SlideShare ist ein Scribd-Unternehmen logo
1 von 1
Downloaden Sie, um offline zu lesen
During a tie change-out job in Greater Toronto, ON, PNR RailWorks
maintained such an impressive pace that customer GO Transit decided
to up its order. And PNR RailWorks delivered.
Restricted to night and weekend work windows, a 26-person gang
changed more than a third more ties than initially required over the
duration of the project. And they did so during the originally allotted time
frame of two and a half months.
The initial scope of the project involved changing 15,600 ties through-
out the Oakville subdivision on main tracks 1, 2, and 3. “As this is an
extremely busy subdivision running GO Transit, VIA Rail, and CN Railway
freight trains, the work was performed on a night shift to obtain addi-
tional working time as compared to a day shift,” notes Arash Barzegar,
who served as project manager. “Shutting down any one of the main
lines was not an option.”
The initial plan was to change 325 ties per shift in between delays in
GO, VIA and CN service. Once beginning the job, the crew discovered it
would experience significant delays while working on such a busy sub-
division. “On a typical night, we were lucky to obtain 5 hours of working
time between several hours of delays for trains passing on adjacent
tracks within our working limits,” says Arash. The mid-week work win-
dows were limited to 6 hours, with 4.5 hours of productivity on average.
Weekend work provided 8-hour work windows. Even with the erratic
work windows, the crew was able to change significantly more ties per
shift than planned. High productivity kept the project on schedule.
Based on this increased production, the scope of the project was
revised to include additional ties within the same work period. By the
time the project period had ended, the crew had changed 21,519 ties –
nearly 38 percent more than initially planned, without a change in the
initial time frame.
Effective organization and coordination between the working crew, pro-
tecting foremen and trains operating within the working limits allowed
PNR RailWorks to average a surprisingly swift 550 ties per shift over
the course of the project. Besides the tie-change crew, a three-man
crew surfaced track, and GO Transit Maintenance performed constant
flagging and crossing support.
The scope of the project also involved removing and disposing of all old
ties from the subdivision.
Project leaders besides Arash included Project Superintendent Bran-
don Berry, Project Coordinator Justin Duval, Foreman Ryan Homeniuk;
and for GO Transit Maintenance, Track Manager Greg Machado, Track
Superintendent Roger Alves and Foreman Dan Bertram.
February 20165
RailWorks Values In Action: Customer Focus
Achieving An Amazing Pace for GO Transit
Operator Tim Dagenais (above left) stands in front of a tie remover/inserter used on the job for GO Transit. Besides the tie replacement, the scope of the project also
involved removing and disposing of all old ties, a job that Operator Dan Springer (above right) helped to handle.
(left to right) Project Manager Arash Barzager, Project Superintendent Brandon
Berry, Project Coordinator Justin Duval and Foreman Ryan Homeniuk led a GO
Transit job to change out thousands of ties on the Oakville Subdivision in Greater
Toronto, ON. Working in confined work windows, a 26-man tie-change crew
from the PNR RailWorks Track group, with support from the PNR RailWorks GO
Transit Maintenance team, replaced an average of 550 ties per shift.

Weitere ähnliche Inhalte

Andere mochten auch

Andere mochten auch (12)

T.p peñaloza caamaño camila.
T.p peñaloza caamaño camila.T.p peñaloza caamaño camila.
T.p peñaloza caamaño camila.
 
Como vivir con Jesús
Como vivir con JesúsComo vivir con Jesús
Como vivir con Jesús
 
Eye Protection
Eye ProtectionEye Protection
Eye Protection
 
Engineering a concrete pour
Engineering a concrete pourEngineering a concrete pour
Engineering a concrete pour
 
Letter of Recommendation; Bart Baird
Letter of Recommendation; Bart BairdLetter of Recommendation; Bart Baird
Letter of Recommendation; Bart Baird
 
Sky siren pcs
Sky siren pcsSky siren pcs
Sky siren pcs
 
Cronica experiencia en tit 2
Cronica experiencia en tit 2Cronica experiencia en tit 2
Cronica experiencia en tit 2
 
Unborn
UnbornUnborn
Unborn
 
Clase 06/11/2015
Clase 06/11/2015Clase 06/11/2015
Clase 06/11/2015
 
EBW Tension Link Load Cell
EBW Tension Link Load CellEBW Tension Link Load Cell
EBW Tension Link Load Cell
 
Prueba de computo
Prueba de computoPrueba de computo
Prueba de computo
 
Proyecto Legislación " Chipas Ña Chaki"
Proyecto Legislación " Chipas Ña Chaki"Proyecto Legislación " Chipas Ña Chaki"
Proyecto Legislación " Chipas Ña Chaki"
 

Ähnlich wie RailWorks-Today-February-2016-F

ACT December 2015 - OM (2)
ACT December 2015 - OM (2)ACT December 2015 - OM (2)
ACT December 2015 - OM (2)Mark Shanholtzer
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...AamerShakoor
 
Geotechnical Engineering Services
Geotechnical Engineering ServicesGeotechnical Engineering Services
Geotechnical Engineering ServicesVictor Panlilio
 
The importance of broad gauge railways in north east india
The importance of broad gauge railways in north      east indiaThe importance of broad gauge railways in north      east india
The importance of broad gauge railways in north east indiaSUBHOJIT NATH
 
Transbay presentation-2-14-13
Transbay presentation-2-14-13Transbay presentation-2-14-13
Transbay presentation-2-14-13Adina Levin
 
Hoover dam bypass bridge
Hoover dam bypass bridgeHoover dam bypass bridge
Hoover dam bypass bridgeBismillah Arif
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zachary Maddox
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Soumalya Bag
 
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiShobhit Acharya
 
1 Nick Foster, Tian Tian,
1  Nick Foster, Tian Tian,1  Nick Foster, Tian Tian,
1 Nick Foster, Tian Tian,AbbyWhyte974
 
Caltrans San Mateo county managed lanes
Caltrans San Mateo county managed lanesCaltrans San Mateo county managed lanes
Caltrans San Mateo county managed lanesAdina Levin
 
Braddock Relife Project Article
Braddock Relife Project ArticleBraddock Relife Project Article
Braddock Relife Project ArticleBob Schluter
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015Phil Morris
 
Offshore Energy Limited - Project lifting management and support services pre...
Offshore Energy Limited - Project lifting management and support services pre...Offshore Energy Limited - Project lifting management and support services pre...
Offshore Energy Limited - Project lifting management and support services pre...RichardTurnbull9
 
Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...Atkins
 

Ähnlich wie RailWorks-Today-February-2016-F (20)

ACT December 2015 - OM (2)
ACT December 2015 - OM (2)ACT December 2015 - OM (2)
ACT December 2015 - OM (2)
 
2015-10-05
2015-10-052015-10-05
2015-10-05
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
 
Geotechnical Engineering Services
Geotechnical Engineering ServicesGeotechnical Engineering Services
Geotechnical Engineering Services
 
The importance of broad gauge railways in north east india
The importance of broad gauge railways in north      east indiaThe importance of broad gauge railways in north      east india
The importance of broad gauge railways in north east india
 
Transbay presentation-2-14-13
Transbay presentation-2-14-13Transbay presentation-2-14-13
Transbay presentation-2-14-13
 
Hoover dam bypass bridge
Hoover dam bypass bridgeHoover dam bypass bridge
Hoover dam bypass bridge
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891
 
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
 
wdfcil
wdfcilwdfcil
wdfcil
 
1 Nick Foster, Tian Tian,
1  Nick Foster, Tian Tian,1  Nick Foster, Tian Tian,
1 Nick Foster, Tian Tian,
 
1 Nick Foster, Tian Tian,
1  Nick Foster, Tian Tian,1  Nick Foster, Tian Tian,
1 Nick Foster, Tian Tian,
 
RailWorks-Today-April-2016-L
RailWorks-Today-April-2016-LRailWorks-Today-April-2016-L
RailWorks-Today-April-2016-L
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
 
Caltrans San Mateo county managed lanes
Caltrans San Mateo county managed lanesCaltrans San Mateo county managed lanes
Caltrans San Mateo county managed lanes
 
Braddock Relife Project Article
Braddock Relife Project ArticleBraddock Relife Project Article
Braddock Relife Project Article
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015
 
Offshore Energy Limited - Project lifting management and support services pre...
Offshore Energy Limited - Project lifting management and support services pre...Offshore Energy Limited - Project lifting management and support services pre...
Offshore Energy Limited - Project lifting management and support services pre...
 
Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...
 

RailWorks-Today-February-2016-F

  • 1. During a tie change-out job in Greater Toronto, ON, PNR RailWorks maintained such an impressive pace that customer GO Transit decided to up its order. And PNR RailWorks delivered. Restricted to night and weekend work windows, a 26-person gang changed more than a third more ties than initially required over the duration of the project. And they did so during the originally allotted time frame of two and a half months. The initial scope of the project involved changing 15,600 ties through- out the Oakville subdivision on main tracks 1, 2, and 3. “As this is an extremely busy subdivision running GO Transit, VIA Rail, and CN Railway freight trains, the work was performed on a night shift to obtain addi- tional working time as compared to a day shift,” notes Arash Barzegar, who served as project manager. “Shutting down any one of the main lines was not an option.” The initial plan was to change 325 ties per shift in between delays in GO, VIA and CN service. Once beginning the job, the crew discovered it would experience significant delays while working on such a busy sub- division. “On a typical night, we were lucky to obtain 5 hours of working time between several hours of delays for trains passing on adjacent tracks within our working limits,” says Arash. The mid-week work win- dows were limited to 6 hours, with 4.5 hours of productivity on average. Weekend work provided 8-hour work windows. Even with the erratic work windows, the crew was able to change significantly more ties per shift than planned. High productivity kept the project on schedule. Based on this increased production, the scope of the project was revised to include additional ties within the same work period. By the time the project period had ended, the crew had changed 21,519 ties – nearly 38 percent more than initially planned, without a change in the initial time frame. Effective organization and coordination between the working crew, pro- tecting foremen and trains operating within the working limits allowed PNR RailWorks to average a surprisingly swift 550 ties per shift over the course of the project. Besides the tie-change crew, a three-man crew surfaced track, and GO Transit Maintenance performed constant flagging and crossing support. The scope of the project also involved removing and disposing of all old ties from the subdivision. Project leaders besides Arash included Project Superintendent Bran- don Berry, Project Coordinator Justin Duval, Foreman Ryan Homeniuk; and for GO Transit Maintenance, Track Manager Greg Machado, Track Superintendent Roger Alves and Foreman Dan Bertram. February 20165 RailWorks Values In Action: Customer Focus Achieving An Amazing Pace for GO Transit Operator Tim Dagenais (above left) stands in front of a tie remover/inserter used on the job for GO Transit. Besides the tie replacement, the scope of the project also involved removing and disposing of all old ties, a job that Operator Dan Springer (above right) helped to handle. (left to right) Project Manager Arash Barzager, Project Superintendent Brandon Berry, Project Coordinator Justin Duval and Foreman Ryan Homeniuk led a GO Transit job to change out thousands of ties on the Oakville Subdivision in Greater Toronto, ON. Working in confined work windows, a 26-man tie-change crew from the PNR RailWorks Track group, with support from the PNR RailWorks GO Transit Maintenance team, replaced an average of 550 ties per shift.