL2014
29-37 Davies St
The Project guidelines
No PAS1192-2 2013âŚWhat do we need to deliver BIM?
ď§ Our Golden Rules document
was the Project BIM Execution
Plan
ď§ Level of Detail was defined by
our knowledge of Sub
Contractor requirements.
ď§ The BIM âsavvyâ design team
needed little encouragement.
23. #BSL2014
29-37 Davies St
Collaboration
ď§ Collaborative workshops to drive solutions were
held weekly at Ibsecad & HOKâs offices.
ď§ All stakeholders had representation at meetings
24. #BSL2014
29-37 Davies St
Design Validation
ď§ Co-ordination Challenge
highlighted with HOK &
MTT at one of the BIM
workshops.
ď§ On Floor Heat Exchanger
unit located in WC Core.
ď§ In order to carry out
maintenance or to
replace the unit a
problem aroseâŚ
25. #BSL2014
29-37 Davies St
Design Validation
ď§ The services were
positioned directly
above the WC Cubicles.
ď§ The WC Cubicles were
finished flush with the
ceiling level.
ď§ In order to remove the
equipment, complete
cubicle removal would
be requiredâŚ
26. #BSL2014
29-37 Davies St
Design Validation
ď§ Several solutions were
tested in the model.
ď§ Design team consulted at
collaborative workshops.
ď§ Equipment and
Attenuation re-selected
to aid the final solution.
ď§ Final solution reached to
suit MTT, HOK & FM team.
27. #BSL2014
29-37 Davies St
Design Validation
ď§ This is just one example where BIM was used to make a
decision and enable the design process
29. #BSL2014
29-37 Davies St
Logistics Testing
ď§ Site logistics were co-ordinated at the right time
ď§ Tower crane influenced final co-ordination in
Basement areas.
30. #BSL2014
29-37 Davies St
Commissioning review
ď§ Services re-routed to accommodate plant Installation
& replacement hatch
ď§ Ensuring full installation âno gapsâ for commissioning
31. #BSL2014
29-37 Davies St
CDM Sign Off
ď§ Carrying a key âlesson learntâ for CDM sign off
ď§ Rodding Eye access; always overlooked
ď§ Opportunity to capture before installation
32. #BSL2014
29-37 Davies St
Sequence of Install
ď§ Install workshops
ď§ Tablet site reviews
ď§ Areas assessed with trades prior to install
33. #BSL2014
29-37 Davies St
Integrate with FM team
ď§ Workshops held with Grosvenor FM team = ď
ď§ Createmaster embraced the collaborative process
34. #BSL2014
29-37 Davies St
The BIM curve?
BIM Process was
being delivered;
ď§ Draw It Once
ď§ Evolve to S/C
ď§ Integrate F.M
36. #BSL2014
29-37 Davies St
Ability to visualise the building during BIM workshops
ď§ In particular Ground Floor Reception & WC Cores
and increased net-letable areas where possible.
What main benefits did the Client gain?
Integration of his existing FM solution
ď§ FM Team already utilised the Createmaster Document
Park Facilities Management software system
Benefits
Re-Allocate risk contingency
37. #BSL2014
29-37 Davies St
No additional Access Panels or bulkheads
ď§ Final co-ordination agreed earlier allowed
collaborative review of Access requirements
What main benefit did the Architect gain?
Benefits
38. #BSL2014
29-37 Davies St
No un-planned Builderswork;
ď§ Concrete Slabs and Shear Walls approved before
build commenced.
What main Benefit did Structures gain?
Benefits
ď§ Steelwork openings
influenced to suit
co-ordination prior
to Fabrication
39. #BSL2014
29-37 Davies St
De-risked design
ď§ Visualise design
and collaborate on
solutions with all
stakeholders prior
to site Installation.
What main benefit did the MEP Consultant gain?
Benefits
40. #BSL2014
29-37 Davies St
Programme advantage
ď§ No design issues at site level, install
could begin âday oneâ
ď§ Confidence in the co-ordinated
solutions
ď§ Simple integration of final procured
equipment details.
What main benefits did the Sub-Contractors gain?
Benefits
41.
42. #BSL2014
29-37 Davies St
Soft Handover - The Brief
ď§ Client had existing established O&M Document park
ď§ Link 3D Model and utilise as an additional FM Tool
ď§ Needs to be âmobileâ and accessed via Tablet
ď§ Integrate with Client FM Team
ď§ Most Important of all;
âŚKeep it simpleâŚ
Handover
43. Development
ď§ Working alongside Createmaster; their DOCUMENT PARK
software was enhanced to include a 3D Model route as well
as the standard Asset Information.
Asset Information
Model
Handover
44. Development
ď§ Navisworks was the chosen navigation tool to develop.
ď§ Created a web browser âfreedomâ style version â therefore
Full license not required for the clientâs FM Team.
Handover
45. #BSL2014
29-37 Davies St
The Product
ď§ Fully integrated Model and online Document Park system
ď§ FM Team can now utilise the model to review their planned
works prior to leaving the office.
ď§ Valuable man hours will be saved by utilising the BIM
Simply click in the model to be taken to
that particular Asset information in the
online Document Park.
This has bidirectional features to keep it
simpleâŚ
Handover
46. #BSL2014
29-37 Davies St
ď§ Cocktail for Success
ď§ The Process
ď§ The Objectives
ď§ The Benefits
ď§ FM Handover
Summary
59. #BSL2014
29-37 Davies St
Typical Stage E Model
ď§ Excessive Clashes
ď§ Lack of Constructability during design
ď§ Inaccurate Data drop
The Journey continues
60. #BSL2014
29-37 Davies St
Start Early Process â Construction experience is vital
ď§ Earlier Contractor involvement
ď§ Resolved clashes and constructible detail
ď§ Improved routes saving on fittings
ď§ MORE accurate data drop
The Journey continues
Welcome â RBGood Morning all, I hope last nights BIM beers havenât clouded your heads too much this morning. Welcome to our seminar class on the story of BIM from design to use from our 29-37 Davies St project.
RHJ
For those of you that donât know me, my name is Richard BaglowI am London Regional Director for Ibsecad and also head up the Business Development department focusing on BIM and R&D within the company. I joined Ibsecad in the year 2000 after graduating from Brunel University as a Mechanical Engineer; Iâve helped implement our 3D capabilities over the years and with the industry shift have been enhancing our own BIM processes and solutions that we offer our clients.RHJ
RHJ
RHJ
Ibsecad were established in 1996; our head office is in London and we also have offices in Leeds, New York and Brisbane. We are BIM specialists and co-ordination experts. We have over 17 years experience in the construction industry, completing over 2000 projects in that time. Obviously NOT all BIM projects but at least 80% involved BIM Level 1, 2 & 3 activities. We now primarily work for Main contractors having previously been appointed with the MEP sub contractor; Iâd say ownership of the BIM has influenced this change â We also cater for MEP consultants and more recently direct for the Client themselves in a BIM manager role.We offer the big 5 BIM solutions â management; authoring; sequencing; scheduling & lifecycle. Our mission statement is our main focus â bringing design and people together BIM is about the people as much as it is about the process â the right people deliver the right solution and building on those relationships is one of the biggest industry challenges.
RBAnd so to 29-37 Davies St, Iâd like to hand back to Rebecca who will now set the scene for the case study today.RHJ
RHJ
RHJ
RHJ
RHJ
RHJRB â NTERJECTThe âstart earlyâ process is something we have been delivering on projects (when possible) since circa 2004. By implementing the right amount of model detail at the right time, we have delivered time & cost savings to our clients on major projects.
RHJ
RHJ
RHJ
RHJ
RHJ
RHJRBIâm going to take you through this process in a bit more detail focusing back on the objectives, aspirations and benefits that were delivered up to the soft handover to FM.
Well as you saw in the previous graphics, Ibsecad were appointed as BIM managers and MEP Authors for Davies Street in 2011.HOK and Ramboll had already produced their own 3D models and MTT had delivered a 2D design to suit their scope of appointment. This was not a Level 2 project.However based on our previous experience and discussions early on with SRM we were certainly ticking a number of boxes in the BIM syllabus which I hope to cover in further detail now.Here you can see one of our model renders in the basement plantroom and its comparative installation photo. Iâd say thatâs pretty closeâŚ
So if we can just recap on the objectives that Rebecca previously raised. Design Validation â build and snag project virtually Reduce Risk & Transparency â Complete tender packageEarly Co-ordination & Clash Detection â its what we doSafety â CDM workshopsSequence & Constructability â Workshop with Install teamSofter Handover â FM integration
We have over 17 years experience in the Construction Industry; the rules and processes we have delivered through Davies St are nothing new. Previously before PAS1192-2 was issued; Ibsecad used to adopt its own Golden Rules document â in essence it was a short form BIM Execution Plan.Not only containing the blueprints for co-ordinating the MEP services it also contained key requirements for the Architecture, Structure and FM requirements.
I can put up countless images of clash resolutions or design issues that were resolved in the co-ordination process. But you will have seen all this before.The key driver for the solutions was âcollaborationâ Itâs the biggest message for any BIM process or solution that needs to happen on any project. We had an extremely proactive design team that embraced the 3D workshops and helped drive those solutions; thus reducing the need for an excessive amount of RFIâs Typical examples
If I was to take one key item from the Model development with the design team then it would be the challenge around the WC Cores.Highlighted as a concern with SRM, HOK & MTT at one of the BIM workshops.Each CAT A Floor contained a Heat Exchanger Supply and Extract system, this was located in the WC Cores.When reviewed in the workshop, In order to carry out maintenance or to replace the unit a problem aroseâŚ
The Supply Fan, Attenuators & Heat Exchanger were positioned directly above the WC Cubicles.The WC Cubicles were finished flush with the ceiling level. Although an accessible ceiling had proposed by HOK. In order to remove the equipment or carry out maintenance, complete cubicle removal would be requiredâŚ
Several solutions were tested and presented in the model and workshops. The Design team were consulted at the following collaborative workshops.Heat Exchanger and Attenuators were reviewed and re-selected to aid the final solution.Final solution reached to suit MTT, HOK & FM team.
This is just one example where BIM was used to make a decision and enable the design process
Builderswork take off for Blockwork & ConcreteFD take off for Gratte Brothers
With regards to the Constructability aspect of the project; services were fully co-ordinated with all aspects of the building fabric â we had a particular focus on;LintelsWindpostsCeiling zone build up thicknessSite tolerancesWe also reviewed the site logistics; scenarios were reviewed with SRM and the design team. This was not a fancy sequencing tool â this was a working ârealâ de-risking processIn particular the Crane location vs services installation; a primary containment route was diverted to ensure âpower onâ date wouldnât be affected by the crane removal date.
Similar to the diverting of services to suit the crane dates. Picking one particular commissioning exampleThe plant installation/removal hatch was fully co-ordinated into the model to ensure full installation and âno gapsâ were left which could affect future commissioning towards the end of the project.Elaborate more on this
One example â SRM have a big drive from a safety perspectiveA primary concern during CDM sign off and a lesson learnt from previous projects was future Rodding Eye access. Whilst this was primarily considered and QAâd during our co-ordination, there was an obvious benefit to demonstrate this before installation. Criteria included;Clear Access from below through ceiling?Sufficient access when above the ceiling?RE not compromised by wall, steel or mep service?
Having a model in advance of Installation was always going to be a benefit. Areas were assessed with Gratte Brothers prior to install and any difficulties out in the field were snagged and reviewed in the model to ensure the install was meeting the original co-ordinated intent.
Youâll have to excuse me for using Lyle but I didnât have a photo of Otto; who is head of FM at Davies Street. Who was involved EARLYIn order to understand the FM teams requirement and Grosvenorâs brief a number of Workshops were held which included Createmaster who were prepared to fully embrace the collaborative process and incorporate the model into their current FM solution. Iâll cover this in more detail shortly.
Did we have a real BIM process being delivered?Excuse the use of a âstandard BIM graphicâ â but its very true of the state of the nation.Davies St was a welcome change from the norm. We see too many projects where a model has been completed by the design team right through to Stage D or E yet is riddled with errors and thereforeâŚwe start again.A smooth curve can be achieved by bringing construction experience forward in the process.
Iâve included a selection of images from the model to demonstrate what the team produced.It was by no means the most complicated project but has been one of the smoothest projects we have worked through. The novation to Gratte Brothers to complete the Installation drawings with procured equipment typified this smooth process. Drawings were issued within two weeks and Gratte Brothers were installing two weeks after that.And so now to the benefits; we understand that each stakeholder gained a benefit from the early adoption, they could finalise and complete their tender information with 100% confidence that it worked. I have highlighted some of the key benefits that have been discussed in our project âlessons learntâ session with SRM.
So what main benefit did the client gain; aside from the fact we kept the project transparent he was able to visualise his building during the BIM workshops.Particular interest on the high finish Reception spaces and WC Cores where access is normally limited. Secondly, integration of his existing FM solution with the 3D model; this was a pilot exercise and the feedback we will receive will go some way to shaping the future of his FM requirements.
The Architectural team had already produced their model, we were able to assist them in finalising their information at tender stage by providing a co-ordinated solution that otherwise may have occurred much later in the process. Additional Access panels and Bulkheads are always a headache for Architects as well as the Main contractor. Being able to drive these out of the design and ensure any accessible equipment was achieved via provided access points was a key benefit in keeping the high standard architectural finish.
Similarly to the Architectural team, Ramboll had already produced their model, we were again able to assist them in finalising their information. This time eradicating un-planned Builderswork in concrete was the primary objective which was achieved. To avoid expensive core drilling on site which could also add delay to the project was high on the agenda for SRM. Also being able to fully co-ordinate the MEP with the steelwork design model before releasing the Trade contractors to produce their fabrication model meant steelwork could be finalised and fabricated to meet programme early.
We were effectively an extension to the MEP consultantâs information delivery. MTT were nothing but positive in this approach and were able to fully visualise their design, collaborate on the solutions and protect their design intent while providing a collaborative solution in a timely manner. This definitely cut down their time in the long run with less involvement on site as would potentially be the case if âstart earlyâ hadnât been adopted.
Chosing to talk about the MEP subcontractor Gratte Brothers install services, they donât need to be bogged down in design issues. In this instance; Co-ordination was completeCould procure quickly Installation drawings were turned around quicklyBegin ahead of schedule
Now we move into the FM handover section
This is by no means an all singing and all dancing FM solution for every project out there. We had a brief from the client and we achieved that brief. We are looking forward to working with the client and the FM team to further develop this product after the pilot exercise was completed.Read Brief
Createmaster deliver an O&M document park as well linked to FM activities required for the project.Working collaboratively this document park was enhanced to include a link to the 3D model by way of an AIM button (Asset in model)
The easiest way to view the Davies Model was via Navisworks and the relevant hyperlinks to the document park could be carried through.Createmaster developed a web browser version of freedom. The client didnât then require a FULL license version of Navisworks. The FM team were able to use Navisworks and we even striped down the number of buttons to again keep it simple.
We now had a fully integrated document park system.The FM team could review relevant asset information; download data sheets and maintenance schedule. Review the asset in the model and plan their required works. This will in time save valuable man hours which has been proven in case studies on the BIM Task Group website. We are looking forward to receiving feedback as the lifecycle progresses.
Summary on each point
RHJ
RHJ
RHJ
So how is Ibsecadâs Journey progressing?We are excited and challenged at the same timeâŚBIM is changing our industry â far more people talk about BIM are trying to understand BIM and deliver BIM on their jobs. However there are limitations that we are seeing as the industry chugs along. We receive models to tender against stating âyou only need to enhance itâ ; âitâs a good modelâ Yet this is what we getâŚread bullet pointsIf its being co-ordinated in 3D â it needs to co-ordinate!
Although our presentation was targeted at the FM softer handover in order to get there we need an accurate model in the first placeâŚConstruction experience & Early Contractor involvement is vital.Models will therefore be constructibleImproved solutions could influence costsData drops will be more accurate
Iâve included this short video demonstration on a recent project. Construction experience was adopted as early as Stage C here. We reviewed, co-ordinated and animated a sequence to suit the contractors requirements when tendering this project. It needed prefabrication, which the design team wouldnât necessarily be interested in but the project needed to benefit fromâŚStart early wouldâve allowed this to be considered and built into the model and tender information. This sequence also highlighted build sequence and safety concerns. Trip hazards for temporary lighting, and leave downs for walls. Everyone has a different view on how to build a project and its this experience which is vital when produced your BIM.